RHP Merchants And Construction Ltd v Treforest Property Company Ltd

Smart Summary

Factual and Procedural Background

This opinion concerns an application by the Defendant, a property development company ("Company B"), seeking a stay and subsequent strike-out of proceedings brought by the Plaintiff, a building contractor ("Company A"). The dispute arises from two adjudication awards related to a construction contract for a residential development. The first adjudication award required Company A to pay Company B a sum, which was enforced by a court order dated 5 November 2020. Despite this enforcement, Company A failed to comply with the payment order.

Shortly after the first adjudication award was enforced, a second adjudication took place between the same parties, resulting in Company B being ordered to pay Company A a sum based on an incorrect assumption that Company A had paid the first adjudication award amount. Company B seeks a stay of the current proceedings until Company A complies with the court order enforcing the first adjudication award, and also seeks strike-out orders should Company A fail to pay within a specified period.

The background includes a contract based on the JCT standard Form, Design and Build 2016 edition, with practical completion certified in August 2019. The dispute involves final account balances, pay less notices, and multiple adjudication and court proceedings. Arbitration proceedings were also initiated but are anticipated to be stayed.

Legal Issues Presented

  1. Whether the Court should exercise its discretion to order a stay of proceedings pending payment of the judgment debt enforced by the first adjudication award.
  2. Whether, in the event of non-payment within a specified time, the Court should strike out the proceedings.
  3. How to balance the statutory policy under the Housing Grants, Construction and Regeneration Act 1996 ("HGCRA") of "pay now, dispute later" against the parties' rights to access the courts and the conduct of litigation.
  4. The relevance and effect of a second adjudication award issued after the first adjudication award and its impact on the enforcement and stay applications.

Arguments of the Parties

Defendant's Arguments

  • Company B argues that Company A has failed to comply with the court order enforcing the first adjudication award, justifying a stay of proceedings and strike-out if payment is not made.
  • The Defendant relies on the statutory policy of the HGCRA emphasizing "pay now, argue later," and the Court's discretion to stay proceedings in cases of bad faith or oppressive conduct as established in Anglo Swiss Holdings Ltd & Ors v Packman Lucas Ltd.
  • Company B highlights that Company A's refusal to pay despite the judgment order and the multiple dispute resolution attempts indicate unreasonable and oppressive behavior.
  • It is submitted that the second adjudication award does not negate the obligation to pay under the first adjudication award, especially given questions over the second adjudicator's jurisdiction.
  • Company B seeks orders for payment of a specified sum within 14 days or alternatively a smaller sum, a stay of proceedings pending payment, and strike-out if payment is not made within six months, as well as costs.

Claimant's Arguments

  • Company A contends that the proceedings should not be stayed as the case differs materially from the precedent relied upon by the Defendant.
  • It is argued that the second adjudication award, which was decided after the first, affects the sums due and thus the "pay now, argue later" policy applies equally to the second award.
  • Company A denies bad faith or oppressive conduct and maintains that it has valid points supporting its entitlement to payment.
  • Company A offered partial payments and indicated willingness to stay proceedings but later resiled from these positions.
  • The Claimant relies on recent case law, including Prater Ltd v John Sisk and Son (Holdings) Ltd, which supports the validity of second adjudication awards pending challenge.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Anglo Swiss Holdings Ltd & Ors v Packman Lucas Ltd [2009] EWHC 3212 (TCC) The Court's power and discretion to stay proceedings, to be used sparingly and in exceptional cases involving bad faith or oppressive conduct; the importance of "pay now, argue later" under the HGCRA. The Court considered this precedent as a guide to when a stay should be granted, noting that it requires clear cases of bad faith or unreasonable behavior, which were not found here.
Kew Holdings Ltd v Donald Insall Associates Ltd [2020] EWHC 1862 (TCC) Emphasizes the importance of access to justice and the balance between "pay now, argue later" and the right to pursue disputes. The Court referenced this case to highlight the tension between enforcing adjudication awards promptly and preserving access to justice, influencing the decision to allow a stay with a time limit.
Prater Ltd v John Sisk and Son (Holdings) Ltd [2021] EWHC 1113 (TCC) Recognition of the validity of second adjudication awards based on first awards until challenged. The Court considered this authority in assessing the effect and jurisdictional challenges relating to the second adjudication award.

Court's Reasoning and Analysis

The Court identified a tension between two key principles: the statutory policy under the HGCRA requiring prompt payment of adjudication awards ("pay now, argue later") and the fundamental right of parties to access justice. The Court acknowledged that adjudication awards are temporary and subject to later challenge but emphasized the importance of compliance with enforcement orders.

The existence of two adjudication awards complicated the matter. The Court expressed considerable doubt about the jurisdiction of the second adjudicator but noted that it was not required to decide that issue at this stage. The second adjudication award was nonetheless relevant to the overall balance of sums owed.

The Court took into account the refusal of Company A to pay the net sum due under the combined effect of the two adjudication awards and court orders, despite partial payment offers. It found no clear evidence of bad faith or oppressive conduct on the part of Company A similar to that in Anglo Swiss, but concluded that some payment should be made in accordance with the "pay now, argue later" principle.

To protect access to justice while enforcing compliance, the Court decided that the proceedings should be stayed on condition that Company A pays a minimum sum within 28 days. Failure to pay would result in strike-out of the proceedings. This approach balances the statutory policy with the parties' rights and prevents indefinite delay.

Holding and Implications

The Court's final decision was to ORDER A STAY OF PROCEEDINGS on condition that the Plaintiff pays the sum of £36,494.69 to the Defendant within 28 days. If payment is not made within this period, the proceedings will be STRUCK OUT. In the meantime, the stay remains in effect.

This decision enforces the statutory "pay now, argue later" regime while preserving access to justice by allowing the dispute to proceed if payment is made. No new precedent was established; rather, the Court applied existing principles to the particular facts, notably the presence of two adjudication awards and the conduct of the parties.

To access the original judgment, please Sign In or Subscribe.

RHP Merchants And Construction Ltd v Treforest Property Company Ltd

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

RHP Merchants And Construction Ltd v Treforest Property Company Ltd
(Oct 22, 2021)