Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Smart Summary

Factual and Procedural Background

The petitioner, Delhi Development Authority (DDA), invited tenders for construction of residential houses and garages at Vasant Kunj, with the contract awarded to the respondent, M/s K.R. Builders Pvt. Ltd. The contract was dated 10 March 1989 with an initial completion period of 18 months, extended without liquidated damages until 30 June 1991. The work was finally completed on 5 August 1993, but the final bill was paid only on 19 October 2005. Dissatisfied with the payment, the Contractor raised 26 claims. An arbitral award dated 29 November 2010 partially allowed some claims in favor of the Contractor. The DDA challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996.

Legal Issues Presented

  1. Whether the deductions made by the DDA towards rebates for monthly payments, release of security, payment of final bill, and sanction of EIS without fulfillment of contractual obligations were lawful (Claim No.1).
  2. Whether the recovery of penal/double rates for unused materials from the final bill was justified (Claim No.2).
  3. Whether the recovery towards alleged risk and cost for pending works on certain flats was justified (Claim No.4).
  4. Whether the payment for ornamental grills, differing from the contractually agreed plain grills, was justified (Claim No.14).
  5. Whether the deduction of amounts on account of RIS/DIS from the final bill was lawful (Claim No.15).
  6. Whether the grant of escalation under Clause 10CC of the agreement and the levy of liquidated damages eight years after completion were justified (Claim No.19).
  7. Whether escalation on amounts awarded against various claims was properly calculated and awarded (Claim No.23).
  8. What is the appropriate rate of interest payable pendente lite and in future on the awarded sums.

Arguments of the Parties

Petitioner's Arguments (DDA)

  • DDA contended that deductions made from the final bill under Claim No.1 were lawful since the Contractor was contractually obliged to submit monthly bills and rebates were applicable if payments were timely.
  • DDA argued that for extra/substituted items, a rebate of 0.1% was due if sanctioned within three months and an additional rebate of 0.25% applied if final billing and security release occurred within stipulated timeframes.
  • Regarding Claim No.2, DDA claimed materials supplied but unused by the Contractor were not returned, justifying recovery.
  • For Claim No.4, DDA asserted that pending work on two flats had to be completed by a third party, justifying recovery of risk and cost.
  • In Claim No.15, DDA maintained that the amounts deducted were "excepted matters" and justified deductions without issuing notices during contract currency.
  • Regarding Claim No.19, DDA sought to levy liquidated damages in 2004, eight years after completion, based on extension granted subject to recovery of liquidated damages.

Respondent's Arguments (Contractor)

  • Contractor contended that it was common practice that monthly bills were not submitted by Contractors and the Engineer-in-Charge prepared the bills, negating entitlement to rebate.
  • Contractor relied on precedent (Saraswati Construction Co. vs. DDA) supporting the position that rebate was not due where monthly payments were not made.
  • Contractor argued that the work, including ornamental grills, was executed beyond original tender items and was entitled to payment.
  • Contractor opposed the levy of liquidated damages made long after contract completion and asserted entitlement to escalation under Clause 10CC for the period after March 1992 until completion.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Saraswati Construction Co. vs. DDA (IA No. 970/94 in Suit No. 2472/93, decided 19 December 2002) Rebate entitlement where monthly payments are not made as per contract. The Court noted this precedent was relied upon by the Arbitrator and the Contractor to support the claim that rebate was not due since monthly payments were not made, but ultimately held that the contractual obligation to submit monthly bills remained with the Contractor, and rebate deductions were justified.

Court's Reasoning and Analysis

The Court undertook a detailed examination of each contested claim in light of the contract terms, correspondence, and arbitral findings. It emphasized the contractual obligation of the Contractor to submit monthly bills and held that the Engineer-in-Charge preparing bills in absence of timely submissions did not negate DDA's entitlement to rebates and deductions. The Court found the Arbitrator erred in allowing Claim No.1 in favor of the Contractor and set aside that part of the award.

Regarding Claim No.2, the Court upheld the Arbitrator's findings that double rate recovery was impermissible and awarded a sum in favor of DDA, finding no error. For Claim No.4, the Court accepted the Arbitrator's factual conclusion that the Contractor completed all flats and declined interference as the matter was factual and beyond the scope of Section 34 challenge.

On Claim No.14, the Court found no fault in awarding the Contractor for ornamental grills, as the work was executed beyond the original agreement. For Claim No.15, the Court agreed with the Arbitrator that deductions made years after completion without proper notice were unjustified.

Concerning Claim No.19, the Court accepted the Arbitrator's reasoning that liquidated damages imposed eight years after completion were untenable, and that escalation under Clause 10CC was rightly awarded for the period post-March 1992 until completion. The Court noted hindrances caused by DDA justified the delay and rejection of liquidated damages.

For Claim No.23, the Court restricted escalation to amounts awarded in claims other than Claim No.1, which was set aside. Finally, the Court modified the interest rate to 6% per annum pendente lite and future interest, considering the delay caused by the Contractor in raising bills, with a higher rate if payment was delayed beyond three months.

Holding and Implications

The Court partially set aside and partially upheld the arbitral award as follows:

  • The deduction of Rs.56,635.28 by DDA under Claim No.1 was held justified, and the award in favor of the Contractor on this claim was set aside.
  • The award on Claim No.2 was upheld in favor of DDA for Rs.8,400/- and no interference was warranted.
  • The Arbitrator's rejection of DDA's Claim No.4 was upheld as a factual finding not amenable to challenge under Section 34.
  • The award of Rs.35,055/- in favor of the Contractor for ornamental grills (Claim No.14) was upheld.
  • The deduction under Claim No.15 was held unjustified due to lack of notice and delay in sanctioning.
  • The levy of liquidated damages eight years post-completion was held unjustified, and escalation under Clause 10CC was awarded to the Contractor for the relevant period.
  • Escalation on amounts awarded in other claims (excluding Claim No.1) was allowed, with the interest rate modified to 6% per annum pendente lite and future interest.
  • The petition was disposed of accordingly.

No new precedent was established; the decision applies existing contractual and arbitration principles to the facts of the case.

To access the original judgment, please Sign In or Subscribe.

    Delhi Development Authority v. K.R. Builders (P) Ltd. .

    $~8 * IN THE HIGH COURT OF DELHI AT NEW DELHI nd

    Date of Decision: 22 January, 2019 + O.M.P. 265/2011

    DELHI DEVELOPMENT AUTHORITY ..... Petitioner Through: Mr. Dhanesh Relan, Mr. Rishi Vohra and Ms. Kanika Singh, Advocates.

    (M:9999498955)

    versus

    M/S K.R BUILDERS (P) LTD. ..... Respondent Through: Mr. Raman Kapur, Senior Advocate with Mr. Aviral Tiwari and Mr. R. P. Singh, Advocate. (M:9810359150)

    CORAM:

    JUSTICE PRATHIBA M. SINGH

    Prathiba M. Singh, J. (Oral)

    1. Present petition under Section 34 of the Arbitration and Conciliation Act, 1996 („the Act") challenges the award dated 29thNovember, 2010 passed by the Ld. Sole Arbitrator, Justice Usha Mehra (Retd).

    2. The Petitioner - DDA (hereinafter, 'DDA') invited tenders for

    "Construction of 630 SFS houses at Vasant Kunj, Sector-'E' Pkt. 5 & 6 falling in category II & III in Vasant Kunj and 60 SFS houses (36 Cat. III,

    24 Cat. II) and 36 s/Garages at Vasant Kunj, Gr. XI." (`Works'). The parties entered into contract dated 10thMarch, 1989. The total cost of the tender was Rs.91.08 lakhs. The Respondent - M/s. K. R. Builders Pvt. Ltd. (hereinafter 'the Contractor') was to complete the work within 18 months i.e. on or before 22ndAugust, 1990. Extension was granted by the DDA without levy of liquidated damages until 30thJune, 1991. Finally, the work

    1

    was completed on 5thAugust, 1993. Date of completion was recorded as 5th August, 1993. However, final bill was paid only on 19thOctober, 2005. The payment of the final bill was not to the satisfaction of the Contractor and claims were raised. A total of 26 claims were raised by the Contractor.

    3. Ld. Arbitrator, after considering all the claims, allowed some of the claims and awarded in favour of the Contractor. Operative portion of the award is set out herein below:

    "Claim No.26 Presuit, Pendentelite and future interest @18% per annum.

    92. I have award a total sum of Rs.9,32,113.85P plus the amount of escalation amounting to Rs.72,832/-, in favour of the claimant and against the respondent. On the awarded amounts, claimant will be entitled to interest pendente lite and future till realization @ 9% per annum."

    4. Mr. Dhanesh Relan, learned counsel appearing for DDA submits that the DDA has challenged the award in respect of some of the claims. Objections have been argued in respect of claim nos.1, 2, 4, 14, 15, 19 & partly 23.

    A. Claim No.1- Claim of Rs.56,635.28 on account of amount unlawfully recovered by the department from final bill towards rebate for monthly payments, release of security, payment of final bill and sanction of EIS without fulfilling the contractual obligations

    5. A perusal of claim no.1 shows that the DDA had, according to the Contractor, unlawfully deducted a sum of Rs.56,635/- towards rebate for monthly payments, release of security, payment of final bill and sanction of EIS. The case of the DDA is that the Contractor was obliged to raise the bills on a monthly basis and upon DDA making the monthly payments, it

    2

    was entitled to rebate on the estimated cost @ 0.25%. It was also claimed by the DDA that on extra/substituted items, the DDA was entitled to 0.1% of the gross amount, if the same was sanctioned within three months from the date of occurrence. DDA further argued that the final bill if paid within 6 months and if release of security deposit happens within one month from the expiry of maintenance period, it is entitled to a further rebate of 0.25%. Submission is that under clause 8, the Contractor was obliged to raise the bill on a monthly basis, which was then to be paid by the DDA on a monthly basis. In the present case, admittedly, the Contractor did not submit the bills in time and the Engineer-in-Charge himself prepared the bill. In view of this, the DDA claims that rebate ought to be given and deductions were rightly made by the DDA. Mr. Relan also relies upon the letter dated 14th February, 1989 which contained the said details of the rebate which can be deducted and was duly accepted by the Contractor.

    6. Mr. Raman Kapur, learned Senior Advocate appearing for the Contractor, submits that as a matter of practice, the Contractors never submit the bill and the measurements are done by the Engineer-in-Charge. Thus, the Engineer-in-Charge himself prepares the bill. Since the payment was not made on a month to month basis, the DDA is not entitled to rebate. Mr. Kapur relies upon the judgment in Saraswati Construction Co. vs. DDA in th IA No. 970/94 in Suit No.2472/93 decided on 19 December, 2002 as is relied upon by the Ld. Arbitrator.

    7. The clause in the contract is clear and categorical that the Contractor has to submit the monthly bill. It is possible that there can be joint measurement, which can be conducted but the obligation for submission of the bill cannot be shifted on the Engineer-in-Charge. If the Contractor did

    3

    not submit the bill in time, the Engineer-in-Charge himself took upon the onus of preparing bills, thus, it cannot be said that the DDA is not entitled to rebate. Similar is the position in respect of the final bill, as also release of security and sanction of EIS. Thus, on this count, the Ld. Arbitrator having clearly noticed that the Engineer-in-Charge prepared the bills, has erred in not upholding the stand of the DDA. It is, accordingly, held that the deduction by the DDA to the tune of Rs.56,635.28 is justified. The award on this claim is set aside.

    B. Claim No.2 - Rs.66,753.48P on account of unlawfully recovery by the department from the final bill towards penal/double rate recovery against steel, G.I. pipe-15mm dia, glazed tiles, C.I.Pipes (Class I.A.) 100mm dia, Bitumen and flush & Panel door shutters etc.

    8. Insofar as claim no.2 is concerned, the DDA claims that cement, steel and other material, which were supplied to the Contractor and were not used, were not returned back to the DDA. Ld. Arbitrator has undertaken a detailed analysis of the correspondence and documents on record and has awarded a sum of Rs.8,400/- in favour of the DDA. The Ld. Arbitrator has taken the price of cement and steel as per BOQ items. Double rate recovery is clearly not permissible as per the settled law. Accordingly, no fault can be found in the award of the Arbitrator on this count.

    C. Claim No.4 - Rs.72,427/- on account of amount unlawfully recovered by the deptt. In the final bill towards alleged risk and cost.

    9. The case of the DDA is that pending works in respect of two flats i.e. Flat Nos.4587 & 4597 had to be got done by a third party. Ld. Arbitrator has, after perusing the exhibits on record and letters exchanged between the parties, arrived at a conclusion that the Contractor, in fact, completed the

    4

    work in respect of all the flats and there was no reason as to why these flats would have been left out by the Contractor. The mere fact that the flat numbers were missing in the letters, does not show that the Contractor had not completed the work. Thus, the Ld. Arbitrator rejected the claim of the DDA. The claim is factual in nature and objections in respect thereof are not maintainable under Section 34. The said award does not warrant any interference.

    D. Claim No.14 - Rs. 35,055.22 on account of balance payment for the work of providing ornamental grills but arbitrarily paid by the deptt. As per agreement item for plain grills.

    10. The Contractor has been awarded a sum of Rs.35,055/- in respect of installing ornamented grills. Case of the Contractor is that ornamental grills were not part of the original tendered items and there is no dispute that the Contractor actually executed the work of erecting ornamental grills. As per the contract, only plain grills were to be erected. Since the Contractor has executed the work and has, in fact, erected the ornamental grills, no fault can be found in the award of the amounts in favour of the Contractor for erection of ornamental grills.

    E. Claim No.15 - Rs.15,960.92 on account of amounts unlawfully and uncontractually recovered by the deptt. In respect of alleged RIS/DIS from final bill.

    11. Stand of the DDA in respect of this claim was that the same constitutes `excepted matter". The DDA was, however, unable to produce any decision of the superintendent engineer in respect of this issue which holding it to be "excepted matter". DDA also did not issue any notice under clause 14 during the currency of the contract and has thus made recovery in

    5

    the running bills without any justification. Ld. Arbitrator, thus, held that the reduction was not justified. Ld. Arbitrator observed that since the completion was recorded as 30thApril, 1997 and reduction was sanctioned 8 years later i.e. 12thAugust, 2005 after the entire work was executed, same is not justified. This reasoning by the Ld. Arbitrator is justified and is not liable to be interfered with.

    F. Claim No.19 - Rs.8,00,000/- on account of balance payment under clause 10(cc) of the agreement

    12. This claim relates to grant of escalation under Clause 10CC. The Contractor completed the work and completion certificate was given on 30th April, 1997. The DDA, however, in 2004 sought to levy liquidated damages vide order dated 8thJune, 2004. Ld. Arbitrator held that levy of liquidated damages in this manner, 8 years after issuance of completion certificate, was wholly unjustified. Ld. Arbitrator records that payment under Section 10CC for escalation was made up to March, 1992 and hence the Contractor is entitled to escalation for a period from March, 1992 to 30thApril, 1997. A perusal of the decision by the DDA dated 8thJune, 2004 shows that levy of liquidated damages is on the basis that extension was granted up to 31st March, 1992 subject to recovery of liquidated damages. Subsequent to March, 1992, there has been correspondence between the parties, which is referred to by the Ld. Arbitrator. In fact, Ld. Arbitrator records that the hindrance register itself shows that there were various hindrances caused as recorded herein below:

    "Clause 2 was partly relied by the respondent and this has resulted in miscarriage of justice. Admittedly after the completion of work in August 1993 and/or 30th

    6

    April 1997 and after expiry of Defect Liability Period, contract came to end except the subsisting of arbitration clause. Hence respondent could not have taken any decision of levying of LD on claimant vide order dated 08.06.2004. Even clause 2 of the agreement, to my mind, does not survive after the Defect Liability Period was over. How can the Superintending Engineer levy compensation in April 2004 with retrospective effect from 01.04.1992 to 30.04.1997 when contract was not surviving. Moreover hindrance register copy of which is filed as Annexure R-3 show that the material like SG Pipe of 75mm dia was not made available by DDA till 14.05.1992, similarly glazed tiles were not made available till 11.02.1993, Aldrin was not made available by the respondent till 18.02.1992. That the work was held up for want of issue of 16mm dia steel as the same was not available at the store of DDA. Foundation drawings were not made available, therefore, work could not proceed. Same was the position of layout plan. Service plan of MCD was not made available. From Annexure R-3 it is apparent that delay of completion of work can be attributable to the respondent. Reference can also be made to Exhibit C-25 and C-26 dated 05.05.94 and 01.07.94 respectively which show that claimant had brought to the notice of respondent that flush door shutters were defective and asked those to be replaced in order to avoid loss of time. This was followed by letter Exhibit C-25. Therefore levy of compensation after 8 years is not justified after the agreement came to an end. Contract did not exist except the arbitration clause."

    13. From a perusal of the above findings of the Arbitrator, it is clear that levy of liquidated damages in June, 2004 without taking into consideration the developments post March, 31stMarch, 1992 is wholly untenable. The Contractor having executed the work is entitled to escalation under Clause

    7

    10CC, as has been rightly awarded by the Ld. Arbitrator. Ld. Arbitrator has given taken into account reconciliation between the parties and as against the claim of Rs.8 lakhs awarded Rs.6,16,347/- in accordance with clause 10CC. The same does not warrant any interference by this Court.

    G. Claim No.23 - Rs.2,50,000/- on account of balance escalation on the amounts to be awarded against various claims.

    14. This is a claim wherein escalation was sought by the Contractor on the amounts payable under earlier claims. On this claim, Ld. Arbitrator has awarded a sum of Rs.72,832/- after considering the amounts awarded in respect of claim nos.1, 2, 6, 7, 14 & 15. By today"s order, award of claim no.1 has been set aside. Accordingly, the award under this claim would be restricted to the amounts awarded under claims 2, 6, 7, 14 & 15.

    15. The Contractor prayed for interest @ 18% per annum and Ld. Arbitrator has awarded 9% per annum. Considering that there was enormous delay in the bills being raised by the Contractor itself, interest is modified to 6% per annum, pendente lite and future interest. The payments be made within three months as per the present order failing which interest @ 8% per annum would be payable.

    16. OMP is disposed of in the above terms.

    PRATHIBA M. SINGH

    JUDGE

    JANUARY 22, 2019/dk

    8