  • Order XXXIX Rules 1 and 2 and Order XXXVIII Rule 5 of the Code of Civil Procedure, 1908 (CPC).
  • SECTION 9 ARBITRATION AND CONCILIATION ACT 1996
  • Section 14(d) of the Specific Relief Act, 1963. 20.
  • Order XXXVIII Rule 5 of the CPC
  • Order 38 Rule 5 CPC.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Order XXXIX Rules 1 and 2 and Order XXXVIII Rule 5 of the Code of Civil Procedure, 1908 (CPC).
  • SECTION 9 ARBITRATION AND CONCILIATION ACT 1996
  • Section 14(d) of the Specific Relief Act, 1963. 20.
  • Order XXXVIII Rule 5 of the CPC
  • Order 38 Rule 5 CPC.
Smart Summary

Case Summary: O.M.P.(I) (COMM.) 372/2020 (Beigh Construction Company Pvt. Ltd. v. Varaha Infra Ltd.)

Factual and Procedural Background

The respondent (Varaha Infra Ltd.) was awarded an EPC contract by the Maharashtra State Road Development Corporation (MSRDC) for rehabilitation/up-gradation of a specified national/state highway project. The respondent and the petitioner (Beigh Construction Company Pvt. Ltd.) entered into a Memorandum of Understanding (MOU) dated 09.01.2019 under which the respondent sub-contracted execution of the EPC Contract to the petitioner. Under the MOU, amounts received from the employer (MSRDC) for works executed by the petitioner were to be deposited in an escrow account, with 99% payable to the petitioner and 1% to the respondent.

The petitioner alleges non-compliance with the MOU: it claims to have executed works for Rs. 39,29,44,384.07, of which MSRDC released Rs. 32,00,60,345.20 (retaining Rs. 1,93,52,129.72), but the petitioner did not receive the contractual 99% share of amounts disbursed by MSRDC; the petitioner alleges that the respondent retained substantial portions in breach of obligations.

On 20.11.2020 the petitioner filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim reliefs, including injunctions restraining the respondent from taking coercive action (including terminating the MOU), from appropriating monies from the project other than as prescribed in the MOU, and seeking ex-parte interim reliefs. The respondent terminated the MOU on 04.10.2020, which was communicated to MSRDC on 06.10.2020; MSRDC acknowledged termination by a letter dated 19.10.2020. The petition was heard and an oral order was pronounced by Vibhu Bakhru, J., on 07 January 2021 dismissing the petition.

Legal Issues Presented

  1. Whether interim reliefs under Section 9 of the Arbitration and Conciliation Act, 1996 should be granted to restrain the respondent from taking coercive steps (including terminating the MOU) and from appropriating monies payable under the MOU pending arbitration.
  2. Whether the amounts received by the respondent from MSRDC are in the nature of trust moneys for the petitioner and therefore liable to be directed to be made over to the petitioner.
  3. Whether an order in the nature of attachment before judgment (i.e., directions under Section 9(1)(ii)(b) of the Act to secure amounts) is justified in the absence of a prima facie case and material showing the respondent is acting to defeat realization of any award.
  4. Whether the prayer for restraining termination of the MOU remains viable in light of the respondent having already terminated the MOU and MSRDC's acknowledgment of termination.

Arguments of the Parties

Petitioner's Arguments (as stated in the opinion)

  • The petitioner sought directions restraining the respondent from taking coercive steps (including termination) and from appropriating monies due under the MOU, pending final adjudication by the Arbitral Tribunal.
  • Mr. Arun Kathpalia, for the petitioner, submitted that MSRDC was in the process of releasing retention money under a Government circular (Atmanirbhar Bharat circular dated 08.06.2020) and that amounts relatable to works executed by the petitioner should not be received by the respondent but instead be made over to the petitioner directly.
  • The petitioner contended that amounts received or to be received by the respondent from MSRDC were held in trust for the petitioner and could not be appropriated by the respondent.
  • Mr. Kathpalia clarified the petitioner sought its 99% share only of disbursals made by MSRDC for works executed after 09.01.2019 (post-MOU).
  • Counsel for the petitioner also contended (in argument) that the respondent was acting to denude itself of assets and thereby frustrate any claim, and that material existed to show this; however, the petition itself did not contain averments to that effect nor produced material on record.

Respondent's Arguments (as stated in the opinion)

  • Mr. Rajeev Sharma, for the respondent, submitted that the Agreement (MOU) had been terminated on 04.10.2020 and that MSRDC had been informed and had acknowledged termination (letter dated 19.10.2020).
  • The respondent relied on MSRDC communications (including a letter dated 20.03.2020 and others) alleging slow, haphazard, and unplanned progress of works and warned of withdrawal/blacklisting; MSRDC had put the respondent to notice and indicated potential contract termination for poor performance.
  • The respondent asserted that because the works were sub-contracted to the petitioner, the petitioner was responsible for alleged poor performance and non-performance of the sub-contracted works.
  • It was pointed out that prior to the petitioner, the respondent had sub-contracted to M/s Monica Constrotech Pvt. Ltd.; disputes and a tripartite supplementary MOU dated 25.02.2019 arose in relation to obligations and dues involving Monica Constrotech, and the petitioner had used Monica's machinery but allegedly failed to pay Monica's dues.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Adhunik Steels Ltd v Orissa Manganese and Minerals (P) Ltd.: (2007) 7 SCC 125 That interim measures under Section 9 of the Arbitration Act must have regard to principles analogous to Order XXXIX (injunctions) and Order XXXVIII Rule 5 of the CPC. Cited to support the proposition that Section 9 interim measures cannot be passed ignoring well-settled CPC principles applicable to interim reliefs.
Nimbus Communications Ltd v Board of Control for Cricket in India: 2014 (4) Arb LR 113 Authority relating to the scope of interim reliefs under arbitration law vis-à-vis civil procedural principles. Relied upon for the same overarching proposition that Section 9 remedies must respect principles analogous to CPC orders.
C V Rao and Krishnapatnam Port Company Ltd., China Investments Pvt Ltd v Strategic Port Investments KPC Ltd.: 218 (2015) DLT 200 (DB) Support for the treatment of Section 9 interim measures in light of civil procedure analogues. Used as part of the judicial matrix showing that Section 9 reliefs are subject to CPC analogues.
Rite Approach Group Ltd. v Rosoboron Export: 111 (2004) DLT 816 Guidance on Section 9(1)(ii)(b) reliefs and attachment before judgment principles under Order XXXVIII Rule 5 CPC. Cited to show that directions to secure claimed amounts under Section 9 are in the nature of attachment before judgment and are therefore governed by Order XXXVIII Rule 5 principles.
Global Company v M/s National Fertilizers Limited: AIR 1998 Delhi 397 Authority concerning attachment before judgment and principles to secure the claim. Referenced as one of the authorities guiding the court's approach to Section 9(1)(ii)(b) reliefs.
Gatx India Pvt Ltd v Arshiya Rail Infrastructure Ltd. & Anr.: 216 (2015) DLT 20 Authority on interim measures and attachment before judgment under CPC analogues. Relied upon as supporting precedent for applying Order XXXVIII Rule 5 principles to Section 9 applications seeking security of amounts.
Natrip Implementation Society v Ivrcl Limited: Arb. A. (Comm.) 21/2016 (decided 31.08.2016) Practical authority related to interim measures in arbitration disputes and securing amounts. Cited among authorities illustrating the approach to Section 9 reliefs analogous to CPC principles.
Raman Tech & Process Engineering Co. and Anr. v Solanki Traders: (2008) 2 SCC 302 Explains the twin conditions for granting attachment before judgment under Order XXXVIII Rule 5 CPC: (i) strong prima facie case; and (ii) satisfaction that defendant is acting to defeat realization of decree. Quoted at length and applied as the governing test: the petitioner must show both a prima facie case and that the respondent is acting to defeat an eventual decree; the court found these requirements were not satisfied on the record before it.

Court's Reasoning and Analysis

The Court set out its analysis in a stepwise fashion, grounded in the material on record and established legal principles:

  1. The petition was filed under Section 9 of the Arbitration and Conciliation Act seeking interim protections; however, the petitioner had not taken steps to constitute an Arbitral Tribunal nor had it invoked the arbitration clause in the MOU as of the date of the order (paras 12, 16).
  2. The Court rejected the contention that amounts received by the respondent were in the nature of trust moneys for the petitioner. It observed that the MOU was a commercial agreement obliging the respondent to deposit amounts in a specified account and remit 99% to the petitioner—the core dispute was one of contractual performance, not necessarily a trust relationship (para 13).
  3. The Court noted there were disputes between the parties as to performance and amounts payable; the respondent alleged poor performance by the petitioner and relied on MSRDC communications critical of project progress (paras 14, 8–9).
  4. The Court emphasized that the petition effectively sought directions under Section 9(1)(ii)(b) to secure amounts claimed—an order tantamount to attachment before judgment—and therefore the established principles under Order XXXVIII Rule 5 CPC must guide the grant of such relief (paras 15–16, 18).
  5. The Court invoked Raman Tech (Supreme Court) setting out the twin conditions for attachment before judgment: (i) a strong prima facie case; and (ii) satisfaction that the defendant is acting so as to defeat realization of the decree. The Court reiterated that without both being satisfied, attachment orders should not be made (para 19 and excerpt at paras 23–24).
  6. Applying these principles, the Court found the petition did not contain averments nor material demonstrating that the respondent was acting to frustrate an award or to denude itself of assets; the petition lacked the requisite pleadings and supporting material to prima facie satisfy the Court on the second limb (paras 16–18).
  7. Regarding the prayer to restrain termination of the Agreement, the Court observed the respondent had already terminated the MOU and MSRDC had acknowledged termination; consequently, the prayer was otiose. The Court referred to Section 14(d) of the Specific Relief Act, 1963 in indicating the Agreement was determinable and that an injunction restraining termination would not be apposite (para 19).
  8. On the basis of the above analysis—absence of arbitral invocation/constitution of tribunal, lack of prima facie material showing an attempt to defeat recovery, and termination already effected—the Court concluded it would not grant the Section 9 reliefs sought and dismissed the petition, while leaving open the petitioner's remedy before the Arbitral Tribunal (para 20).

Holding and Implications

Final Holding: The petition under Section 9 of the Arbitration and Conciliation Act, 1996 is DISMISSED (order dated 07 January 2021).

Implications and immediate consequences:

  • The interim reliefs sought (restraining respondent from taking coercive steps including terminating the MOU, and restraining appropriation of monies) were refused.
  • The Court found no sufficient prima facie material to conclude the respondent was acting to defeat realization of any prospective award; therefore, attachment-before-judgment type reliefs were not justified on the record before it.
  • The prayer to restrain termination did not survive because the respondent had already terminated the Agreement and MSRDC had acknowledged termination; the Agreement was treated as determinable and an injunction against termination was considered inapt in light of Section 14(d) of the Specific Relief Act, 1963.
  • The dismissal does not preclude the petitioner from pursuing appropriate remedies before the Arbitral Tribunal; the Court expressly clarified that the order would not prevent the petitioner from moving an appropriate application before the tribunal.
  • No new precedent was pronounced; the Court applied established principles (including those in Raman Tech and authorities addressing the interplay between Section 9 and CPC provisions) to the facts and declined interim relief on the basis of insufficiency of pleadings/materials.

Date of order as recorded in the opinion: 07 January 2021. Coram: Hon'ble Mr. Justice Vibhu Bakhru.

To access the original judgment, please Sign In or Subscribe.

    Beigh Construction Company Private Limited v. Varaha Infra Limited .

    + O.M.P.(I) (COMM.) 372/2020 & I.A. 207/2021 BEIGH CONSTRUCTION COMPANY PRIVATE LIMITED ..... Petitioner Through Mr Arun Kathpalia, Senior Counsel with Mr Angad Mehta and Mr Kauser Hussain, Advocates. versus VARAHA INFRA LIMITED .....Respondent Through Mr Rajeev Sharma, Advocate with Mr Abhishek Birth, Ms Somya Budholia, Mr Prateek Seth and Mr Adeem Ahmed, Advocates. CORAM: HON'BLE MR. JUSTICE VIBHU BAKHRU [Hearing held through videoconferencing] VIBHU BAKHRU, J. (ORAL)

    1. The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter the Act), inter alia, praying as under:-

    a) Restrain the Respondent from taking any coercive steps against the Petitioner, including terminating the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal. O.M.P.(I) (COMM.) 372/2020 Page 2 of 10

    b) Restrain the Respondent from appropriating monies from the Project in any manner other than in the manner prescribed in Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.

    c) Restrain the Respondent from taking any coercive steps against the Petitioner which would adversely affect the Petitioner in undertaking its obligations and enjoying its rights under the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.

    d) grant ad-interim ex-parte reliefs in terms of Prayers (a) to (c) above

    2. The respondent was awarded the contract for executing an Engineering, Procurement and Construction Contract for Rehabilitation & Up-gradation to 2 Lane with Paved shoulder/4 laning configuration of Wakan Pali Khopoli Road NH-548A(SH93) connecting New NH (SH88), MPEW, AH47 (NH4) and NH66 (NH17) from KM.0/000 to 40/600 in the state of Maharashtra on Engineering, Procurement & Construction (EPC) mode by the Maharashtra State Road Development Corporation (MSRDC). And, the said parties (respondent no.1 and MSRDC) entered into the Engineering, Procurment and Construction Agreement (hereafter the EPC Contract) on 07.04.2017.

    3. The present petition arises out of disputes that have arisen between the parties in connection with a Memorandum of O.M.P.(I) (COMM.) 372/2020 Page 3 of 10 Understanding dated 09.01.2019 (hereafter the Agreement), whereby the respondent had agreed to sub-contract the execution of the EPC Contract to the petitioner.

    4. In terms of the Agreement, it was agreed that the petitioner would execute the EPC Contract and the entire amount received from the employer (MSRDC) would be deposited in an escrow account. The petitioner would be entitled to 99% of the said amounts and the respondent would be entitled to the balance 1%.

    5. It is the petitioner's grievance that the terms of the Agreement are not being complied with. The petitioner claims that it has executed works for an amount of 39,29,44,384.07 against which a payment of 32,00,60,345.20 has been released by MSRDC after retaining a sum of 1,93,52,129.72. However, the petitioner has not received 99% of the said amounts disbursed by MSRDC. The petitioner alleges that the respondent has illegally and in breach of its obligations retained substantial portion of the same.

    6. Mr Kathpalia, learned senior counsel appearing for the petitioner submitted that MSRDC is now in the process of releasing the retention money in proportion to the work completed in terms of a policy circular (Atmanirbhar Bharat: Relief for Contractors/Developers of Road Section no. Ro/MUM/GEN-Corrs/2020- 21/210 dated 08.06.2020) issued by the Ministry of Road Transport and Highways, Government of India. He submits that since the said amounts are directly relatable to O.M.P.(I) (COMM.) 372/2020 Page 4 of 10 the works executed by the petitioner, directions ought to be issued to the respondent to ensure that it does not receive the said sums and makes over the said sums directly to the petitioner. He earnestly contends that the amounts received or to be received by the respondent from MSRDC are in the nature of amounts received in trust and therefore, cannot be appropriated by the respondent.

    7. Mr Rajeev Sharma, learned counsel appearing for the respondent has countered the aforesaid submission. He points out that the Agreement dated 09.01.2019 was terminated on 04.10.2020 and this was also communicated to MSRDC on 06.10.2020. He referred to a letter dated 19.10.2020 sent by MSRDC, acknowledging that the sub- contract between the petitioner and the respondent stood terminated.

    8. Mr Sharma referred to a letter dated 20.03.2020 issued by MSRDC alleging that the progress of the works was slow and the same was being done in a haphazard and unplanned manner. It had further cautioned the respondent to take corrective steps failing which it would withdraw the works and debar (blacklist) the respondent for a period of five years. He also referred to certain other letters written by MSRDC alleging that the progress of work was extremely slow. He referred to a letter dated 16.06.2020, whereby MSRDC had put the respondent to notice that the execution of the works would monitored for a period of one month and if there was no improvement, the works would be withdrawn and the EPC Contract would be cancelled. By a letter dated 24.09.2020, MSRDC had indicated its intention to terminate the O.M.P.(I) (COMM.) 372/2020 Page 5 of 10 contract on account of slow progress of the work alleging that the respondent had not shown any will to complete the work and had failed to live up to its commitments.

    9. He submits that since the execution of the works was sub- contracted to the petitioner, it was responsible for not performing the works, as was agreed. He further submitted that prior to the parties entering into the Agreement, the respondent had entered into a sub- contract with one M/s Monica Constrotech Private Limited. The said sub-contract was terminated, however, there were some disputes with the said sub-contractor. Accordingly, the petitioner and the respondent had entered into a tripartite agreement with M/s Monica Constrotech Private Limited Supplementary Memorandum of Understanding dated 25.02.2019 whereby the parties had undertaken certain obligations towards M/s Monica Constrotech Private Limited. He states that disputes have arisen regarding performance of the said obligations as well. He further submitted that the petitioner had used the machinery of M/s Monica Constrotech Private Limited, however, had failed to pay its dues.

    10. Mr Kathpalia countered the submissions. He clarified that the petitioner was seeking its share (99%) of the disbursals made by MSRDC for works executed after 09.01.2019 and not prior to the said date. He further contended that although MSRDC had issued letters alleging slow progress, the respondent had contested the same and according to it the said allegations were untrue. O.M.P.(I) (COMM.) 372/2020 Page 6 of 10

    11. I have heard the learned counsel appearing for the parties.

    12. At the outset, it is relevant to note that although the present petition was moved on 20.11.2020, the petitioner has not taken any steps for constitution of the Arbitral Tribunal. Admittedly, the petitioner has, as yet, not issued any letter invoking the arbitration clause under the Agreement (the Memorandum of Understanding dated 09.01.2020).

    13. The contention that the amount received by the respondent from MSRDC is in the nature of a trust for and on behalf of the petitioner, is unpersuasive. It is clear that the Agreement is a commercial agreement between the petitioner and the respondent. Indisputably, in terms of the Agreement, the respondent was obliged to deposit the amounts received from MSRDC in respect of the works executed by the petitioner in the specified account and make over 99% of the said amount to the petitioner. The petitioner, essentially, claims that the respondent has failed and neglected to perform its contractual obligations. However, according to the respondent, the petitioner has failed to satisfactorily execute the works sub-contracted to it.

    14. The reply filed by the respondent is not on record but it is apparent that there are disputes between the parties with regard to the amounts payable by the respondent to the petitioner.

    15. In the circumstances, the petitioner's prayer seeking an order restraining the respondent from appropriating any amount received O.M.P.(I) (COMM.) 372/2020 Page 7 of 10 from MSRDC, essentially, amounts to seeking a directions to secure the amounts claimed as due and payable by the respondent. It is well settled that orders for interim measures of protection under Section 9 of the Act cannot be passed ignoring the well settled principles as are applicable for exercising the analogous power conferred under Order XXXIX Rules 1 and 2 and Order XXXVIII Rule 5 of the Code of Civil Procedure, 1908 (CPC). [See Adhunik Steels Ltd vs Orissa Manganese and Minerals (P) Ltd.: (2007) 7 SCC 125, Nimbus Communications Limited v Board of Control for Cricket in India: 2014 (4) Arb LR 113, and C V Rao and Krishnapatnam Port Company Limited, China Investments Private Limited v. Strategic Port Investments KPC Ltd.

    218 (2015) DLT 200 (DB)]

    16. As noticed above, the petitioner essentially seeks an order under Section 9(1)(ii)(b) of the Act to secure the amounts, which it asserts are owed to it. This is, plainly, seeking an order in the nature of attachment before judgement. Therefore, the principles as applicable under Order XXXVIII Rule 5 of the CPC would guide the grant of such relief. [see: Rite Approach Group Ltd. vs Rosoboron Export: 111 (2004) DLT 816, Global Company v M/s National Fertilizers Limited: AIR 1998 Delhi 397, Gatx India Pvt Ltd v Arshiya Rail Infrastructure Limited & Anr:

    216 (2015) 216 DLT 20 and Natrip Implementation Society v. Ivrcl Limited: Arb. A. (Comm.) 21/2016 decided on 31.08.2016]

    19. In Raman Tech & Process Engineering Co. and Anr. v. Solanki Traders: (2008) 2 SCC 302, the Supreme Court had explained the twin O.M.P.(I) (COMM.) 372/2020 Page 8 of 10 conditions that are required to be satisfied before issuing any directions in terms of Order XXXVIII Rule 5 of the CPC. First, that the plaintiff must establish a strong prima facie case; and second, that the court is prima facie satisfied that the defendant is acting in a manner so as to defeat the realisation of the decree that may be passed. The relevant extract of the said decision is set out below:-

    4. The object of supplemental proceedings (applications for arrest or attachment before judgment, grant of temporary injunctions and appointment of receivers) is to prevent the ends of justice being defeated. The object of Order 38 Rule 5 CPC in particular, is to prevent any defendant from defeating the realization of the decree that may ultimately be passed in favour of the plaintiff, either by attempting to dispose of, or remove from the jurisdiction of the court, his movables. The Scheme of Order 38 and the use of the words "to obstruct or delay the execution of any decree that may be passed against him" in Rule 5 make it clear that before exercising the power under the said Rule, the court should be satisfied that there is a reasonable chance of a decree being passed in the suit against the defendant. This would mean that the court should be satisfied that the plaintiff has a prima facie case. If the averments in the plaint and the documents produced in support of it, do not satisfy the court about the existence of a prima facie case, the court will not go to the next stage of examining whether the interest of the plaintiff should be protected by exercising power under Order 38 Rule 5 CPC. It is well-settled that merely having a just or valid claim or a prima facie case, will not entitle the plaintiff to an order of attachment before judgment, unless he also establishes that the defendant is attempting to remove or dispose of his assets with the intention of defeating the decree that may be passed. Equally well settled is the position that even where the O.M.P.(I) (COMM.) 372/2020 Page 9 of 10 defendant is removing or disposing his assets, an attachment before judgment will not be issued, if the plaintiff is not able to satisfy that he has a prima facie case. [ underlined for emphasis]

    17. However, it is seen that the present petition does not contain any averments to the effect that the respondent is acting in the manner so as to frustrate an award that may be made by made in favour of the petitioner. There are neither any averments to the said effect nor any material placed on record that would, prima facie, satisfy the Court in this regard.

    18. Notwithstanding the above, Mr Kathpalia has earnestly contended that the respondent is acting in a manner to frustrate any claim that may be made by the petitioner by ensuring that it denudes itself for substance. He also states that there is material available to establish the same. Be that as it may, no averments have been made in the present petition to the aforesaid effect. More importantly, since no material has been placed on record that would satisfy this Court that the respondent is acting in a premeditated manner to defeat the recovery of any amount that may be awarded in favour of the petitioner, this Court does not consider it apposite to accede to the prayer made in this regard.

    19. Insofar as the prayer for restraining the respondent from terminating the Agreement is concerned, the respondent has already terminated the same and thus, the said prayer does not survive. In any O.M.P.(I) (COMM.) 372/2020 Page 10 of 10 view, the Agreement is determinable and therefore, it would not be apposite to pass any order restraining the respondent from terminating the Agreement in view of Section 14(d) of the Specific Relief Act, 1963.

    20. In view of the above, the present petition is dismissed. It is, however, clarified that this order would not preclude the petitioner from moving an appropriate application before the Arbitral Tribunal, if so advised. VIBHU BAKHRU, J JANUARY 7, 2021