ORDER
1. Mr. Proteek Debnath, learned Counsel for the applicant is present in Court.
2. The applicant in this Original Application No.73/2022/EZ is seeking quashing of the Impugned Order dated 12.05.2021 whereby the State Government has rejected the application of the applicant for to operate the Ghuma Ghusua Black Stone Quarry in Athgarh Forest Division Cuttack District on the ground that the quarry along with the project road and the parking zone to the quarry fall within the Eco-Sensitive Zone of Kapilash Wild Life Sanctuary and stone quarrying is a prohibited activity in the eco- sensitive zone.
3. From the documents on record, we find that the applicant has not filed the Environmental Clearance granted by the MoEF & CC/SEIAA, Odisha required for operating a Black Stone Quarry; even averments to that effect are not there in any paragraph of the Original Application No.73/2022/EZ, stating that Environmental Clearance was granted to the applicant. All that has been stated is that Stage-I and Stage-II Forest Clearance were granted for diversion of 4.9 hectares of Forest Land in the Baniabandha Reserve Forest in Athgarh Forest Division but those documents have also not been filed with this Original Application.
4. The learned Counsel has referred to Annexure A-3 Page-31 of the Original Application wherein the Divisional Forest Officer, Athgarh has stated that the project has got consent of the Odisha Pollution Control Board. Regarding Environmental Clearance it is stated that since the project is at distance of 5(five) kilometers from the
2
Kapilash Wild Life Sanctuary, accordingly, the proposal along with Part-I, II, III for National Board for Wild Life Clearance has already been submitted to the Divisional Forest Officer, Dhenkanal vide letter dated 08.05.2014 and forwarded to the Regional Chief Conservator of Forest Angul vide letter 26.08.2014 and also to the Principal Chief Conservator of Wild Life , Odisha vide letter dated
10.10.2014.
5. This shows that as of today the applicant does not have Environmental Clearance granted by the MoEF & CC/SEIAA, Odisha. The impugned order of 12.05.2021 also indicates that the applicant does not have the requisite wild life clearance from the Standing Committee of the National Board for Wild Life (NBWL).
6. The learned Counsel for the applicants submits that as per the Odisha Space Application Centre report, the quarry and approach road does not fall within the Eco-sensitive zone. In our opinion this question can only be examined by the MoEF & CC and the State Government of Odisha. The petitioner is at liberty to approach the State Government of Odisha, Respondent No.2 & 3.
7. For reasons stated above, we do not find any merit in the Original Application No. 73/2022/EZ, and the same is accordingly dismissed.
.....................................
B. Amit Sthalekar, JM
...................................
Saibal Dasgupta, EM
July 13, 2022, Original Application No.73/2022/EZ
BD