Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Neutral Citations
2025 DHC 6257
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2025 DHC 6257
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Acts
Smart Summary

Case Summary: O.M.P. (COMM.) 278/2025 — Union of India v. M/s Garg Builders (High Court of Delhi)

Factual and Procedural Background

This petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenges an arbitral award dated 01.09.2022 and a modified award dated 20.09.2022 passed in Arbitration Case ARB/OPB/CPWD/72. The petitioner (Union of India) was served with the awards on the dates of those awards.

Procedural chronology (as set out in the opinion):

  • 03.01.2023: Petitioner filed a challenge to the award before the Karnal District Court (the opinion records this consumed 104 days).
  • 20.07.2024: Karnal District Court returned the petition to the petitioner with liberty to file before the appropriate territorial court and observed that the petitioner would be entitled to the benefit of Section 14 of the Limitation Act, 1963.
  • 21.08.2024: Petitioner filed the Section 34 petition before the Rohini District Court (the opinion records this consumed another 30 days from 20.07.2024).
  • 19.10.2024: Rohini District Court issued notice and stayed the effect and operation of the impugned award.
  • 03.04.2025: Rohini District Court returned the petition under Order VII Rule 10 of the Code of Civil Procedure, 1908, directing presentation before the court of competent jurisdiction within one month from that date.
  • 29.05.2025: Petitioner filed the present petition before the High Court of Delhi (this filing occurred 55 days after 03.04.2025).
  • The petitioner also filed I.A. 17604/2025 seeking condonation of a delay of 25 days. Earlier applications for exemption (I.A. 17607/2025 & I.A. 17608/2025) were allowed subject to exceptions and disposed of.

Legal Issues Presented

  1. Whether the Section 34 petition is within the period of limitation prescribed under Section 34(3) of the Arbitration and Conciliation Act, 1996, read with the Limitation Act, 1963.
  2. Whether the periods spent prosecuting the petition before other courts (Karnal District Court and Rohini District Court) can be excluded under Section 14 of the Limitation Act, 1963.
  3. Whether, in circumstances where an arbitrator was allegedly appointed unilaterally, the arbitration is void ab initio and whether that ground can be raised at the stage of setting aside or execution of the award.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner contended that the arbitration proceedings were void ab initio due to unilateral appointment of the arbitrator. The petitioner relied upon Supreme Court decisions (referenced in the opinion) including Perkins Eastman Architects DPC v. H(SCC India) Ltd. (2020) 20 SCC 760 and TRF Ltd. v. Energo Engineering Projects Ltd. (2016) SCC OnLine SC 1928 in support of that contention.
  • The petitioner sought condonation of delay (I.A. 17604/2025) in filing the Section 34 petition before this Court, asserting entitlement to exclusion of time under Section 14 of the Limitation Act for periods during which proceedings were prosecuted before other courts.

Respondent's Arguments

The opinion does not contain a detailed account of the respondent's legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Simplex Infrastructure Limited v. Union Of India, (2019) 2 SCC 455 The proviso to Section 34(3) allows extension of the three-month period by another period of up to thirty days on sufficient cause being shown; the extension cannot be beyond thirty days ("but not thereafter"). The Court relied on Simplex to hold that delay beyond the three months plus thirty days is not condonable; the statutory timeline is strict and a delay beyond that cannot be excused.
National Research Development Corporation & Anr. v. Chromous Biotech Pvt. Ltd., O.M.P. (COMM) 238/2023 (08.01.2024) Followed Simplex's exposition of the temporal limits under Section 34(3) and its proviso (paragraphs quoted in the opinion). The Court followed the reasoning in this High Court decision (which itself follows Simplex) to reinforce that a delay of more than the permitted extension cannot be condoned.
M/s Singhal Credit Management LLP v. M/s Religare Securities Ltd. & Anr., FAO (COMM) 34/2022 (24.03.2022) Sets out parameters on limitation: limitation once commenced does not get interrupted; applicability of the Limitation Act to arbitration by Section 43 of the 1996 Act; how the three-month period is to be ascertained; applicability and scope of Section 14 of the Limitation Act to exclude time spent bonafidely prosecuting proceedings before a wrong forum. The Court relied on this decision for guidance on how to treat periods spent prosecuting remedies in other courts and the limited circumstances under which Section 14 exclusion is available.
State of H.P. v. Himachal Techno Engineers, (2010) 12 SCC 210 Explains how to ascertain the terminal date of a three-month period (distinguishes a three-month period from 90 days; depending on calendar months, three months may be 89-92 days etc.). The Court cited this decision for the correct method of computing the three-month limitation period under Section 34.
Union Of India v. Popular Construction Co., (2001) 8 SCC 470 Holds that the period of limitation for setting aside an award commences from the date of receipt of the award (or disposal of a Section 33 request); Section 5 of the Limitation Act is not applicable to proceedings under Section 34. The Court relied on this principle to treat the date of receipt of the award (or modified award) as the commencing point of limitation for Section 34 petitions.
Consolidated Engineering Enterprises v. Irrigation Deptt., (2008) 7 SCC 1692 Explains criteria for application of Section 14 of the Limitation Act: proceedings prosecuted with due diligence, same matter in issue, prosecuted in good faith in a court which could not have entertained it due to a defect in jurisdiction or similar cause. The Court cited these criteria when considering whether the time spent before other courts could be excluded under Section 14.
Perkins Eastman Architects DPC v. H(SCC India) Limited, (2020) 20 SCC 760 Authority relied upon for the proposition that unilateral appointment of an arbitrator is impermissible and may render arbitration flawed. The petitioner relied on this decision to contend that the arbitration was void ab initio; the Court recorded the reliance but directed that such objections may be raised at the stage of execution of the award.
TRF Ltd. v. Energo Engineering Projects Ltd., (2016) SCC OnLine SC 1928 Authority relied upon in support of the proposition against unilateral appointment of arbitrator. The petitioner relied on this decision in arguing the arbitral process was defective; the Court allowed the petitioner liberty to raise the objection later (at execution).

Court's Reasoning and Analysis

The Court's analysis proceeded in the following steps (as contained in the opinion):

  1. The Court observed that under Section 34(3) of the Arbitration and Conciliation Act a shortened statutory period applies: a three-month period (90 days as a practical yardstick), and the proviso allows an extension for a further period of up to thirty days on showing sufficient cause — but "not thereafter". The Court reiterated the binding exposition in Simplex and subsequent authorities that delay beyond that combined period cannot be condoned.
  2. The Court set out the factual timeline of filings and returns: receipt of award(s) in September 2022; initial filing in Karnal District Court on 03.01.2023 (104 days consumed); return by Karnal on 20.07.2024 with liberty to file elsewhere; filing before Rohini on 21.08.2024 (consuming another 30 days); Rohini's stay on 19.10.2024; Rohini returning the petition on 03.04.2025 under Order VII Rule 10 with one month to present before competent court; filing before this Court on 29.05.2025 (55 days after 03.04.2025).
  3. The Court applied Section 14 of the Limitation Act to exclude only the periods during which the petitioner was bonafidely prosecuting proceedings before other courts (explicitly stating the periods 03.01.2023 to 20.07.2024 and 21.08.2024 to 03.04.2025 are to be excluded).
  4. After excluding those periods, the Court calculated that the petitioner had still consumed more than 185 days in filing the petition before the High Court. Even if the 30 days granted by the Rohini District Court were also excluded, the petitioner had still consumed more than 155 days. Both figures exceed the maximum tolerable period under Section 34(3) (three months plus thirty days).
  5. The Court relied on the principle that once limitation commences it is not interrupted (Section 9 of the Limitation Act) and that Section 14 only excuses time bonafidely spent prosecuting before a wrong forum and subject to the conditions noted in jurisprudence (as set out in the cited decisions).
  6. Accordingly, the Court concluded that the petition is time-barred. The Court recorded the petitioner's contention that the arbitration was void ab initio due to unilateral appointment of the arbitrator (relying on Perkins Eastman and TRF) but held that the petitioner is at liberty to raise those objections at the stage of execution of the award rather than by rescuing the present time-barred petition.

Holding and Implications

HOLDING: The petition under Section 34 is DISMISSED as barred by limitation.

Implications and practical consequences as stated in the opinion:

  • The petition was dismissed on the ground of being time-barred: the combined limitation period under Section 34(3) and its proviso was exceeded and the Court could not condone the delay in view of settled law.
  • The petitioner retains the liberty to raise objections relating to the alleged unilateral appointment of the arbitrator (i.e., challenge of the arbitration being void ab initio) at the stage of execution of the arbitral award.
  • The opinion does not pronounce or record any new legal principle; it applies established Supreme Court and High Court authorities on the computation of limitation, the limited scope of Section 14 exclusions, and the non-extendibility beyond thirty days under the proviso to Section 34(3).

Order dated: 25 July 2025 (Corrected and released on 30 July 2025).
Coram: Jasmeet Singh, J.

To access the original judgment, please Sign In or Subscribe.

    UNION OF INDIA  v. M/S GARG BUILDERS

    O.M.P. (COMM.) 278/2025 Page 1 of 8 $~93

    * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of Decision : 25.07.2025 + O.M.P. (COMM) 278/2025, I.A. 17603/2025, I.A. 17604/2025, I.A. 17605/2025, I.A. 17606/2025

    UNION OF INDIA .....Petitioner

    Through: Mr. Ruchir Mishra, Mr. Mukesh

    Kumar Tiwari and Mr. Reba Mishra,

    Advs.

    versus

    M/S GARG BUILDERS .....Respondent

    Through:

    CORAM:

    HON'BLE MR. JUSTICE JASMEET SINGH

    : JASMEET SINGH, J (ORAL)

    I.A. 17607/2025 & I.A. 17608/2025

    Exemption allowed, subject to all just exceptions. The application is disposed of.

    O.M.P. (COMM) 278/2025

    1. This is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 ("the Act") challenging the Arbitral Award dated 01.09.2022 and modified award dated 20.09.2022 passed by the learned arbitrator in Arbitration Case being ARB/OPB/CPWD/72.

    2. At the outset, learned counsel for the petitioner has been asked to address the issue as to how the petition is filed within the limitation

    1

    period.

    3. In the present case, there is no dispute that the petitioner was served with the arbitral award dated 01.09.2022 and modified award dated 20.09.2022 on the said dates.

    4. On 03.01.2023, the petitioner challenged the award before the Karnal District Court. Hence, on 03.01.2023, the petitioner had consumed 104 days.

    5. However, on 20.07.2024, the Karnal District Court returned the petition to the petitioner with liberty to file before the appropriate territorial jurisdictional court and also observed that the petitioner would be entitled to the benefit of Section 14 of the Limitation Act, 1963 ("the limitation act").

    6. Thereafter, on 21.08.2024, the petitioner filed the petition under Section 34 of the Act before the Rohini District Court, thereby consuming another period of 30 days from 20.07.2024.

    7. On 19.10.2024, the Rohini District Court issued notice and stayed the effect and operation of the impugned award.

    8. Thereafter, vide the Order dated 03.04.2025 passed by the Rohini District Court, the petition was returned to the petitioner under Order VII Rule 10 of the Code of Civil Procedure, 1908, for presenting the same before the court of competent jurisdiction within a period of 1 month from 03.04.2025.

    9. On 29.05.2025, the petitioner filed the present petition before this Court, i.e., after a period of 55 days from 03.04.2025.

    10. Hence, the petitioner has filed an application bearing I.A. 17604/2025 seeking condonation of delay of 25 days in filing the petition.

    2

    11. I have heard learned counsel for the petitioner and perused the material on record.

    12. Under Section 34(3) of the Act, a delay beyond 120 days (90 days plus another 30 days in case of sufficient cause) cannot be condoned. It is a settled law as held by the Hon'ble Supreme Court in the judgment of Simplex Infrastructure Limited v. Union Of India . (2019) 2 SCC 455 and followed by this Court in National Research Development Corporation & Anr. v. Chromous Biotech Pvt. Ltd., O.M.P. (COMM) 238/2023, dated 08.01.2024. The relevant paragraph of National Research Development Corporation (supra) reads as under:

    "11. Further, in Simplex Infrastructure Limited v. Union Of India . (2019) 2 SCC 455, the Supreme Court held that the proviso to Section 34(3) of the Arbitration and Conciliation Act, 1996 allows the said period to be further extended by another period of thirty days on sufficient cause being shown by the party for filing an application. It observed that the intent of the legislature is evinced by the use of the words "but not thereafter" in the proviso. According to the Supreme Court, these words make it abundantly clear that as far as the limitation for filing an application for setting aside an arbitral award is concerned, the statutory period prescribed is three months which is extendable by another period of upto thirty days (and no more) subject to the satisfaction of the Court that sufficient reasons arere provided for the delay. The relevant portion of the said decision is as follows:

    3

    "13. A plain reading of sub-section (3) along with the proviso to Section 34 of the 1996 Act, shows that the application for setting aside the award on the grounds mentioned in sub-section (2) of Section 34 could be made within three months and the period can only be extended for a further period of thirty days on showing sufficient cause and not thereafter. The use of the words "but not thereafter" in the proviso makes it clear that the extension cannot be beyond thirty days. Even if the benefit of Section 14 of the Limitation Act is given to the respondent, there will still be a delay of 131 days in filing the application. That is beyond the strict timelines prescribed in sub-section (3) read along with the proviso to Section 34of the 1996 Act. The delay of 131 days cannot be condoned. To do so, as the High Court did, is to breach a clear statutory mandate."

    13. As regards exclusion of time for the period the petitioner was prosecuting his remedies before the other courts is concerned, I rely on the Division Bench decision of this Court in M/s Singhal Credit Management LLP v. M/s Religare Securities Ltd. & Anr., FAO (COMM) 34/2022, dated 24.03.2022, particularly paragraphs 2, 3.4 to 3.7, which read as under:-

    "2. However, before we proceed further, some important parameters need to be set forth, as enunciated in law, to decide the issue at hand :

    (i) Once limitation commences, it does not get

    4

    interrupted.

    (ii) The Limitation Act, 1963 (in short "the 1963 Act") is applicable to arbitration proceedings by virtue of Section 43 of the 1996 Act.

    (iii) The limitation period prescribed for filing a petition under Section 34 of the 1996 Act, is three [3] months. (iiia) Since the 1996 Act does not define the expression

    "month", the same will have the same meaning, as defined in Section 2(35) of the General Clauses Act, 1897. The said section provides that the expression

    "month" means a month reckoned according to the British calendar. Where the period prescribed is a calendar month running from an arbitrary date, it expires with the day in the succeeding month immediately preceding the day, corresponding to the date upon which the period starts, save and except where the period starts at the end of the calendar month which contains more days than the succeeding month, the period expires at the end of the latter month. [See Halsbury's Laws of England Volume 37 (third edition)]

    (iiib) However, the Supreme Court in the judgment rendered in State of H.P. v. Himachal Techno Engineers, (2010) 12 SCC 210, made the following observations with regard to how the terminal date of the three months timeframe should be ascertained : "18. Therefore when the period prescribed is three months (as contrasted from

    5

    90 days) from a specified date, the said period would expire in the third month on the date corresponding to the date upon which the period starts. As a result, depending upon the months, it may mean 90 days or 91 days or 92 days or 89 days."

    (iiic) The period of limitation commences from the date of receipt of the award, or if a request under Section 33 of the 1996 Act is made, the date on which the request is disposed of. Section 5 of the 1963 Act is not applicable to proceedings instituted under 34 of the 1996 Act. [See Union Of India v. Popular Construction Co. ., (2001) 8

    SCC 470.]

    (iv) Section 14 of the 1963 Act is applicable to Section 34 proceedings, preferred under the 1996 Act, provided the petitioner meets the requisite criteria i.e., the proceedings are prosecuted with due diligence, the matter in issue is the same, and was being taken forward in good faith in a court which could not have entertained it on account of a defect in the jurisdiction, or any other cause of like nature. [See Consolidated Engg. Enterprises v. Irrigation Deptt., (2008) 7 SCC 1692 .] ***

    3.4. In the instant case, the prescribed period of limitation [i.e., three months], commenced from 30.10.2012, and, therefore, even if the maximum leeway is given, the limitation would expire on 30.01.2013.

    6

    3.5. The petitioner, concededly, filed the Section 34 petition under the 1996 Act in the first instance, as noticed in the order dated 04.03.2022, only on 28.01.2013. This petition was instituted in the Court of District and Sessions Judge, Jaipur Metropolitan, in the State of Rajasthan [hereafter referred to as

    "Jaipur Court"].

    3.6. The Jaipur Court, however, returned the petition on 02.06.2018, while granting liberty to the petitioner to approach the Court of competent jurisdiction.

    3.7. The petitioner, thereafter, approached the District Judge (Commercial Court)-02, Patiala House Court at New Delhi [hereafter referred to as "Delhi Court"] and instituted a petition under Section 34 of the 1996 Act, only on 29.09.2018.

    4. Therefore, even if we were to exclude the time between, when the Section 34 petition was filed for the first time in the Jaipur Court i.e., 28.01.2013 and the date when the petition was returned by the said court i.e., 02.06.2018, it would not help the cause of the petitioner.

    4.1. The limitation period in the petitioner's case expired, on 04.06.2018."

    14. On perusal, under Section 9 of the Limitation Act, once the limitation period begins to run, no subsequent disability or inability to institute a suit or make an application stops it and under Section 14 of the Limitation Act, only the period spent bonafidely in pursuing litigation before a wrong forum is excluded.

    15. Hence, in the present case, the limitation period began from

    7

    20.09.2022 and the present petition was filed on 29.05.2025.

    16. As per Section 14 of the Limitation Act, the period from 03.01.2023 to 20.07.2024 and 21.08.2024 to 03.04.2025 is to be excluded. Even after excluding the said period, the petitioner has consumed more than 185 days in filing the petition before this Court.

    17. Even if the period of 30 days as granted by the Rohini District Court is excluded, the petitioner has still consumed more than 155 days in filing the petition before this Court.

    18. Hence, the petition is barred by limitation.

    19. However, it is the case of the petitioner that the arbitration proceedings are void ab initio as it is a case of unilateral appointment of arbitrator, which is impermissible in the light of the Hon'ble Supreme Court judgements in Perkins Eastman Architects DPC vs. HSCC (India) Limited, (2020) 20 SCC 760 and TRF Ltd. vs. Energo Engineering Projects Ltd., (2016) SCC OnLine SC 1928.

    20. The petitioner is at liberty to take these objections at the stage of execution of the arbitral award.

    21. For the said reasons, the petition is dismissed granting liberty as aforesaid.

    JASMEET SINGH, J

    JULY 25, 2025/DM

    (Corrected and released on 30.07.2025)

    8

    Use AI to get other relevant cases.

    Comments

    UNION OF INDIA  v. M/S GARG BUILDERS
    (Jul 25, 2025)