Factual and Procedural Background

A batch of consumer complaints was filed before the National Consumer Disputes Redressal Commission (NCDRC) by the Capital Greens Flat Buyers Association and individual purchasers against a real-estate developer. The complainants alleged substantial delay in handing over possession of their apartments and challenged the developer’s recovery of car-parking and club charges. The developer invoked the force majeure clause, citing (i) delay in approval of building plans and (ii) stop-work orders issued following fatal accidents at the site. On 3 January 2020, NCDRC rejected the force majeure defence and passed diverse directions including compensation at 7% p.a. for the delay and refund of parking and club charges. The developer appealed to the Supreme Court.

Legal Issues Presented

  1. Whether the developer’s plea of force majeure—based on delayed plan approvals and stop-work orders—absolved it from liability for delay in handing over possession.
  2. Whether NCDRC correctly awarded compensation at 7% p.a., or whether compensation should be confined to the contractual rate of Rs 10 per sq. ft. per month (or otherwise reduced).
  3. Whether the developer was liable to refund car-parking and club charges along with interest, in light of the Supreme Court’s earlier judgment in Arifur Rahman Khan.

Arguments of the Parties

Appellant (developer)

  • Force majeure conditions—delay in plan approvals and stop-work orders due to site accidents—prevented timely completion.
  • Offered “exit” options twice, refunding consideration with 9% interest; 45% of buyers have sold their flats and enjoyed capital appreciation.
  • Agreements stipulate compensation of Rs 10 per sq. ft. per month; hence the 7% p.a. award is excessive and undifferentiated.
  • Reliance on Arifur Rahman Khan to contend that directions to refund parking and club charges with interest are unsustainable.

Respondents (flat buyers)

  • NCDRC correctly found no cogent evidence to substantiate force majeure; delays in approvals are normal incidents of construction and cannot excuse performance.
  • Exit offers do not meet the needs of genuine home-buyers who seek possession, not merely a monetary return.
  • Contractual compensation of Rs 10 per sq. ft. is inadequate; substantial delay warrants interest-based compensation.
  • Left the question of parking and club charges to the Court’s discretion in view of Arifur Rahman Khan.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Arifur Rahman Khan v. DLF Southern Homes (P) Ltd. (2020) 16 SCC 512 Guidance on refund of parking and club charges; compensation rate of 6% p.a. in similar delay context. Used to set aside NCDRC’s direction to refund parking and club charges and to moderate compensation from 7% to 6% p.a.
Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan (2019) 5 SCC 725 Principles governing compensation for delay to genuine home-buyers even where refund offers exist. Cited to affirm that flat purchasers are entitled to compensation notwithstanding refund options, and that contractual rates may be inadequate.

Court's Reasoning and Analysis

Force majeure defence: The Court affirmed NCDRC’s factual findings that (a) no cogent evidence supported alleged delays in plan approvals, and (b) stop-work orders resulted from the developer’s own safety lapses. Such circumstances are neither unforeseeable nor beyond the developer’s control; therefore, the force majeure clause does not apply.

Compensation for delay: Guided by Pioneer Urban and Arifur Rahman Khan, the Court reiterated that genuine home-buyers seek possession, and a mere refund is inadequate. While acknowledging the contractual rate of Rs 10 per sq. ft., it found this insufficient given Delhi’s higher real-estate values. Balancing equities, the Court reduced the interest component from 7% to 6% p.a., directing adjustment of any amounts already paid under the contractual formula.

Parking and club charges: Applying the ratio in Arifur Rahman Khan, the Court ruled that NCDRC’s order directing refund of these charges (with interest) cannot stand and therefore quashed that part of the relief.

Holding and Implications

PARTLY ALLOWED. The Supreme Court upheld NCDRC’s order except for two modifications:

  • Compensation for delay reduced from 7% to 6% simple interest per annum, subject to adjustment for any contractual compensation already paid.
  • Directions to refund parking and club charges, and the corresponding interest, are set aside.

All other directions of NCDRC remain operative. The developer must comply within two months. The ruling primarily affects the parties; it refines, but does not create new, precedent on compensation and ancillary charges in real-estate consumer disputes.

    Dlf Home Developers Limited (earlier Known As Dlf Universal Limited) And Another v. Capital Greens Flat Buyers Association And Others

    Order

    1. These appeals arise from a judgment of the National Consumer Disputes Redressal Commission dated 3-1-2020 2020 SCC OnLine NCDRC 3 in a batch of consumer complaints. The complaints were instituted inter alia by an association representing flat purchasers, called the Capital Greens Flat Buyers Association and by individual flat purchasers against the appellant. The gist of the grievance was that there was a substantial delay on the part of the developer in handing over possession of the apartments which were contracted to be sold. The complainants also specifically challenged the recovery of parking and club charges by the developer. A claim for compensation for delay in handing over possession of the flats was made.

    2. The appellants in their defence to the complaints inter alia contended that as a result of force majeure conditions, they were prevented from achieving timely completion of their contractual obligations. The circumstances which according to the appellants triggered the force majeure clause of the agreements with flat buyers were:

    (i) delay in the approval of building plans; and
    (ii) issuance of stop-work orders as a result of fatal accidents during the course of construction.

    Ncdrc has, after a detailed evaluation of the facts, rejected the force majeure defence.

    3. While allowing the complaints, Ncdrc has issued the following directions in para 49 of its impugned decision 2020 SCC OnLine NCDRC 3: (Capital Greens Flat Buyer Assn. case 2020 SCC OnLine NCDRC 3, SCC OnLine Ncdrc)

    “49. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
    (i) The OP is entitled to the additional demand on account of increase in the super area of the apartments.
    (ii) The OP is not entitled to car parking charges.
    (iii) The OP is not entitled to club charges.
    (iv) The allottees shall be entitled to early payment rebate and timely payment rebate, wherever they have complied with the terms on which the said rebates were offered by the developer or wherever the benefit of the said rebates was extended to them, either by the developer itself or by this Commission.
    (v) The OP shall pay compensation in the form of simple interest @ 7% p.a. from the expected date for delivery of possession till the date on which the possession was actually offered to the allottees. In case of subsequent purchasers, the period expected for the delivery of possession will be computed from the date of purchase by them.
    If the possession was delayed solely on account of the allottee having not executed the indemnity-cum-undertaking, prescribed by the OP, the compensation in the form of simple interest @ 7% p.a. shall be payable with effect from the expected date for delivery of possession till the date on which the consumer complaint by/on behalf of such an allottee was instituted. The compensation shall be paid within a period of three months from today.
    (vi) The car parking charges and club charges wherever already paid to the developer shall be refunded to the allottee concerned within three months from today, failing which the said charges shall carry interest @ 9% p.a. from the date of this order, till the date of refund.
    (vii) The conveyance deed in favour of the allottees shall be executed within three months from today, subject to payment of outstanding dues, if any, payable by the allottees to the developer, in terms of this order and the requisite stamp duty and registration charges.
    (viii) In CC/351/2015 and CC/2047/2016, the developer shall pay Rs 50,000 as the cost of litigation in each complaint, whereas in the other consumer complaints, the developer shall pay Rs 46,000 as the cost of litigation in each complaint.”

    4. Mr Pinaki Misra, learned Senior Counsel appearing on behalf of the appellants submits that in view of the recent judgment of this Court in Arifur Rahman Khan v. DLF Southern Homes (P) Ltd. (2020) 16 SCC 512, the direction for the refund of parking and club charges together with interest would have to be set aside. This decision was in the context of a consumer dispute in relation to another project of the same developer, in Bengaluru. The present dispute relates to a construction project in Delhi. Apart from this, it has been urged that force majeure conditions at the site occasioned the delay. Laying stress on the conduct of the developer in the present case, and to establish its bona fides, it was submitted that:

    4.1. Exit offers were given to the flat buyers on two occasions when the developer became aware of the fact that there was a delay beyond the contractual period of thirty-six months and the purchasers were offered refunds of the consideration together with interest @ 9% p.a.

    4.2. 45% of the flat buyers in the project have sold away their apartments.

    4.3. The flat buyers have the benefit of an appreciation in the capital value of the apartments purchased.

    4.4. The developer has extended the benefit of other contractual terms, such as timely payment and goodwill rebates to the flat purchasers.

    5. Moreover, the learned Senior Counsel submits that the flat buyer agreements provide compensation of Rs 10 per square foot per month towards compensation. Hence, it was urged that apart from the force majeure defence, the award of compensation @ 7% on account of the delay of the developer is erroneous. It has been submitted that Ncdrc has not distinguished between the facts of individual cases.

    6. Responding to the above submissions, Mr Shyam Divan, learned Senior Counsel appearing on behalf of the respondent submitted that Ncdrc has carefully evaluated the grounds which were set up in support of the force majeure defence. Hence, there is no need for this Court to interfere with a finding which is borne out from the evidentiary record. On the aspect of compensation for delay, it has been urged that the Tribunal took due notice of the fact that the developer had offered exit options to the flat purchasers, and that it was justified in coming to the conclusion that the offer of a refund of consideration together with interest did not subserve the needs of particularly those flat buyers who entered into the project not as investors, but as genuine flat buyers. Hence, it has been submitted that the direction against the appellant for the payment of compensation is justified since there is admittedly a substantial delay in the completion of the project. Mr Divan urged that an omnibus contention that several flat buyers in the project have sold their apartments should not prevent the complainants from receiving the benefit of the compensation which has been awarded by Ncdrc, particularly in a situation where the contractual rate of Rs 10 per square foot provides inadequate recompense. On the aspect of parking and club charges, Mr Divan has fairly submitted that the Court may take an appropriate view of the matter having regard to its decision dated 24-8-2020 in Arifur Rahman Khan (2020) 16 SCC 512.

    7. At the outset, we must deal with the force majeure defence. Ncdrc has carefully evaluated the basis on which the defence was set up and has come to the conclusion that there is no cogent evidence in regard to the nature of the delay and the reasons for the delay in the approval of the building plans. Quite apart from this finding of fact, it is evident that a delay in the approval of building plans is a normal incident of a construction project. A developer in the position of the appellant would be conscious of these delays and cannot set this up as a defence to a claim for compensation where a delay has been occasioned beyond the contractually agreed period for handing over possession. As regards the stop-work orders, there is a finding of fact that these were occasioned by a succession of fatal accidents which took place at the site and as a result of the failure of the appellant to follow safety instructions. This is a pure finding of fact. There is no error of law or fact. Hence, we find no substance in the force majeure defence.

    8. On the compensation for delay in handing over of possession, this Court is guided by the principles which have been formulated in the judgment in Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan (2019) 5 SCC 725, delivered by one of us (Hon'ble Indu Malhotra, J.). The judgment in Pioneer Urban Land & Infrastructure Ltd. (2019) 5 SCC 725 was cited in Arifur Rahman Khan (2020) 16 SCC 512 rendered on 24-8-2020. The fact that the developer offered an exit option with interest at 9% would not disentitle the flat purchasers from claiming compensation. For a genuine flat buyer, who has booked an apartment in the project not as an investor or financier, but for the purpose of purchasing a family home, a mere offer of refund would not detract from the entitlement to claim compensation. A genuine flat buyer wants a roof over the head. The developer cannot assert that a buyer who continues to remain committed to the agreement for purchase of the flat must forsake recourse to a claim for compensation occasioned by the delay of the developer. Mere refund of consideration together with interest would not provide a just recompense to a genuine flat buyer, who desires possession and remains committed to the project. It was for each buyer to either accept the offer of the developer or to continue with the agreement for purchase of the flat.

    9. Similar is the position in regard to the submission on the appreciation of the value of the flats. Undoubtedly, this is one factor which has to be borne in mind in considering whether and, if so to what extent, compensation for delay should be awarded. Having regard to the principles which have been enunciated in the earlier two decisions (2020) 16 SCC 512 (2019) 5 SCC 725 which have been noted above, we are unable to subscribe to the submission that the flat buyers are not entitled to any payment whatsoever on account of delayed compensation.

    10. Mr Misra submitted that in the present case, the agreement provided for compensation @ Rs 10 per square foot as distinct from the agreement in the decision of this Court in Arifur Rahman Khan (2020) 16 SCC 512 where the contractual compensation was @ Rs 5 per square foot per month. Hence, it was submitted that no compensation over and above the contractual rate should be allowed. Alternatively, it was urged that in the present case if the Court is inclined to award compensation, it should be brought down to a 6% p.a. (or even less) which was awarded in the above case.

    11. It is true that in the present case, the contractual rate of Rs 10 per square foot per month is double the rate fixed in the agreements in the above case. On the other hand, the Court must be conscious of the fact that the situation in the real estate market in Delhi is very distinct from that in Bengaluru both in terms of rentals and land values. This has not been disputed. The flat buyers had to suffer on account of a substantial delay on the part of the appellants. In such a situation, they cannot be constrained to the compensation of Rs 10 per square foot provided by the agreements for flat purchase. However, having regard to all the facts and circumstances, we are of the view that the compensation on account of delay should be brought down from 7% to 6%. Moreover, the amount, if any, which has been paid in terms of the contractual rate shall be adjusted while computing the balance due and payable in terms of the judgment. (In the earlier decision noted above, compensation at 6% was ordered to be paid in addition to the contractual rate since the amenities agreed to be provided by the developer had not been set up).

    12. Insofar as the parking and club charges are concerned, in view of the decision of this Court in Arifur Rahman Khan (2020) 16 SCC 512, the direction of Ncdrc in that regard shall stand set aside.

    13. Accordingly, we allow the appeals in part to the following extent:

    13.1. The compensation on account of delay in handing over possession of the flats to the flat buyers is reduced from 7% to 6%.

    13.2. The direction for the refund of parking charges and club charges and interest on these two components shall stand set aside.

    14. We clarify that the directions of Ncdrc are upheld, save and except, for the above two modifications in terms of paras 13.1 and 13.2 above. The payment @ 6% p.a. shall be made after making due adjustments for the compensation for delay at the contractual rate (where it has been paid in terms of the agreement to the flat purchasers). The order shall be complied with within a period of two months from today.

    15. The civil appeals are partly allowed in the above terms.

    16. Pending applications, if any, stand disposed of.

    IA No. 128417 of 2020 in Civil Appeals Nos. 3864-89 of 2020

    17. The interlocutory application recites that settlements have been entered into with two sets of flat buyers. In view of the settlements, two sets of flat buyers, namely, Sharad Mittal (CC/410/2015) and Chetali Goyal and Deepak Goyal (CC/1751/2016) shall be treated as pro forma respondents. They shall be governed by their own settlements.