  • Section 24 of the 2013 Act
  • Section 16 of the 1894 Act
  • Section 24(2) of the Act, 2013
  • Section 24(2) of the 2013 Act
  • Section 4 of the 1894 Act
  • Section 34 of the said Act
  • Section 31 of the Land Acquisition Act, 1894
  • Section 24(1)(b) of the 2013 Act
  • Section 24(1)(a) of the Act, 2013
  • Section 31(1) of the 1894 Act
  • Section 24(1)(b) of the Act, 2013
  • Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2023 INSC 165
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 24 of the 2013 Act
  • Section 16 of the 1894 Act
  • Section 24(2) of the Act, 2013
  • Section 24(2) of the 2013 Act
  • Section 4 of the 1894 Act
  • Section 34 of the said Act
  • Section 31 of the Land Acquisition Act, 1894
  • Section 24(1)(b) of the 2013 Act
  • Section 24(1)(a) of the Act, 2013
  • Section 31(1) of the 1894 Act
  • Section 24(1)(b) of the Act, 2013
  • Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The Delhi Development Authority (“DDA”) challenged a judgment of the High Court of Delhi in Writ Petition (C) No. 3561 of 2015. The High Court had declared that the acquisition of the land in question had “deemed to have lapsed” under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“the 2013 Act”). In its counter-affidavit before the High Court, the DDA asserted that possession of the land had been taken over and handed to the beneficiary department on 23 September 1981, and that compensation had been sent to the Revenue Deposit owing to a dispute. Despite these assertions, the High Court—relying on Pune Municipal Corporation v. Harakchand Misirimal Solanki—held the acquisition to have lapsed because compensation had not been paid to the owners in the manner prescribed by law. The DDA appealed that decision to the Supreme Court.

Legal Issues Presented

  1. Whether an acquisition can be deemed to have lapsed under Section 24(2) of the 2013 Act when possession has been taken but the compensation has not been paid directly to the landowners.
  2. Whether the High Court’s reliance on Pune Municipal Corporation v. Harakchand Misirimal Solanki remains good law in light of the later Constitution Bench judgment in Indore Development Authority v. Manoharlal.

Arguments of the Parties

Delhi Development Authority (Appellant)

  • Possession of the subject land was taken on 23 September 1981 and handed to the beneficiary department.
  • Compensation was tendered and sent to Revenue Deposit owing to disputes, satisfying the requirement of Section 31 of the Land Acquisition Act, 1894.
  • Under Indore Development Authority v. Manoharlal, lapse occurs only if both possession has not been taken and compensation has not been paid; therefore, the High Court’s declaration of lapse is contrary to binding precedent.

Landowners/Respondents

  • Relied on Pune Municipal Corporation v. Harakchand Misirimal Solanki to contend that compensation had not been paid “in the manner known to law,” thereby triggering a deemed lapse under Section 24(2) of the 2013 Act.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Indore Development Authority v. Manoharlal, (2020) 8 SCC 129 Section 24(2) causes a deemed lapse only when both conditions—(i) possession not taken and (ii) compensation not paid/tendered—are concurrently satisfied. The word “or” in Section 24(2) is to be read as “and”. The Supreme Court applied this binding Constitution Bench ruling to hold that, because possession had been taken, the acquisition could not lapse even if compensation had not been received by the landowners.
Pune Municipal Corporation v. Harakchand Misirimal Solanki, (2014) 3 SCC 183 Earlier view that non-payment of compensation alone could trigger a deemed lapse under Section 24(2). The High Court relied on this case; the Supreme Court overruled that reliance, noting that Pune Municipal Corporation stands impliedly overruled by the later Constitution Bench judgment in Indore Development Authority.

Court's Reasoning and Analysis

The Supreme Court noted that the High Court’s conclusion was “just contrary” to the law laid down in Indore Development Authority v. Manoharlal. Quoting paragraph 366 of that Constitution Bench judgment, the Court emphasised that:

  • Lapse under Section 24(2) occurs only when both possession has not been taken and compensation has not been paid for a period of five years preceding 1 January 2014.
  • Once possession is taken, the land vests in the State and cannot be divested by Section 24(2).
  • Tendering compensation is sufficient to meet the statutory obligation; refusal or dispute by landowners does not create a lapse.

Applying these principles, the Court found that possession had indisputably been taken in 1981 and that compensation had been tendered (albeit deposited in Revenue Deposit). Consequently, one of the twin conditions for lapse was absent, and the High Court’s judgment could not stand.

Holding and Implications

Appeal Allowed; High Court judgment quashed and set aside. The acquisition of the land in question has not lapsed.

Direct Implications: The land remains vested in the Delhi Development Authority, and the landowners cannot claim lapse under Section 24(2). No costs were awarded. The decision does not set a new precedent but reaffirms the binding authority of Indore Development Authority v. Manoharlal over earlier conflicting rulings.

To access the original judgment, please Sign In or Subscribe.

    DELHI DEVELOPMENT AUTHORITY v. RAJENDER SINGH

    M.R. Shah, J.:— Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 3561 of 2015, by which, the High Court has allowed the said writ petition and has declared that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Delhi Development Authority has preferred the present appeal.

    2. Having heard learned counsel appearing on behalf of the respective parties and having gone through the impugned judgment and order passed by the High Court and even the counter affidavit filed before the High Court by the Delhi Development Authority wherein it was the specific case on behalf of the respondent therein that the possession of lands in question was taken over and handed over to the beneficiary department on 23.09.1981 and the compensation with respect to the said lands was sent in RD due to dispute.

    3. However, thereafter despite the above and relying upon the earlier decision of this Court in the case of Pune Municipal Corporation v. Harakchand Misirimal Solanki, (2014) 3 SCC 183, the High Court has declared that the acquisition with respect to the lands in question is deemed to have lapsed under Section 24(2) of the Act, 2013 solely on the ground that the compensation was not paid in the manner known to law to the land owners.

    4. The view taken by the High Court is just contrary to the law laid down by this Court in the case of Indore Development Authority v. Manoharlal, (2020) 8 SCC 129. In paragraph 366, the Constitution Bench of this Court has observed and held as under:—

    “366. In view of the aforesaid discussion, we answer the questions as under:

    366.1. Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act.

    366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed.

    366.3. The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.

    366.4. The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act.

    366.5. In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or non-deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act.

    366.6. The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b).

    366.7. The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2).

    366.8. The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years.

    366.9. Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.”

    5. Thus, as per the law laid down by this Court in the case of Indore Development Authority (supra) for deemed lapse under Section 24(2) of the Act, 2013, twin conditions, namely, (i) the possession is not taken and (ii) the compensation is not tendered/paid are to be satisfied and if one of the conditions is not satisfied there shall not be any lapse or deemed lapse under the Act, 2013.

    6. Applying the law laid down by this Court in the case of Indore Development Authority (supra), the impugned judgment and order passed by the High Court is unsustainable and the same deserves to be quashed and set aside and is accordingly quashed and set aside. There shall be no deemed lapse of the acquisition with respect to the lands in question.

    7. Present appeal is accordingly allowed. No costs.