    Samay Alloys (India) Ltd Petitioner(S) v. Paschim Gujarat Vij Co Ltd (S)

    ORAL ORDER

    Initially, petitioner has filed one petition before this Court being Special Civil Application No. 11011 of 2009, Page 156, Annexure - H. This Court has passed an order on 4th November 2009. The relevant observations made by this Court in Para 5 and 6 are quoted as under :

    “5. In view of the above, the impugned Notice/Order dated 30.09.2009 will be treated as a notice to the petitioner-Company and not a order. The petitioner-Company will make a representation to the Chief Engineer of the respondent-Company on or before 14.11.2009 On such representation being filed by the petitioner-Company, the Chief Engineer will give a personal hearing to the representative of the petitioner-Company, preferably within a period of ten days from the receipt of such representation and will, thereafter, decide the same on merits.

    6. It is made clear that if the petitioner is desirous to get any documents from the respondent-Company, it shall make appropriate application in that regard on or before 06.11.2009 and on such application being made, the said documents shall be supplied to the petitioner-Company on or before 10.11.2009 Consequently, the order of disconnection passed by the respondent-Company will not survive. With the above observations, the petition stands disposed of. Direct service today.”

    In view of above observations made by this Court, the objection raised by petitioner has been examined by respondent - Electricity Company by order dated 30 January 2010, Annexure I, Page 159 and rejected the representation made by petitioner.

    Against which, immediately, petitioner has approached on 8 February 2010, Page 161 to Consumer Grievances Redressal Forum (CGRF) under Section 42(5) of the Indian Electricity Act, 2003, but, this application is pending before Forum till date.

    Meanwhile, petitioner received notice dated 5 July 2010, Page 44 from respondent Electricity Company demanding the amount claimed by respondent Electricity Company to be paid within 15 days, otherwise, electricity will be disconnected by respondent Electricity Company.

    In view of these facts, when application made to Forum is not decided and pending from 8 February 2010 and when alternative remedy has been availed by petitioner, this Court is not entertaining this petition only on that ground.

    Accordingly, it is directed to Consumer Grievances Redressal Forum (CGRF), Corporate Office, PGVCL, Rajkot to decide this application dated 8 February 2010 submitted by petitioner and examine the grievance of the petitioner and thereafter to pass appropriate reasoned order in accordance with law within a period of three months from the date of receiving copy of present order.

    Let petitioner may also approach the Forum by separate application for granting interim relief against operation of notice dated 5 July 2010 within a period of one week from the date of receiving copy of present order.

    Thereafter, Forum has to examine such application for interim relief in accordance with law.

    Meanwhile, it is directed to respondent Electricity Company to maintain status-quo till the decision of interim relief application which will be filed by petitioner before Forum.

    In view of above observation and directions, present petition is disposed of without expressing any opinion on merits.

    Direct service is permitted.