  • provisions of the Mines and Minerals (Regulation and Development) Act, 1957
  • Rule 59 of the Mineral Concession Rules, 1960.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of the Mines and Minerals (Regulation and Development) Act, 1957
  • Rule 59 of the Mineral Concession Rules, 1960.

    National Mineral Development Corporation Ltd. v. State Of Karnataka

    ORDER

    1. The petitioner, which is a Government owned company, incorporated with the object of exploration and extraction of minerals, for meeting the domestic as well as export requirements of the country, has assailed the Recommendation dated 09/02/2004 (Annexure “H”), issued by the first respondent and has sought certain other reliefs.

    2. Briefly stated, it is the case of the petitioner that it had applied for a mining lease to develop iron are mining in Kumaraswamy Iron Ore Deposit at Bellary District. It is stated that an extent of 1600 Acres was sanctioned on 04/07/1972 and a Notification to that effect was issued by the erstwhile Government of Mysore, under the provisions of the Mines and Minerals (Regulation and Development) Act, 1957 (hereinafter, referred to as the “Act”). A registered lease deed for a period of thirty years was also executed in favour of the petitioner on 18/10/1972 (Annexure “A1). Another application for a mining lease in a contiguous area extending up to 413 hectares was made by the petitioner. This extent of land was earlier Part of lend leased to Sandur Manganese Iron Ore Company Limited. By a Communication of September 1973 issued by the Government of India to the first respondent, it was stated that this area of 413 hectares (9 Sq. Miles) was required by the petitioner herein for its developmental activities. As there was no consideration of the application filed by the petitioner seeking this extent of land for a mining lease, a Revision Petition was filed before the second respondent under Section 30 of the Act. The petitioner was later informed by a letter dated 30/11/1999 that this extent of land (413 hectares; was forest land and therefore, necessary clearance from the Forest Department was requited before the area could be granted.

    3. When the matter stood thus, first respondent issued Notification dated 17/02/2003 (Annexure “E”) to the effect that an extent of 11,620.56 sq.kms, including Block No. 17 of Bellary District, which was reserved for State exploitation of various minerals had been dereserved. Consequently, the aforesaid area was available for grant of mineral concession under Rule 59 of the Mineral Concession Rules, 1960. Accordingly, a Notification was issued on 15/02/2003, calling upon interested persons to make necessary applications for grant of a mining lease. In response to this petitioner, who had earlier made an application dated 08/10/1987 (Annexure “B”) filed one more application on 16/02/2003, seeking reduction in the area from 413 hectares to 185 hectares. Thereafter, the petitioner made a representation before the second respondent on 24/07/2003. Petitioner's case was considered along with the other applicants. Ultimately, fourth respondent was proposed to be granted the mining lease to an extent of 218.20 hectares for a period of 20 years. A Recommandation dated 09/02/2004 to that effect was made. Aggrieved by the Recommendation made in favour of the fourth respondent on 09/02/2004 as well as the Notification dated 17/02/2003 dereserving the area said to have been earlier reserved for the petitioner herein, this writ petition has been preferred.

    4. We have heard the learned Attorney General instructed by counsel for the petitioner, learned Addl. Govt. Advocate for respondents 1 and 2 and the learned counsel for respondents No. 3 and 4 and perused the material on record.

    5. At the outset, the order dated 26/11/2012 of Division Bench of this Court in W.P No. 12072/2004 and connected matters was brought to our notice. Relying upon a decision of the Hon'ble Supreme Court in case of Geomin Minerals & Marketing Private Limited v. State of Orissa [(2013) 7 SCC 571], it was held that those writ petitions were premature and hence, liberty was reserved to the petitioners therein to agitate their rights as and when the occasion would arise. In light of that order dated 26/11/2013, it was contended that having regard to the Communication at Annexure “C”, issued by the Central Government to the State Government, the impugned Notification at Annexure “E” dated 17/02/2003 incorporating an extent of 413 hectares in respect of which, an application was filed by the petitioner on 08/10/1987 for grant of mining lease, could not have been issued. If that be so, then no portion of the land reserved for the petitioner could have been recommended to be granted to the fourth respondent. Learned Attorney General of India has relied upon the observations recorded by the Apex Court in Sandur Manganese and Iron Ores Limited v. State of Karnataka reported in [(2010) 13 SCC 1] and submitted that the land was reserved by the Central Government in exercise of its plenary powers flowing from Section 2 of the Act, for a public sector undertaking and in public interest. Under these circumstances, the only relief pressed by the petitioner at this stage was for a consideration of the representation of the petitioner by the first respondent or any other competent authority. It was stated that a representation would be made by the petitioner before the competent authority bringing to its notice the Communication of September 1973 as well as Notification dated 17/02/2003 of the State Government. It was also fairly submitted that while considering the representation of the petitioner, fourth respondent could also be heard in the matter.

    6. Learned Addl. Govt. Advocate appearing for respondents 1 and 2 had no objection to this submission as the recommendation made by the State Government in favour of the fourth respondent had been returned by the Central Government as is noted in the order of this Court dated 26/11/2013.

    7. In the circumstances, the only relief that can be granted to the petitioner is to permit the petitioner to make a representation before the first respondent or any other competent authority explaining its position and also stating its grievances. If such a representation is made, then the first respondent or any other competent authority shall consider the same in accordance with law and after giving an opportunity to the fourth respondent in respect of whom the Recommendation dated 09/02/2004 stands. In all other respects, the order dated 26/11/2013 applies to this case as well.

    8. With the aforesaid direction and observations, the writ petition stands disposed without any order as to costs.

    9. All contentions on both sides are left open to be urged before the competent authority.

    Use AI to get other relevant cases.

    Comments

    National Mineral Development Corporation Ltd. v. State Of Karnataka
    (Jan 2, 2014)