Court Opinion Summary — High Court at Calcutta (Circuit Bench at Jalpaiguri)

Factual and Procedural Background

These consolidated appeals (MAT/85/2023 through MAT/127/2023 and associated IAs) concern retired employees of Uttarbanga Kshetriya Gramin Bank ("the bank"). The appellants retired before the issuance of a notification dated 30 November 2018. On 30 November 2018 the bank's Board, with required consultations and sanctions, introduced the "Uttarbanga Kshetriya Gramin Bank Employees Pension Regulation, 2018", which was notified in the Gazette of India on 10 December 2018. The regulation fixed 1 April 2018 as the effective date for certain benefits and applied, as relevant here, to employees who retired on or before 30 March 2018 and who opted to become members of the Bank's Employees Provident Fund under Regulation 4.

The appellants claimed entitlement to pension benefits and commutation with effect from 1 April 2018 and sought interest for delayed payment of commuted pension. A learned Single Judge held that the appellants were entitled to interest on the delayed payment of commutation from 1 December 2018 to 31 January 2020 (interest at 8% p.a.), an order which the bank complied with and paid. However, the Single Judge disallowed the appellants' claim for payment of 1/3rd of monthly pension from 1 April 2018 on the ground that such payment would lead to double payment because the commuted lump sum had been calculated and paid later (in February 2020) using 1 April 2018 as the absolute date. The appellants appealed that portion of the order.

Legal Issues Presented

  1. Whether the appellants, who retired before the 30 November 2018 notification but opted into the scheme, were entitled to pension and commutation with effect from the regulation's effective date of 1 April 2018.
  2. Whether appellants are entitled to interest for delayed payment of the commuted value of pension (i.e., interest on the lump sum commutation paid belatedly).
  3. Whether the appellants were entitled to receive 1/3rd of monthly pension from 1 April 2018 up to the date of actual payment (and whether such payment would result in double payment given the later calculation and payment of the commuted value).

Arguments of the Parties

Appellants' Arguments

  • The Regulation, having fixed 1 April 2018 as the effective date, entitled the appellants to pension and commutation from that date; therefore commuted lump-sum payments should have been treated as payable from 1 April 2018.
  • Because the bank delayed releasing commutation, the appellants were entitled to interest on the commuted amount for the period between 1 April 2018 and the date of actual payment.
  • The learned Single Judge erred in denying payment of 1/3rd of monthly pension from 1 April 2018; the appellants relied on Regulation 39(9) and submitted that where an application for commutation was made in Form VI within one year from retirement and other conditions were satisfied, commutation became absolute from 1 April 2018.
  • The bank failed to forward option forms and was unable to create the pension fund within the prescribed period, causing delay for which the appellants should not be disadvantaged.

Respondent Bank's Arguments

  • The constitution of the pension fund was delayed for reasons beyond the bank's control; individual contributions were transferred in May 2019, and only from that date could entitlement for pension crystallize because the corpus was not in place earlier.
  • Although there was no obligation to pay pension for the earlier period, the bank nevertheless paid pension with effect from 1 April 2018 for employees' benefit.
  • The bank calculated and paid the commuted amount in February 2020 by using 1 April 2018 as the absolute date and reduced the pension as per Regulation 39(6); that calculation and payment were made in accordance with the regulations and implementation realities.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court heard the consolidated appeals together because they raised common questions. The reasoning focused on how entitlement to pension and commutation interacts with the practical requirement that a pension corpus must be created before benefits can be paid.

First, the Court acknowledged that the Regulation fixed 1 April 2018 as the effective or "absolute" date for the pension scheme. However, the court emphasized that the obligation of the bank to pay pension upon commutation under Regulation 39 (and related provisions) depended on the creation of the entire corpus of the fund. In the absence of full deposit of the corpus by the superannuated employees and related administrative steps, the fund could not be created and corresponding payments could not be operationally made.

Second, the Court took into account the difficulties the bank encountered in implementing the scheme. The bank faced substantial financial implications connected with exemption applications under the EPF Act and the process of obtaining exemption from the Regional Provident Fund Commissioner (the exemption was ultimately granted on 25 February 2020). The National Pension System for staff members was introduced on 24 May 2019 and the bank circulated the regulations and option forms around that time for collection.

Third, the Court noted that the bank calculated the commuted amount using 1 April 2018 as the absolute date (i.e., applying the regulation's date for calculating commutation and reducing the pension accordingly) and subsequently paid the commuted lump sum in February 2020. The writ petitioners had enjoyed the amounts paid and had also received interest on the lump sum payment pursuant to the Single Judge's order.

Given these factors, the Court concluded that the Single Judge's finding — disallowing a separate claim for payment of 1/3rd of monthly pension from 1 April 2018 to January 2020 because that would produce a double payment — was justified. The Court characterized the petitioners' grievance as, at most, a claim for delayed payment of pension for which they had already been compensated by the interest awarded by the Single Judge.

The Court also observed that the bank had complied with the Single Judge's order by making the required payments and interest.

Holding and Implications

DISMISSED — All the appeals and the connected applications were dismissed by the Court. The court declined to interfere with the order of the learned Single Judge.

Implications and consequences:

  • The Bank's compliance with the Single Judge's order (payment of commuted amounts and interest as directed) was noted and accepted by the Court.
  • The Court upheld the approach that, although the regulation fixed 1 April 2018 as the effective date, operational entitlements tied to a pension corpus depend on the corpus' creation and related administrative steps; delayed payment was compensated by interest rather than an independent additional back-payment of 1/3rd pension that would cause double payment.
  • No broader or new declaratory precedent was announced beyond the facts and reasoning applied to these consolidated matters; the decision affirms the Single Judge's order and directly affects the parties by dismissing the appeals. The Court ordered no costs ("there shall be no order as to costs").

Judges: Hon'ble Justice Soumen Sen and Hon'ble Justice Partha Sarathi Sen. Hearing concluded: 1 May 2024. Judgment delivered: 2 May 2024.

To access the original judgment, please Sign In or Subscribe.

    PARTHA SARATHI BISWAS AND ANR v. UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS

    IN THE HIGH COURT AT CALCUTTA

    CIVIL APPELLATE JURISDICTION

    CIRCUIT BENCH AT JALPAIGURI

    BEFORE: -

    The Hon'ble Justice Soumen Sen And

    The Hon'ble Justice Partha Sarathi Sen MAT/85/2023

    SUSHANTA ACHARJEE AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/86/2023

    RANJIT KUMAR SHOME AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/87/2023

    SWAPAN KUMAR CHOWDHURY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/88/2023

    DANESH CHAKRABORTY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/89/2023

    MOHINI MOHAN SAHA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    1

    2

    AND

    MAT/90/2023

    SUKRAJ KUMAR BASU AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/91/2023

    SANTI RANJAN SAHA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/92/2023

    TAPAS KUMAR DEB AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/93/2023

    SWAPAN KUMAR BHATTACHARYA AND ANR.

    VS.

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/94/2023

    PRANESH SARKAR AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/95/2023

    SANDIP BHATTACHARJEE AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    3

    MAT/96/2023

    SIKHA BANIK AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/97/2023

    SAMPA CHAKRABORTY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/98/2023

    SHILA GHOSH AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/99/2023

    ARUN KUMAR BHATTACHARYYA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/100/2023

    SHUVAPADA CHAUDHURI AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/101/2023

    BARUN KUMAR SAHA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    4

    MAT/102/2023

    SANKAR DUTTA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/103/2023

    DINES CHANDRA LASKAR AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/104/2023

    KABERI SARKAR (BASU) AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/105/2023

    ASIM DAS AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/106/2023

    BARUN KUMAR CHANDA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/107/2023

    PHANI BHUSAN ROY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    5

    MAT/108/2023

    ABHIJIT MAULIK AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/109/2023

    ANANYA DEY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/110/2023 PANGANATH ROY @ PANGA NATH ROY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/111/2023

    DILIP KUMAR BARMAN AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023

    AND

    MAT/112/2023

    BRAJESHWAR MALLICK AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/113/2023

    PINAKI RANJAN CHAKRABORTY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    6

    MAT/114/2023

    DEBABRATA GHOSH DASTIDAR AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/115/2023

    ASHOK KUMAR CHOWDHURY AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/116/2023

    ASIM BISWAS AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/117/2023

    ARABINDA SIDDHANTA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/118/2023

    PARTHA SARATHI BISWAS AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/119/2023

    RABINDRA HARI KARJEE AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    7

    MAT/120/2023

    TARUN KUMAR MANTA AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/121/2023

    SAMIR RANJAN SARKAR AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/123/2023

    SUDIP SANYAL AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023

    AND

    MAT/127/2023

    MOUMITA BARMAN KAR AND ANR.

    VS

    UTTARBANGA KSHETRIYA GRAMIN BANK AND ORS.

    IA NO: CAN/1/2023, CAN/2/2023 For the Appellants : Mr. Jagriti Mishra, Adv. Ms. Ananya Bhattacharya, Adv.,

    Mr. Raj Kumar Mitra, Adv.,

    Ms. Mrinmayee Das, Adv.,

    For the Opposite Party : Mr. Chitra Bhanu Gupta, Adv., Ms. Supriya Singh, Adv.,

    Hearing concluded on : 1stMay, 2024

    Judgment on : 2ndMay, 2024

    8

    Soumen Sen, J.:

    1. The appeals and the applications are heard together as they involve common questions of law and fact and disposed of by this common order.

    2. The appellants were employees of Uttarbanga Kshetriya Gramin Bank (in short, 'the bank'). They retired from service prior to issuance of the notification dated 30thNovember, 2018.

    3. On 30thNovember, 2018 the Board of Directors of the said bank in exercise of the power conferred by Section 30 read with sub-Section (1) of Section 17 of the Regional Rural Banks Act, 1976 after consultation with the Central Bank of India being the sponsor bank and the National Bank and with the previous sanction of the Central Government introduced Uttarbanga Kshetriya Gramin Bank Employees Pension Regulation, 2018. It was notified in the gazette of India on 10thDecember, 2018. The said regulation applied to three different categories of employees and in so far as the present writ petitioners are concerned they come under the category of employees who retired from service on or before 30thMarch, 2018 and opted to become a member of Uttarbanga Kshetriya Gramin Bank Employees Provident Fund constituted under Regulation 4.

    4. The principal issue raised in this appeal is with regard to the payment of pension with effective date upon commutation of pension.

    5. Before the learned Single Judge the appellants urged that in terms of the relevant provisions of the said Regulation 2018 they would be

    9

    entitled to pension with effect from 1stApril, 2018 and such calculation would be based on the methodology mentioned in the said regulation for commutation of pension. The benefit of such pension was extended to the appellants in the month of February, 2020, however, the amount which has been monthly commuted for lump sum payment towards commutation of pension should have been paid to the writ petitioners from 1stApril, 2018 till the date of actual payment and due to delay in releasing the commutation of pension in terms of the regulations of 2018 the appellants are entitled to get interest on commutation of pension.

    6. Although the claim was resisted before the learned Single Judge by the respondent bank the learned Single Judge observed that since commutation of pension was paid from February, 2020 and it ought to have been paid just after the issuance of the notification dated 30thNovember, 2018, the writ petitioners would be entitled to get interest on delayed payment of commutation to which writ petitioners are entitled from 1stApril, 2018. The relevant notification was issued on 30thNovember, 2018 and not on 1stApril, 2018 and therefore, the period from 1stApril, 2018 till 30th November, 2018 needs to be condoned while considering the claim for interest for delay in releasing commutation of pension. Accordingly, the learned Single Judge directed the authorities concerned to pay interest at the rate of 8 per cent per annum on commutation of pension that was released in favour of the writ petitioners for the period from 1stDecember, 2018 till

    10

    31stJanuary, 2020. The respondent bank has accepted the said order and paid the said interest.

    7. However, the writ petitioners are aggrieved by the other directions in the impugned order by which the contention of the petitioners for payment of 1/3rdPension which has been commuted for payment of pension in terms of the Regulation of 2018 was disallowed on the ground that the direction for payment of any further amount to the extent of 1/3rdof the monthly pension for the period from April, 2018 till January, 2020 would lead to double payment.

    8. The learned Single Judge in arriving at the said conclusion was of the view that the respondent authorities on calculation from 1stApril, 2018 in terms of the regulation of 2018 calculated the commuted value of pension and released the same in the month of February, 2020 and the claim of the appellant can at best be for delayed payment of pension and not for payment of 1/3rdpension from 1stApril, 2018 as it would in effect would lead to double payment of 1/3rdof pension from 1stApril, 2018 till January,

    2020.

    9. The leaned Counsel on behalf of the appellants has submitted that the learned Single Judge has misconstrued the scope of the Regulation and the benefits to which the superannuated employees would be entitled to under the said Regulation. The release for the 1/3rdcommuted value from 1st April, 2018 cannot be escaped and denied by the respondents as the notification has fixed 1stApril, 2018 as the effective date. The bank was

    11

    unable to create the fund within the period prescribed under the Regulations and did not forward the option forms to the interested and willing employees to avail the benefit of pension under the said scheme. Even after the commuted amount was paid there has been an unreasonable delay on the part of the respondent bank to release the pension in terms of the regulation.

    10. It is submitted that in terms of Regulation 39(9) the superannuated employees who opted to become member of the fund under the said Regulations on 1stApril, 2018 and where the application of commutation was made in form VI within one year from the date of retirement would be entitled to commutation of pension from 1stApril, 2018 as the commutation of pension become absolute under the aforesaid sub- regulation on fulfillment of the aforesaid criteria.

    11. Per contra the learned Counsel for the respondents banks has submitted that there has been a delay in the constitution of the pension fund for the reasons beyond the control of the bank inasmuch as the writ petitioners transferred their contribution in May, 2019 and on and from that date only they became eligible to pension.

    12. Although there was no obligation on the part of the bank to release pension for the earlier period, however, taking into consideration the effective date as 1stApril, 2018 for the benefit of its employees pension was paid with effect from 1stApril, 2018. The appellants received the commuted value along with arrears since 1stApril, 2018 even if the notification was issued on 30thNovember, 2018.

    12

    13. It is submitted that this pension scheme was introduced for the benefit of the superannuated employees and although they were not eligible for the commuted value of the pension prior to their depositing the entire corpus which was admittedly made in May, 2019.

    14. Moreover, if commutation of pension were to be paid to the writ petitioners considering the absolute date that is 1stApril, 2018 then as per regulation the reduction of amount in pension on account of commutation shall become operative from its inception, that is, 1stApril, 2018.

    15. In the aforesaid backdrop the claim of the appellants needs to be considered.

    16. The requirement of the respondent bank to pay pension upon commutation in terms of Regulation 39 read with the other regulations in our view would be dependent upon the entire corpus being deposited by the superannuated employees as in absence of any such deposit the corpus of fund could not be created. It is no doubt that they would be entitled for pension if they fulfil all the conditions which had inter alia, include exercise of option but unless the corpus is created and deposits are made by the individual willing retired employees they cannot get the benefit of retrospective effect of the notification.

    17. Moreover, the difficulties explained by the bank in implementing the said scheme needs to be considered. The bank faced various difficulties at the time of creation of the fund as it involves huge financial implication inasmuch as the application for exemption from the Regional Provident Fund

    13

    Commissioner, Jalpaiguri under Section 17(1), 17(1)(C) of EPF Act, 1952 was pending. The exemption was ultimately granted on 25thFebruary, 2020.

    18. It appears that the National Pension System for staff members was introduced on 24thMay, 2019 and prior thereto all the branches were informed to circulate the regulations to collect option forms from the staffs.

    19. The bank relying on the provisions of the relevant regulations calculated the commuted amount of pension considering 1/3rdof basic pension of the writ petitioner multiplied by the age of the writ petitioners as on 1stApril, 2018 being the absolute date and reduction was made accordingly as per clause 6 of Section 39 and was ultimately paid.

    20. The writ petitioners have enjoyed the entire amount till it was actually deposited although they got the benefit with retrospective effect and over and above the same they have also received interest on the lump sum amount paid to them towards commuted value in terms of the order of the learned Single Judge.

    21. In the aforesaid circumstances, we are of the view that the finding of the learned Single Judge that the writ petitioners would not be entitled to payment of 1/3rdof pension on April, 2018 till January, 2022 is justified. In fact, simply put it could be seen as a delayed payment of pension for which the writ petitioners have been duly compensated by payment of interest.

    22. The bank has already complied with the order of the learned Single Judge.

    14

    23. On such consideration we do not find any reason to interfere with the order passed by the learned Single Judge.

    24. All the appeals and the connected applications are accordingly dismissed.

    25. However, there shall be no order as to costs. I agree (Soumen Sen, J.)