Smart Summary

Case Summary: National Consumer Disputes Redressal Commission — First Appeal No. 276 of 2013

Factual and Procedural Background

The complainant (an ex-serviceman) booked a residential flat in the project "Maaria Annexe" developed by the appellant in August 2005 for a consideration of Rs.24,65,000/-. A registered agreement dated 18.3.2006 was executed after payment of the entire sale consideration. Construction was not completed and possession was not delivered, whereupon the complainant filed a consumer complaint before the State Commission (Maharashtra), seeking possession and compensation.

The State Commission, by its order dated 08.01.2013, partly allowed the complaint and directed that the appellants hand over possession within four months or, alternatively, pay Rs.99,79,200/- (market price) within two months with 9% p.a. interest; the opponents were to bear their own costs and pay Rs.25,000/- to the complainant. The developer (appellant) challenged that order before the National Commission by way of this appeal. The complainant did not challenge the State Commission's order.

During appellate proceedings the appellant admitted execution of the agreement and receipt of payment but explained delay by reference to issues arising from development under the Slum Rehabilitation Scheme (SRA), including an encroacher (Mr. Nilkantha Narayan) who had not vacated a portion of the land, pending administrative action by MCGM and a pending request for conversion from SRA-225 to SRA-269 and for higher FSI. The appellant also relied on Clause 13 of the agreement which, they said, permitted refund without interest or penalty in delays beyond the appellant's control. The National Commission reserved and subsequently issued the impugned order dated 27 February 2020 disposing the appeal and the complaint with directions.

Legal Issues Presented

  1. Whether the appellant's stated reasons (encroachment, pending administrative actions under the SRA scheme, attempts to obtain higher FSI or conversion between SRA schemes) constitute a valid excuse for non-delivery of possession.
  2. What relief the complainant is entitled to: specific performance by delivery of possession or monetary compensation (refund/market-price remedy) and on what basis the compensation should be calculated.
  3. What evidentiary standard and material are acceptable to determine the market value of the flat for purposes of compensation (i.e., admissibility of newspaper reports versus sale deeds or Ready Reckoner/circle rate).
  4. Consequences and adjustments in respect of amounts already deposited/withdrawn during interlocutory proceedings.

Arguments of the Parties

Appellant's Arguments

  • Admitted execution of agreement and receipt of the sale consideration.
  • Construction was delayed due to factors beyond their control arising from the Slum Rehabilitation Scheme process: necessity to demolish old units, accommodate tenants, presence of an encroacher (Mr. Nilkantha Narayan) who would not vacate, pending action by MCGM after directions by the CEO of the Slum Rehabilitation Scheme, and pending applications for higher FSI and conversion from SRA-225 to SRA-269.
  • Reliance on Clause 13 of the agreement: in case of delay beyond the control of the appellant the complainant could claim refund of the amount paid without interest or penalty.
  • At various hearings, the appellant through counsel undertook that the building would be completed and possession handed over within 18 months, and offered to pay interest @ 9% p.a. on the amount deposited/paid by the complainant from the date of deposit till date of payment.

Respondent / Complainant's Arguments

  • The complainant asserted that construction of the allotted flat was almost complete and expressed willingness to take possession along with compensation at 9% p.a. for the delayed period.
  • The complainant relied on the State Commission's order which alternatively required the developer to pay the market price of the flat (Rs.99,79,200/-) with interest if possession was not delivered.
  • The complainant had withdrawn an interim deposit (about Rs.41 lakhs) which had been deposited earlier with the National Commission pursuant to an interim order.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The National Commission analyzed the factual matrix and the parties' positions and reached the following conclusions based strictly on the materials and statements on record:

  1. On the appellant's justification for delay: the Commission found no merit in the claim that administrative and encroachment difficulties excused the delay. The Commission held that the appellant ought not to have accepted the booking unless it was in possession of the whole land on which construction was to occur. If part of the land was under encroachment, the appellant should have removed the encroachment before accepting bookings; accepting the booking despite encroachment amounted to taking a calculated risk. Further, attempts to obtain higher FSI or to convert schemes to enhance profit were not a valid justification for delay vis-à-vis the complainant.
  2. On enforcement of relief: the appellant had earlier undertaken before the National Commission that it would deliver possession within 18 months and pay interest @ 9% p.a.; the complainant indicated willingness to accept possession per that undertaking. However, because some parts of construction were still incomplete and an occupancy certificate had not been obtained, and because the appellant declined to deliver possession until full completion and issuance of the occupancy certificate, the Commission concluded that the alternative monetary relief ordered by the State Commission (payment of market price) became enforceable.
  3. On the appropriate measure of compensation/market price: the State Commission had relied upon newspaper reports to fix a market price of Rs.99,79,200/-. The National Commission held that newspaper reports do not constitute legally admissible evidence to prove market value. The complainant had not produced sale deeds of comparable flats or the Ready Reckoner (circle rate) to prove prevailing market price. The Commission therefore adopted the Ready Reckoner approach: compensation should be the difference between the current market value of the flat as calculated by reference to the current Ready Reckoner (circle) rate and the price the complainant had already agreed to pay the appellant. The Ready Reckoner was characterized as reflecting the minimum market price on a particular date and being a government/municipal document, hence an appropriate basis for calculating compensation.
  4. On interim amounts: it appeared that approximately Rs.41 lakhs had been deposited by the appellant with the Commission pursuant to an interim order and that the complainant later withdrew that amount on 14.10.2014. The Commission directed that amounts already withdrawn be adjusted against compensation payable, with interest @ 9% p.a. from the date of withdrawal until adjustment; if the withdrawn amount exceeded compensation payable the complainant must refund the excess with interest @ 9% p.a., and if compensation exceeded the withdrawn amount the balance would be payable when possession is offered.
  5. The Commission formulated a remedial scheme that prioritized delivery of possession (completion and occupancy certificate with one year to deliver) but also provided detailed monetary remedies and adjustments, including enhanced measures if possession was not delivered within one year (refund of principal and payment of difference between circle rate and amount paid, plus further adjustments tied to circle rate changes after one year), and an award for mental agony and litigation costs.

Holding and Implications

DISPOSED OF. The appeal and the underlying consumer complaint were disposed of by the National Commission by ordering a remedial regime comprising performance (delivery of possession on completion and issuance of occupancy certificate within one year) together with specified monetary compensation and adjustments. The key outcomes and direct effects on the parties are summarized below.

Direct Holding (as ordered)

  • The appellant shall complete construction, obtain the requisite occupancy certificate, and hand over possession of the allotted flat to the complainant within one year from the date of the National Commission's order (the complainant being willing to wait one year).
  • When delivering possession, the appellant shall pay simple interest @ 9% p.a. to the complainant on the entire amount of Rs.24,65,500/- with effect from three years from the date of the booking till the date possession is offered (note: the opinion records the principal in this paragraph as Rs.24,65,500/-).
  • The amount already withdrawn by the complainant (about Rs.41 lakhs) shall be adjusted against compensation payable, with interest @ 9% p.a. from the date of withdrawal until adjustment.
  • If the amount withdrawn by the complainant exceeds the compensation payable under the order, the complainant shall refund the excess with interest @ 9% p.a.; if compensation exceeds the withdrawn amount, the appellant shall pay the balance when possession is offered.
  • If the appellant fails to deliver possession in terms of the order within one year, it shall refund the principal amount received and also pay the difference between compensation equivalent to the current circle rate / Ready Reckoner rate of the flat and the amount paid by the complainant; adjustments for the amount already withdrawn (with interest) shall apply.
  • If the appellant does not deliver possession within one year, it shall additionally pay the difference between the current circle rate of the flat and the circle rate prevalent after one year from the date of the order.
  • The complainant is awarded Rs.2,00,000/- for mental agony and harassment, and Rs.25,000/- as litigation costs, to be paid within two months from the date of the order.

Implications

The decision directly affects the parties by prescribing a clear remedial pathway: either the developer completes construction and hands over possession within the stipulated time while paying interest compensation, or, if it fails, it must refund the principal and pay compensation based on Ready Reckoner/circle rates and additional adjustments. The Commission rejected the use of newspaper reports as proof of market value and required more authoritative municipal/government valuation (Ready Reckoner) or comparable sale evidence for market-value determinations. No novel legal precedent beyond application of these evidentiary and remedial principles is announced in the opinion; the order applies these principles to the facts of the case to determine the appropriate relief.

Date of order: 27 February 2020. Presiding Member: Justice V.K. Jain.

To access the original judgment, please Sign In or Subscribe.

    M/S. LAKADWALA DEVELOPERS P. LTD. v. AMARJEET SINGH BARYAM SINGH

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    FIRST APPEAL NO. 276 OF 2013

    (Against the Order dated 08/01/2013 in Complaint No. 174/2011 of the State Commission Maharashtra)

    1. M/S. LAKADWALA DEVELOPERS P. LTD. 2/3, KHUSHNUMA APARTMENT, BYCULLA STATION

    ROAD, AGRIPADA,

    MUMBAI-400011

    2. SHRI. ANWAR ESMIL LAKDAWALA

    A-21, 105 GORDON HALL APARTMENTS, C.H.S. LTD.,

    SOFIYA ZUBAIR ROAD,

    NAGPADA

    MUMBAI-400008

    3. SHRI EBRAHIM ESMAIL LAKDAWALA

    C-11, 105 GORDON HALL APARTMENTS C.H.S. LTD.,

    SOFIYA ZUBAIR ROAD,

    NAGPADA,

    MUMBAI

    4. SHRI MOHAMMED ISMAIL LAKDAWALA

    A-72, 105, GORDON HALL APARTMENTS C.H.S. LTD.,

    SOFIYA ZUBAIR ROAD,

    NAGPADA,

    MUMBAI

    5. SHRI MUSA ESMAIL LAKDAWALA

    C-51, 105, GORDON HALL APARTMENTS C.H.S. LTD.,

    SOFIYA ZUBAIR ROAD,

    NAGPADA,

    MUMBAI

    6. SHRI USMAN ISMAIL LAKDAWALA

    A-72, 105, GORDON HALL APARTMENTS C.H.S. LTD.,

    SOFIYA ZUBAIR ROAD,

    NAGPADA,

    MUMBAI

    7. SHRI MOHAMMED ZUBAIR ADAM LAKDAWALA

    175-A,DIMTIMKAR ROAD, MEMNI BUILDING, FIRST

    FLOOR, FLAT NO. 15,

    NAGPADA,

    MUMBAI ...........Appellant(s) Versus

    1. AMARJEET SINGH BARYAM SINGH

    KALPATARU HARMONY, FLAT NO. 93, KILLA ROAD,

    NEAR M.T.N.L. EXCHNGE, SION (EAST)

    MUMBAI-400022 ...........Respondent(s)

    BEFORE:

    HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER

    1

    For the Appellant : Mr. Shaurya Kuthiala, Advocate Mr. Samrat Nigam, Advocate

    For the Respondent : Mr. Madhurendra Kumar, Advocate with respondent in person

    Dated : 27 Feb 2020

    ORDER

    JUSTICE V.K. JAIN, PRESIDING MEMBER (ORAL)

    The complainant, who is an ex-serviceman, booked a residential flat with the appellant in a project namely "Maaria Annexe" which the appellant was to develop in Mumbai, in August, 2005 for a consideration of Rs.24,65,000/-. A registered agreement dated 18.3.2006 was also executed between the parties on payment of the entire sale consideration to the appellant. Since the construction was not completed and the possession was not offered to him, the complainant approached the concerned State Commission by way of a consumer complaint, seeking possession of the flat, with compensation etc.

    2. The complaint was resisted by the appellant, which admitted the agreement executed with the complainant as well as the payment received from him. It was inter-alia stated in the written version filed by the appellant that the appellant had been granted approval for development of a piece of land under the Slum Rehabilitation Scheme of Government of Maharashtra and therefore, was required to demolish the existing old dwelling units and construct new multi storied buildings. The appellant was to accommodate the tenants of the old structure and was permitted to sell the other part of the new construction to be raised by them. It was further stated by the appellant that the construction got obstructed on account of an encroacher Mr. Nilkantha Narayan having not vacated the piece of land occupied by him. They approached the Hon'ble High Court by way of a writ petition wherein the Chief Executive Officer of the Slum Rehabilitation Scheme was directed to consider the matter and pass an appropriate order. The Chief Executive Officer passed an order on 20.11.2007, directing MCGM to decide the request of Mr. Nilkantha Narayan for grant of lease in respect of land admeasuring 112.52 sq. mtr. However, MCGM did not dispose of the matter. It was also stated in the written version filed by the appellant that they had applied to the Slum Rehabilitation Authority for grant of 4 FSI in accordance with high density scheme and since there was no progress on their proposal, they sought conversion of the project from SRA-225 to SRA-269 scheme, which was also pending. It was also stated in the written version that in terms of Clause 13 of the agreement, in case of delay beyond the control of the appellant, the complainant could claim refund of the entire amount paid by him without interest or penalty. The appellant also expressed his readiness and willingness to hand over possession of the flat to the complainant on completion of the project.

    3. The State Commission vide impugned order dated 08.1.2013 directed as under:

    "1. Complaint is partly allowed.

    2. Opponents are directed to hand over possession of flat No.703 on seventh floor of B Wing in the proposed 'Maaria Annexe' admeasuring 712.80 sq. ft. within a period of four months from the date of the order.

    2

    OR

    If fails to hand over the possession, opponents are directed to pay 99,79,200/- market price of the flat within a period of two months, failing which, the amount will carry interest of 9% p.a. till realization of the amount.

    3. Opponent to bear their own costs and pay costs of Rs.25,000/- to the complainant."

    4. The complainant has not challenged the order passed by the State Commission. The developer however, is before this Commission by way of this appeal.

    5. When this appeal came up for hearing on 18.4.2013, the learned counsel for the appellant stated that they were ready to hand over possession of the flat to the complainant and that the construction work had been stopped because of reasons beyond their control. He was asked to take instructions as to whether the appellant was ready to pay interest @ 9% per annum to the complainant form the date of deposit till the date of handing over possession, without demanding any escalation. On 28.5.2013, the learned counsel for the appellant he having taken instructions stated that the building would be completed and possession would be handed over to the complainant within eighteen months, no further interest shall be charged from the complainant and the appellant shall also pay interest @ 9% per annum to the respondent on the amount deposited by him for the delayed period in handing over of possession, from the date of deposit till the date of payment. On this statement, the operation of the order passed by the State Commission was stayed by this Commission.

    6. When the matter came up for hearing on 09.12.2013, the learned counsel for the appellant stated that as per his instructions it will not be possible to hand over possession of the flat within the time noted in the order dated 4.9.2013. Thereupon this Commission directed to appellant to deposit the entire amount with this Commission, which the complainant had paid to it along with 9% per annum interest on that amount form the date of each payment.

    7. The learned counsel for the appellant states on instructions that the appellant is not in a position to give possession of the allotted flat to the complainant. He states that he is not aware whether the said flat stands constructed. The complainant, who is present in the Court however maintains that the construction of flat has been almost completed and he is interested in taking possession of the allotted flat with compensation in terms of the statement made by the appellant before this Commission.

    8. As far as justification given by the appellant for the delay in construction of the flat is concerned, I find no merit in the said justification. The appellant ought not to have accepted the booking made by the complainant, unless it was in possession of the whole of the land on which the building was to be constructed by it. If a part of the said land was under encroachment, the appellant, in my opinion, ought to have first got the encroachment removed before accepting the booking. Having taken a calculated risk by accepting the booking, despite a part of the land being under encroachment at that time, the appellant has only itself to blame for a situation for which the construction could not be completed in time on account of

    3

    encroacher having not vacated the piece of land occupied by him. Moreover, the attempt of the appellant to get a higher FSI or conversion from SRA 225 Scheme to SRA 269 Scheme, which it had attempted to enhance its profit, cannot be a valid justification for the delay qua the complainant.

    9. The next question which arises for consideration is as to what relief the complainant is entitled as on today. As noted earlier, the appellant had agreed before this Commission that it would deliver possession of the allotted flat to the complainant within eighteen months of the date on which the said statement was made, along with compensation by way of interest @ 9% per annum. In all fairness, the appellant should give possession in terms of the statement which its counsel had made before this Commission on instructions from it. If the appellant acts in terms of the aforesaid statement there would be practically no difficulty in the matter since the complainant also wants to take possession in terms of the said statement, along with interest @ 9% per annum and maintains that the construction of the allotted flat is almost complete. The complainant, however admits that the construction work is not complete in some respects and the requisite occupancy certificate has not been obtained. He is ready to wait for the work to finish and the occupancy certificate to be issued but the appellant is not willing to deliver possession of the allotted flat to the complainant as and when the construction is complete in all respects and the requisite occupancy certificate is obtained. In these circumstances, it is the second part of the order of the State commission, which becomes enforceable.

    10. The State Commission directed the appellant to pay a sum of Rs.99,79,200/- to the complainant along with 9% interest, holding that the above referred figure reflected the market price of the flat as per the newspaper reports which were referred before it. However, the newspaper report in my opinion does not constitute legally admissible evidence to prove the market value of a flat. No sale deed was filed by the complainant before the State Commission to prove the prevailing market value of the similar flats in the locality in which the allotted flat is situated. Even the Ready Reckoner was not produced before the State Commission to prove the ready reckoner price of the flat on the date the consumer complaint came to be decided or even on the date on which the consumer complaint had been instituted. In my opinion, considering that the complainant did not produce any sale deed or other authentic document to prove the prevailing market price of a similarly situated flat of similar specifications in the same or a comparable locality, the appellant should pay, to the complainant, as compensation the difference between the current market value of the flat, calculated as per the Ready Reckoner price of today and the price which he had agreed to pay to the appellant for the flat booked by it. The Ready Reckoner reflects the minimum market price of a flat / plot on a particular date and is a document issued by the concerned Government / Municipal Authority. Therefore, I see no reason why the compensation payable to the complainant should not be calculated on the basis of the current ready reckoner price of the flat.

    11. It transpired during the course of the arguments that the amount of about Rs.41 lacs was deposited by the appellant with this Commission, pursuant to an interim order passed by this Commission and the said amount was later withdrawn by the complainant on 14.10.2014. Considering all the facts and circumstances as discussed hereinabove, the appeal and the consumer complaint filed by the respondent are disposed of in terms of the following order:

    4

    (i) The appellant shall complete the construction of the allotted flat in all respects, obtain the requisite occupancy certificate and hand over its possession to the complainant with one year from today, the complainant being ready and willing to wait for one year.

    (ii) While delivering possession in terms of this order, the appellant shall also pay compensation in the form of simple interest @ 9% per annum to the complainant on the entire amount of Rs.24,65,500/- with effect from three years from the date of the booking till the date on which the possession is offered in terms of this order.

    (iii) The amount already withdrawn by the complainant shall be adjusted out of the compensation payable to him in terms of this order, along with interest @ 9% per annum on that amount from the date on which it was withdrawn by him till the date of adjustment.

    (iv) If it is found that the amount withdrawn by him was more than the compensation found payable to him in terms of this order, he shall refund the said excess amount to the appellant, along with interest on that amount @ 9% per annum. If however, the compensation by way of interest payable to the complainant in terms of this order is more than the amount withdrawn by the complainant, the balance amount payable by the appellant to the complainant shall be paid at the time the possession is offered.

    (v) If the appellant does not deliver possession of the flat in terms of this order within one year from today, after completing the construction in all respects and obtaining the requisite occupancy certificate, before expiry of one year from today, it shall refund the principal amount received from him and will also pay to him difference between the compensation equivalent to the current circle rate, / ready reckoner rate of the flat and the amount paid to it by the complainant for the allotted flat. The amount which the complainant has already withdrawn, shall in that case, be adjusted along with 9% interest on that amount with effect from the date on which it was withdrawn by the complainant, till the date of such adjustment.

    (vi) If the appellant does not deliver possession to the complainant in terms of this order within one year from today, it shall in addition to the compensation calculated in terms of direction No.(v) above, also pay to him the difference between the current circle rate of the flat and the circle rate prevalent after one year form today.

    (vii) The respondent / complainant shall also be entitled to a compensation quantified at Rs.2.00 lacs for the mental agony and harassment suffered by him, and the cost of litigation quantified at Rs.25,000/-, to be paid within two months from today.

    ......................J

    V.K. JAIN

    5

    PRESIDING MEMBER

    6