2019 INSC 458
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 2(1)(r) of the Consumer Protection Act, 1986
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • 199th Report of the Law Commission of India on 'Unfair (Procedural & Substantive) Terms in Contract'
  • Section 2(1)(o) of the Consumer Protection Act, 1986
  • Section 23 of the Consumer Protection Act, 1986
  • Article 14 of the Constitution
  • Section …, draft legislation provided in the 199th Report
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2019 INSC 458
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 2(1)(r) of the Consumer Protection Act, 1986
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • 199th Report of the Law Commission of India on 'Unfair (Procedural & Substantive) Terms in Contract'
  • Section 2(1)(o) of the Consumer Protection Act, 1986
  • Section 23 of the Consumer Protection Act, 1986
  • Article 14 of the Constitution
  • Section …, draft legislation provided in the 199th Report
Smart Summary

Factual and Procedural Background

The appellant–builder launched a residential project known as “Araya Complex” at Gurugram and entered into an Apartment Buyer’s Agreement dated 08-05-2012 with the respondent for a flat priced at Rs 4,83,25,280. Under Clause 11.2 the builder was to apply for the occupancy certificate within 39 months from excavation (04-06-2012), extendable by a 6-month grace period—i.e. by 04-03-2016. The builder failed to do so.

The respondent filed a consumer complaint before the National Consumer Disputes Redressal Commission (NCDRC) on 27-01-2017 alleging deficiency of service and seeking, inter alia, refund with interest. On 06-02-2017 the NCDRC passed an ex-parte interim order restraining cancellation of the allotment. During the pendency of the complaint the builder obtained the occupancy certificate on 23-07-2018 and offered possession on 28-08-2018, which the respondent declined owing to the delay.

By final order dated 23-10-2018 (2018 SCC OnLine NCDRC 1164) the NCDRC directed the builder to refund Rs 4,48,43,026 with interest @ 10.7% p.a. calculated in terms of Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017. The builder appealed to the Supreme Court under Section 23 of the Consumer Protection Act, 1986. The present judgment disposes of those statutory appeals.

Legal Issues Presented

  1. Whether the respondent flat-purchaser was entitled to terminate the Apartment Buyer’s Agreement and claim refund despite not issuing a separate 90-day termination notice contemplated by Clause 11.5(ii) of the agreement.
  2. Whether contractual clauses limiting the builder’s liability to interest @ 6% or 9% p.a. could restrict the consumer forum from awarding a higher statutory rate of 10.7% p.a. under Rule 15 of the Haryana RERA Rules, 2017.
  3. Whether the one-sided clauses in the Apartment Buyer’s Agreement constituted unfair trade practices and were therefore unenforceable.

Arguments of the Parties

Appellant Builder's Arguments

  • The respondent was not entitled to refund because he never terminated the agreement through a 90-day notice as mandated by Clause 11.5(ii); filing a consumer complaint could not substitute this notice.
  • Even if the complaint is treated as termination, it was premature—filed before 04-03-2017, i.e. before the expiry of 12 months after the grace period.
  • The NCDRC erred in awarding interest @ 10.7% p.a.; the contract limited interest to 6% (Clause 20) or 9% (Clause 11.5(iv)). Reliance was placed on Bharathi Knitting Co. v. DHL Worldwide Express Courier, (1996) 4 SCC 704 to argue that compensation cannot exceed contractual terms.

Respondent Flat Purchaser's Arguments

  • The consumer complaint itself should be treated as the termination notice; the builder’s delay was already beyond the contractual and grace periods.
  • The clauses were patently one-sided: the builder could charge 18% p.a. for buyer’s delay, yet limit its own liability to 9% p.a. for its delay.
  • Interest @ 10.7% p.a. was correctly awarded under Rule 15 of the Haryana RERA Rules; respondent had serviced a bank loan @ 10% p.a. during the entire period.
  • Sought dismissal of the appeal and early payment so that loan liabilities could be cleared.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
LDA v. M.K. Gupta, (1994) 1 SCC 243 Delay in delivery of housing constitutes “deficiency of service” under the Consumer Protection Act. Used to affirm that the builder’s delay amounted to deficiency of service.
Fortune Infrastructure v. Trevor D'Lima, (2018) 5 SCC 442 Allottee cannot be forced to wait indefinitely; entitled to refund with compensation. Cited to justify permitting the purchaser to opt for refund rather than belated possession.
Central Inland Water Transport Corp. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156 Court will not enforce unfair or unreasonable contractual terms between parties of unequal bargaining power. Relied upon to strike down one-sided clauses in the Apartment Buyer’s Agreement.
Bharathi Knitting Co. v. DHL Worldwide Express Courier, (1996) 4 SCC 704 Tribunals should normally not grant compensation beyond contractual stipulations. Invoked by builder; Court distinguished it, holding statutory rules permitted higher interest.
BDA v. Syndicate Bank, (2007) 6 SCC 711 Allottee is entitled to refund with reasonable interest when possession is not delivered in time. Supported the NCDRC’s award of interest from the dates of payment till refund.

Court's Reasoning and Analysis

1. Deficiency of Service: The Court noted the builder obtained the occupancy certificate nearly two years after the stipulated deadline, clearly constituting deficiency of service as defined in LDA v. M.K. Gupta.

2. Right to Refund: Relying on Fortune Infrastructure, the Court held the respondent could not be compelled to accept possession after such inordinate delay and was entitled to refund with compensation.

3. Unfair Contract Terms: Examining Clauses 6.4, 11.5, 20 and 23.4, the Court found a stark imbalance: the builder could charge 18% p.a. for buyer delay, but the buyer could only claim 9% p.a. for builder delay and had limited termination rights. Using principles from Central Inland Water Transport, the Court declared these clauses one-sided, oppressive and therefore unenforceable.

4. Rate of Interest: The Court rejected the builder’s reliance on contractual caps, holding that Rule 15 of the Haryana RERA Rules provided a statutory measure—SBI MCLR + 2%—which the NCDRC correctly computed as 10.7% p.a. The award was also equitable because no interest was granted for the period when the stay on cancellation operated.

5. Distinguishing Bharathi Knitting Co.: That decision did not override statutory provisions; here, statutory rules justified departure from the contractual rate.

6. Conclusion on Liability: Finding no illegality or perversity in the NCDRC’s order, the Supreme Court affirmed the refund directive and the interest computation.

Holding and Implications

HOLDING: The civil appeals are dismissed; the NCDRC’s order dated 23-10-2018 is affirmed.

Implications: The appellant builder must refund Rs 4,48,43,026 with interest @ 10.7% p.a. (computed as directed by the NCDRC) within three months. The decision reinforces judicial scrutiny of one-sided builder-buyer agreements and affirms the applicability of statutory interest rates under the Haryana RERA Rules. No new precedent is set, but existing principles on unfair contract terms and consumer protection are robustly applied.

To access the original judgment, please Sign In or Subscribe.

    Pioneer Urban Land And Infrastructure Limited v. Govindan Raghavan .

    Indu Malhotra, J.— The present statutory appeals have been filed under Section 23 of the Consumer Protection Act, 1986 to challenge the final judgment and order dated 23-10-2018 passed in Geetu Gidwani Verma v. Pioneer Urban Land and Infrastructure Ltd. 2018 SCC OnLine NCDRC 1164 by the National Consumer Disputes Redressal Commission (hereinafter referred to as “the National Commission”).

    2. Since a common issue arises in both the civil appeals, they are being disposed of by the present common judgment and order.

    3. For the sake of brevity, the facts in CA No. 12238 of 2018 are being referred to, being the lead matter. The factual matrix of the said civil appeal is as under:

    3.1. The appellant builder launched a residential project by the name “Araya Complex” in Sector 62, Golf Course Extension Road, Gurugram. The respondent flat purchaser entered into an apartment buyer's agreement dated 8-5-2012 with the appellant builder to purchase an apartment in the said project for a total sale consideration of Rs 4,83,25,280. As per Clause 11.2 of the agreement, the appellant builder was to make all efforts to apply for the occupancy certificate within 39 months from the date of excavation, with a grace period of 180 days.

    3.2. The excavation of the project commenced on 4-6-2012. As per Clause 11.2 of the agreement, the builder was required to apply for the occupancy certificate by 4-9-2015, or within a further grace period of 6 months i.e. by 4-3-2016, and offer possession of the flat to the respondent flat purchaser. The appellant builder however failed to apply for the occupancy certificate as per the stipulations in the agreement.

    3.3. The respondent flat purchaser filed a consumer complaint before the National Commission on 27-1-2017 alleging deficiency of service on the part of the appellant builder for failure to obtain the occupancy certificate, and hand over possession of the flat. The respondent prayed inter alia for:

    (i) Refund of the entire amount deposited being Rs 4,48,43,026, along with interest @18% p.a.; and
    (ii) Compensation of Rs 10,00,000 for mental agony, harassment, discomfort and undue hardship; and
    (iii) Refund of the wrongfully charged taxes including service tax, and other charges along with interest @18% p.a.; and
    (iv) Litigation costs of Rs 1,00,000.

    3.4. On 6-2-2017 2017 SCC OnLine NCDRC 1990, the National Commission passed an ex parte interim order restraining the appellant builder from cancelling the allotment made in favour of the respondent flat purchaser during the pendency of the consumer case.

    3.5. During the pendency of the proceedings before the National Commission, the appellant builder obtained the occupancy certificate on 23-7-2018, and issued a possession letter to the respondent flat purchaser on 28-8-2018.

    3.6. The appellant builder submitted before the National Commission that since the construction of the apartment was complete, and the occupancy certificate had since been obtained, the respondent flat purchaser must be directed to take possession of the apartment, instead of directing refund of the amount deposited.

    3.7. The respondent flat purchaser however submitted that he was not interested in taking possession of the apartment on account of the inordinate delay of almost 3 years. The respondent flat purchaser stated that he had, in the meanwhile, taken an alternate property in Gurugram, and sought refund of the entire amount of Rs 4,48,43,026 deposited by him along with interest @18% p.a.

    3.8. The National Commission vide final judgment and order dated 23-10-2018 2018 SCC OnLine NCDRC 1164 allowed the consumer complaint filed by the respondent flat purchaser, and held that since the last date stipulated for construction had expired about 3 years before the occupancy certificate was obtained, the respondent flat purchaser could not be compelled to take possession at such a belated stage. The grounds urged by the appellant builder for delay in handing over possession were not justified, so as to deny awarding compensation to the respondent flat purchaser. The clauses in the agreement were held to be wholly one-sided, unfair, and not binding on the respondent flat purchaser.

    3.9. The appellant builder was directed to refund Rs 4,48,43,026 i.e. the amount deposited by the respondent flat purchaser, along with interest @10.7% SI p.a. towards compensation. The rate of interest @10.7% SI p.a. was fixed in accordance with Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 which reads as follows:

    “15. Interest payable by promoter and allottee.—An allottee shall be compensated by the promoter for loss or damage sustained due to incorrect or false statement in the notice, advertisement, prospectus or brochure in the terms of Section 12. In case, allottee wishes to withdraw from the project due to discontinuance of promoter's business as developers on account of suspension or revocation of the registration or any other reason(s) in terms of clause (b) sub-section (1) of Section 18 or the promoter fails to give possession of the apartment/plot in accordance with terms and conditions of agreement for sale in terms of sub-section (4) of Section 19. The promoter shall return the entire amount with interest as well as the compensation payable. The rate of interest payable by the promoter to the allottee or by the allottee to the promoter, as the case may be, shall be State Bank of India highest marginal cost of lending rate plus two per cent.”
    (emphasis supplied)

    3.10. However, for the period when the interim order dated 6-2-2017 2017 SCC OnLine NCDRC 1990 was in operation, which restrained the appellant builder from cancelling the respondent's allotment, no interest was awarded. The National Commission ordered payment of interest from the date of each instalment till 5-2-2017; and from the date of the order passed by the Commission till the date on which the amount would be refunded.

    3.11. Aggrieved by the order dated 23-10-2018 2018 SCC OnLine NCDRC 1164 passed by the National Commission, the appellant builder preferred the present statutory appeal under Section 23 of the Consumer Protection Act, 1986.

    4. Mr C.A. Sundaram, Senior Counsel appeared for the appellant builder, drew our attention to the following clauses in the apartment buyer's agreement dated 8-5-2012 viz. Clauses 11.5(ii), (iv) and (v) along with Clause 20 which read as under:

    “11.5. (ii) In the event of further delay by the Developer in handing over of the possession of the Unit even after 12 months from the end of grace period, then in such case, the intending Allottee shall have an additional option to terminate this agreement by giving termination notice of 90 days to the Developer and refund of the actual instalment paid by him against the Unit after adjusting the taxes paid/interest/penalty on delayed payments.
    ***
    (iv) Developer shall, within ninety (90) days from the date of receipt of termination notice of said Unit, refund to the intending Allottee, all the monies received excluding the service tax collected on various remittances, till the date of the refund, from the Intending Allottee under this agreement. In case the Developer fails to refund the Sale Price, the Developer shall pay interest to the Intending Allottee @9% p.a. for any period beyond the said period of ninety (90) days. The Intending Allottee shall have no other claim against the Developer in respect of the said Unit along with the parking space. The Intending Allottee in this event shall have no right to seek any compensation apart from the interest as stipulated herein.
    (v) If the Intending Allottee fails to exercise his right of termination within the time limit as aforesaid, by delivery to the Developer of a written notice acknowledged by the Developer in this regard, then he shall not be entitled to terminate this agreement thereafter and he shall continue to be bound by the provisions of this agreement, provided that in such case, the Developer shall continue to pay the compensation provided herein.
    ***
    20. Right of cancellation by the allottee
    Except to the extent specifically and expressly stated elsewhere in this agreement, the Intending Allottee shall have the right to cancel this agreement solely in the event of the clear and unambiguous failure of the warranties of the Developer that leads to frustration of the contract on that account. In such case, the Allottee shall be entitled to a refund of the instalments actually paid by it along with interest thereon @6% p.a., within a period of 90 days from the date of communication to the Developer in this regard less any payments made towards taxes paid by the Developer or interest paid due or payable, any other amount of a non-refundable nature. No other claim, whatsoever, monetary or otherwise shall lie against the Developer nor shall be raised otherwise or in any manner whatsoever by the Allottee. Save and except to this limited extent, the Allottee shall not have any right to cancel this agreement on any ground whatsoever.”
    (emphasis supplied)

    4.1. It was submitted that the respondent flat purchaser was not entitled to refund of the amount deposited, since the apartment buyer's agreement was not terminated by the respondent flat purchaser in accordance with Clause 11.5(ii) of the agreement, which stipulates that the allottee has to terminate the agreement by giving a termination notice of 90 days to the Developer. Since the respondent flat purchaser had not terminated the agreement by a written notice as per Clause 11.5, the builder could not sell the apartment, and refund the money to the respondent flat purchaser. On the contrary, the respondent filed a consumer complaint and obtained an ex parte interim order dated 6-2-2017 2017 SCC OnLine NCDRC 1990 restraining the builder from cancelling the allotment made in favour of the respondent.

    4.2. It was further submitted that if the filing of the consumer complaint is considered as an act of termination of the agreement, then the same was premature. As per Clause 11.5(ii), the respondent flat purchaser could have claimed refund only after the expiry of 12 months after the grace period came to an end i.e. after 4-3-2017. However, the consumer complaint was filed on 27-1-2017. In these circumstances, even if it is found that the appellant builder is liable to refund the amount deposited with interest, then the date of the impugned order i.e. 23-10-2018 2018 SCC OnLine NCDRC 1164, must be treated as the date of serving the termination notice as per Clause 11.5(ii) of the agreement, and the appellant builder should be held liable to pay interest only after 90 days from the date of termination i.e. from 23-1-2019.

    4.3. With respect to the rate of interest awarded by the National Commission, it was submitted that the Commission erred in granting interest @10.7% SI p.a. even though Clause 20 of the agreement provided interest @6% p.a. in case of delay in handing over possession. Even under Clause 11.5 of the agreement, the builder was liable to pay interest @9% p.a., but not @10.7% SI p.a. The learned Senior Counsel relied upon this Court's judgment in Bharathi Knitting Co. v. DHL Worldwide Express Courier Division of Airfreight Ltd. (1996) 4 SCC 704 and submitted that the National Commission could not have granted compensation in excess of the rate prescribed by the agreement.

    5. Mr Sushil Kaushik, learned counsel represented the respondent flat purchaser.

    5.1. It was submitted that the filing of the consumer complaint may be treated as his termination notice under Clause 11.5(ii) of the agreement. Under the agreement, the builder was obligated to apply for the occupancy certificate within 39 months from the date of excavation, with a grace period of further 6 months. The period got over by 4-3-2016 after taking into account the grace period. Admittedly, the appellant builder offered possession after an inordinate delay of almost 3 years on 28-8-2018. On account of the inordinate delay, the respondent flat purchaser had no option but to arrange for alternate accommodation in Gurugram. Hence, he could not be compelled to take possession of the apartment after such a long delay. It was in these circumstances that the respondent flat purchaser sought stay of the cancellation of the allotment as a collateral, till his claim for refund was adjudicated by the National Commission.

    5.2. It was further submitted that the clauses of the agreement were one-sided. As per Clause 6.4(ii) of the apartment buyer's agreement, the appellant builder could charge interest @18% p.a. for delayed payments. However, the appellant builder was not required to pay equivalent interest to the respondent flat purchaser for delay in handing over possession of the flat. On the contrary, as per Clause 11.5(iv) of the agreement, in case of delay on the part of the appellant builder in handing over possession of the flat, the respondent flat purchaser was entitled to interest @9% p.a. only.

    5.3. The respondent further submitted that the National Commission had ordered payment of interest as per the statutory Rules i.e. Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 @10.7% SI p.a. The respondent flat purchaser submitted that he had obtained a loan for Rs 3,30,00,000 from Standard Chartered Bank to purchase the flat in question, and had entered into a tripartite loan agreement with the Bank and the builder. The respondent flat purchaser had to pay interest @10% p.a. for servicing the loan for the entire period. Hence, interest @10.7% SI p.a. awarded by the National Commission was just and fair. It was pointed out that even though the National Commission had not granted interest for the period during which the order of stay of cancellation of the allotment was in operation, the respondent flat purchaser had to pay interest to the Bank even for this period.

    5.4. The respondent flat purchaser submitted that the present appeal be dismissed, and the builder be directed to pay the amount awarded by the National Commission with interest, within 1 week, so that the respondent can discharge his loan liability.

    6. We have heard the learned counsel for both the parties, and perused the pleadings, and written submissions filed.

    6.1. In the present case, admittedly the appellant builder obtained the occupancy certificate almost 2 years after the date stipulated in the apartment buyer's agreement. As a consequence, there was a failure to hand over possession of the flat to the respondent flat purchaser within a reasonable period. The occupancy certificate was obtained after a delay of more than 2 years on 28-8-2018 during the pendency of the proceedings before the National Commission. In LDA v. M.K. Gupta (1994) 1 SCC 243, this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2(1)(o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service. In Fortune Infrastructure v. Trevor D'Lima (2018) 5 SCC 442, this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.

    6.2. The respondent flat purchaser has made out a clear case of deficiency of service on the part of the appellant builder. The respondent flat purchaser was justified in terminating the apartment buyer's agreement by filing the consumer complaint, and cannot be compelled to accept the possession whenever it is offered by the builder. The respondent purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation.

    6.3. The National Commission in the impugned order dated 23-10-2018 2018 SCC OnLine NCDRC 1164 held that the clauses relied upon by the builder were wholly one-sided, unfair and unreasonable, and could not be relied upon. The Law Commission of India in its 199th Report, addressed the issue of “Unfair (Procedural & Substantive) Terms in Contract”. The Law Commission inter alia recommended that a legislation be enacted to counter such unfair terms in contracts. In the draft legislation provided in the Report, it was stated that:

    “… a contract or a term thereof is substantively unfair if such contract or the term thereof is in itself harsh, oppressive or unconscionable to one of the parties.”

    6.4. A perusal of the apartment buyer's agreement dated 8-5-2012 reveals stark incongruities between the remedies available to both the parties. For instance, Clause 6.4(ii) of the agreement entitles the appellant builder to charge interest @18% p.a. on account of any delay in payment of instalments from the respondent flat purchaser. Clause 6.4(iii) of the agreement entitles the appellant builder to cancel the allotment and terminate the agreement, if any instalment remains in arrears for more than 30 days. On the other hand, as per Clause 11.5 of the agreement, if the appellant builder fails to deliver possession of the apartment within the stipulated period, the respondent flat purchaser has to wait for a period of 12 months after the end of the grace period, before serving a termination notice of 90 days on the appellant builder, and even thereafter, the appellant builder gets 90 days to refund only the actual instalment paid by the respondent flat purchaser, after adjusting the taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the appellant builder is liable to pay interest @9% p.a. only.

    6.5. Another instance is Clause 23.4 of the agreement which entitles the appellant builder to serve a termination notice upon the respondent flat purchaser for breach of any contractual obligation. If the respondent flat purchaser fails to rectify the default within 30 days of the termination notice, then the agreement automatically stands cancelled, and the appellant builder has the right to forfeit the entire amount of earnest money towards liquidated damages. On the other hand, as per Clause 11.5(v) of the agreement, if the respondent flat purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the agreement thereafter, and shall be bound by the provisions of the agreement.

    6.6. Section 2(1)(r) of the Consumer Protection Act, 1986 defines “unfair trade practices” in the following words:

    “2.(1)(r) “unfair trade practice” means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice.…”,
    and includes any of the practices enumerated therein. The provision is illustrative, and not exhaustive.

    6.7. In Central Inland Water Transport Corpn. Ltd. v. Brojo Nath Ganguly (1986) 3 SCC 156 this Court held that:

    “89. … Our Judges are bound by their oath to “uphold the Constitution and the laws”. The Constitution was enacted to secure to all the citizens of this country social and economic justice. Article 14 of the Constitution guarantees to all persons equality before the law and the equal protection of the laws. … This principle is that the courts will not enforce and will, when called upon to do so, strike down an unfair and unreasonable contract, or an unfair and unreasonable clause in a contract, entered into between parties who are not equal in bargaining power. It is difficult to give an exhaustive list of all bargains of this type. No court can visualise the different situations which can arise in the affairs of men. One can only attempt to give some illustrations. For instance, the above principle will apply where the inequality of bargaining power is the result of the great disparity in the economic strength of the contracting parties. It will apply where the inequality is the result of circumstances, whether of the creation of the parties or not. It will apply to situations in which the weaker party is in a position in which he can obtain goods or services or means of livelihood only upon the terms imposed by the stronger party or go without them. It will also apply where a man has no choice, or rather no meaningful choice, but to give his assent to a contract or to sign on the dotted line in a prescribed or standard form or to accept a set of rules as part of the contract, however unfair, unreasonable and unconscionable a clause in that contract or form or rules may be. This principle, however, will not apply where the bargaining power of the contracting parties is equal or almost equal. This principle may not apply where both parties are businessmen and the contract is a commercial transaction. … These cases can neither be enumerated nor fully illustrated. The court must Judge each case on its own facts and circumstances.”
    (emphasis supplied)

    6.8. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the agreement dated 8-5-2012 are ex facie one-sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2(1)(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the builder.

    7. In view of the above discussion, we have no hesitation in holding that the terms of the apartment buyer's agreement dated 8-5-2012 were wholly one-sided and unfair to the respondent flat purchaser. The appellant builder could not seek to bind the respondent with such one-sided contractual terms.

    8. We also reject the submission made by the appellant builder that the National Commission was not justified in awarding interest @10.7% SI p.a. for the period commencing from the date of payment of each instalment, till the date on which the amount was paid, excluding only the period during which the stay of cancellation of the allotment was in operation. In BDA v. Syndicate Bank (2007) 6 SCC 711 a Coordinate Bench of this Court held that when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable interest thereon from the date of payment till the date of refund.

    9. In the present case, the National Commission has passed an equitable order. The Commission has not awarded any interest for the period during which the order of stay of cancellation of the allotment was in operation on the request of the respondent flat purchaser. The National Commission has rightly awarded interest @10.7% SI p.a. by applying Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 from the date of each instalment till 5-2-2017 i.e. till the date after which the order of stay of cancellation of the allotment was passed; and thereafter, from the date of the Commission's final order till the date on which the amount is refunded with interest.

    10. We see no illegality in the impugned order dated 23-10-2018 2018 SCC OnLine NCDRC 1164 passed by the National Commission. The appellant builder failed to fulfil his contractual obligation of obtaining the occupancy certificate and offering possession of the flat to the respondent purchaser within the time stipulated in the agreement, or within a reasonable time thereafter. The respondent flat purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the agreement expired. During this period, the respondent flat purchaser had to service a loan that he had obtained for purchasing the flat, by paying interest @10% to the Bank. In the meanwhile, the respondent flat purchaser also located an alternate property in Gurugram. In these circumstances, the respondent flat purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with interest.

    11. The civil appeals are accordingly dismissed, and the final judgment and order dated 23-10-2018 2018 SCC OnLine NCDRC 1164 passed by the National Consumer Disputes Redressal Commission is affirmed. The appellant is granted a period of three months from today to refund the amount to the respondent. All pending applications, if any, are accordingly disposed of.