Factual and Procedural Background

This appeal was preferred by Mr. Prateek Gupta, a Director and shareholder of Petrolube India Limited, against the order dated 25 January 2018 passed by the Adjudicating Authority (National Company Law Tribunal), Bench III, New Delhi. The impugned order had admitted an application under Section 9 filed by the respondent, M/s Columbia Petro Chem Pvt. Ltd., imposed a moratorium and appointed an Interim Resolution Professional with certain directions. The appeal was filed on 26 March 2018. The court considered the appeal timely based on the appellant's date of knowledge, since the appellant was not a party before the Adjudicating Authority by name.

Legal Issues Presented

  1. Whether the impugned order under Section 9 was passed without notice to the Corporate Debtor (i.e., whether notice under Section 8(1) was served).
  2. Whether a demand notice under Section 8(1) of the I&B Code was in fact served on the Corporate Debtor.
  3. Whether there existed a pre-existing dispute by the Corporate Debtor regarding the Operational Creditor's claim prior to issuance of the Section 8(1) notice.

Arguments of the Parties

Appellant's Arguments

  • The impugned order was passed by the Adjudicating Authority without notice to the Corporate Debtor.
  • Notice under Section 8(1) was never served on the Corporate Debtor; specifically, the demand notice dated 03.08.2017 was only shown to be at a Post Office at Mera Bagh (suggesting it was not properly served).
  • There exists a dispute (contention raised that a dispute existed regarding the creditor's claim).

Respondent's Arguments

  • The Respondent disputed the appellant's claim that notices were not served and submitted that notices were in fact served on the Corporate Debtor.
  • The Respondent produced a letter dated 07.02.2017 from Mr. Vinit N. Misha, Advocate (High Court, Mumbai) concerning the demand notice issued under Section 8(1).
  • The Respondent produced postal evidence: an Indian Post receipt and tracking record showing the Section 8(1) notice dated 07.02.2017 was booked on 09.02.2017 and delivered with acknowledgement at the Punjabi Bagh Office of the Corporate Debtor (the receipt is noted as being at page 61 of the record).

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court first addressed timeliness: although the impugned order was dated 25 January 2018 and the appeal was filed on 26 March 2018, the appeal was held to be timely in view of the appellant's date of knowledge because the appellant was not a party before the Adjudicating Authority by name.

On the notice issue, the appellant contended that the Section 8(1) demand notice was not served. The court observed an absence of any record suggesting that notices were issued to the Corporate Debtor and therefore stated it would not deliberate on whether the application had been admitted without notice. However, the Respondent produced specific documentary evidence: a letter from its counsel and postal receipts/tracking showing booking and delivery with acknowledgement at the Corporate Debtor's Punjabi Bagh office. Based on that postal evidence (including the Indian Post receipt referenced at page 61), the court concluded that the notice under Section 8(1) was served on the Corporate Debtor.

Regarding the existence of a dispute, the court observed there was nothing on record to indicate that the Corporate Debtor had disputed any of the Operational Creditor's claims prior to the issuance of the Section 8(1) notice.

In light of these findings—service of the Section 8(1) notice established by postal evidence and absence of a pre-existing dispute—the court found no reason to interfere with the Adjudicating Authority's order admitting the Section 9 application, imposing the moratorium and appointing an Interim Resolution Professional.

Holding and Implications

DISMISSED

The appeal was dismissed and no costs were awarded. The direct consequence is that the impugned order dated 25 January 2018 of the Adjudicating Authority stands: the Section 9 application remains admitted, the moratorium remains in place, and the Interim Resolution Professional continues in office. The opinion does not discuss any broader legal implications or establish a new precedent.

To access the original judgment, please Sign In or Subscribe.

    Prateek Gupta v. Columbia Petro Chem Pvt. Ltd.

    28.05.2018: This appeal has been preferred by Mr. Prateek Gupta, Director and shareholder of Petrolube India Limited against order dated 25th January, 2018 passed by the Adjudicating Authority (National Company Law Tribunal), Bench III, New Delhi whereby and whereunder an application under Section 9 preferred by Respondent M/s Columbia Petro Chem Pvt. Ltd. has been admitted, order of moratorium has been passed and Interim Resolution Professional has been appointed with certain directions.

    2. The impugned order was passed on 25th January, 2018 but the appeal was filed on 26th March, 2018. However, in view of the fact that the Appellant is the Director and Shareholder of the Corporate Debtor and was not a party before the Adjudicating Authority by name, on the basis of date of knowledge of the Appellant, we find that the appeal is on time.

    3. Learned counsel appearing on behalf of the appellant submitted that the impugned order has been passed by the Adjudicating Authority without notice to the Corporate Debtor. She further submitted that notice under Section 8(1) was never served on the Corporate Debtor.

    4. Learned counsel appearing on behalf of the Respondent disputed such claim and taken plea that notices were served on the Corporate Debtor.

    5. However, in absence of any record to suggest that the notices were issued to the Corporate Debtor, we are not deliberating on question whether the application was admitted without notice to the Corporate Debtor or not.

    6. The other question raised by the learned counsel for the appellant is that there is an existence of dispute. But there is nothing on record to suggest that the Corporate Debtor disputed any of the claim of the Operational Creditor prior to issuance of notice under Section 8(1) of the I&B Code.

    7. Learned counsel for the Appellant submits that demand notice under Section 8(1) was not served on the Corporate Debtor. Referring to the notice under Section 8(1) dated 03.08.2017 it is submitted that record suggest that the said notice was served in the Post Office at Mera Bagh.

    8. Learned counsel appearing on behalf of the Respondent brought on record the letter dated 07.02.2017 issued by Mr. Vinit N Misha, Advocate, High Court Mumbai, whereunder the demand notice issued under Section 8(1) on the Corporate Debtor. The Respondent has also filed the receipt issued by the Indian Post and track record of consignment shows that the notice under Section 8(1) dated 07.02.2017 was booked on 09.02.2017, and was delivered with acknowledgement at Punjabi Bagh Office of the Corporate Debtor. This is apparent from the Indian Posts receipt at page 61. Therefore, we find that notice under Section 8(1) was served on the Corporate Debtor. Company Appeal (AT) (Insolvency) No. 133 of 2018

    9. For the reasons aforesaid, we are not inclined to interfere with the impugned order. We find no merit in this appeal. It is accordingly dismissed. No costs. [Justice S. J. Mukhopadhaya] Chairperson [Justice Bansi Lal Bhat] Member (Judicial) am/gc Company Appeal (AT) (Insolvency) No. 133 of 2018