AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Smart Summary

Factual and Procedural Background

This matter involves a petition (No. 365/MP/2019) by a solar power developer (the Petitioner) who was awarded one 250 MW unit in the 750 MW Rewa Solar Project (RfS dated 16.03.2013; LOI dated 21.02.2017). The Petitioner executed two Power Purchase Agreements (PPAs) dated 17.04.2017 with MPPMCL (Respondent No.1) and DMRC (Respondent No.2) to supply 78% and 22% of the power respectively, at a tariff of INR 2.979/kWh with annual escalation.

After signing of the PPAs, the Central Government issued a Safeguard Duty Notification dated 30.07.2018 imposing safeguard duties (25%/20%/15% ad valorem in phases) on import of solar cells/modules. The Petitioner claimed that this Safeguard Duty amounted to a "Change in Law" under Article 17 of the PPAs and sought compensation, including reimbursement for additional costs and carrying cost/interest on incremental working capital. Different figures for the Petitioner's claimed impact appear in the record (the Petitioner is recorded as asserting an impact of Rs. 132.41 crores in one place and additional liability of Rs. 1,33,50,000/- in another submission).

The Commission heard the matter via video conference on 07.07.2020. Written submissions were filed by the Respondents on 14.07.2020 and by the Petitioner on 23.07.2020. The Commission examined preliminary procedural objections (including challenges to the validity of the Safeguard Duty in various courts) and proceeded to decide the merits. The Order disposes Petition No. 365/MP/2019.

Legal Issues Presented

  1. Whether the imposition of Safeguard Duty on import of solar modules/panels/cells is an event covered by the "Change in Law" definition in Article 1.1 and Article 17 of the PPAs, and whether a mechanism is required to compensate the Petitioner for increased recurring and non-recurring expenditure on account of that Change in Law?
  2. Whether the Petitioner may be restored to the same economic condition prior to the Change in Law through an appropriate mechanism, and whether the Petitioner's claim for interest on working capital and carrying cost for delay in reimbursement by the Respondents is sustainable?

Arguments of the Parties

Respondent No.1 (MPPMCL) — Key Arguments

  • There is no provision in the PPA for restoration to the same economic position; hence carrying cost should not be applicable and principles of equity cannot be invoked to award carrying cost (relied on Alopi Parshad & Sons Ltd.).
  • Relief for Change in Law is available only if additional capital expenditure, interest and associated costs exceed the Threshold Limit (INR 20,000,000 / Rs. 2 crores) for each event under Article 17.1(c); the Threshold applies to each independent incidence and not cumulatively.
  • The impact of Change in Law, if established, should be recovered by way of tariff adjustment rather than a lump-sum payment; lump-sum payment would be financially burdensome for MPPMCL and would amount to paying capital costs irrespective of future supply performance.
  • The Petitioner's claimed impact (including a stated figure) must be strictly proved with supporting import documentation and invoices.
  • MPPMCL argued the remedy for safeguard duty is against the EPC contractor (supplier) under contract, not against the procurer.
  • MPPMCL sought that if relief is allowed, it should be confined to the 250 MW covered by the PPA with MPPMCL.

Respondent No.2 (DMRC) — Key Arguments

  • Relied on Commission's prior orders (e.g., ACME Jaipur order dated 15.10.2019 and Renew Solar Power order) that held where PPAs lack restitution provisions, claims for separate interest on working capital, return on equity and carrying costs are not admissible.
  • Argued the PPA's Change in Law procedures (Article 17) were not followed by the Petitioner (notably Article 17.1(b) obligations to hold joint meetings and demonstrate reasonable endeavours to mitigate impact), and the Petitioner failed to place records showing efforts to minimize the effect of Change in Law.
  • DMRC noted the Petitioner awarded its EPC/supply contract only on 05.02.2018 (well after PPA date 17.04.2017), and that delayed or untimely procurement could have avoided additional costs — suggesting lack of mitigation by the Petitioner.
  • Consequently, DMRC argued the Petitioner's claims for carrying cost and interest on incremental working capital should be rejected.

Petitioner — Key Arguments

  • The Safeguard Duty Notification of 30.07.2018 is a Change in Law under Article 17 read with Article 1.1(e) of the PPAs because it introduced a tax changing the incidence of tax liability after the Proposal Due Date (proposal due date: 23.01.2017).
  • The Petitioner's commercial decisions (e.g., to import modules) taken at bidding/implementation stage cannot be second-guessed after imposition of a subsequent tax; prior Commission orders (e.g., ACME Bhiwadi) support that position.
  • Restitution (restoring to the same economic position) is an integral part of Change in Law compensation; carrying cost and interest on additional working capital are necessary to truly restore the Petitioner to the pre-change economic position.
  • Relied on contractual implication principles (Nabha Power) and decisions such as Sumitomo v. ONGC and Piloo Dhunjishaw Sidhwa to support entitlement to carrying cost and, alternatively, invoked quantum meruit / Section 70 of the Contract Act to support payment of carrying cost if not contractually provided.
  • Pointed to earlier Commission orders (e.g., those concerning projects in the same Rewa solar park) where the Commission treated Safeguard Duty as Change in Law and granted relief; argued identical/factually similar precedents bind (cited Mamleshwar Prasad).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Alopi Parshad and Sons Ltd. v. Union of India (1960) 2 SCR 793 / AIR 1960 SC 588 Relied on by MPPMCL to argue against invoking principles of equity to award carrying cost where PPA lacks such provision. The Commission noted MPPMCL placed reliance on this authority as part of the argument against restitutionary relief; the Commission ultimately decided on the basis of the PPAs and other authorities.
Mamleshwar Prasad & Anr. v. Kanahiya Lal (Dead) Through Legal Representative (1975) 2 SCC 232 Principle that decisions rendered on indistinguishably identical facts and law are binding (precedent binding effect). The Petitioner invoked this principle to argue that earlier Commission decisions on identical facts (Rewa projects) should bind the Commission; Commission considered prior orders but made its decision on contractual terms.
Nabha Power Limited v. Punjab State Power Corporation Ltd. & Anr. (Civil Appeal No.179 of 2017) Used to support implying contractual terms on grounds of business efficacy and commercial common sense (to support carrying cost as part of restitution under Change in Law). Petitioner cited it to argue an implied right to carrying cost; the Commission analysed entitlement primarily against explicit PPA terms and prior Commission/APTEL/Supreme Court decisions.
Sumitomo Heavy Industries Ltd. v. ONGC Ltd. (2010 (1J) SCC 296J) Relied upon to support restitutionary compensation including carrying costs arising from contractual or quasi-contractual claims. Petitioner cited this case in support of carrying cost; Commission evaluated carrying cost claim against PPA provisions and precedents of regulatory tribunals and Supreme Court.
Piloo Dhunjishaw Sidhwa v. Municipal Corporation of the City of Poona [(1970) 1 SCC 213] Invoked in relation to quantum meruit / Section 70 arguments asserting entitlement to compensation for benefit conferred. The Petitioner relied on it as part of a quantum meruit/Section 70 submission; Commission considered contractual remedies and applicable precedents in rejecting carrying cost given PPA wording.
ACME Jaipur Solar Power Pvt. Ltd. & Ors. v/s M.P. Power Management Company Ltd. (Order dated 15.10.2019) Commission held where PPAs lack provision dealing with restitution to the same economic position, claims for separate Interest on Working Capital/Return on Equity/Carrying Costs are not admissible. The Commission treated that Order as squarely applicable to the instant case and relied on its reasoning to conclude claims for separate interest on working capital and carrying cost are not admissible here.
Renew Solar Power Pvt. Ltd. & Ors. v. Solar Energy Corporation of India Ltd. (Petition No. 14/MP/2019) Reliance on applicability of Tariff-based Competitive Bidding Guidelines (03.08.2017) and on interpretation of contractual provisions. DMRC relied on this order to argue the Petitioner was not entitled to carrying costs and interest on incremental working capital; Commission considered it among prior decisions.
ACME Rewa Solar Energy Pvt. Ltd. & Ors. v. SECI & Ors. (Order dated 02.05.2019, Petition No. 342/MP/2018) Commission's prior treatment of Safeguard Duty as Change in Law (considered earlier under similar PPAs). The Commission cited this earlier order when determining that Safeguard Duty falls within Change in Law under the PPAs.
Arinsun Clean Energy Pvt. Ltd. v. M.P. Power Management Company Ltd. and Ors. (connected with 19/MP/2019) (Order dated 15.10.2019) Prior Commission decision on same issue (Safeguard Duty / Change in Law) in Rewa projects; used to show binding value of identical facts. The Petitioner cited this order; the Commission acknowledged prior orders and applied consistent principles but decided on the present record and PPA wording.
ACME Bhiwadi Solar Power Pvt. Ltd. v. SECI & Ors. (Order dated 09.10.2018, Petition No. 187/MP/2018) Held it is not appropriate to question developers' commercial decisions (e.g., supplier selection) made prior to change in law. The Commission referenced this reasoning to find that the Petitioner's procurement choices should not be impugned merely because Safeguard Duty was later imposed.
Adani Power Ltd. v. CERC (APTEL judgment dated 13.04.2018 in Appeal No. 210 of 2017) APTEL allowed carrying cost where the PPA provided for restoration to the same economic position (restitution); carrying cost not applicable where PPA lacks such a provision. The Commission relied on the distinction drawn by APTEL — that carrying cost is permissible where the PPA expressly contemplates restitution; because the instant PPAs lack restitution provisions, APTEL's allowance did not apply here.
M/s GMR Warora Energy Ltd. v. CERC (APTEL judgment dated 14.08.2018, Appeal No. 111 of 2017) APTEL reiterated allowance of carrying cost on Change in Law where PPA provided restitutionary remedy (citing Adani reasoning). The Commission cited this as part of the body of tribunal jurisprudence addressing carrying cost, reinforcing the focus on PPA wording.
Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v. Adani Power Ltd. & Ors. (Supreme Court judgment dated 25.02.2019, Civil Appeals) Supreme Court affirmed that restitutionary principle in relevant PPA clause must be considered when determining carrying cost and compensation; validated APTEL's approach. The Commission relied on the Supreme Court's reasoning to conclude that because the instant PPAs do not provide restitution, the Petitioner's carrying cost/interest claims are not admissible.
Indian Council for Enviro-Legal Action v. Union of India & Ors. Cited in APTEL jurisprudence as supporting restitutionary principles in certain contexts. The Commission referred to this authorities' role in APTEL reasoning but decided the instant matter on the explicit terms of the PPAs and subsequent Supreme Court guidance.
Renew Wind Energy (TN2) Pvt. Ltd. & Ors. (Order dated 05.02.2019, Petition No. 187/MP/2017 & Others) Commission held procurers/respondents cannot question developers' commercial decisions taken prior to a Change in Law event regarding procurement methods. The Commission applied this reasoning to support the conclusion that the Petitioner's procurement choices were commercial decisions and not a ground to deny relief for Change in Law.

Court's Reasoning and Analysis

The Commission followed a structured analysis applying PPA definitions and prior orders:

  1. Definition and timing: The Commission examined the PPA definitions of "Change in Law" (Article 1.1, including part (e) covering modification/introduction of any Tax resulting in a change in incidence of tax liability) and "Taxes" (Article 1.1). It noted the Safeguard Duty Notification dated 30.07.2018 imposed duties on import of solar cells/modules and therefore altered the incidence of tax liability effective 30.07.2018.
  2. Precedential treatment: The Commission referred to its prior orders (e.g., matters disposed on 02.05.2019 and 15.10.2019 concerning Rewa projects) that had treated Safeguard Duty as a Change in Law under comparable PPAs. The Petitioner relied on such prior orders and on the binding effect of identical-fact decisions; the Commission treated those orders as relevant and consistent with its view that the Notification fell within Change in Law.
  3. Threshold limit and single-event characterization: The Commission interpreted Article 17.1(c), which prescribes a Threshold Limit of INR 20,000,000 (Rs. 2 crores) applicable "to each event constituting a Change in Law" and not cumulatively. It concluded the imposition of Safeguard Duty constituted one single event of Change in Law and that the threshold applies accordingly; the Respondents' contention that separate incidences of taxation should be counted independently was rejected due to lack of justification.
  4. Commercial decisions and mitigation: The Commission addressed arguments that the Petitioner should have mitigated by sourcing from jurisdictions not subject to safeguard duty or by earlier procurement. Relying on prior Commission holdings (e.g., ACME Bhiwadi and Renew Wind), it found it inappropriate to question commercial choices taken prior to imposition of the Safeguard Duty and accepted that project implementation/procurement decisions are commercial in nature.
  5. Mechanism for compensation: The Commission observed Article 17.1(e) of the PPAs expressly provides that amounts determined on account of Change in Law can be adjusted either in tariff or by lump-sum payment. Accordingly, it held there was no need to devise a separate compensation mechanism; it directed compensation in a time-bound manner (payment within 60 days or annuity alternative) and required documentary corroboration from the Petitioner to reconcile claims.
  6. Carrying cost / interest on working capital: The Commission carefully analyzed the Petitioner's claim for carrying cost and interest on working capital. It reviewed tribunal (APTEL) decisions (Adani; GMR Warora) that allowed carrying cost where PPAs provided restitution and the Supreme Court's affirmation (Uttar Haryana) that restitutionary clauses in the PPA must be considered. The Commission concluded that the PPAs in the instant case do not contain restitution provisions restoring the developer to the same economic position and, following the reasoning in the cited APTEL and Supreme Court decisions, rejected the Petitioner's separate claim for carrying cost and interest on working capital.
  7. Procedural matters and reconciliation: The Commission directed the Petitioner to furnish documentary proof (invoices and auditors' certificates) showing direct correlation between imported goods and the project up to COD (or extended COD) and instructed Respondents to reconcile claims promptly (within 15 days) so payment could be made within the directed time frame, failing which late payment surcharge per PPA would apply.

Holding and Implications

Final Ruling:

  • The Commission held that the imposition of the Safeguard Duty via Notification No. 1/2018-Customs (SG) dated 30.07.2018 is an event of "Change in Law" under Article 17 (and Article 1.1 parts (a) and (e)) of the PPAs.
  • The Commission directed compensation for the impact of Safeguard Duty: the Petitioner and the Respondents are to settle the compensation either by one-time lump-sum payment within sixty days from the date of the Order or submission of claims (whichever is later), failing which late payment surcharge under the PPAs applies. Alternatively, the parties may agree to an annuity (spread over a period not exceeding the PPA duration) as a percentage of the tariff.
  • Documentary requirement and reconciliation: The Petitioner must provide relevant invoices and auditors' certificates to demonstrate a one-to-one correlation between imported goods and the project up to COD (or extended COD). Respondents must reconcile the claims within 15 days of submission.
  • Carrying cost and interest on working capital: The Commission rejected the Petitioner's separate claim for carrying cost and interest on incremental working capital for the period from imposition of the Safeguard Duty (30.07.2018) because the PPAs in this matter do not contain restitution provisions to restore the same economic position; thus separate carrying cost/interest claims are not admissible.
  • Disposition: The Commission disposed of Petition No. 365/MP/2019 consistent with the above directions.

Implications: The direct consequences for the parties are the Commission's directions for payment, documentation and reconciliation as stated above. The Order applies the PPAs' contractual text and prior Commission/APTEL/Supreme Court authorities to the facts; it does not, on its face, announce a novel legal doctrine beyond applying existing precedent and the PPA terms to these facts.

Note: This summary is confined to the information and findings expressly contained in the provided opinion. No information has been added or inferred beyond the text of that opinion.

To access the original judgment, please Sign In or Subscribe.

    Mahindra Renewables Private Limited v. M.P. Power Management Company Limited And Others

    Limited v- CERC and Ors, in support of the argument that there being no provision in the PPA for restoration to the same economic position, the carrying cost will not be applicable. MPPMCL has also placed its reliance on the judgement of Honble Supreme Court in the matter of Alopi Parshad and Sons Ltd. v. Union of India, (1960) 2 SCR 793 : AIR 1960 SC 588, for the argument against principles of equity and to argue that that the present case is not of amounts being denied/ withheld at appropriate time or any deprivation of amount due to actions of the procurers. Order in Petition No. 365/MP/2019 Page 11 of 33

    27. MPPMCL has submitted that relief for change in law in the case of PPA dated 17.04.2017 between the Petitioner and the Respondent with regard to any tax is available only If the additional capital expenditure, interest and associated costs that the SPD incur as a result of the Change in Law exceeds the Threshold Limit (INR 20,000,000). As per Article 17.1(c), the threshold limit has been prescribed as Rs. 20,000,000 (twenty million) for each incidence of Change in Law and the same is not to be considered on a cumulative basis. Accordingly, each incidence of taxation has to be considered independently and separately and only if the amount of claim in respect to such independent incidence of taxation exceeds the threshold limit, the claim will be admissible. The above has to be considered before determining the liability of the MPPMCL to pay for the Change in Law.

    28. MPPMCL has submitted that impact of change in law, if established by the Commission, should be recovered by way of tariff. The payment by way of lump sum is financially burdensome for MPPMCL. It is also an accepted principle that the capital cost/ capital expenditure is recovered by way of tariff and not as a lump-sum payment. One of the reasons for the same is that the increased costs have been claimed to have been incurred for the purpose of supply of power and, therefore, the costs should be recovered only if the Petitioner makes available the power. If the petitioner does not supply the requisite power, the Petitioner should not be entitled to recover the cost similar to any other capital cost. On the other hand, if the Petitioner is allowed to recover it in lump sum, then the Respondents would have paid for capital cost even if the Petitioner makes short supply of power in the future.

    29. MPPMCL has submitted that as stated by the Petitioner impact of the Safeguard Duty Notification is Rs 132.41 crores. This claim must be put to strict proof thereof and should be examined based on the supporting documents with regard to the import and other relevant materials before considering the claim.

    30. MPPMCL has submitted that the reliance placed by the Petitioner on the Guidelines for Tariff based Competitive Bidding Process issued by the Ministry of Power by notification dated 03.08.2017 is misplaced. In the present case, the Request for Proposal was issued on 16.03.2016, Letter of Award was issued on 21.02.2017 and the PPA was executed on Order in Petition No. 365/MP/2019 Page 12 of 33 17.04.2017. Therefore, the documents governing bidding and procurement process of the solar power from the Petitioner were executed prior to issuance of the Guidelines dated 03.08.2017. Further, Guidelines dated 03.08.2017 issued by Government of India have no retrospective effect but are only prospective in operation. In terms of RFS, the 750 MW solar power project was to be setup in Rewa district of Madhya Pradesh with support from MNRE in accordance with the scheme for Development of Solar Parks and Ultra Mega Solar Power Projects effective from 12.12.2014. Rejoinder of the Petitioner

    31. The Petitioner has reiterated most of the submissions already made in the petition. Therefore, the same have not been reproduced for the sake of brevity. Additionally, the Petitioner has submitted that: a. the business and commercial decisions made by developers, such as opting to import modules as opposed to using domestic modules or importing modules from certain countries and not others, cannot be questioned post the award of the bid since there was no Safeguard Duty imposed on import of solar cells from China and Malaysia or any other country on the date of the bid. b. The Petitioner has set up the project pursuant to a competitive bid process which had factored in the price of modules and other business assumptions based on competitive rates being offered by module suppliers manufacturing modules of good quality and having the inventory to meet the Petitioners demand within the timeframes set out under the PPAs. c. Provisions of PPA nowhere specify or prescribe that modules or any goods required for setting up the project are required to be imported from a specific location or sourced domestically and it is was, therefore, left to the generator to make specific sourcing decisions based on its calculations and assumptions. d. The bid was submitted on an assurance that relief for any event of Change in Law under the PPA post the submission of bid would be provided to the Petitioner. Moreover, in terms of the definition of Change in Law provided in the PPA, the date of signing the supply agreements has no relevance for the purpose of ascertaining whether an event is a Change in Law event or not. e. The grant of carrying cost is in line with the principles enshrined under Section 61(b), (c) and (d) of the Electricity Act, 2003 to conduct generation, transmission and distribution Order in Petition No. 365/MP/2019 Page 13 of 33 on commercial principles. The impact of Change in Law event is to be passed on by way of tariff adjustment effective from the date of adoption, promulgation, amendment, re- enactment or repeal of the law or change in law. This can be achieved only if carrying cost is considered. f. The legal principles/ intent as set out in the Guidelines of the Ministry of Power cannot be ignored while interpreting the contractual terms as set out in the PPA and, therefore, the same should be considered for the purpose of determination of claims of the Petitioner. Hearing held on 07.07.2020

    32. The matter was heard through video conferencing on 07.07.2020. As allowed vide record of proceedings for the hearing, the Respondents filed their written submissions on 14.07.2020 and the Petitioner filed its written submission on 23.07.2020. Submissions of Respondent No.1 (MPPMCL) by way of written submissions

    33. The Respondent No.1 MPPMCL has mostly reiterated its submissions made earlier in reply to the Petition. The same are summarised as under: a. The Petitioner issued notice about change in law as mandated by Article 17 of the PPA on 20.03.2019 i.e. after 8 months. b. The Petitioner has not furnished any details with regard to the imports made before and after 30.07.2018. c. In terms of Article 17 of the PPA, the remedy of the Petitioner to claim compensation for payment of Safeguard Duty on account of imposition of Safeguard Duty effective from 30.07.2018 is against the EPC contractor and not against the Respondent. d. The impact of change in law, if any, should be recovered by way of tariff. The payment by way of lump sum is financially burdensome. It is an accepted principle that capital costs/ capital expenditure is recovered by way of tariff and not as a lump-sum payment. e. Increased costs have been claimed to have been incurred for the purpose of supply of power. These costs should be recovered only if the Petitioner makes available the power. If the petitioner does not supply the requisite power, the petitioner should not be entitled to recover the cost similar to any other capital cost. f. The Petitioners claim on Interest on Working Capital and Carrying Cost are liable to be rejected. Order in Petition No. 365/MP/2019 Page 14 of 33 g. In the event of allowing the claim on Safeguard Duty, the said relief should be confined only to 250 MW for which the PPA has been entered into by the Petitioner with the Respondent. Submissions of Respondent No. 2 (DMRC) by way of written submissions

    34. DMRC has placed its reliance on the Order dated 15.10.2019 in Petition No. 19/MP/2019 and 46/MP/2019, passed by the Commission in the matter of ACME Jaipur Solar Power Pvt. Ltd. &Ors. v/s M.P. Power Management Company Ltd., wherein, while allowing the claim against reimbursement of costs incurred for procurement of the solar modules pursuant to the Safeguard Duty Notification, it was held that, The Commission observes that since the PPAs do not have a provision dealing with restitution principles of restoration to same economic position therefore, the claim regarding separate Interest on Working Capital/Return on Equity/ Carrying Costs is not admissible.

    35. DMRC has submitted that the relevant clauses of the contract including the provisions qua Change in Law i.e. Article 17 in the instant case, are similar to the Change in law clause in the above-stated judgments. Even the date of issuance of RFP, the relevant contractual provisions under the PPA and the location of the projects is similar. Therefore, as per the ratio of the findings rendered by this Commission in the above noted judgments/ orders with regard to the claims against Interest on Working Capital, claim against carrying costs and qua relief of change in law on O&M costs is liable to be rejected, in as much as the principles laid down by this Commission squarely apply to the facts and the circumstances of the instant case.

    36. DMRC has placed its reliance on the order of the Commission in the matter of Renew Solar Power Pvt. Ltd &Ors V/s Solar Energy Corporation of India Ltd. passed in Petition No. 14/MP/2019 as regards applicability of the Guidelines for Tariff Based Competitive Bidding process for Procurement of Power from Grid Connected Solar PV Power Projects issued by the Ministry of Power vide Notification bearing No. 23/27/2017-R&R dated 03.08.2017. Thus, the Petitioner is legally not entitled to claim carrying costs and interest on incremental working capital as prayed for in the Petition. DMRC has further placed its reliance on the Order dated 02.05.2019 passed by the Commission in the matter of ACME Rewa Solar Energy Pvt. Ltd &Ors. V/s Solar Energy Corporation of India Ltd &Ors. passed in the Order in Petition No. 365/MP/2019 Page 15 of 33 Petition No. 342/MP/2018 and submitted that the same applies to the facts of the instant case also.

    37. DMRC has submitted that there is a breach of Article 17 of PPA by the Petitioner. Article 17 of the PPA provides for consequence of Change in Law and the process which needs to be followed by the parties for giving effect to Change in Law event, if any. However, the Petitioner has failed to comply with the terms and conditions of the Article 17.1(b) of the PPA, which envisages joint meeting of the parties for the purposes of demonstrating through evidence that all reasonable efforts for minimizing the effect of Change in Law had been made by the Petitioner. However, in the instant case, the Petitioner has not placed any document on record which in any manner evidences that the Petitioner had used any reasonable endeavour to minimise the effect of the alleged Change in Law.

    38. DMRC has submitted that the PPA was executed between the parties on 17.04.2017. However, the Petitioner awarded the contract for supply of the modules only on 05.02.2018

    i.e. after a period of more than 10 months from the date of signing of the PPA. Had the Petitioner awarded the contract for supply of the modules on a timely basis, no additional costs in the form of Safeguard Duty would have been borne by the Petitioner and its supplier. Submissions of the Petitioner by way of written submissions

    39. The Petitioner has reiterated the submissions made in the Petition. Additionally, the Petitioner has summarised its reply to the various objections raised by the Respondents.

    40. The Petitioner has submitted that by way of the notice for Change in Law, it had notified the Respondents that introduction of the Safeguard Duty on import of solar cells qualifies as a Change in Law event under the PPAs and has resulted in a change in the incidence of tax liability on the Petitioner. It has imported more than 95% of the solar modules as required for the project and, therefore, the additional liability incurred towards taxes on account of imposition of Safeguard Duty on the import of solar modules is Rs.1,33,50,000/-. It had commissioned 235 MW capacity till the date of filing of the petition and the balance capacity was commissioned on 03.01.2020. Introduction of the Safeguard Duty is a Change in Law event under the PPA Order in Petition No. 365/MP/2019 Page 16 of 33

    41. The Petitioner has submitted that the imposition of the Safeguard Duty is a Change in Law event under Article 17 read with Article 1.1 of the respective PPAs. A bare perusal of the definition as contained in the PPAs makes it abundantly clear that the introduction of any new tax resulting in a change in the incidence of tax liability would be a Change in Law event, if such event has occurred subsequent to the proposal due date as set out in the RfP i.e. 23.01.2017. Further, the Commission in its Order dated 15.10.2019 passed in 46/MP/2019 titled Arinsun Clean Energy Private Limited vs. M.P. Power Management Company Limited and Ors. (connected with 19/MP/2019) decided on the same issue with respect to the project of other solar power generators located in the same solar park as that of the Petitioners i.e. in Rewa, Madhya Pradesh. It is a well settled principle that the precedents with identical facts have binding value. In this regard, the Petitioner has placed its reliance on the judgement of the Honble Supreme Court dated 04.03.1975 in Mamleshwar Prasad and Another vs. Kanahiya Lal (Dead) Though Legal Representative (1975) 2 SCC 232 wherein it was categorically held that when a decision rendered on facts and law, indistinguishably identical, such decision must bind. Petitioner has the right to make its commercial decisions

    42. The Petitioner has submitted that the business and commercial decisions such as opting to import modules as opposed to using domestic modules or importing modules from certain countries and not others, cannot be questioned post award of the bid. It is pertinent to note that since there was no Safeguard Duty imposed on import of solar cells from China and Malaysia or any other country on the date of the bid, the Petitioner could not have taken into account the cost of the same while submitting its bid. The Petitioner has placed its reliance on the Commissions order dated 09.10.2018 passed in Petition No. 187/MP/2018 titled as ACME Bhiwadi Solar Power Private Limited vs. SECI and Ors in which it was held that it would not be appropriate to question such commercial decisions. Prudent call

    43. The Petitioner has submitted that it had submitted its bid after considering the market and economic conditions prevailing then and since the Safeguard Duty Notification was issued subsequent to the proposal due date as provided in the RFP, its impact could not be factored at the time of bid submission. The PPAs provide a clear remedy and relief in case of Order in Petition No. 365/MP/2019 Page 17 of 33 occurrence of a Change in Law event. Therefore, the diligence and prudent business call made by the Petitioner cannot be questioned. Carrying cost/Interest on Working Capital

    44. The Petitioner has submitted that it is entitled to carrying cost on additional costs incurred by it on account of imposition of Safeguard Duty since the essence of Change in Law clause under Article 17 of the PPAs is to restore the affected party to the same economic position as if the said Change in Law event had not occurred. As restitution is an integral part of the compensation granted under Change in Law, carrying cost is to be allowed as part of compensation on account of the Change in Law provision.

    45. The Petitioner has submitted that the economic position which is sought to be restored in terms of the Change in Law clause does not limit itself to a simple correlation of increased expenditure and a corresponding compensation amount but also ought to include compensation in terms of carrying costs incurred with respect to the said Change in Law events. This is also supported by the principle of business efficacy, in the case of Nabha Power Limited v. Punjab State Power Corporation Limited and Anr. [Civil Appeal No. 179 of 2017] which provides that a contractual term can be implied in light of the express terms of the contract, commercial common sense and the facts known to both parties at the time of entering into the contract. Further, a Change in Law clause being a restitution clause, demands that the Petitioner should be compensated for all necessary and reasonable extra costs including carrying cost and/or interest on the additional cost incurred on account of Change in Law. In this regard, the Petitioner has placed reliance on the case of Sumitomo Heavy Industries Limited v. ONGC Limited, reported at [2010 (1J) SCC 296J].

    46. The Petitioner has submitted that it is also entitled to carrying cost under the principles of quantum meruit. Assuming the alternative argument that there is no implied clause in the PPA for payment of carrying cost and/or interest, the principles of quantum meruit as statutorily enshrined in Section 70 of the Contract Act, 1872 will be attracted and the Petitioner would be entitled to carrying cost. Section 70 of the Act provides that where a person lawfully does anything for another person and does not do so gratuitously, and such other person enjoys the benefit thereof, the latter is bound to make compensation to the former in respect of, or to restore, the thing so done or delivered. In view thereof, since the Order in Petition No. 365/MP/2019 Page 18 of 33 Petitioner has not incurred additional capital cost on account of introduction of the Safeguard Duty gratuitously, it is entitled to compensation for the same and such compensation has to be for all reasonable costs, including carrying cost. In this regard, the Petitioner has placed reliance on the decision in the case of Piloo Dhunjishaw Sidhwa v. Municipal Corporation of the City of Poona, [(1970) 1 SCC 213. Analysis and Decision

    47. We have heard the learned counsels for the Petitioner and the Respondents and have carefully perused the records.

    48. The brief facts of the case are that the Respondent No.1, MPPMCL issued RfS dated 16.03.2013 for SPDs for development of Rewa Solar Project of 750 MW (3 x 250 MW). The Petitioner was declared as a successful bidder for development of one unit of 250 MW capacity of the 750 MW Rewa Solar Project. The Petitioner was awarded LOI on 21.02.2017 for project development and sale of solar power to MPPMCL and DMRC (Respondent No.

    2). Thereafter, the Petitioner signed two PPAs dated 17.04.2017 with MPPMCL and DMRC respectively for 78% and 22% of the power respectively to be generated by the Project of the Petitioner, at a tariff of INR 2.979/kWh with escalation of 5 paise/kWh every year till the 16th year of the PPAs. Subsequent to signing of PPAs on 17.04.2017, the Central Government imposed Safeguard Duty vide Safeguard Duty Notification dated 30.07.2018 as per the following rates on the import of solar cells and modules:- a. 25% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th July 2018 to 29th July 2019; b. 20% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th July 2019 to 29th January 2020; c. 15% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th January 2020 to 29th July 2020.

    49. The Petitioner has submitted that issuance of Safeguard Duty Notification has resulted in an increase in recurring and non-recurring expenditure for the Petitioner and has adversely impacted its business. The imposition of Safeguard Duty is covered under Article 17 of the PPAs which provides for Change in law and requested that relief for such Change in Law may be allowed. It is also entitled to interest on incremental working capital and carrying Order in Petition No. 365/MP/2019 Page 19 of 33 cost to put Petitioner in the same economic position as if change in law has not occurred. Per Contra, the Respondents in their reply have submitted that application of Safeguard Duty Notification is prospective in nature; the Petitioner should rather claim compensation for payment of Safeguard Duty from its EPC contractor and it is not a change in law in terms of the PPAs. Respondents also denied claim of interest of working capital and carrying cost as there is no provision of restitution in the PPAs.

    50. Before dealing with specific claims of the Petitioner, it is imperative that we first dispose of some preliminary objections raised by the Respondents. It has been submitted by the Respondents that the claim of Safeguard Duty by the Petitioner is subject to challenge to the imposition of such duty pending before the Honble Supreme Court/ High Court.

    51. The Commission observes that a number of writ petitions were filed before various High Courts against imposition of Safeguard Duty. In one such writ petition, WP(C) No. 12817/2018 filed before the Honble Orissa High Court, the Honble Court in I.A. No. 10566/2018 vide Interim Order dated 23.07.2018, instructed Union of India not to issue any notification under Rule 12 of the Customs Tariff (Identification and Assessment of Safeguard Duty) Rules, 1997 without the leave of the Court. A special leave petition SLP (C) 24009- 24010/2018 was filed in Honble Supreme Court against this interim order of Honble Orissa High Court. The Honble Supreme Court vide order dated 10.09.2018 stayed the said interim order dated 23.07.2018 and also stayed further proceedings in WP(C) No. 12817/2018 pending before Honble Orissa High Court. Therefore, there is no stay from Honble Supreme Court/ High Court on the matter and therefore, we can proceed with deciding on the claims of the Petitioner. Needless to mention, if any judgement is pronounced by Honble Supreme Court or High Courts, the same will be applicable.

    52. We now proceed to deal with the issues on merit. From the submissions of the parties, the following issues arise for adjudication: Issue No.1: Whether the imposition of Safeguard Duty on the import of solar modules/ panels/ cells can be considered an event covered under Change in Law in terms of the Article

    17 of the PPAs? And whether there is a need to evolve a suitable mechanism to compensate the Petitioner for the increase in recurring and non-recurring expenditure incurred by the Petitioner on account of Change in Law? Order in Petition No. 365/MP/2019 Page 20 of 33 Issue No. 2: Whether the Petitioner may be restored to the same economic condition prior to occurrence of the Change in Law through suitable mechanism? And whether the claim of Petitioner regarding interest on Working Capital and Carrying Cost for delay in reimbursement by the Respondents is sustainable?

    53. No other issue was pressed or claimed. We now discuss the issues one by one. Issue No.1: Whether the imposition of Safeguard Duty on the import of solar modules/ panels/ cells can be considered an event covered under Change in Law in terms of the Article 17 of the PPAs? And whether there is a need to evolve a suitable mechanism to compensate the Petitioner for the increase in recurring and non-recurring expenditure incurred by the Petitioner on account of Change in Law?

    54. Change in law has been defined under Article 1.1 of the PPAs as under:- Change in Law means the occurrence of any of the following events in India, subsequent to the Proposal Due Date (as defined in the RFP), and such event(s) has/have an impact on the Unit or on any of the rights and obligations of the Parties under any of the Project Agreements: (a) the modification, amendment, variation, alteration or repeal of any existing Applicable Laws; (b) the enactment of any new Applicable Law or the imposition, adoption or issuance of any new Applicable Laws by any Government Authority; (c) changes in the interpretation, application or enforcement of any Applicable Laws or judgment by any Government Authority; (d) the introduction of a requirement for the SPD to obtain any new Applicable Permit; (e) the modification, amendment, variation, introduction, enactment or repeal of any Tax, resulting in a change in the incidence of Tax liability, including pursuant to any Applicable Laws promulgated or to be promulgated in furtherance of the Constitution (122ndAmendment) Bill, 2014. It is clarified that for the purposes of Change in Law, Taxes shall not include taxes on corporate income, any withholding tax on dividends distributed to the shareholders of the SPD or income tax.

    55. Taxes has been defined under the Article 1.1 of the PPAs as under: Taxes means any Indian taxes, whether direct or indirect, including levies, imposts, cesses, duties and other forms of taxation, including income tax, sales tax, value added tax, octroi, entry tax, corporation profits tax, advance corporation tax, capital gains tax, residential and property tax, customs and other import and export duties, excise duties, stamp duty or capital duty (whether central, state or local) on the goods, materials, equipment and services incorporated in and forming part of the Unit charged, levied or imposed by any Government Authority, but excludes any interest, penalties and other sums in relation thereto imposed on any account whatsoever.

    56. Article 17 of the PPAs provides for Change in Law which stipulates as under: -

    17. Change in Law 17.1 Consequences of Change in law (a) If a Change in Law occurs or is shortly to occur, then a Party shall notify the other Parties expressing its opinion on its likely effects and giving details of its opinion of Order in Petition No. 365/MP/2019 Page 21 of 33 whether:

    (i) any changes are required to the scope of work to be performed by the SPD under this Agreement;

    (ii) any changes are required to the terms of this Agreement to deal with such Change in Law;

    (iii) relief from compliance with any obligations is required, including the obligation of the SPD to achieve the Unit SCOD;

    (iv) any increase or decrease in costs (other than incurring additional capital expenditure), or any increase in Taxes or delay is likely to result from the Change in Law; and

    (v) any capital expenditure is required or no longer required as a result of a Change in Law. (b) As soon as practicable but no later than 15 (fifteen) Days after receipt of any notice from a Party under Article 170 1 ( a), the Parties shall discuss the issues referred to therein and any ways in which the Parties can mitigate the effect of the Change in Law, including:

    (i) demonstrating that the SPD has used reasonable endeavours (including, where practicable, the use of competitive quotes) to minimise any increase in costs and maximise any reduction in costs;

    (ii) demonstrating how any capital expenditure to be incurred or avoided is being measured in a cost effective manner, including showing that when such expenditure is incurred or would have been incurred, foreseeable Changes in Law at that time have been taken into account by the SPD;

    (iii) demonstrating as to how the Change in Law has affected prices charged by similar businesses to the Unit, including similar businesses in which the shareholders or their associates carry on business;

    (iv) demonstrating to the Procurer that the Change in Law is the direct cause of the increase or decrease in costs and/or loss or gain of revenue or delay and the estimated increase or decrease in costs or loss or gain in net profits after Tax could not reasonably be expected to be mitigated or recovered by the SPD acting in accordance with Good Industry Practice; and

    (v) demonstrating that any expenditure, which was anticipated to be incurred to replace or maintain assets that have been affected by the Change in Law, has been taken into account in the amount stated in its opinion presented under Article l7.1 (a). (c) If the Parties have complied with Article 17.1 (b) or upon elapse of the time specified in the Article 17.1 (b) and if the SPD is required to incur any additional costs, including additional capital expenditure due to a Change in Law the aggregate financial effect of which, over the remaining Term of the PPA, is up to INR 20,000,000 (twenty million) (Threshold Limit), then the SPD shall obtain funding for such additional costs, including capital expenditure, at its cost and expense. The SPD shall bear all additional capital expenditure and/or interest and additional costs incurred to obtain any funding to the extent of the Threshold Limit. For the avoidance of doubt, it is clarified that the Threshold Limit shall apply to each event constituting a Change in Law and shall not be applied on a cumulative basis. If the additional capital expenditure, interest and associated costs that the SPD may incur as a result of the Change in Law exceeds the Threshold Limit, then the Procurer or the SPD shall approach the Appropriate Commission to seek approval of such Change in Law and the consequent impact on the Applicable Tariff. (d) If the Parties have complied with Article 17.l(b) or upon elapse of the time specified in the Article 17.l (b) and if as a result of the Change in Law, there is a decrease in costs, or decrease Order in Petition No. 365/MP/2019 Page 22 of 33 in Taxes and/or gain in revenue or net profits after Tax, then any financial benefit accruing to the SPD on account of such decrease in costs, or decrease in Taxes and/or gain in revenue or net profits after Tax shall be passed through to the Procurer in its entirety. (e) The amount determined in accordance with Article 17.l(c) and Article 17.l(d) in the eventuality of any increase or decrease in cost ( or decrease or increase in revenues or net profits after Tax) of the SPD on account of a Change in Law shall be adjusted either in the Tariff Payment or through a lump sum payment, and shall be paid through a Supplementary Bill to be raised by either the SPD or the Procurer in terms of Article 10. In case of any change in the Applicable Tariff by reason of Change in Law, as determined in accordance with this Agreement, the Monthly Bill to be raised by the SPD after such change in Applicable Tariff shall appropriately reflect the changed Applicable Tariff and the Procurer agrees to pay the revised Applicable Tariff accordingly.

    57. Additionally, the DMRC PPA has following provisions under Article 17.1 (c). If the additional capital expenditure, interest and associated costs that the SPD may incur as a result of the Change in Law exceeds the Threshold Limit, then the Parties agree and confirm that the decision of the Appropriate Commission applicable to the SPD and MPPMCL for such Change in Law event under the MPPMCL PPA shall be applicable to DMRC and the SPD, under this Agreement. The SPD shall immediately forthwith inform the Procurer of the decision of the Appropriate Commission or the appellate authority as the case may be.

    58. The Commission observes that Safeguard Duty Notification imposed Safeguard Duty as per the following rates on the import of solar cells, whether or not assembled in modules or panels:- a. 25% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th July 2018 to 29th July 2019; b. 20% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th July 2019 to 29th January 2020; c. 15% ad valorem, minus anti-dumping duty, if any, when imported during the period from 30th January 2020 to 29th July 2020.

    59. The Commission observes that as per part (e) of the definition of Change in law as contained in Article 1.1 of the PPAs, the modification, amendment, variation, introduction, enactment or repeal of any Tax, resulting in a change in the incidence of tax liability is covered under Change in Law. The Safeguard Duty Notification stipulates that a safeguard duty at twenty five per cent to fifteen per cent ad valorem minus anti-dumping duty payable has been levied on Solar Cells whether or not assembled in modules or panels when imported into India during the period from 30th July, 2018 to 29th July, 2020 (both days inclusive). The Notification provides for a diminishing Safeguard Duty in the range of Order in Petition No. 365/MP/2019 Page 23 of 33 25% to 15% ad valorem as applicable on the imports from 30.07.2018 till 29.07.2020. The impact of Safeguard Duty Notification is on any portion of import whose point of taxation is on or after the Notification dated 30.07.2018.

    60. The issue of Safeguard Duty as change in law was considered by the Commission in Petition No 342/MP/2018 and Petition No. 343/MP/2018 vide order dated 02.05.2019. The relevant extract of the order is as under:

    133. From the above, it is apparent that any tax or application of new tax on supply of power covers the taxes on inputs required for such generation and supply of power to the Distribution Licensees. In the instant case, Safeguard Duty has been levied on import of Solar Cells whether or not assembled in modules or panels. The change in duties/ tax imposed by the Central Government has resulted in the change in cost of the inputs required for generation.

    134. Accordingly, the Commission of the view that as per the Government of India Notification No. 01/2018-Customs (SG) dated 30.07.2018 and provision of PPAs related to change in law the imposition of the Safeguard Duty is covered under Change in Law under first, second and sixth bullet of Article 12 of the PPAs.

    135. The Commission observes that the Notification No. 01/2018-Customs (SG) New Delhi dated 30.07.2018 stipulates that a safeguard duty at twenty five per cent to fifteen per cent ad valorem minus anti-dumping duty payable has been levied on Solar Cells whether or not assembled in modules or panels when imported into India during the period from 30th July, 2018 to 29th July, 2020 (both days inclusive). The Commission observes that since the duration of the safeguard duty levied is two years, hence as per requirement of the Customs Tariff Act, 1975 the duty is progressively liberalized at regular intervals during the period of its imposition. The notification provides for a diminishing Safeguard Duty slab in the range of 25% to 15% applicable ad valorem on the imports from 30.07.2018 till 29.07.2020. The impact of Safeguard Duty notification is on/any portion of import whose point of taxation is on or after implementation of the Notification dated 30.07.2018 the same will be subjected to purview of Safeguard Duty.

    136. The Commission is of the view that Safeguard Duty became effective from 30.07.2018 and hence the date of notification becomes the cut-off date for imposing the same. Meaning thereby, the notification/imposition of Safeguard Duty will directly affect the projects where Solar Cells whether or not assembled in modules or panels were imported on or after 30.07.2018 where:-

    a) the bids have been accepted and crystalized before 30.07.2018 or the Power Purchase Agreements have been executed before 30.07.2018 and the Scheduled Date of Commissioning of the project is after 30.07.2018; OR

    b) the bids have been accepted and crystalized before 30.07.2018 or the Power Purchase Agreements have been executed before 30.07.2018 and the Scheduled Date of Commissioning of the project is before 30.07.2018 but the same stands extended after the cut-off date i.e. 30.07.2018 due to the circumstances permitted under provisions of the executed PPAs; Order in Petition No. 365/MP/2019 Page 24 of 33

    61. Subsequently, vide order dated 15.10.2019 in Petition No. 19/MP/2019 and Petition No. 46/MP/2019, where the provisions of the PPA have the same provisions as in the instant Petition, the Commission held as under:

    74. The Commission observes that in the instant petitions, the Proposal Due Date which assumes relevance for determination of change in law event is 23.01.2017 as per Schedule 1 of the RfS dated 16.03.2016 read with Addendum39 dated 06.01.2017. The PPAs were executed on 17.04.2017, and Safeguard Duty has been levied on import of Solar Cells whether or not assembled in modules or panels on 30.07.2018 i.e. before the SCoD of the projects which is 16.11.2018. The change in duties/ tax imposed by the Central Government has resulted in the change in cost of the inputs required for generation. Accordingly, the Commission is of the view that as per the Safeguard Duty Notification and provision of PPAs related to change in law the imposition of the Safeguard Duty is covered under Change in Law Article 1.1(a) and 17 of the PPAs.

    62. The Commission also observes that in the instant petition, the PPAs were executed on 17.04.2017. Further, as per Article 4.1(b) read with Article 2.1 of PPAs, SCOD works out to 16.11.2018. PPAs also provide for extension of SCOD. As such, the SCOD is 16.11.2018 or a later date as extended in terms of the provisions of PPAs. However, the petition does not mention the actual date of commissioning of the unit (s)/project(s). Safeguard Duty has been levied on import of Solar Cells whether or not assembled in modules or panels on 30.07.2018 i.e. after the PPAs were signed and before SCOD of the projects. As per Article 1 of the PPAs, the occurrence of any of the following events in India, subsequent to the Proposal Due Date (as defined in the RFP), and such event(s) has/have an impact on the Unit or on any of the rights and obligations of the Parties under any of the Project Agreements has been defined as Change in Law. The Proposal Due Date as per PPAs is 23.01.2017. The Safeguard Duty imposed by the Central Government through the Safeguard Duty Notification has resulted in the increase in cost for the Petitioner. Accordingly, the Commission is of the view that the Safeguard Duty Notification imposing the Safeguard Duty is covered under part (a) and part (e) of the definition of Change in Law read with definition of Taxes under Article 1.1 and Article 17 of the PPAs.

    63. The Respondents have contended that in terms of the Change in Law provisions, the relief for change in law is available only If the additional capital expenditure, interest and associated costs that the SPD incur as a result of the Change in Law exceeds the Threshold Limit (INR 20,000,000). As per Article 17.1(c) of the PPA, the threshold limit has been prescribed as Order in Petition No. 365/MP/2019 Page 25 of 33 Rs. 2,00,00,000 (Rs. two crores) for each incidence of Change in Law and is not to be considered on a cumulative basis. .

    64. On the other hand, the Petitioner has submitted that the Threshold Limit as specified in the PPAs applies to each event constituting a Change in Law and not to each incidence of taxation. The imposition of Safeguard Duty constitutes a single event of Change in Law in terms of the relevant definitions of the PPAs, and entitles the Petitioner to claim relief under the PPAs as its financial impact exceeds the Threshold Limit set out under the PPAs.

    65. Article 17.1(c) of the PPAs stipulates as under:

    17. Change in Law 17.1 Consequences of Change in law (c) If the Parties have complied with Article 17 .1 (b) or upon elapse of the time specified in the Article 17.1 (b) and if the SPD is required to incur any additional costs, including additional capital expenditure due to a Change in Law the aggregate financial effect of which, over the remaining Term of the PPA, is up to INR 20,000,000 (twenty million) (Threshold Limit), then the SPD shall obtain funding for such additional costs, including capital expenditure, at its cost and expense. The SPD shall bear all additional capital expenditure and/or interest and additional costs incurred to obtain any funding to the extent of the Threshold Limit. For the avoidance of doubt, it is clarified that the Threshold Limit shall apply to each event constituting a Change in Law and shall not be applied on a cumulative basis. If the additional capital expenditure, interest and associated costs that the SPD may incur as a result of the Change in Law exceeds the Threshold Limit, then the Procurer or the SPD shall approach the Appropriate Commission to seek approval of such Change in Law and the consequent impact on the Applicable Tariff.

    66. Thus, Article 17.1(c) provides that the SPD i.e. Petitioner shall bear all additional capital expenditure and/or interest and additional costs incurred to obtain any funding to the extent of the Rs. 2.00 crores (Threshold Limit). Further, the Threshold Limit shall apply to each event constituting a Change in Law and shall not be applied on a cumulative basis.

    67. Plain reading of the Article 17.1(c) makes it clear that different events of change in law should not be clubbed to claim benefits of change in law on cumulative basis. Though the Respondents have raised this issue, but they have not substantiated as to how the imposition of Safeguard Duty is not a single event. In our view, the imposition of Safeguard Duty constitutes one single event of Change in Law in terms of Article 17.1(c) of the PPA and the Order in Petition No. 365/MP/2019 Page 26 of 33 threshold limit of Rs. 2,00,00,000/- is to be applicable accordingly. The contention of the Respondents is, therefore, rejected.

    68. Another argument of MPPMCL is that the Petitioner was duty bound to employ a cost- effective approach as it was under an obligation to mitigate and procure the solar cells from such countries where the import is not subject to Safeguard Duty. On the other hand, the Petitioner has submitted that none of the provisions of the PPAs prescribe that the goods required for establishing the solar power generating stations be sourced from a specific location to avoid the impact of a Change in Law event. Since Safeguard Duty was not prevalent at the time of bid submission, it could not have factored in at the time of quoting the bid tariff. The Petitioner has submitted that it had selected its module supplier after considering several techno-commercial factors and its decision to source its supplies from a specific module supplier cannot be considered imprudent merely due to a subsequent imposition of the Safeguard Duty.

    69. The Commission is of the view that the decision for project implementation including the mode of procurement of goods and services were taken by the Petitioner at the time of bidding and prior to imposition of the Safeguard Duty. It would not be appropriate to question such commercial decisions.

    70. Another point raised by MPPMCL is that the Petitioner has entered into a Supply and Erection & Commissioning Services Agreement dated 05.02.2018 with Mahindra Susten Private Limited (EPC contractor) for, inter alia, supply of solar PV modules, a key component of a solar power plant constituting a major portion/ approximately 60% of a solar power projects total cost (EPC contract). In view of the above, MPPMCL has submitted that the imposition of the Safeguard Duty, if any, is on the suppliers/ importers.

    71. The Commission is of the view that the Petitioner is well within its rights to execute the EPC contract and to schedule with the EPC contractor, imports to match its plans for implementation of the project. These are purely commercial decisions made by the Petitioner. Further, the Commission in its Order dated 05.02.2019 passed in Petition No. 187/MP/2017 & Others in case of M/s Renew Wind Energy (TN2) Private Limited & Ors has already held that the procurers/ Respondents cannot question the commercial decisions of the solar power Order in Petition No. 365/MP/2019 Page 27 of 33 developers for project implementation including mode of procurement of goods and services taken by the solar power developers prior to the Change in Law event.

    72. The Petitioner has requested that in order to provide relief to it, there is the need to evolve a suitable mechanism for compensation. The Respondent MPPMCL has submitted that in case the Safeguard Duty is declared as a change in law event in terms of the PPA, the amount should be recovered by way of tariff and that payment by way of lump sum is financially burdensome for the Respondents. It has submitted that the Petitioner has claimed increased costs for the purpose of supply of power and, therefore, the costs should be recovered only if the Petitioner makes available the power. If the Petitioner does not supply the requisite power, the Petitioner should not be entitled to recover the cost similar to any other capital cost. It has submitted that if the Petitioner is allowed to recover it in lump sum, the Petitioner would have recovered this cost even if there is short supply of power in the future. MPPMCL has referred to Article 17.1(e) of the PPA that provides for adjustment of the amount determined by the Commission to be payable on account of Change in Law either in tariff payment or through a lump sum payment..

    73. We have considered the submissions of the parties. We note that Article 17.1(e) of the PPA provides for lumpsum payment or recovery through tariff to compensate for a change in law event. We, therefore, do not find a need to devise any separate mechanism for compensation. In our view, compensation on account of imposition of Safeguard Duty w.e.f. 30.07.2018 should be discharged by the Petitioner and the Respondents as one-time payment in a time bound manner within sixty days from the date of issue of this Order or from the date of submission of claims by the Petitioner, whichever is later, failing which it shall attract late payment surcharge as per rates provided in the PPAs. Alternatively, the parties may mutually agree to a mechanism for the payment of such compensation on annuity basis spread over such period not exceeding the duration of the PPAs as a percentage of the tariff agreed in the PPAs. This will obviate the hardship of the Respondents for one-time payment.

    74. The Commission directs the Petitioner to make available to the Respondents, all relevant documents exhibiting clear and one to one correlation between the projects and the supply of imported goods till the COD as per PPA or till the COD upon extension of SCOD in terms of PPA, duly supported by relevant invoices and Auditors Certificate. The Respondents are Order in Petition No. 365/MP/2019 Page 28 of 33 further directed to reconcile the claims for Change in Law on receipt of the relevant documents from the petitioner and pay the amount.

    75. The issue is decided accordingly. Issue No. 2: Whether the Petitioner may be restored to the same economic condition prior to occurrence of the Change in Law through suitable mechanism? And whether the claim of Petitioner regarding interest on Working Capital and Carrying Cost for delay in reimbursement by the Respondents is sustainable?

    76. The Petitioner has submitted that Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects have been issued by the Ministry of Power vide notification No. 23/27/2017-R&R. dated 03.08.2017. Under the provisions of Section 63 of the Electricity Act, 2003 for the long term procurement of electricity by distribution licensees from grid-connected Solar PV Power Projects having a size of 5 MW and above through competitive bidding, Para 5.7.1 of these Guidelines states that if any Change In Law event results in any adverse financial loss/ gain to the Solar Power Developer, the Solar Power Developer/ Procurer shall be entitled to compensation by the other party in order to ensure that the Solar Power Developer is placed in the same financial position as it would have been, had it not been for the occurrence of the Change in Law event.

    77. Per contra, MPPMCL has submitted that reliance placed by the Petitioner on these Guidelines issued by Ministry of Power (by Notification dated 03.08.2017) is misplaced. In the present case, the Request for Proposal was issued on 16.03.2016, Letter of Award was issued on 21.02.2017 and the PPAs were executed on 17.04.2017. Therefore, the documents governing bidding and procurement process of the solar power from the Petitioner were executed prior to issuance of the Guidelines dated 03.08.2017. Further, Guidelines dated 03.08.2017 of the Government of India do not have retrospective application. DMRC has submitted that the matter in the instant petition is very similar to that in the Petition No. 19/MP/2019 and 46/MP/2019 in which the Commission has already passed Order dated 15.10.2019 in matter of ACME Jaipur Solar Power Pvt. Ltd. & Ors. v/s M.P. Power Management Company Ltd. DMRC has further submitted that the relevant clauses of the contract including the provisions qua Change in Law i.e. Article 17 in the instant case, are similar to the Change in law clause in the above noted judgments. Even the date of issuance Order in Petition No. 365/MP/2019 Page 29 of 33 of RFP, the relevant contractual provisions under the PPA, the location of the Projects are similar. Therefore, as per the ratio of the findings rendered by this Commission in the above noted judgments/orders, the claims against Interest on Working Capital, Claim against Carrying Costs and qua relief of Change in law on O&M costs are liable to be rejected, in as much as the principles as laid down by this Commission squarely apply to the facts and the circumstances of the instant case.

    78. The Commission vide order dated 15.10.2019 in Petition No. 19/MP/2019 and Petition No. 46/MP/2019 in the matter of ACME Jaipur Solar Power Pvt. Ltd. & Ors. v/s M.P. Power Management Company Ltd. held as under:

    87. The Commission observes that the Para 5.7.1 of the 2017 Guidelines stipulates as under: 5.7.1. In the event a Change in Law results in any adverse financial loss/ gain to the Solar Power Generator then, in order to ensure that the Solar Power Generator is placed in the same financial position as it would have been had it not been for the occurrence of the Change in Law, the Solar Power Generator/ Procurer shall be entitled to compensation by the other party, as the case may be, subject to the condition that the quantum and mechanism of compensation payment shall be determined and shall be effective from such date as may be decided by the Appropriate Commission.

    88. The Commission is of the view that the PPAs stand executed and the Petitioners did not raise any objections regarding PPAs not being consistent with the Tariff Guidelines. In view of the above, the provisions of the PPAs have become final and binding on the Petitioners and Respondents. Further, the Petitioners have neither approached the Commission for the alignment of the PPAs with the Tariff Guidelines nor is there a prayer in the petition to this effect. In view of the above, the Commission decides to proceed with the matter taking into consideration only the PPAs as presented before us.

    79. The above order is squarely applicable in the instant case. Therefore, claims of the Petitioner have to be decided taking into consideration only the PPAs.

    80. The Petitioner has claimed carrying cost for the change in law event and prayed that it may be restored to the same economic position as if change in law had not occurred. The Petitioner has submitted that restitution is an integral part of the compensation granted under Change in Law and, therefore, carrying cost is to be allowed as part of compensation on account of the Change in Law provision. The Petitioner has submitted that the economic position which is sought to be restored in terms of the Change in Law clause does not limit Order in Petition No. 365/MP/2019 Page 30 of 33 itself to a simple correlation of increased expenditure and a corresponding compensation amount but also ought to include compensation in terms of carrying costs incurred with respect to the said Change in Law events.

    81. On the other hand, the Respondents have submitted that there being no provision of carrying cost or restitution to the same economic position in the PPAs, the Petitioner cannot be allowed any carrying cost. They have referred to various orders of the Commission in this regard.

    82. The issue of carrying cost has been dealt with by APTEL in its judgement dated 13.04.2018 in Appeal No. 210 of 2017 in Adani Power Limited v. Central Electricity Regulatory Commission and Ors. and it was held that since Gujarat Bid-01 PPA had no provision for restoration to the same economic position, the decision of allowing carrying cost will not be applicable. The relevant extract of the Judgment dated 13.04.2018 reads as under: ISSUE NO.3: DENIAL OF CARRYING COST

    x. Further, the provisions of Article 13.2 i.e. restoring the Appellant to the same economic position as if Change in Law has not occurred is in consonance with the principle of restitution i.e. restoration of some specific thing to its rightful status. Hence, in view of the provisions of the PPA, the principle of restitution and judgement of the Hon'ble Supreme Court in case of Indian Council for Enviro-Legal Action vs. Union of India &Ors., we are of the considered opinion that the Appellant is eligible for Carrying Cost arising out of approval of the Change in Law events from the effective date of Change in Law till the approval of the said event by appropriate authority. It is also observed that the Gujarat Bid-01 PPA have no provision for restoration to the same economic position as if Change in Law has not occurred. Accordingly, this decision of allowing Carrying Cost will not be applicable to the Gujarat Bid-

    01 PPA.

    83. While dealing with the issue of carrying cost, in another matter, APTEL in its judgement dated 14.08.2018 in Appeal No. 111 of 2017 in the matter of M/s. GMR Warora Energy Limited v. Central Electricity Regulatory Commission and Ors., held as under:

    xiii. Now we have reached to the final issue raised by GWEL related to carrying cost on the allowed Change in Law events. For the sake of brevity we are not discussing the claims of GWEL and counter claims of the Discom/Prayas Energy Group on this issue as the said issue has been decided by this Tribunal vide judgement dated 13.4.2018 in Appeal No. 210 of 2017 in case of Adani Power Ltd. v. CERC wherein this Tribunal after detailed analysis has allowed carrying cost on the allowable Change in Law events. We straight way come to the relevant portion of the said judgement which is reproduced below:

    12 d) ................

    ix. In the present case we observe that from the effective date of Change in Law the Appellant is subjected to incur additional expenses in the form of arranging for working Order in Petition No. 365/MP/2019 Page 31 of 33 capital to cater the requirement of impact of Change in Law event in addition to the expenses made due to Change in Law. As per the provisions of the PPA the Appellant is required to make application before the Central Commission for approval of the Change in Law and its consequences. There is always time lag between the happening of Change in Law event till its approval by the Central Commission and this time lag may be substantial. As pointed out by the Central Commission that the Appellant is only eligible for surcharge if the payment is not made in time by the Respondents Nos. 2 to 4 after raising of the supplementary bill arising out of approved Change in Law event and in PPA there is no compensation mechanism for payment of interest or carrying cost for the period from when Change in Law becomes operational till the date of its approval by the Central Commission. We also observe that this Tribunal in SLS case after considering time value of the money has held that in case of redetermination of tariff the interest by a way of compensation is payable for the period for which tariff is re-determined till the date of such re-determination of the tariff. In the present case after perusal of the PPAs we find that the impact of Change in Law event is to be passed on to the Respondents Nos. 2 to 4 by way of tariff adjustment payment as per Article 13.4 of the PPA. The relevant extract is reproduced below: 13.4 Tariff Adjustment Payment on account of Change in Law 13.4.1 Subject to Article 13.2 the adjustment in Monthly Tariff Payment shall be effective from (a): the date of adoption, promulgation, amendment, re-enactment or repeal of the Law or Change in Law; or (b) the date of order/ judgment of the Competent Court or tribunal or Indian Government instrumentality, it the Change in Law is on account of a change in interpretation of Law. (c) the date of impact resulting from the occurrence of Article 13.1.1. From the above it can be seen that the impact of Change in Law is to be done in the form of adjustment to the tariff. To our mind such adjustment in the tariff is nothing less then re-determination of the existing tariff.

    x. Further, the provisions of Article 13.2 i.e. restoring the Appellant to the same economic position as if Change in Law has not occurred is in consonance with the principle of 'restitution' i.e. restoration of some specific thing to its rightful status. Hence, in view of the provisions of the PPA, the principle of restitution and judgment of the Hon'ble Supreme Court in case of Indian Council for Enviro Legal Action vs. Union of India &Ors., we are of the considered opinion that the Appellant is eligible for Carrying Cost arising out of approval of the Change in Law events from the effective date of Change in Law till the approval of the said event by appropriate authority. It is also observed that the Gujarat Bid-01 PPA have no provision for restoration to the same economic position as if Change in Law has not occurred. Accordingly, this decision of allowing Carrying Cost will not be applicable to the Gujarat Bid-01 PPA.

    84. The judgement of the Tribunal dated 13.04.2018 in Appeal No. 210 of 2017 in Adani Power Limited v. Central Electricity Regulatory Commission and Ors., was challenged before the Honble Supreme Court wherein the Honble Supreme Court vide its judgment dated 25.2.2019 in Civil Appeal No.5865 of 2018 with Civil Appeal No. 6190 of 2018 (Uttar Haryana Bijili Vitran Nigam Limited & Anr. Vs. Adani Power Ltd. & Ors.) has held as under: Order in Petition No. 365/MP/2019 Page 32 of 33

    10. A reading of Article 13 as a whole, therefore, leads to the position that subject to restitutionary principles contained in Article 13.2, the adjustment in monthly tariff payment, in the facts of the present case, has to be from the date of the withdrawal of exemption which was done by administrative orders dated 06.04.2015 and 16.02.2016. The present case, therefore, falls within Article 13.4.1(i). This being the case, it is clear that the adjustment in monthly tariff payment has to be effected from the date on which the exemptions given were withdrawn. This being the case, monthly invoices to be raised by the seller after such change in tariff are to appropriately reflect the changed tariff. On the facts of the present case, it is clear that the respondents were entitled to adjustment in their monthly tariff payment from the date on which the exemption notifications became effective. This being the case, the restitutionary principle contained in Article 13.2 would kick in for the simple reason that it is only after the order dated 04.05.2017 that the CERC held that the respondents were entitled to claim added costs on account of change in law w.e.f. 01.04.2015. This being the case, it would be fallacious to say that the respondents would be claiming this restitutionary amount on some general principle of equity outside the PPA. Since it is clear that this amount of carrying cost is only relatable to Article 13 of the PPA, we find no reason to interfere with the judgment of the Appellate Tribunal. ******* 16.....There can be no doubt from this judgment that the restitutionary principle contained in Clause 13.2 must always be kept in mind even when compensation for increase/decrease in cost is determined by the CERC.

    85. We note that the PPAs in the instant matter do not have restitution provisions. Therefore, in view of above judgements of APTEL and Honble Supreme Court, since the PPAs in the instant Petition do not have a provision dealing with restitution principles of restoration to same economic position, the claim regarding interest on Working Capital and carrying cost is not admissible.

    86. Our decisions in this Order are summed up as under: a. Issue No. 1: The imposition of the Safeguard Duty vide Notification No. 1/2018 (SG) dated 30.07.2018 is an event of Change in Law under Article 17 of the PPAs. The Commission directs the Petitioner to make available to the Respondents all relevant documents exhibiting clear and one to one correlation between the project and the supply of imported goods till the COD as per PPA or till the COD upon extension of SCOD in terms of PPA, duly supported by relevant invoices and Auditors Certificate. The payment shall be made within sixty days from the date of issue of this Order or from the date of submission of claims by the Petitioner, whichever is later, failing which it will attract late payment surcharge at rates provided under PPAs. To ensure time bound payment, it is directed that the Respondents shall reconcile the claim related documents within 15 days of submission of claim by the Petitioner. Alternatively, the Petitioner and Order in Petition No. 365/MP/2019 Page 33 of 33 the Respondents may mutually agree to a mechanism for the payment of such compensation on annuity basis spread over the period not exceeding the duration of the PPAs as a percentage of the tariff agreed in the PPAs. b. Issue No. 2: The claim regarding separate Interest on Working Capital or Carrying Cost for the period from imposition of Safeguard Duty i.e. 30.07.2018 is not admissible.

    87. Accordingly, the Petition No. 365/MP/2019 is disposed of. Sd/- Sd/-

    Use AI to get other relevant cases.

    Comments

    Mahindra Renewables Private Limited v. M.P. Power Management Company Limited And Others
    (Jan 24, 2021)