Factual and Procedural Background
The Claimant, Company A, contracted with the Defendant, Company B, for engineering piping works related to a new paint manufacturing facility ("the Plant") at a business park in The City. The contract, executed as a deed in December 2012, initially valued at approximately £1.9 million, was expanded significantly by Project Manager's Instruction No.3 in February 2013, increasing the works' value to approximately £10 million or more, with payments made to Company B totaling £20.9 million by the time of litigation.
Company B performed manufacture, construction, installation, commissioning, and handover of steelworks and tank offloading. The project was managed initially by Company A personnel but from mid-2014 was taken over by personnel from Company A's parent, Company C, whose project management approach led to disputes.
From October 2014, Company B ceased receiving payments, and welding was suspended by instruction. Allegations of defective welding were made by Company C's team, which Company B disputes. A letter dated 17 February 2015 from Company A accepted what it considered to be repudiation by Company B and terminated the contract. Company B disputed this and alleged repudiation by Company A.
Subsequent adjudications awarded payments to Company B, but financial difficulties ensued, leading to Company B entering voluntary liquidation in early 2017. The litigation was split into liability and quantum phases, with the liability trial heard before the court.
Legal Issues Presented
- Whether the non-destructive testing (NDT) required was dye-penetration testing of 10% of welds, excluding radiographic testing as per BS 4677.
- If dye-penetration testing only was agreed, the applicability of Table 5 of BS 4677 for PMI 03 works.
- The percentage of welding defective such that it breached the contract and BS 4677.
- Whether Company B breached the contract by:
- Failing to hand over requested project documentation;
- Removing project documentation from the Plant to its fabrication shop;
- Failing to provide an adequate remedial plan;
- Failing to provide evidence or proposals ensuring welders were qualified;
- Denying the Project Manager access to the fabrication shop, including issues on the validity of the Project Manager's appointment.
- Whether Company B repudiated the contract as of 17 February 2015, entitling Company A to instruct Company B to leave site.
- Whether Company A repudiated the contract by instructing Company B to leave site on 17 February 2015.
- Whether Company A validly terminated Company B's obligation under clause 90 of the NEC contract.
- The basis for assessing damages for defective work, considering the court's findings on termination and repudiation.
- Whether the termination accounting process under clauses 90 and 93 of the NEC3 contract applies.
- Whether Company A is entitled to recover any overpayment made to Company B in restitution.
- Whether Company A is prevented from challenging the value of Company B's work.
- Whether Company B is entitled to damages for repudiation if Company A repudiated the contract.
- If so, how such damages should be assessed.
- Whether Company A is entitled to a final injunction requiring delivery of specified documents and related issues.
- Alternatively, whether Company A is entitled to damages for non-delivery of documents.
- If so, how such damages should be assessed.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| CG Group Ltd v Breyer Group Ltd [2013] EWHC 2722 (TCC) |
Explanation of "smash and grab" adjudications concerning payment notices under the Housing Grants, Construction and Regeneration Act 1996. |
Used to explain the nature and perception of payment notice adjudications and the legal framework governing them. |
| Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) |
Further explanation and criticism of the "smash and grab" phrase and adjudication claims based on payment notice failures. |
Clarified the court's view on adjudication claims related to payment notices and the statutory regime. |
| Scheldebouw BV v St James Homes [2006] EWHC 89 (TCC) |
Legal principles concerning the role and duties of decision-makers (Project Managers) under construction contracts, including independence and impartiality. |
Applied to assess the validity of the Project Manager's appointment and role in this case, concluding no proper appointment was made and the Project Manager lacked independence. |
| De Beers UK Ltd v Atos [2010] EWHC 3276 (TCC) |
Contractual obligations and refusal to comply with contract terms leading to termination and repudiation issues. |
Rejected parallels drawn by Company A regarding alleged conduct of Company B in refusing to comply with contract terms. |
| Stocznia Gdynia SA v Gearbulk Holdings [2009] EWCA Civ 75 |
Interplay between contractual termination and repudiation; termination rights and consequences. |
Considered but distinguished; court held that contractual termination rights are not necessarily the same as acceptance of repudiation, and this case's contract did not equate them. |
| ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC) |
Effect of failure to serve valid payless notices and valuation of works in interim payment adjudications. |
Considered but distinguished; court found the case concerned timing and not substantive final valuation, and did not support Company B's argument that interim payments definitively fix valuation. |
| MJ Harding Contractors v Paice and Springall [2015] EWCA Civ 1231 |
Jurisdiction of adjudicators and the nature of disputes in serial adjudications. |
Supported the court's view that valuation disputes may be referred to adjudication multiple times and that interim payments do not conclusively fix valuation. |
| Brown v Complete Building Solutions Ltd [2016] EWCA Civ 1 |
Repeated adjudications and the scope of disputes; adjudicator jurisdiction. |
Supported the principle that disputes must be assessed in context and that later adjudications can address different issues. |
| Galliford Try Building Ltd v Estura Ltd [2015] EWHC 412 (TCC) |
Clarification of ISG v Seevic concerning valuation and timing of interim payments. |
Supported the view that interim payment valuations are not definitive for all purposes and can be challenged. |
| Kersfield Developments (Bridge Road) Ltd v Bray and Slaughter Ltd [2017] EWHC 15 (TCC) |
Effect of default notice mechanisms under the Housing Grants, Construction and Regeneration Act 1996 on substantive rights. |
Confirmed that procedural defaults regulate cash flow but do not affect substantive contractual rights to challenge valuations. |
| Hyundai Industries Heavy Industries Co Ltd v Papadopoulos [1980] 1 WLR 1129 |
Effect of contract cancellation on accrued payment rights. |
Supported the principle that accrued rights to payment survive contract cancellation. |
| Ferguson & Associates v Sohl [1992] 62 BLR 96 |
Application of total failure of consideration to part of a payment balance for restitution claims. |
Referenced regarding restitution and apportionment principles in partial payment recovery. |
| Van Der Garde BV and others v Force India Formula One Team Ltd [2010] EWHC 2373 (QB) |
Necessity of apportionment in restitution claims relating to partial failure of consideration. |
Discussed apportionment as a tool in restitution claims for undelivered work. |
| Aspect Contracts (Asbestos) Ltd v Higgins Construction plc [2015] UKSC 38 |
Right to recover payments made pursuant to adjudicator's decision; cause of action timing. |
Held cause of action arises on payment; recovery possible contractually or in restitution; relevant to overpayment claims here. |
Court's Reasoning and Analysis
The court undertook a detailed factual and legal analysis, structured around the agreed issues. It found that the contract between the parties was governed by the NEC3 form with amendments, incorporating a Project Manager role intended to be independent and impartial. The court held that the purported appointment of the Project Manager by Company A's parent company was invalid and breached the contract, as no proper independent Project Manager was in place after PROJEN's resignation.
Regarding the testing regime, the court accepted that the parties agreed in early 2013 that non-destructive testing would be limited to visual inspection and dye-penetration testing of 10% of welds, explicitly excluding radiographic testing. This was finally conceded by Company A at trial, undermining Company A's prior position that radiographic testing was contractually required.
The court found that the expert evidence from Company A's experts was partisan and flawed, particularly due to reliance on a non-representative sample of weld reports and failure to consider the agreed testing regime. The expert evidence from Company B's expert was preferred as impartial and reliable.
On the issue of defective welds, the court found that the maximum defect rate consistent with the agreed testing regime was 5%, which is within normal expectations, and rejected Company A's higher defect estimates based on flawed extrapolations.
The court dismissed all allegations of repudiatory breaches by Company B concerning failure to produce documents, wrongful removal of documents, failure to provide remedial plans, failure to provide evidence of welders' qualifications, and denial of access to the fabrication shop. It found that Company B complied with reasonable requests and that no repudiatory breach existed.
On repudiation, the court held that Company B was not in repudiatory breach as of 17 February 2015, but Company A was in repudiatory breach by instructing Company B to leave site without proper grounds and without valid contractual termination procedures. The letter of 17 February 2015 was a repudiation by Company A, not a valid contractual termination.
Regarding recovery of overpayments, the court held that accrued rights to recover overpayments survive repudiation and that interim payment assessments are not definitive valuations for all purposes. The court found that Company A has a contractual right to recover any overpayments made to Company B, and restitutionary claims were unnecessary but potentially available as an alternative.
The court also found that Company A had an accrued contractual right to project documents but had not made a proper request prior to 17 February 2015. The request made on that date was unreasonably short in timeframe, and Company B was not in breach for failing to comply immediately. The court further found no wrongful removal of documents by Company B, and that Company A's failure to obtain documents earlier did not cause proven loss.
Finally, the court answered the agreed issues based on these findings, confirming the agreed testing regime, defect rates, absence of repudiatory breaches by Company B, repudiation by Company A, and Company A's entitlement to recover overpayments and damages consistent with the contract and principles of law.
Holding and Implications
Holding: The court held that Company A repudiated the contract by instructing Company B to leave site without valid contractual grounds, and Company B was not in repudiatory breach. The agreed testing regime excluded radiographic testing, and the defect rate did not exceed 5%. Company A is entitled in principle to recover any overpayments made to Company B under the contract or alternatively in restitution. Company B is entitled to damages for repudiation by Company A.
Implications: The decision directly affects the parties by resolving the liability issues in Company B's favour on repudiation and defect claims, and confirms Company A's right to recover overpayments. No new precedent is established beyond applying existing principles on Project Manager independence, contract termination, adjudication, and valuation under NEC3 contracts. The findings emphasize the importance of proper appointment of decision-makers, adherence to agreed testing regimes, and strict compliance with contractual termination procedures.