2022 INSC 336
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 31(6) of the Act (Maharashtra Regional and Town Planning Act, 1966)
  • Section 127 of the Land Acquisition Act, 1894
  • Constitution of India (Articles 141, 142, and 144)
  • Maharashtra Act 42 of 2015
  • Section 126 of the Maharashtra Regional and Town Planning Act, 1966
  • Section 126 of the Act
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2022 INSC 336
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 31(6) of the Act (Maharashtra Regional and Town Planning Act, 1966)
  • Section 127 of the Land Acquisition Act, 1894
  • Constitution of India (Articles 141, 142, and 144)
  • Maharashtra Act 42 of 2015
  • Section 126 of the Maharashtra Regional and Town Planning Act, 1966
  • Section 126 of the Act
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

A final Development Plan for Latur, including Reservation Site No. 217 earmarked for a playground, was published on 2 January 2002 and came into force on 18 February 2002. The appellants purchased portions of the reserved land on 21 November 2002. For ten years no steps were taken to acquire the land. On 16 August 2016 the appellants served a notice under Section 127 of the Maharashtra Regional and Town Planning Act, 1966, calling upon the Municipal Corporation to acquire the property within one year. No acquisition occurred.

The appellants filed a writ petition in the Bombay High Court seeking a declaration that the reservation had lapsed and that their land was released for residential use. The High Court ruled on 6 August 2021 that the reservation had indeed lapsed but granted the Planning Authority an additional one-year period to acquire the land, relying on Municipal Corpn., Greater Mumbai v. Hiraman Sitaram Deorukhar (2019) 14 SCC 411. The landowners alone appealed to the Supreme Court, challenging the extra year granted for acquisition.

Legal Issues Presented

  1. Whether a court can grant an additional period for acquisition of land beyond the statutory timelines prescribed in Sections 126 and 127 of the Maharashtra Regional and Town Planning Act, 1966.
  2. Whether the High Court’s reliance on Municipal Corpn., Greater Mumbai v. Hiraman Sitaram Deorukhar to allow an extra year constitutes a binding precedent that overrides the statutory scheme.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Municipal Corpn., Greater Mumbai v. Hiraman Sitaram Deorukhar (2019) 14 SCC 411 The Court, exercising Article 142 powers, had directed acquisition of land reserved for a public park within six months. The Supreme Court clarified that this direction was fact-specific, issued under Article 142, and does not constitute a binding precedent permitting courts to extend statutory acquisition periods.
Bangalore Medical Trust v. B.S. Muddappa (1991) 4 SCC 54 Land reserved for a public park cannot be converted to other public purposes; authorities act as trustees of such land. Cited to explain the limited context in which courts may intervene to preserve park land; distinguished from the present case where the issue was delay in acquisition, not change of use.

Court's Reasoning and Analysis

The Supreme Court noted that Sections 126 and 127 of the Maharashtra Act fix a strict timeline: ten years for the Planning Authority to acquire reserved land, and an additional one year after service of a purchase notice by the landowner. Once these periods lapse without acquisition, the reservation automatically lapses.

The Court held that the High Court’s grant of an extra year was not contemplated by the statute. It reasoned that:

  • Statutory timelines are “sacrosanct” and cannot be extended judicially.
  • The Deorukhar decision provided a direction under Article 142 based on its own facts and does not create a general rule allowing extension.
  • Courts cannot compel the State to exercise its power of eminent domain; acquisition depends on the State’s satisfaction that the land is required for a public purpose.
  • Prolonged restrictions on a landowner’s use of property without acquisition are unjustified.

Holding and Implications

Holding: The Supreme Court allowed the appeal and set aside the High Court’s direction granting the Planning Authority an additional one-year period to acquire the land.

Implications: The reservation over the appellants’ land has lapsed, and no further statutory or court-imposed time remains for compulsory acquisition. The decision re-affirms that courts cannot extend statutory acquisition timelines and that Article 142 directives in other cases do not serve as binding precedent for such extensions.

To access the original judgment, please Sign In or Subscribe.

    Laxmikant And Others (S) v. State Of Maharashtra And Others (S).

    The Judgment of the Court was delivered by

    Hemant Gupta, J.— The challenge in the present appeal is to an order dated 6-8-2021 2021 SCC OnLine Bom 9324 passed by the High Court of Judicature at Bombay, Bench at Aurangabad, holding that the reservation of land in the Development Plan stands lapsed as no declaration under Section 126 of the Maharashtra Regional and Town Planning Act, 1966 (for short “the Act”) was published. However, the Planning Authority was given one year time to acquire the land once reserved relying upon the judgment of this Court reported as Municipal Corpn., Greater Mumbai v. Hiraman Sitaram Deorukhar (2019) 14 SCC 411.

    2. A final Development Plan was published under Section 31(6) of the Act on 2-1-2002 which came into force on 18-2-2002 in respect of land including the land owned by the appellants such as Latur Reservation Site bearing No. 217 for playground. The appellants purchased the land bearing Plot Nos. 1, 2, 9 & 10 admeasuring 1394.05 sq m out of Survey No. 73, admeasuring 6500 sq m on 21-11-2002.

    3. Though the Development Plan was finalised, but the same was never implemented nor any action was taken for acquisition of the land under the Land Acquisition Act, 1894. After expiry of ten years, the appellants issued notice on 16-8-2016 under Section 127 of the Act so as to purchase the reserved land within one year of the date of the notice. Such notice was acknowledged by the respondent Municipal Corporation on 20-8-2016/22-8-2016 to submit measuring plan showing reservation thereon including the area owned by the appellants.

    4. It was thereafter that the appellants filed a writ petition before the High Court for a writ of mandamus directing the respondents to treat the land of the appellants bearing Survey No. 73 as released from the Development Plan of Latur Municipal Corporation and that reservation of Site No. 217 for playground be declared to have lapsed to the extent of the land owned by the appellants and that the land is available for the residential use of the appellants. In the counter-affidavit filed by the Municipal Corporation, it was inter alia submitted that the proposal was submitted to Respondent 2 i.e. the Collector, Latur to take effective steps for acquiring the land bearing Survey No. 73 as the land was reserved for playground. The proposal was returned by the competent authority but no effective decision has been taken over the said proposal.

    5. Thus, it was beyond dispute that the land once included in the Development Plan under Section 31(6) of the Act was not acquired within the period of ten years and within additional period of one year after purchase notice was submitted by the appellants on 16-8-2016 and, in fact, not till the writ petition was decided by the High Court. The Municipal Corporation is not aggrieved against the declaration granted by the High Court of the fact that the reservation of the land stands lapsed. It is only the landowner who has come in appeal before this Court against the restriction of one year put by the High Court giving additional time to the respondents to acquire the land.

    6. This Court in Municipal Corpn., Greater Mumbai (2019) 14 SCC 411 was examining the reservation of land for a garden in a Development Plan in the year 1966 but the same was not acquired even after purchase notice was served by the landowner. However, relying upon the judgment of this Court reported as Bangalore Medical Trust v. B.S. Muddappa (1991) 4 SCC 54 and some other judgments, it was held that the land reserved for public park cannot be permitted to be converted for other public purposes.

    7. We have heard the learned counsel for the parties and find that the liberty given by the High Court to acquire the land within an additional period of one year is not contemplated by the statute. This Court in Bangalore Medical Trust (1991) 4 SCC 54, a public interest litigation, interfered with the decision of the Bangalore Development Authority to convert the land reserved for public parks for the purposes of construction of a hospital. It was in these circumstances that this Court intervened, indicting the land reserved for public parks to be used for other purposes.

    8. This Court in Municipal Corpn., Greater Mumbai (2019) 14 SCC 411 held that the authorities have been given a duty to act as a cestui que trust (beneficiary of the trust) with respect to public park and had thus directed to acquire land under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 within a period of six months. Such direction was given under Article 142 of the Constitution of India keeping in view the facts of the case. Such direction and period for acquisition of land is not a law declared by this Court which is to be treated as binding precedent for this Court and the subordinate courts, subordinate in terms of Article 141 read with Article 144 of the Constitution. Therefore, once the Act does not contemplate any further period for acquisition, the Court cannot grant additional period for acquisition of land.

    9. The land was reserved for a public purpose way back in 2002. By such reservation, the landowner could not use the land for any other purpose for ten years. After the expiry of ten years, the landowner had served a notice calling upon the respondents to acquire the land but still the land was not acquired. The landowner cannot be deprived of the use of the land for years together. Once an embargo has been put on a landowner not to use the land in a particular manner, the said restriction cannot be kept open-ended for indefinite period. The statute has provided a period of ten years to acquire the land under Section 126 of the Act. Additional one year is granted to the landowner to serve a notice for acquisition prior to the amendment by Maharashtra Act 42 of 2015. Such timeline is sacrosanct and has to be adhered to by the State or by the authorities under the State.

    10. The State or its functionaries cannot be directed to acquire the land as the acquisition is on its satisfaction that the land is required for a public purpose. If the State was inactive for long number of years, the Courts would not issue direction for acquisition of land, which is exercise of power of the State to invoke its rights of eminent domain.

    11. In view thereof, the direction to acquire land within a period of one year is in fact contravening the timeline fixed under the statute. Consequently, the direction to acquire the land within one year is set aside. The appeal is allowed.

    Use AI to get other relevant cases.

    Comments

    Laxmikant And Others (S) v. State Of Maharashtra And Others (S).
    (Mar 23, 2022)