  • provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, Consumer Complaint No.752 of 2019 4 PAPRA).
  • Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995,
  • SECTION 17 CONSUMER PROTECTION ACT 1986
  • sub-section (1) of section 6
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Acts
  • provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, Consumer Complaint No.752 of 2019 4 PAPRA).
  • Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995,
  • SECTION 17 CONSUMER PROTECTION ACT 1986
  • sub-section (1) of section 6
Smart Summary

Judicial Opinion Summary — Consumer Complaints Nos. 752 & 753 of 2019

Factual and Procedural Background

This opinion disposes two consumer complaints (Nos. 752 and 753 of 2019) filed under Section 17 of the Consumer Protection Act, 1986 against the same opposite parties. The complaints were filed by different complainants (in No.752 the complainants are a son and father) alleging that the opposite parties, promoters/developers of an under‑construction commercial complex (C & C Capital / Bus Terminal‑cum‑Commercial Complex, Sector 57, Mohali), failed to complete construction and deliver possession of allotted units within the contractual/stipulated period.

In Consumer Complaint No.752 of 2019 the complainants alleged allotment of Unit No.32, Tower‑C (super area 738 sq.ft.) by allotment letter dated 09.02.2011 for a basic sale price of Rs. 53,32,050/-. The complainants asserted payment of Rs. 21,95,550/- (though documentary proof on record reflected Rs. 12,54,600/- and an unexplained cash payment). The allotment letter (Clause 1.3.5) envisaged completion within 30 months from the lease start date (15.12.2009), i.e. by 15.06.2012.

The complainants allege no development at site, abandonment of work, and receipt of letters from the opposite parties indicating inability to complete the project (letter dated 21.11.2017 offering refunds or interest at 8.8% to investors; letter dated 06.06.2018 requesting extension until 30.09.2018). The complainants also learned via public notice that GMADA had served notices and initiated termination proceedings (termination notice dated 04.04.2016).

In Consumer Complaint No.753 of 2019 facts are materially similar: allotment of Unit No.4 (super area 774 sq.ft.), allotment letter dated 25.08.2010, basic sale price Rs. 38,70,000/-, and alleged payments (cheque evidence and claimed but undocumented cash payment). Possession was also not delivered by the stipulated date of 15.06.2012.

The opposite parties did not appear before the Commission despite service and were proceeded against ex parte by order dated 04.12.2019. The complainants filed affidavits and documentary evidence (brochure Ex.C‑1, receipts Ex.C‑2, demand notice Ex.C‑3, cheques Ex.C‑4, allotment letter Ex.C‑5, and letters Ex.C‑6 to Ex.C‑8). The Commission heard counsel for the complainants and examined the record.

Legal Issues Presented

  1. Whether the opposite parties committed deficiency in service and adopted unfair trade practice by failing to complete the project and deliver possession of the allotted commercial units within the stipulated period.
  2. Whether the opposite parties violated provisions of the Punjab Apartment and Property Regulation Act, 1995 (PAPRA) and its Rules (specifically Sections 3, 5, 9 of PAPRA and Rule 17 of the Rules) in relation to disclosures, permissions and maintenance of separate accounts for buyers' deposits.
  3. What reliefs/remedies the complainants are entitled to (physical delivery of possession, interest on deposited amounts, compensation for mental agony/harassment, litigation expenses, and directions regarding sale/conveyance deed and adjustment of remaining sale consideration).

Arguments of the Parties

Complainants' Arguments

  • The complainants purchased the units to run self‑employment businesses (Construction Consulting office and Industrial Automation & Consulting office respectively) and paid substantial amounts to the opposite parties as per allotment/allocation arrangements.
  • Construction was contractually to be completed within 30 months from the lease start date (15.12.2009), but no development occurred and the opposite parties failed to deliver possession by 15.06.2012.
  • Opposite parties admitted delay in a letter dated 21.11.2017 which offered refunds or 8.8% interest to investors who wished to remain invested; a later letter (06.06.2018) sought extension due to lack of funds. GMADA had initiated termination proceedings and supplied information showing no construction licence/grant of licence to the opposite parties.
  • Due to non‑performance, the opposite parties committed deficiency in service and unfair trade practice and are liable to deliver possession, pay interest on deposits, compensate for mental agony and litigation expenses.
  • Documentary proof filed included allotment letters, receipts/cheques and correspondence; where cash payments were asserted the complainants could not produce receipts but relied on other documentary record and the opposite parties' communications evidencing failure to perform.

Opposite Parties' Arguments

The opposite parties did not appear and no detailed account of their arguments is available in the provided opinion.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Consumer Complaint No.343 of 2016 (Sharanjeet Kaur v. C and C Towers Ltd. & Ors.) decided on 02.06.2017 Earlier decision dealing with similar facts and merits of delayed/non‑completion by same opposite parties. The Commission treated this decision as covering the merits and relied on it in disposing the present complaints.
Consumer Complaint No.314 of 2017 (Indu Laroia & Anr. v. C and C Towers Limited & Ors.) decided on 07.11.2017 Earlier decision dealing with similar facts and merits of delayed/non‑completion by same opposite parties. Relied upon as part of a series of earlier decisions covering the same issues to dispose the present complaints.
Consumer Complaint No.99 of 2018 (Dharam Pal Nanda v. C & C Towers Ltd. & Ors.) decided on 19.07.2018 Earlier decision dealing with similar facts and merits of delayed/non‑completion by same opposite parties. Used to establish consistent earlier findings against the opposite parties on similar factual matrix.
Consumer Complaint No.825 of 2018 (Harpreet Singh v. C & C Towers Ltd. & Ors.) decided on 20.02.2019 The Commission in Harpreet Singh held that where GMADA records showed no construction licence, initiation of cancellation proceedings, and the delay was due to paucity of funds, the developer's conduct amounted to deficiency in service and unfair trade practice. The court quoted and relied on the Harpreet Singh observations to support finding of deficiency/unfair practice in the present complaints where similar GMADA communications and paucity of funds were on record.
Consumer Complaint No.183 of 2019 (Darshan Singh v. C & C Towers Ltd. & Ors.) decided on 15.05.2019 Earlier decision dealing with similar facts and merits of delayed/non‑completion by same opposite parties. Referenced as part of the line of earlier decisions covering the merits; relied upon to dispose the present complaints consistently.
Consumer Complaint No.930 of 2018 (Ms. Kusum Sharma & Ors. v. C & C Towers Ltd. & Ors.) decided on 04.04.2019 Earlier decision dealing with similar facts and merits of delayed/non‑completion by same opposite parties. Also relied upon as precedent covering the merits and supporting disposal in favour of the complainants.

Court's Reasoning and Analysis

The Commission's analysis proceeded in a structured manner based solely on the pleadings, documentary evidence filed by the complainants, the opposite parties' non‑appearance (resulting in ex parte proceedings) and earlier consistent decisions of the Commission on virtually identical factual matrices.

Key steps and findings in the reasoning:

  • Adverse inference from non‑appearance: Because the opposite parties were duly served but did not appear or file a reply, the averments in the complaint were deemed admitted and the complainants' evidence remained unrebutted. The Commission explicitly drew an adverse inference against the opposite parties for failing to contest the complaints.
  • Documentary proof and admissions: The Commission noted the allotment letters, receipts/cheques, and opposites' letters (Ex.C‑6 dated 21.11.2017 and Ex.C‑7 dated 06.06.2018) in which the opposite parties offered refunds or promised interest to investors or sought extension due to paucity of funds. These communications were treated as corroborative of the complainants' contention that the opposite parties had failed to complete the project.
  • PAPRA compliance: On the record, the opposite parties failed to produce evidence of requisite approvals/permissions from competent authorities, did not demonstrate compliance with disclosure obligations under Section 3 of PAPRA, did not produce evidence of permission to develop the land as required by Section 5, and did not show that a separate bank account for buyers' deposits (as required by Section 9) had been maintained. The Commission found violations of Sections 3, 5 and 9 of PAPRA.
  • Statutory rule on interest: Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995 (framed under Section 45 of PAPRA) prescribes refund of amounts collected together with interest at 12% per annum from date of receipt till repayment where agreements are cancelled. The Commission applied this rule to determine the rate of interest payable for delay in delivery.
  • Misrepresentation and deficiency: The Commission found that the opposite parties had made false statements about delivery timelines and had misrepresented their capacity/position to perform, which amounted to misrepresentation, deception, deficiency in service and unfair trade practice. The Commission observed that the complainants suffered loss of opportunity, mental agony and harassment because they had to pursue legal remedies.
  • Principle on compensation: The Commission reiterated the settled principle that compensation should be just, fair and reasonable and commensurate with the loss suffered. The Commission further noted precedential findings (a “catena of judgments” of higher forums) that builders are liable to compensate allottees for non‑delivery and that claimants are put to long legal battles to obtain relief.
  • Relief framing: Applying the above legal and factual findings, and relying on earlier Commission decisions that covered the same issues, the Commission framed reliefs including physical delivery of the unit (subject to payment of balance sale consideration), payment of interest at 12% per annum on amounts deposited after the stipulated delivery date (15.06.2012) until actual delivery, compensation for mental/physical harassment and litigation expenses, and adjustment mechanisms for remaining sale consideration.

Holding and Implications

HOLDING: The Commission allowed both complaints. In the words of the order, the complaints are "allowed" and specific directions were issued against the opposite parties.

Direct orders and consequences for the parties (as directed by the Commission):

  • The opposite parties are directed to deliver actual and physical possession of the allotted units (complete in all respects) with agreed facilities and amenities and with Completion/Occupation Certificate, subject to payment of the balance sale consideration (without interest or penalty thereon), and to execute the Sale/Conveyance Deed in favour of the complainants.
  • The opposite parties are directed to pay compensation for delay in delivery of possession at the rate of 12% per annum on the amount deposited by the complainants with them after the stipulated delivery date (15.06.2012) until actual and physical delivery of possession.
  • In Consumer Complaint No.752 of 2019 the opposite parties were directed to pay composite litigation expenses and compensation for mental and physical harassment to the tune of Rs. 30,000/-. In Consumer Complaint No.753 of 2019 the comparable sum directed was Rs. 18,000/-.
  • The remaining sale consideration payable by the complainants was to be adjusted from the opposite parties' above liabilities.
  • Compliance with the orders in both complaints was directed to be made by the opposite parties within 60 days of receipt of the certified copy of the order.

Implications beyond the parties: The Commission relied on earlier Commission decisions addressing the same promoter and project; the present order applies established principles to the facts at hand and enforces PAPRA and its Rules (including Rule 17's 12% interest provision). The opinion does not purport to announce a novel legal principle; it applies existing statutory provisions and prior Commission holdings to reach its decision.

Administrative Details

Panel/bench: Justice Paramjeet Singh Dhaliwal, President. Date of order: December 19, 2019. The complainants were represented by Sh. A.K. Batra, Advocate. The opposite parties were proceeded against ex parte.

To access the original judgment, please Sign In or Subscribe.

    Manoj Goyal & Anr. v. C & C Towers Ltd

    2) To be referred to the Reporters or not? Yes/No

    3) Whether judgment should be reported in the Digest? Yes/No Present:- For the complainants : Sh. A.K. Batra, Advocate For the opposite parties: Ex parte. JUSTICE PARAMJEET SINGH DHALIWAL, PRESIDENT This order will dispose of above mentioned two (2) Consumer Complaints filed by the complainants, under Section 17 of the Consumer Protection Act, 1986 (in short, the Act), as the facts and the questions of law involved in these complaints are the same and both the complaints have been filed against the same opposite parties by the different complainant(s). The facts are taken from Consumer Complaint No.752 of 2019. Consumer Complaint No.752 of 2019 Consumer Complaint No.752 of 2019 The complainants, who are son and father, have filed this complaint, under Section 17 of the Act, against the opposite parties, seeking following directions to them:

    i) to hand over possession of the unit/retail space immediately; ii) to pay interest at the rate of 12% per annum on the deposited amount till actual date of delivery of possession; iii) to pay compensation of 3,50,000/- on account of mental agony and harassment suffered by the complainants; and iv) to pay 31,000/- towards litigation expenses. Facts of the Complaint

    2. Brief facts, as set out in the complaint, are that being allured by the advertisement given by the opposite parties regarding their under construction Complex known as Bus Terminal-cum- Commercial Complex situated in Sector 57, Mohali, the complainants applied for purchasing a unit, exclusively for the purpose of creating the source of livelihood by way of self-employment by running a Construction Consulting office. The opposite parties offered unit No.32, Tower-C, 2nd Floor, having super area of 738 sq.ft. for basic sale price of 53,32,050/- at the rate of 7,225/- per sq.ft. The complainants paid a total sum of 21,95,550/- to the opposite parties towards the price of that unit, as per details given in Para Nos.4 to 6 of the complaint. Thereafter, letter of allotment dated 09.02.2011 was issued to them regarding the said unit. The opposite parties received various amounts from the complainants, ignoring the provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, Consumer Complaint No.752 of 2019 PAPRA). They failed to complete the construction of the unit within

    30 months from the date of compliance i.e. 15.12.2009, as per Clause 1.3.5 of the letter of allotment. No development was started and the work was abandoned by them. The complainants opted for Construction Linked Plan for making payment of instalments of price of the unit. However, on 21.11.2017, opposite party No.3 sent a letter to all the investors, stating that the Company would refund the deposited amount of investors, along with interest and that the investors, who wanted to stay with the Company, would be paid interest at the rate of 8.8% on their deposited amount. Since the construction was not started at the site, so there was no question of the complainants making payment of instalments. The complainants came to know through a public notice published in newspaper that GMADA had served a notice upon the opposite parties for non- completion of the construction and also for cancellation of the agreement. On 06.06.2018, opposite party No.3 sent another letter, requesting extension of time till 30.09.2018 for fulfilling the promises as made in the allotment letter. GMADA had replied to a letter sent by C & C Mohali Junction Buyer Association, stating that GMADA had already issued termination notice on 04.04.2016, but opposite party No.1 had sought extension of time for completion of the project. The aforesaid act and conduct of the opposite parties amount to deficiency in service. Hence, the present complaint.

    3. The opposite parties did not appear before this Commission, despite their service and, as such, they were proceeded against ex parte, vide order dated 04.12.2019. Consumer Complaint No.752 of 2019 Evidence of the Parties

    4. To prove their claim, the complainants filed their joint affidavit, along with copies of documents i.e. brochure Ex.C-1, receipt Ex.C-2, demand notice Ex.C-3, cheques Ex.C-4, letter of allotment Ex.C-5, letters Ex.C-6 to 8. Contentions of the Parties

    5. I have heard learned counsel for the complainants and have gone through the record carefully.

    6. Learned counsel for the complainants has argued on the lines of the complaint. It has been further contended that the complainants purchased the unit, in question, for running Construction Consulting Office for earning their livelihood by way of self- employment. It was further contended that as per clause 1.3.5 of allotment letter, the construction of the unit was to be completed within

    30 months from the date of lease period, after obtaining necessary approvals and sanctions. The opposite parties received a sum of 21,95,550/- from the complainants towards the price of the unit, in question, but they failed to complete the project, in question, within the said stipulated period, without disclosing any cogent reasons. No development was carried out at the site of Commercial Complex. The delay in completing the project and delivering possession has been duly admitted by the opposite parties in letter dated 21.11.2017, whereby they offered refund of the amount deposited by the investors and the investors, who wanted to retain the units, were to be awarded interest at the rate of 8.8% on their deposited amount. The opposite parties have neither delivered possession of the unit, in question, nor Consumer Complaint No.752 of 2019 refunded the amount deposited by them. Thus, they committed deficiency in service and unfair trade practice, by not honouring their commitments, as per the allotment letter. Accordingly, it has been contended that the complaint be allowed and all the reliefs, as prayed for in the complaint, be awarded in favour of the complainants. Consideration of Contentions

    7. I have given my thoughtful consideration to the contentions raised by the learned counsel for the complainants.

    8. At the outset, it is relevant to mention that the merits of the present complaints are squarely covered by the earlier verdicts given by this Commission in following cases:

    i) Consumer Complaint No.343 of 2016 (Sharanjeet Kaur v. C and C Towers Ltd. & Ors.) decided on 02.06.2017; ii) Consumer Complaint No.314 of 2017 (Indu Laroia & Anr. v. C and C Towers Limited & Ors.) decided on 07.11.2017; iii) Consumer Complaint No.99 of 2018 (Dharam Pal Nanda v. C & C Towers Ltd. & Ors.) decided on 19.07.2018; iv) Consumer Complaint No.825 of 2018 (Harpreet Singh v. C & C Towers Ltd. & Ors.) decided on 20.02.2019;

    v) Consumer Complaint No.183 of 2019 (Darshan Singh v. C & C Towers Ltd. & Ors.) decided on 15.05.2019; and vi) Consumer Complaint No.930 of 2018 (Ms. Kusum Sharma & Ors. v. C & C Towers Ltd. & Ors.) decided on 04.04.2019. So, I proceed to dispose of the present complaints, in view of the decisions given in the above noted cases. Consumer Complaint No.752 of 2019

    9. Admittedly, the complainants were allotted unit No.32, Tower-C, C & C Capital, having super area of 738 sq.ft. in the above said project of the opposite parties, vide letter of allotment dated 09.02.2011 Ex.C-5. The basic sale price of unit was 53,32,050/-. The complainants alleged in the compliant that they paid a total sum of 21,95,550/- with the opposite parties towards the price of the unit. However, as per receipts/cheques Ex.C-2 and Ex.C-4 (coly.) only a sum of 12,54,600/- stood deposited. They alleged that a sum of 9,40,950/- was also deposited by them in cash on 28.12.2010, but no receipt qua the same has been produced on record. As per clause 1.3.5 of the letter of allotment, Ex.C-3, the construction of the unit was likely to be completed within 30 months from the date of lease period

    i.e. from 15.12.2009 after obtaining all the necessary approvals and sanctions, subject to force majeure circumstances. Therefore, the construction of the unit, in question, was to be completed and possession was to be delivered up to 15.06.2012. The complaint has been filed on 11.10.2019 i.e. more 7 years therefrom. However, the opposite parties failed to complete the construction of project/unit within the stipulated period, without any sufficient cause, so as to deliver possession of the unit, in question, to the complainants. It is also relevant to mention that opposite parties wrote letter dated 21.11.2017, Ex.C-6, to the investors, offering refund of the amount deposited by the allottees. It was also mentioned therein that the investors, who wanted to stay invested with the Company, were to be paid interest at the rate of 8.8% per annum on the amount deposited by them, along with other applicable conditions. This letter clearly Consumer Complaint No.752 of 2019 proves that the opposite parties failed to complete the project within the stipulated timeframe, that is why they offered aforesaid rate of interest on the deposited amount of the investors, including complainants. Letter dated 06.06.2018, Ex.C-7, issued by the opposite parties also proves that they were not having sufficient funds for raising the project and, as such, they requested for extension of time till 30.09.2018 for repayment, as per commitment made vide letter Ex.C-6.

    10. In Harpreet Singhs case (supra), it was held as under: It is also relevant to mention that one another allottee sought information under RTI Act from GMADA. GMADA, vide letter dated 29.09.2016, Ex.C-7, supplied the requisite information to her, informing that no licence of construction was granted to the opposite parties, nor any agreement was entered into by the opposite parties with the Government. Still further, as per letter dated 11.03.2016, Ex.C-9, issued by GMADA, the process for cancelling the agreement of the opposite parties had already been initiated, due to non-completion of the project within the stipulated period. It is also mentioned therein that the reason for delay in completing the project was disclosed by the opposite parties to be paucity of funds. In such circumstances, the complainant cannot be made to wait for an indefinite period of time for the completion of the project and delivery of the space/unit in question. This certainly amounts to deficiency in service and adoption of unfair trade practice on the part of the opposite parties. From perusal of observations made by this Commission in the aforesaid case also, it is clear that the opposite parties failed to complete the project within the stipulated period due to paucity of Consumer Complaint No.752 of 2019 funds with them and GMADA had initiated process for cancellation of their licence.

    11. The whole purpose of pleadings is to give fair notice to each party of what the opponents case is and to ascertain with precision the point(s) on which the parties agree and those on which they differ. The purpose is to eradicate irrelevancy. The complaint is a concise statement of facts and if no reply is filed to the complaint, the averments made therein are deemed to have been admitted. For the sake of repetition, it is relevant to mention that the opposite parties failed to appear before this Commission, despite their service and, as such, they were proceeded against ex parte. Thus, all the averments made in the complaint are deemed to have been admitted by them and the evidence led by the complainants stands unrebutted; for which an adverse inference is to be drawn against them. Since the opposite parties are ex parte, so no evidence has come on record, whether they have obtained the requisite approvals and permissions from the competent authorities, before launching their project.

    12. Keeping in view the above circumstances, I hold that the opposite parties have failed to comply with the provisions of PAPRA. As per Section 3 (General Liabilities of Promoter) of the PAPRA, the opposite parties were required to make full and true disclosure of the nature of their title to the land, on which such project is developed or such building is constructed or is to be constructed, make full and true disclosure of all encumbrances on such land, including any right, title, interest or claim of any party in or over such land. They were also required to give inspection on seven days notice or demand of the Consumer Complaint No.752 of 2019 layout of the colony and plan of development works to be executed in a project, as approved by the prescribed authority in the case of a project. However, they failed to comply with Section 3 of the PAPRA.

    13. As per Section 5 (Development of land into Colony) of PAPRA, the opposite parties were liable to obtain permission from the competent authority for developing the project, but they failed to produce on record any such valid permission. So, they also violated Section 5 of PAPRA.

    14. As per Section 9 of PAPRA, every builder is required to maintain a separate account in a scheduled Bank, for depositing the amount deposited by the buyers, who intend to purchase the plots/flats/commercial space/unit, but no evidence has been led on the record by the opposite parties to prove that any account has been maintained by them in this respect. As such, the opposite parties also violated Section 9 of the PAPRA.

    15. As per Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995, framed under Section 45 of the PAPRA, it has been provided as under:-

    17. Rate of interest on refund of advance money upon cancellation of agreement.- The promoter shall refund full amount collected from the prospective buyers under sub-section (1) of section 6 together with interest thereon at the rate of twelve per cent per annum payable from the date of receipt of amount so collected till the date of re-payment. The Act came into being in the year 1986. It is the benevolent piece of legislation to protect the consumers from exploitation. The spirit of the benevolent legislation cannot be overlooked and its object is not to be frustrated. The complainants have made payment of substantial Consumer Complaint No.752 of 2019 amount to the opposite parties, with the hope to get the possession of the unit within a reasonable period. The circumstances clearly show that they made false statement of facts about the goods and services

    i.e. allotment of unit and delivery of possession in a stipulated period. The act and conduct of the opposite parties is a clear case of misrepresentation and deception, which resulted in the injury and loss of opportunity to the complainants. There is escalation in the price of construction also. The builder is under obligation to deliver the possession of the plot/unit/flat/space within a reasonable period. From the facts and evidence brought on the record of the complaint, it is clearly made out that the opposite parties i.e. builders knew from the very beginning that they had not complied with the provisions of the PAPRA and Rules and would not be able to deliver the possession within the stipulated period, thus by misrepresentation induced the complainants to book the unit, due to which the complainants have suffered mental agony and harassment. It is the settled principle of law that compensation should be commensurate with the loss suffered and it should be just, fair and reasonable and not arbitrary. The builder is bound to compensate for the loss and injury suffered by the complainants for failure to deliver the possession, so has been held in catena of judgments by the Honble Supreme Court and the Honble National Commission. To get the relief, the complainants have to wage a long drawn and tedious legal battle. As such, the complainants were at loss of opportunities. In these circumstances, opposite parties are liable to deliver physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Consumer Complaint No.752 of 2019 Completion/Occupation Certificate, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainants. For delay in delivery of possession, the opposite parties are also liable to pay compensation in the shape of interest at the rate of 12% per anum on the amount deposited by the complainants with them after the stipulated period for delivery of possession i.e. 15.06.2012 till actual and physical delivery of possession of the unit, as discussed above. Besides this, the complainants are also entitled to suitable litigation expenses and compensation for the mental agony and harassment suffered by them.

    16. Accordingly, the complaint is allowed and following directions are issued to the opposite parties:

    i) to deliver actual and physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Completion/Occupation Certificate, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainants; ii) to pay compensation for delay in delivery of possession at the rate of 12% per anum on the amount deposited by the complainants with them after the stipulated period for delivery of possession i.e. 15.06.2012 till actual and physical delivery of possession of the unit, as ordered above; and Consumer Complaint No.752 of 2019 iii) to pay composite litigation expenses and compensation for the mental and physical harassment suffered by the complainants to the tune of 30,000/-. iv) The remaining sale consideration payable by the complainants shall be adjusted from above said liability of the opposite parties. Consumer Complaint No.753 of 2019

    17. Similarly, in this complaint, complainant was allotted unit bearing No.4 having super area of 774 sq.ft. Tower-C, 12th Floor, in the project/Complex of the opposite parties, vide allotment letter dated 25.08.2010, Ex.C-3(colly.). The Basic Sale Price of the said unit was 38,70,000/-. As per provisional receipt Ex.C-2, a sum of 8,51,400/- was paid by the complainant to the opposite parties towards the price of the unit, vide cheque No.158384 dated 25.08.2010. Details of this cheque also reflect in Application Form Ex.C-3 (colly). The complainant alleged that a sum of 7,74,000/- was paid by him in cash, but no document to prove this fact has been produced in the complaint. The complainant booked the said unit for earning his livelihood by way of self-employment by running an Industrial Automation & Consulting office. As per Clause 1.3.5 of the allotment letter, construction of the unit was likely to be completed within 30 months from the date of start of lease period i.e. 15.12.2009. Thus, the possession was to be delivered up to 15.06.2012. However, the possession of the unit, in question, was not delivered by the opposite parties to the complainant within the stipulated period. Other averments are similar to that of Consumer Complaint No.752 of 2019. Consumer Complaint No.752 of 2019 Similar prayer has been made, similar documents have been produced and similar arguments have been made in the complaint.

    18. Similarly, in this case also, the opposite parties did not appear before this Commission, despite their service and, as such, they were proceeded against ex parte, vide order dated 04.12.2019.

    19. In view of the reasons and discussion held in Consumer Complaint No.752 of 2019, this complaint is allowed and following directions are issued to the opposite parties:

    i) to deliver actual and physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Completion/Occupation Certificate, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainants; ii) to pay compensation for delay in delivery of possession at the rate of 12% per anum on the amount deposited by the complainant with them after the stipulated period for delivery of possession i.e. 15.06.2012 till actual and physical delivery of possession of the unit, as discussed above; and iii) to pay composite litigation expenses and compensation for the mental and harassment suffered by the complainants to the tune of 18,000/-. iv) The remaining sale consideration payable by the complainant shall be adjusted from above liability of the opposite parties. Consumer Complaint No.752 of 2019

    20. The compliance of the orders passed in both the complaints shall be made by the opposite parties within a period of 60 days of the receipt of certified copy of the order. (JUSTICE PARAMJEET SINGH DHALIWAL) PRESIDENT December 19, 2019. (Gurmeet S)