Citation Codes
Equivalent Citations
citation codes
Judges
- JUSTICE
- HIS HONOUR JUDGE BOWSHER Q.C.
- HIS HONOUR JUDGE BOWSHER Q.C. IS
- HIS HONOUR
- JUSTICE TO THE SUBMISSIONS OF
See more information ...
Click here to read the full judgment
Whiteways Contractors (Sussex) Ltd v. Impresa Castelli Construction Ltd
Smart Summary
Factual and Procedural Background
The Plaintiff, a plastering sub-contractor, was engaged by the Defendant in connection with the construction of a hotel in London under a subcontract incorporating the standard form DOM/1. A dispute arose during the works which was referred to adjudication under the Housing Grants, Construction and Regeneration Act 1996 (HGCRA). The first adjudication resulted in a decision ordering the Defendant to pay the Plaintiff a sum which was paid. Subsequently, the Plaintiff gave notice of intention to refer a further dispute to adjudication, resulting in a second adjudicator's decision ordering the Defendant to pay the Plaintiff £95,383.50 plus VAT. The Defendant made no payment in response to this second decision, and the Plaintiff initiated proceedings to enforce it by way of summary judgment under CPR Part 24.
Legal Issues Presented
- Whether the adjudicator acted within jurisdiction in deciding the matters referred to, particularly concerning disputes not explicitly included in the notice of intention to refer adjudication.
- Whether the Defendant could rely on matters of abatement to reduce the amount ordered to be paid.
Arguments of the Parties
Defendant's Arguments
- The adjudicator exceeded his jurisdiction by considering disputes not indicated in the notice of intention to refer adjudication.
- The Defendant was entitled to rely on abatement (but not set-off) to reduce the amount payable under the adjudicator's decision.
- Procedural breaches were suggested but not pressed before the court.
Plaintiff's Arguments
- The Defendant waived jurisdictional objections by agreeing that the adjudicator should decide his own jurisdiction.
- The adjudicator correctly construed and applied the contract terms governing adjudication.
- The Defendant's abatement arguments were not valid under the HGCRA scheme.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Fastrack Contractors v. Morrison [2000] BLR 168 |
Options available to a party challenging the adjudicator's jurisdiction, including consenting to the adjudicator deciding his own jurisdiction. |
The court found that the parties had adopted the option of allowing the adjudicator to decide his own jurisdiction, which was binding pending final determination. |
Court's Reasoning and Analysis
The court examined the contractual provisions under clause 38A of DOM/1 and the HGCRA statutory framework governing adjudication. The adjudicator had issued a detailed decision on his jurisdiction, finding that he had jurisdiction to consider all matters raised in the referral except for the extension of time application, which was not expressly included in the notice but was necessary for a fair consideration of related claims. The court agreed with the adjudicator's interpretation that the notice of intention to refer must briefly identify the dispute to enable unambiguous identification, and that the adjudicator's jurisdiction is limited to those disputes unless the parties agree otherwise.
The court rejected the Defendant's argument that the adjudicator acted in excess of jurisdiction, noting the Defendant's solicitors had invited the adjudicator to decide the jurisdictional issue. The court emphasized that once the adjudicator had made his jurisdictional decision, it was binding under the contract and could not be challenged in enforcement proceedings.
Regarding abatement, the court analysed sections 109 to 111 of the HGCRA, which govern payment notices and withholding payments. It held that while the Act requires notice of intention to withhold payment, it does not distinguish between set-offs and abatements in this context. The court found no basis to allow the Defendant to rely on abatement claims outside the scope of the adjudication or without proper notice, rejecting the Defendant's submissions on this point.
Holding and Implications
The court granted summary judgment in favour of the Plaintiff for the sum of £95,383.50 inclusive of VAT, plus agreed interest of £2,215.40, totaling £97,598.90. The Defendant was ordered to pay the Plaintiff's costs assessed at £5,600 exclusive of VAT plus £738 for taking the judgment, totaling £6,338.
The decision enforces the adjudicator's award, affirming the binding nature of adjudicators' jurisdictional determinations when parties have consented. The court declined to entertain jurisdictional challenges at enforcement stage and clarified the application of HGCRA provisions on abatement, requiring proper notice for withholding payments. No new precedent was set beyond affirming established principles regarding adjudication jurisdiction and payment withholding under the HGCRA.
Click here to read the full judgment