  • Kerala Conservation of Paddy Land and Wetland Act, 2008 (the Act)
  • Rule 12(9) of the Rules.
  • Rule 12(9) of the Kerala Conservation of Paddy Land and Wetland Rules (the Rules)
  • provisions of this Act. (2) Every rule
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Kerala Conservation of Paddy Land and Wetland Act, 2008 (the Act)
  • Rule 12(9) of the Rules.
  • Rule 12(9) of the Kerala Conservation of Paddy Land and Wetland Rules (the Rules)
  • provisions of this Act. (2) Every rule
Smart Summary

Judicial Opinion Summary

Factual and Procedural Background

The petitioner, a builder, owns land within Kochi Corporation measuring 17.62 ares, of which 6.93 ares was recorded earlier as 'nilam' but was not notified as paddy land or wetland under the Kerala Conservation of Paddy Land and Wetland Act, 2008. That 6.93 ares therefore falls within the Act's definition of "un-notified land". The petitioner's predecessors applied under Section 27A(1) of the Act for permission to utilise that land for other purposes; the competent authority allowed that application by order dated 23.01.2020 (Ext.P2). Pursuant to that order, the land was reclassified in revenue records as 'purayidom' under Section 27C, and the petitioner purchased the land on 25.06.2020. The petitioner obtained an initial building permit (Ext.P10) on 08.09.2020 for a building of 670.78 sq. meters and later applied (Ext.P13) for a revised building permit for construction of a building of 9,274.44 sq. meters.

The petitioner contends that because part of the land is un-notified land and its use is by virtue of Ext.P2, the petitioner is obliged to pay a fee of Rs.100 per square foot for the area of building exceeding 3,000 square feet under Rule 12(9) of the Kerala Conservation of Paddy Land and Wetland Rules (the Rules). The petitioner challenges Rule 12(9) as ultra vires the Act to the extent it levies such a fee and sought an interim direction that the Corporation process Ext.P13 without insisting on payment under Rule 12(9).

Procedurally, the writ petition was admitted on 03.02.2021. Notice was served and the matter was listed for interim relief hearings beginning 26.03.2021, with hearings occurring on 30.03.2021 when counsel for both sides were heard.

Legal Issues Presented

  1. Whether Rule 12(9) of the Kerala Conservation of Paddy Land and Wetland Rules is ultra vires Section 27A of the Act to the extent that it prescribes a fee calculated by reference to the area of a building exceeding 3,000 square feet proposed on un-notified land.
  2. Whether the petitioner is estopped (or otherwise precluded) from challenging Rule 12(9) because the petitioner's predecessors had accepted Ext.P2, which imposed a condition to pay fees under Rule 12(9), and acted upon that order (including reclassification of the land).
  3. Whether interim relief should be granted directing the Corporation to process the petitioner's application (Ext.P13) without insisting on payment of the fee under Rule 12(9) pending final disposal of the writ petition.

Arguments of the Parties

Petitioner's Arguments

  • Section 27A(1) empowers the competent authority to grant permission to utilise un-notified lands for residential, commercial or other purposes; the statutory concern is to ensure that such utilisation does not undermine the object of the Act (e.g., water flow and conservancy measures).
  • The area of any building proposed on such land is irrelevant to the statutory grant of permission under Section 27A; therefore, a rule that levies a fee based on the area of the building (as Rule 12(9) does for area exceeding 3,000 sq. ft.) is inconsistent with and ultra vires the Act.
  • The petitioner sought an interim order directing the Corporation to process Ext.P13 without insisting on payment under Rule 12(9).

Respondent's (State/Corporation) Arguments

  • The petitioner's predecessors accepted Ext.P2 which granted permission under Section 27A(1) subject to payment of fees under Rule 12(9), and acted on it (including seeking reclassification). Therefore, the petitioner (as successor-in-title) is estopped from challenging Ext.P2's fee condition.
  • The Additional Advocate General relied on State of Punjab v. Dhanjit Singh Sandhu (2014) KHC 4167 (as cited) to invoke the doctrine of approbate and reprobate — that one cannot both accept and later repudiate the same transaction or instrument.
  • Alternatively, the respondents contend that the petitioner cannot obtain the relief sought without challenging Ext.P2 itself.
  • The impugned Rule falls within the rule-making power under Section 30 of the Act and is within the scope of carrying the Act into effect; hence, the Rule is not beyond the State Government's power to make.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Cellular Operators Association of India v. TRAI, (2016) 7 SCC 703 Rules made to give effect to a statute must be consistent with the statute's purpose. The court invoked this trite principle to emphasize that Rules under the Act must align with the object and provisions of the Act when exercising rule-making power under Section 30.
Global Energy Ltd. v. Central Electricity Regulatory Commission, (2009) 15 SCC 570 A subordinate legislative authority cannot create obligations or disabilities in rules not contemplated by the statute. Used to support the proposition that Rule 12(9) cannot impose obligations (fee based on building area) that are not contemplated by Section 27A.
Union of India v. Saroj Kumar Shukla, (2012) 7 SCC 683 If a rule supplants any provision for which power has not been conferred, it becomes ultra vires. Applied to conclude that any Rule going beyond the statute's confines (e.g., imposing a building-area based fee) would be ultra vires.
Bharathidasan University v. All-India Council for Technical Education, (2001) 8 SCC 676 When the power to make regulations is confined to certain limits, courts ignore those regulations made outside those confines when enforcement is sought. Cited to support the proposition that the court must disregard rules beyond conferred power and may refuse enforcement of ultra vires regulations.
State of Punjab v. Dhanjit Singh Sandhu, (2014) KHC 4167 Explains the doctrine of "approbate and reprobate" (election doctrine): a person should not accept and later repudiate the same instrument to gain advantage. Relied on by the Additional Advocate General to argue estoppel; the court considered this authority but distinguished it on the basis that estoppel cannot legitimize ultra vires acts.
Express Newspapers (P) Ltd. v. Union of India, (1986) 1 SCC 133 Rule of estoppel is not available in respect of ultra vires acts of statutory bodies/authorities. Relied upon by the court to reject the estoppel argument that would validate an ultra vires rule.
Home Secy., U.T. of Chandigarh v. Darshjit Singh Grewal, (1993) 4 SCC 25 Same principle: estoppel cannot validate ultra vires actions by statutory authorities. Again cited to support the proposition that acceptance of an ultra vires condition does not preclude later challenge to the ultra vires condition.
A.P. Steel Re-Rolling Mill Ltd. v. State of Kerala, (2007) 2 SCC 725 Estoppel cannot be invoked to uphold ultra vires actions of statutory bodies. Used with the other authorities to demonstrate that Dhanjit Singh Sandhu (approbate/reprobate) does not permit validation of an ultra vires rule.
Health for Millions v. Union of India, (2014) 14 SCC 496 If a rule is ex facie ultra vires the statute, interim relief can be granted despite the presumption in favour of intra vires rules. Cited by the court to justify granting the interim relief where Rule 12(9) appears prima facie ultra vires Section 27A.

Court's Reasoning and Analysis

The court proceeded by reference to the statute's object and the scope of the relevant provisions and rule-making power:

  1. The long title and object of the Act: The Act is enacted to conserve paddy lands and wetlands, promote agricultural growth and sustain ecological systems; Section 27A permits utilization of un-notified lands for residential, commercial or other purposes subject to safeguarding the objects of the Act (e.g., water flow and conservancy).
  2. Nature and purpose of Section 27A: Section 27A is a statutory provision to allow owners of un-notified lands to change user while ensuring no disruption to neighbouring paddy lands and adequate water conservancy measures. The court emphasized that Section 27A's focus is on permissible use and ecological safeguards, not on the scale of buildings per se.
  3. Rule-making power under Section 30: The Rules were duly framed under Section 30; however, rules must be consistent with the statute's purpose. The court quoted the text of Section 30 and reiterated the settled principles governing subordinate legislation.
  4. Application of established principles: The court relied on settled principles (as reflected in the precedents cited) that rules cannot introduce obligations or disabilities beyond what the statute contemplates; if a rule ventures beyond conferred power it is ultra vires and unenforceable.
  5. Specific analysis of Rule 12(9): Rule 12(9) prescribes fee for permission under Section 27A and, through the schedule, includes a fee of Rs.100 per square foot for building area exceeding 3,000 sq. ft. The court found that the area of the building is "irrelevant and extraneous" to the statutory permission under Section 27A which is concerned with ensuring that user does not undermine the Act's object. Accordingly, levying a fee based on building area appears prima facie inconsistent with Section 27A and thus prima facie ultra vires to that extent.
  6. On estoppel and Ext.P2: The court addressed the respondent's estoppel argument (predecessors accepted Ext.P2 which contained the fee condition). It distinguished the authority relied upon (Dhanjit Singh Sandhu) noting the doctrine of approbate and reprobate but held that estoppel cannot legitimize an ultra vires act — relying on authorities that the rule of estoppel is not available to validate ultra vires actions of statutory authorities.
  7. Interim relief analysis: Although rules are presumed intra vires and interim relief is not routinely granted in rule-challenges, the court applied the principle that when a rule is ex facie ultra vires the statute, an interim order can be appropriate (citing Health for Millions).

Holding and Implications

Interim relief granted.

Holding (direct order): The court directed the Corporation to process the petitioner's Ext.P13 building-permit application without insisting on payment of the fee prescribed under the impugned part of Rule 12(9) (i.e., fee for building area exceeding 3,000 square feet). This relief is granted on an interim basis and is expressly made subject to the final decision in the writ petition.

Implications:

  • Immediate/direct effect: The Corporation must proceed to process Ext.P13 without requiring payment under the impugned portion of Rule 12(9) until the writ petition is finally decided.
  • Scope of judgment: The court treated the impugned portion of Rule 12(9) as prima facie ultra vires Section 27A and therefore unenforceable for interim purposes; the order does not constitute a final adjudication on the rule's validity and the matter remains open for final determination.
  • Precedential effect: The opinion grants interim relief based on established principles regarding ultra vires subordinate legislation and the limits of estoppel against ultra vires acts. The court did not purport to lay down novel precedent beyond applying these settled principles; the order is interim and subject to final adjudication.

Note: This summary strictly reflects matters set out in the provided opinion. It does not add facts or inferences beyond those expressly contained in the opinion.

    Abad Builders Private Limited, Rep.By Its Managing Director Petitioner/S v. State Of Kerala, Rep. By Secretary To Government And Others /S.

    P.B. Suresh Kumar, J.:— Petitioner seeks, among others, a declaration that Rule 12(9) of the Kerala Conservation of Paddy Land and Wetland Rules (the Rules) framed under the Kerala Conservation of Paddy Land and Wetland Act, 2008 (the Act) is ultra vires the provisions of the Act to the extent it provides for levy of a fee for the area of buildings exceeding 3000 square feet proposed in lands defined as un-notified lands under the Act.

    2. The writ petition was admitted to file on 03.02.2021 and the same was brought up by the petitioner after service of notice on 26.03.2021 for the interim relief sought in the matter. An adjournment was sought by the State on 26.03.2021 for hearing on the prayer of the petitioner for interim relief, and the matter was accordingly adjourned initially to 29.03.2021 and then to 30.03.2021. On 30.03.2021, the learned counsel for the petitioner as also the learned Additional Advocate General were heard on the prayer for interim relief.

    3. The facts relevant for considering the prayer for interim relief are the following : The petitioner is a builder. They own a land within the limits of Kochi Corporation (the Corporation) measuring 17.62 Ares, of which 6.93 Ares was shown earlier in the revenue records as ‘nilam’. This 6.93 Ares of land was however not notified as paddy land or wetland under the Act and as such, the same is a land falling within the definition of “unnotified land” in terms of the provisions of the Act. The predecessors of the petitioner, in the circumstances, applied for permission under Section 27A(1) of the Act to utilise the said land for other purposes, and the application has been allowed by the competent authority on 23.1.2020 as per Ext.P2 order. Later, pursuant to the said order, the said extent of land has been reclassified in the revenue records as ‘purayidom’ as provided for under Section 27C of the Act. The petitioner purchased the land only thereafter on 25.06.2020. Later, on 8.9.2020, the petitioner obtained Ext.P10 building permit from the Corporation for construction of a building in the land owned by them, having an area of 670.78 square meters. Subsequently, they submitted an application before the Corporation for a revised building permit for construction of a building having an area of 9274.44 square meters in the said land. Ext.P13 is the application preferred by the petitioner in this regard. It is stated by the petitioner that since a portion of the land where the petitioner proposes to put up the building is an unnotified land in terms of the Act and since the petitioner is making use of the said land for construction of the building on the strength of Ext.P2 order, the petitioner is obliged to pay fee at the rate of Rs. 100/- per square foot for the area of the building exceeding 3000 square feet in terms of Rule 12(9) of the Rules. It is also stated by the petitioner that earlier in the matter of obtaining Ext.P2 order, the predecessors of the petitioner have paid only the fee payable in terms of the said rule for the land covered by the application as there was no proposal then to put up any building in the land. It is alleged by the petitioner that the Corporation is now insisting the petitioner to pay fee for the area of the building exceeding 3000 square feet as provided for under Rule 12(9) also for processing Ext.P13 application. The petitioner is challenging Rule 12(9) of the Rules to the extent it provides for levy of fee as aforesaid in the above background on the ground mainly that the same to the extent aforesaid is ultra vires the provisions of the Act. The interim relief sought by the petitioner, in the circumstances, is for a direction to the Corporation to process Ext.P13 application without insisting payment of fee prescribed in terms of Rule 12(9) for the building proposed in the land.

    4. Rule 12(9) is the provision in the Rules prescribing the fee payable for grant of permission under Section 27A (1) of the Act to utilize lands falling under the definition of ‘un-notified land’ for residential, commercial or other purpose. Rule 12(9) provides that the fee payable for the purpose is as prescribed in the schedule to the Rules. The schedule to the Rules provides that fee shall be payable for the extent of the land covered by the application at the rates prescribed therein and at the rate of Rs. 100/- per square foot for the area of building exceeding 3000 square feet proposed in the land. It was argued by the learned counsel for the petitioner that Section 27A being a provision in the Act empowering the competent authority to grant permission to utilize un-notified lands for other purposes, levy of a fee for the same on the basis of the area of the building proposed in the land cannot be construed as one consistent with Section 27A and one contemplated by the legislature. According to the learned counsel, the stipulation in Rule 12(9) as regards the fee payable having regard to the area of the building proposed in the land is therefore ultra vires the provisions of the Act.

    5. Per contra, the learned Additional Advocate General pointed out that the predecessors of the petitioner have been granted permission under Section 27A (1) of the Act in terms of Ext.P2 order subject to the condition that they shall pay fee for the same as provided for under Rule 12(9) of the Rules. It was argued by the learned Additional Advocate General that the predecessors of the petitioner having accepted Ext.P2 order and acted upon same for the purpose of obtaining reclassification of the land in the revenue records, the petitioner who is claiming under them is estopped from seeking the declaration sought for by them in the writ petition. The learned Additional Advocate General has relied on the decision of the Apex Court in State of Punjab v. Dhanjit Singh Sandhu, (2014) KHC 4167 in support of the said argument. It was also argued by the learned Additional Advocate General that at any rate, the petitioner is not entitled to the declaration sought for in the writ petition without challenging Ext.P2 order. It was further argued by the learned Additional Advocate General that having regard to the purpose for which Section 27A is introduced in the Act, it cannot be said that the impugned Rule is one falling beyond the scope of the power conferred on the State Government under the Act to frame Rules for the purpose of carrying into effect the provisions of the Act.

    6. I have considered the contentions advanced by the learned counsel for the parties.

    7. The long title of the Act indicates beyond doubt that the Act is one brought into force to conserve paddy lands and wet lands in the State with a view to promote growth in the agricultural sector and to sustain ecological system. Similarly, Section 27A of the Act indicates that the same is a provision intended to permit owners of un-notified lands namely lands which have been included as paddy land or wetland in the basic tax register maintained in village offices, but are not notified as paddy land or wetland in terms of the provisions of the Act, to utilise the same for residential or commercial or other purposes. The grant of permission provided for under Section 27A of the Act being a service rendered by Government officials to individuals, though not as a privilege, levy of a fee for the same cannot be said to be ultra vires the provisions of the Act. But, the pointed question is as to whether such a fee could be levied having regard to the area of the building proposed in such lands. 8. The Rules have been framed by the Government in exercise of the power conferred under Section 30 of the Act. Section 30 of the Act reads thus:

    30. Power to make rule. - (1) The Government may, by notification in the Gazette, make rules for the purpose of carrying into effect the provisions of this Act.

    (2) Every rule made under this Act shall be laid, as soon as may be after it is made, before the Legislative Assembly while it is in session for a total period of fourteen days, which may be comprised in one session or in two successive sessions and if before the expiry of the session in which it is so laid or the session immediately following, the Legislative Assembly makes any modification in the rule or decides that the rule should not be made, the rule shall thereafter have effect only in such modified form or be of no effect, as the case may be; so however that any such modification or annulment shall be without prejudice to the validity of anything previously done under that rule.

    8. It is trite that the Rules made for the purpose of giving into effect a provision in a statute shall be consistent with the purpose for which the provision has been enacted [See Cellular Operators Assn. of India v. TRAI, (2016) 7 SCC 703]. It is equally trite that in exercise of the rule-making power conferred on a subordinate legislative authority for the purpose of carrying into effect a provision in a statute, the subordinate legislative authority cannot bring into existence obligations or disabilities in the rules which are not contemplated by the statute [See Global Energy Ltd. v. Central Electricity Regulatory Commission, (2009) 15 SCC 570]. Similarly, it is trite that if a Rule supplants any provision for which power has not been conferred, it becomes ultra vires [See Union of India v. Saroj Kumar Shukla, (2012) 7 SCC 683].

    9. As rightly contended by the petitioner, Section 27A(1) is a provision in the Act empowering the competent authority to grant permission to utilize unnotified lands for residential or commercial or other purposes. It is seen that such a provision is made in the statute in order to ensure that when such lands are utilized for residential or commercial or other purposes, there is no disruption to the free flow of water to the neighbouring paddy lands, if any, and sufficient land is available in the vicinity for water conservancy measures. The provision therefore is certainly in tune with the object of the Act. The permission contemplated under the said provision being a permission for utilisation of un-notified lands for residential or commercial or other purposes, after ensuring that user of the same would not in any manner undermine the object of the Act, the area of the building, if any, proposed by the applicant in the land is irrelevant and extraneous in the context of the statute, and levy of a fee for such permission on the basis of the area of the building proposed in the land cannot therefore be construed as one consistent with Section 27A and one contemplated by the legislature. In the said view of the matter, according to me, the Rule, to the extent it provides for levy of a fee for the area of buildings exceeding 3000 square feet proposed in un-notified lands, appears to be prima facie ultra vires the provisions of the Act.

    10. A Rule which is ultra vires the provisions of the Act is void and unenforceable. In Bharathidasan University v. All-India Council for Technical Education, (2001) 8 SCC 676, it was held by the Apex Court that when the power to make regulations is confined to certain limits, the courts are bound to ignore those made or shown and found to be not made within its confines but outside them, when the question of their enforcement arises. In the light of the aforesaid principles, there is absolutely no merit in the contentions raised by the learned Additional Advocate General that it was obligatory for the petitioner to challenge Ext.P2 order for the purpose of claiming the relief sought for in the writ petition and that the petitioner is estopped from challenging Ext.P2 order insofar as it fastens liability on them to pay fees in terms of Rule 12(9) of the Rules. Dhanjit Singh Sandhu relied on by the learned Additional Advocate General is a case where the Apex Court has explained the doctrine “approbate and reprobate”. True, law does not permit a person to both approbate and reprobate. This principle is based on the doctrine of election which postulates that no party can accept and reject the same instrument and that a person cannot say at one time that a transaction is valid and thereby obtain some advantage, to which he could only be entitled on the footing that it is valid and then turn around and say that it is void for the purpose of securing some other advantage. According to me, the said judgment cannot have any application to the facts of the present case, for it is now settled that no estoppel can legitimate an action which is ultra vires, and the rule of estoppel is not available in respect of ultra vires acts of statutory body/authority [See Express Newspapers (P) Ltd. v. Union of India, (1986) 1 SCC 133, Home Secy., U.T. of Chandigarh v. Darshjit Singh Grewal, (1993) 4 SCC 25 and A.P. Steel Re-Rolling Mill Ltd. v. State of Kerala, (2007) 2 SCC 725].

    11. As noted, the petitioner seeks, by way of interim order, a direction to the fourth respondent to process the application for building permit submitted by the petitioner without insisting payment of fees for the building in terms of the Schedule to the Rules. True, every rule is presumed to be intra vires and in a challenge against the rule on the ground that the same is ultra vires, an interim order is normally not issued. But, it is settled that if the Court finds that the rule is ex facie ultra vires the provisions of the Act, there cannot be an impediment in granting an interim relief in the matter [See Health for Millions v. Union of India, (2014) 14 SCC 496].

    12. For the reasons aforesaid, I am of the view that the petitioner is entitled to the interim relief sought for in the matter. The Corporation is directed to process Ext.P13 application without insisting payment of the fee in terms of the Rule which is impugned in the writ petition. It is however made clear that the aforesaid arrangement would be subject to the final decision in the writ petition.