  • Section 31 A to the Travancore Cochin Hindu Religious Institutions Act, 1950 (Amendment Act 5 of 2007),
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 31 A to the Travancore Cochin Hindu Religious Institutions Act, 1950 (Amendment Act 5 of 2007),
Smart Summary

Factual and Procedural Background

The petitioners, devotees of the Ambalappuzha Sree Krishna Swami temple, challenged the extension of the Temple Advisory Committee’s (TAC) term by the Travancore Devaswom Board. The TAC’s original term was two years from 27.02.2019 to 27.02.2021, as per bye laws approved by the Court. The TAC requested an extension of two years on the ground of completing ancillary works, specifically making the pavement of tiles at the temple’s western entrance more attractive, after having completed the construction of the Gopuram Vathil. The petitioners opposed the extension, submitting complaints and information under the Right to Information Act that no developmental work was pending. The Board initially extended the TAC’s term by one year through Ext.P5 order, then withdrew it and reissued Ext.P11 extending the term again by one year for ancillary development works. The petitioners challenged both extensions by filing a writ petition. Respondents filed a counter affidavit defending the extension based on the TAC’s request and the Board’s authority under statutory bye laws, citing difficulties in conducting elections due to the Covid-19 pandemic.

Legal Issues Presented

  1. Whether the Travancore Devaswom Board validly exercised its power under the approved bye laws to extend the term of the Temple Advisory Committee beyond the original two-year period.
  2. Whether the reasons cited for the extension—completion of the Gopuram Vathil and making the pavement of tiles more attractive—constitute valid grounds for extension under the statutory framework.
  3. Whether the extension of the TAC’s term was arbitrary, illegal, or vitiated by extraneous considerations.
  4. The extent of the Board’s discretion to extend the term of the TAC in light of statutory provisions and the Covid-19 pandemic affecting elections.

Arguments of the Parties

Petitioners' Arguments

  • The construction of the Gopuram Vathil was completed and inaugurated on 10.01.2021, thus the reason for extension in Ext.P5 is baseless, illegal, and arbitrary.
  • Information obtained under the Right to Information Act confirmed no developmental work was pending, negating the justification for extension.
  • The substitution of reasons in Ext.P11 after withdrawal of Ext.P5 is equally unsustainable and based on extraneous considerations.

Respondents' Arguments

  • The TAC requested extension to beautify the pavement of tiles after completing the western entrance and adjoining gates.
  • Contradictory reports from the Administrative Officer and Assistant Devaswom Commissioner led the Board to rely on the Assistant Commissioner’s report, which did not substantiate complaints against the TAC.
  • The Board has exclusive power under the bye laws to extend the term of TACs, especially given the inability to conduct elections during the Covid-19 pandemic.
  • The extension was a considered administrative decision and not vitiated by extraneous factors.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court analyzed the statutory framework under the Travancore Cochin Hindu Religious Institutions Act, 1950, and the approved bye laws for formation and tenure of Temple Advisory Committees. The term of TAC is fixed at two years, with possible extensions of one year each under exceptional circumstances involving development works or unavoidable rituals, but not beyond two years in total.

The Court found that the work of paving tiles at the entrance does not qualify as a development work warranting extension, as such minor works can be undertaken by a succeeding committee without affecting temple activities. The Court emphasized that the power to extend the term is not to be exercised routinely but based on concrete developmental or ritual necessities, supported by proper reports and evidence.

The Court held that the reasons stated in Ext.P11 for the extension were neither plausible nor reasonable. The substitution of reasons after withdrawal of Ext.P5 was seen as an attempt to justify an otherwise baseless extension. The Court underscored the objective of the bye laws to ensure timely elections and avoid unnecessary delays in constituting committees.

Holding and Implications

The Court set aside Ext.P11 proceedings of the Travancore Devaswom Board extending the term of the Temple Advisory Committee.

The Court directed the respondents to conduct elections to the TAC in accordance with the approved bye laws as soon as conditions permit, following Covid-19 protocols. Until elections are held and approved by the Devaswom Commissioner, an adhoc Temple Advisory Committee must be constituted excluding members of the outgoing TAC.

This decision directly affects the parties by invalidating the extension and mandating fresh elections, but does not establish any new precedent beyond affirming the statutory limits and proper exercise of discretion under the bye laws.

To access the original judgment, please Sign In or Subscribe.

    Chandu K. v. Travancore Devaswom Board

    Murali Purushothaman, J.:— The petitioners who are devotees of Ambalappuzha Sree Krishna Swami temple (hereinafter referred to as the ‘temple’) have approached this Court challenging the extension of the period of the Temple Advisory Committee (TAC) of the temple by the Travancore Devaswom Board.

    2. As per the bye laws for the formation of Temple Advisory Committees in temples under the Travancore Devaswom Board approved by this Court, the term of office of the said Committees is for a period of 2 years from the date of approval of the election by the Devaswom Commissioner. The TAC of the temple was granted approval by the 2 respondent Devaswom Commissioner w.e.f. 27.02.2019 and the term of the TAC was up to 27.02.2021.

    3. According to the petitioners, there were complaints against the functioning of the TAC. The present TAC submitted application for extension of their period before the 3 respondent Assistant Devaswom Commissioner on 25.01.2021. The extension of term was sought for by the TAC on the ground that, though the work on the western entrance of the temple and the adjoining gates have been completed by the TAC, they want to make the pavement of tiles at the entrance gate more attractive. They sought for extension of term of the TAC by two years.

    4. The petitioners submitted Ext.P2 complaint dated 27.01.2021 before the 4 respondent Administrative Officer of the temple, requesting not to extend the term of the present TAC. On the report called for on the request for extension of term, the Assistant Devaswom Commissioner submitted Ext.P4 report to the Devaswom Commissioner stating that the construction of the Gopuram Vathil has been completed by the present TAC satisfactorily and that no works are pending to be completed by the TAC. In Ext.P4 report, the Assistant Devaswom Commissioner observed that complaints are received against the present TAC with regard to the construction of the Gopuram Vathil, but the allegation levelled against the TAC could not be substantiated by the complainants with clear evidence.

    5. On the basis of the report of respondents 2 to 4, the 1 respondent Board issued Ext.P5 order extending the period of the TAC by one year. In Ext.P5, it is stated that the term of the present TAC is extended by one year for the purpose of completion of the ‘Gopuram Vathil’ of the temple. It is challenging Ext.P5 that the petitioners have approached this Court by filing the above writ petition.

    6. The petitioners contend that the construction of the ‘Gopuram Vathil’ was completed and it was opened on 10.01.2021 by the President of the Board in the presence of other Board members, Devaswom authorities and TAC members and therefore, the reason stated in Ext. P5 for extension of the period of TAC is absolutely baseless and is illegal and arbitrary. The petitioners also refer to Ext.P6 information furnished to the third petitioner by the Assistant Devaswom Commissioner under the Right to Information Act which states that no developmental activity or work is pending to be done by the TAC in the temple.

    7. During the pendency of the writ petition, the 1 respondent Board issued Ext.P11 proceedings withdrawing Ext.P5 communication and extending the term of the TAC by one year stating that the Board does not find any reason to reject the request of the present TAC for extension of period to complete the ancillary development works in the temple.

    8. The petitioners have amended the writ petition incorporating pleadings challenging Ext. P11. The petitioners contend that there is no development activity or any work pending to be carried out by the present TAC in the temple and that when the Board found the reason in Ext. P5 cannot stand the scrutiny of law, the same was substituted with another reason, which is equally unsustainable and issued on extraneous considerations.

    9. A counter affidavit is filed on behalf of respondents 1 to 4 wherein it is stated that the present TAC submitted a request to the Devaswom Commissioner stating that the work on the western entrance of the temple and adjoining gates had been completed under the leadership of the TAC and they want to make the pavement of tiles more attractive and therefore the term of TAC may be extended for two years and since the report of the Administrative officer and the Assistant Commissioner called for were contradictory, the matter was submitted to the Board for decision and the Board found that the report of the Assistant Commissioner does not contain any explicit allegation against the present committee and the report shows that the functioning of the TAC has gone smoothly and they have carried out the construction of Gopuram Vathil satisfactorily and the Board does not find it reasonable to reject the request of the TAC for an extension. It is stated that Ext. P5 was withdrawn and Ext. P11 was issued as the Board decision in its meeting dated 19.02.2021 was not correctly communicated in Ext. P5. The counter affidavit further states that the Board has the exclusive power under the bye laws to take decision regarding extension of term of temple advisory committees and in view of Covid-19 pandemic it is not possible to conduct election to form committees and the Board has taken a general view to extend the term of advisory committees which are free from allegations and the petitioners have no authority to interfere with the decision of the Board in terms of the bye laws approved by this court. They also denied the allegation raised by the petitioners that the decision to extend the term is vitiated by extraneous factors.

    10. Heard Sri K. Sasikumar, the learned counsel for the petitioners, Sri. K.S. Hariharaputhran, the learned counsel for the TAC, Sri G. Santhosh Kumar, learned standing counsel for the Respondents 1 to 4.

    11. With the insertion of Section 31 A to the Travancore Cochin Hindu Religious Institutions Act, 1950 (Amendment Act 5 of 2007), the formation of Temple Advisory Committees in temples has become statutory. The Board, in exercise of the rule making power under Section 35(2)(a) of the Act, has framed rules for the formation of Temple Advisory Committees in temples under Travancore Devaswom Board and this Court by order dated 03-11-2011 in DBA No. 153/2009 has approved the draft bye laws. As per clause 11 of the approved bye laws, the term of office of the Temple Advisory Committee shall be 2 years from the date of approval of the election by the Devaswom Commissioner. However, the Devaswom Commissioner has the authority to extend the term of the committee by one year in case of development works or unavoidable rituals in the temple. The Board will have the power to extend the term by a further period of one year. The term shall not to be extended beyond the period of two years. Thus, the term of the committees is statutorily fixed. The term can be extended by one year or up to two years under certain unavoidable circumstances and no longer.

    12. The reason stated by the TAC in their request for extending the term, which was allowed by the Board for a period of one year is that, the work on the western entrance of the temple and adjoining gates had been completed and they now want to make the pavement of tiles more attractive. The pavement of tiles cannot be construed as a development work which requires the extension of term of the Temple Advisory Committee. The said work can also be done by the succeeding committee. The fact that the present TAC has completed the work of ‘Gopuram Vathil’ satisfactorily and that the report of the Assistant Commissioner does not contain any explicit allegations against the present TAC are also not factors to extend the term of the TAC. The development works referred to in clause 11 of the bye laws are such major works in the temple which have to go on without break and a change of Temple Advisory Committee during such work shall not affect the progress of the work. Though we do not want to enumerate as to what are the developmental works in a temple which permit the Devaswom Commissioner or the Board to extend the term of the Temple Advisory Committees, which has to be considered in the facts and circumstances of each case, we have no hesitation to hold that the work of paving tiles at the entrance of the temple cannot be a reason for extension of term of the present TAC. The object of providing duration of office of Temple Advisory Committees in the approved bye laws is to see that timely elections are held and the constitution of the Committees are not delayed. The power of the Devaswom Commissioner or the Board to extend the term of the Temple Advisory Committee which is fixed as per the approved bye laws shall not be exercised as a matter of course. They shall call for report regarding the developmental works going on in the temple concerned or the unavoidable rituals to be carried out in the temple concerned and apply their mind to the materials and form a decision as to whether extension of term has to be given or not.

    13. The reasons stated in Ext. P11 to extend the term of the TAC by the Board are not plausible or reasonable. Accordingly, we set aside Ext. P11 proceedings of the 1 respondent Board extending the term of the 5 respondent TAC. The respondents 1 to 3 are directed to take steps to conduct election to the TAC of the temple in accordance with the provisions of clause 5 of the approved bye laws of the Board expeditiously as and when the situation becomes conducive for the conduct of election following the Covid-19 protocols, if any, issued by the Government. Till election is held and the approved by the Devaswom Commissioner in terms of clause 8 of the approved bye laws, the respondents 1 to 3 shall constitute an adhoc Temple Advisory Committee for the temple from among the members. Needless to say that the composition of such adhoc committee shall not be with persons who are members of the outgoing TAC.

    14. The writ petition is disposed of with the above directions.