Factual and Procedural Background
The Plaintiff leases land on which a digital media advertising totem was constructed. The Plaintiff and Defendant entered into missives intending that the Plaintiff would sub-let the land and totem to the Defendant, subject to a suspensive condition that the obligation to enter the sub-lease would only take effect upon notice of completion of the works. The Defendant resiled from the missives, arguing that completion had not occurred. The Plaintiff seeks a declarator that the suspensive condition was purified and that the Defendant had no right to resile, as well as payment of £480,000 due under the missives at entry. The case proceeded to debate, with the Plaintiff challenging the relevancy and specification of the Defendant's averments and seeking decree de plano.
In 2018 and 2019, the Plaintiff entered into multiple contracts related to the construction and use of the advertising totem on land at Glasgow Airport, including a head lease with a third party (GAL), a licence for works authorising construction, a building contract with a contractor (Company B), and the missives with the Defendant for sub-letting. The missives included a suspensive condition tied to completion under the licence for works, with detailed procedures for notice, inspection, and dispute resolution involving an independent expert. Completion was defined as the date a completion certificate was issued by the project manager under the licence for works.
The completion certificate was issued by an individual named Mr Chandler on behalf of the Plaintiff on 14 October 2020, and notice was given to the Defendant. The Defendant disputed that practical completion had occurred, alleging defects and incomplete works, and sent letters resiling from the missives on 26 October 2020. The Defendant advanced three grounds for resiling: the certificate was not issued in accordance with the contracts; breach of five implied terms; and fraudulent and dishonest issuance of the certificate by Mr Chandler, whose knowledge was attributed to the Plaintiff.
Legal Issues Presented
- Whether the purported completion certificate was issued in accordance with the parties' contract.
- Whether certain terms should be implied into the contract contained in the missives.
- Whether the purported completion certificate was issued fraudulently and dishonestly, justifying reduction of the certificate.
Arguments of the Parties
Plaintiff's Arguments
- The suspensive condition in clause 4.1 of the missives was purified by the notice of 14 October 2020, indicating completion as defined in the licence for works.
- The Defendant's averments about defects lacked specification and were irrelevant, failing to show contractual significance or why they precluded certification.
- The Defendant had explicit contractual rights to challenge certain defects under clauses 4.2 to 4.7 but did not rely on these rights.
- The contractual scheme excluded third party rights, making the Defendant's broader challenge inconsistent and irrelevant.
- The project manager's duties under the building contract were owed to the employer and contractor, not third parties like the Defendant; parties are free to appoint any project manager.
- The Defendant's fraud allegations were irrelevant and scandalous; mental states of Mr Chandler and the Plaintiff in issuing and relying on the certificate do not affect its validity.
- Legal principles cited establish that fraud requires a false pretence causing loss, which the Defendant failed to show in relation to the certificate.
Defendant's Arguments
- The completion certificate was not issued in accordance with the parties' contract because practical completion had not occurred.
- There is no definition of "practical completion" in the licence for works; the Defendant's definition requires works to comply with contract requirements and be free from material defects.
- The building contract and licence for works do not correspond; the certificate under the building contract did not satisfy the licence for works.
- The works were incomplete and defective; no project manager could genuinely believe practical completion was achieved.
- Mr Chandler was not entitled to issue the certificate as he was not an independent or properly appointed project manager under the missives.
- The five implied terms contended for are necessary and meet the test for implication, including duties of reasonableness, honesty, and avoidance of conflicts of interest.
- The fraud and dishonesty averments justify reduction of the certificate as a false document that would otherwise purify the suspensive condition and bind the Defendant.
- The Defendant's expert report and pleadings provide fair notice of the alleged defects and incomplete state of the works.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Apcoa Parking (UK) Ltd v Crosslands Properties Ltd [2016] CSOH 63 |
Support for limited obligations of sub-tenant under commercial lease |
Referenced to explain the limited nature of the Defendant's obligations under the sub-lease. |
| Marks and Spencer plc v BNP Paribas Securities Services Trust Co (Jersey) Limited [2016] AC 742 |
Test for implication of terms into contracts |
Applied to assess the validity of the Defendant's proposed implied terms, which were rejected. |
| Philips Electronique Grand Public SA v British Sky Broadcasting Ltd [1995] EMLR 472 |
Principles of contractual interpretation and implication |
Referenced in context of implied terms discussion. |
| Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973] 1 WLR 601 |
Principles relating to implied terms and contractual duties |
Referenced in relation to implied terms and duties of reasonableness and honesty. |
| Keating on Construction Contracts (11th ed) |
Project manager duties and certification under building contracts |
Used to explain the duties owed by project managers and the nature of practical completion. |
| Sutcliffe v Thackrah [1974] AC 727 |
Project manager duties and impartiality |
Supported the explanation of project manager's duty to act impartially and fairly. |
| Costain Limited v Bechtel Limited [2005] EWHC 1018 |
Project manager's role and duties under building contracts |
Referenced to clarify that duties are owed to contracting parties, not third parties. |
| Imperial Chemical Industries Limited v Merit Merrell Technology Limited [2017] EWHC 1763 |
Requirement for project managers to act independently and impartially |
Applied to reject Defendant's argument that the Plaintiff was bound to appoint an independent project manager. |
| Van Oord UK Ltd v Dragados UK Ltd [2021] CSIH 50 |
Contractual interpretation requiring clear language to impose onerous obligations |
Applied to reject an interpretation that would place the Defendant at the mercy of a third party. |
| Scheldebouw BV v St James Homes (Grosvenor Dock) Ltd [2006] EWHC 89 |
Project manager's duties of independence, impartiality, fairness, and honesty |
Discussed in relation to whether Mr Chandler was properly appointed and independent. |
| Re Brown v GIO Insurance Ltd [1998] CLC 650 |
Implication of terms to ensure business efficacy and fairness |
Referenced to support the principle that unilateral contractual powers may give rise to implied terms. |
| Gordon District Council v Wimpey Homes Holdings Ltd 1989 SLT 141 |
Implied terms and contractual fairness |
Referenced in the context of implied terms and business efficacy. |
| John H Wyllie v Ryan Industrial Fuels Ltd 1989 SLT 302 |
Implied terms and contractual fairness |
Referenced alongside other cases on implied terms. |
| Rainy Sky SA v Kookmin Bank [2011] 1 WLR 2900 |
Principles of contractual interpretation |
Applied to support the objective, contextual, and purposive approach to contract construction. |
| Arnold v Britton [2015] AC 1619 |
Contractual interpretation principles |
Referential in the court's approach to interpreting the missives. |
| Wood v Capita Insurance Services Limited [2017] AC 1173 |
Contract interpretation principles |
Referenced in support of the court’s interpretative approach. |
| Park's of Hamilton (Holdings) Limited v The Scottish Football Association Limited [2021] CSIH 61 |
Contract construction must be objective, contextual, purposive, and commercially sensible |
Applied to guide the court’s interpretation of the contract terms. |
| Marine & Offshore (Scotland) Limited v Hill 2018 SLT 239 |
Definition and elements of fraud |
Used to explain the legal requirements for fraud including false pretence and resultant loss. |
| Politakis v John Wood Group plc [2021] CSOH 7 |
Fraud requires material false pretence relied upon causing loss |
Referenced to clarify the elements of fraud in civil claims. |
| Campbell v Edwards [1976] 1 WLR 403 |
Fraud invalidates expert determinations |
Applied by analogy to support the Defendant’s argument that fraud would invalidate the completion certificate. |
| Henia Investments Inc v Beck Interiors Ltd [2015] EWHC 2433 |
Fraud unravels interim payment certificates |
Used by analogy to support the argument that fraud invalidates certificates of completion. |
Court's Reasoning and Analysis
The court applied established principles of contractual interpretation, emphasizing an objective, contextual, purposive approach consistent with commercial common sense. The missives, professionally drafted and appended with drafts of related contracts, created a contractual scheme where completion was a matter determined under separate contracts between the Plaintiff and third parties, notably GAL, not involving the Defendant.
The suspensive condition in the missives required notice of completion as defined in the licence for works. The Defendant had no contractual right to challenge whether completion under those contracts had occurred but was entitled to inspect the works and make representations under specific clauses. The Defendant’s broader challenge to completion based on alleged defects unrelated to those clauses was inconsistent with the contractual scheme and excluded third party rights.
The court rejected the Defendant’s argument that the project manager had to be independent and impartial under the missives, noting that appointments and duties of project managers arise under the building contract, not the missives. The Defendant’s construction that the Plaintiff was at the mercy of a third party was unmerited given the rights to inspection and representation.
Regarding implied terms, the court found no basis to imply the terms contended for by the Defendant. Given the contractual context and the parties’ knowledge of the contractual scheme, the tests for implication (business efficacy and officious bystander) were not met.
On the fraud allegation, the court acknowledged the serious nature of the averments and held that the issue was not bound to fail at proof stage. The court explained that fraud, defined as a false pretence causing loss, could justify reduction of the completion certificate, which would otherwise purify the suspensive condition and bind the Defendant. The court reserved this matter for proof, taking the Defendant’s averments pro veritate.
The court fixed a by-order hearing to determine which averments should be excluded from probation and to manage further procedure, reserving all questions of expenses.
Holding and Implications
The court held that the Defendant’s contentions on the construction of the missives and on implied terms must fail. However, the issue of reduction of the completion certificate on grounds of alleged fraud and dishonesty was not resolved at this stage and remains a matter for proof.
The case was not disposed of but procedural steps were ordered to clarify the pleadings and manage further proceedings.
The direct effect is that the Defendant’s challenge to the certificate on contractual construction grounds was rejected, but the serious fraud allegations require further examination. No new precedent was set; the decision primarily clarifies the application of contractual interpretation and the approach to allegations of fraud in this context.