JUDGMENT & ORDER
By means of this petition filed under Article 227 of the Constitution of India, the judgment and order dated 10.02.2012 delivered in Civil Misc. Appeal 04 of 2013 by the District Judge, South Tripura, Udaipur has been challenged. While dismissing the said miscellaneous appeal, the judgment and order dated 13.09.2013 delivered in Civil Misc. Case No. 10 of 2013 arisen from Title Suit No. 06. of 2013 has been affirmed. By the said order, the petitioner and the respondent No. 2, the defendants in the suit and their men or agent have been injuncted from creating any sort of disturbance/obstruction over the peaceful enjoyment of the suit path described in the Schedule-B to the plaint by the plaintiff. The petitioner and the respondent No. 2 have been further restrained or injuncted from creating any sort of disturbance in the process of installing the domestic water supply connection to the Schedule-A land till disposal of this suit.
[2] The suit has been filed by the respondent No. 1 for declaration and the consequential reliefs. According to the respondent No. 1, the suit path described in the Schedule-B land has been created by an agreement, executed by the petitioner and the respondents. Except the suit path, there is no other easement from the homestead land of the respondent No. 1 described in the Schedule-A to the plaint. Recently, while the respondent No. 1 was preparing for installing the domestic water supply connection along the road in terms of the said agreement, the petitioner and the respondent No. 2 made desperate venture to impede that work. On apprehension of recurrence of similar acts, the respondent No. 1 has filed the suit along with a petition under Order XXXIX, Rule 1 & 2 of the C.P.C for a temporary injunction restraining the petitioner and the respondent No. 2 from obstructing the use of the said suit path in terms of the agreement or laying the domestic water supply connection to his homestead.
[3] On 13.09.2013, the Civil Judge, Sr. Division, South Tripura, Udaipur passed the order of temporary injunction against the petitioner and the respondent No. 2. in Civil Misc. 10 of 2013, arisen from T.S 06 of 2013. Being aggrieved, the petitioner filed a miscellaneous appeal under Order XLIII Rule 1(r) of the C.P.C in the court of the District Judge, South Tripura, Udaipur being Misc. Appeal No. 04 of 2013. By the impugned order dated 10.02.2014, the District Judge has dismissed the appeal holding that:
Accordingly this Court of appeal considered that the injunction order was rightly passed by the court below and the order is hereby affirmed. In exercise of discretionary power, this Appellate Court, therefore, restrained the defendantCappellant to disturb the peaceful possession over the ACSchedule land as pathway and also restrained the plaintiffCrespondent to make any disturbance or use any force in respect of installation of the domestic water supply land by Udaipur Nagar Panchayet.
[4] Mr. A.K Bhowmik, learned senior counsel appearing for the petitioner has contended that the suit path as described in the Schedule-B is so vaguely described that the suit path cannot be identified definitely on repelling uncertainties as regards the boundary of the suit path. Notwithstanding the specific objection raised by the defendant No. 1, the petitioner herein, both the trial court and the appellate court discarded such plea to the serious detriment of the petitioner. Mr. Bhowmik, learned senior counsel has referred first to the Schedule-B land and thereafter to the description of the suit path appearing in the schedule of the agreement dated 25.11.2011 executed by the plaintiff and the defendants, to contend that the boundaries as described in the said Schedule appended to the agreement cannot be vehicle to identify land of the plaintiff and the defendants No. 1 & 2 inasmuch as the breadth and length of the land falling in the share of each of the parties have not been incorporated. By simply writing that in the North, the land of the first, second and third parties do exist, the suit path cannot be demarcated. No order of injunction cannot be passed where the suit land is vaguely described or uncertain. Mr. Bhowmik, learned senior counsel has further submitted that the plaintiff has provided an imaginary hand sketch map as the suit path with the plaint and the said hand sketch map has been relied on, as it appears, by the trial court.
[5] Mr. Bhowmik, learned senior counsel referring to the unit of the measurement as used in the said agreement dated 25.11.2011 has submitted that no agreement which does not conform to the provisions of the Legal Metrology Act, 2009 can be enforced in view of provisions of Section 11 of the Act, which reads as under:
(1) No person shall, in relation to any goods, things or service,
(a) quote, or make announcement of, whether by word of mouth or otherwise, any price or change, or
(b) issue or exhibit any price list, invoice, cash memo or other document, or
(c) prepare or publish any advertisement, poster or other document, or
(d) indicate the net quantity of a preC packaged commodity, or
(e) express in relation to any transaction or protection, any quantity or dimension, otherwise than in accordance with the standard unit of weight, measure or numeration.
[6] Mr. Somik Deb, learned counsel appearing for the respondent No. 1 has seriously questioned the proposition as advance by Mr. Bhowmik, learned senior counsel. He has vehemently disagreed that the description of the suit path as provided in the said agreement is vague or so uncertain that would render the agreement void. He has reread the description and submitted that from the volume and the northern boundary, the length and breadth of the parcels of land that have been curved out respectively from the land of the petitioner, the respondent No. 1 and the respondent No. 2. The suit path can easily be demarcated, inasmuch as in the agreement South boundary has been described specifically stating that in the South boundary there falls the land of one Maidhar Ali. Mr. Deb, learned counsel has submitted that the respective volume of the land of each of the defendants along with the plaintiff have been specifically provided in the schedule of the agreement. The agreement has been executed for permanent settlement of the suit path. Based on such settlement, the plaintiff has purchased the land, described in the Schedule-A to the plaint. There is no dispute that for ingress and egress from the Schedule-A land, except the said path there is no other means of easement. The conditions of the agreement are definite and not subject to any other meaning. It also provides that the said path would be used by the plaintiff and the defendants forever and no part of the said path should be transferred by any of the parties. The upkeep of the pathway shall be a collective responsibility. The parties also would be permitted to draw water supply connection, electricity connection or gas pipe line through and over that pathway. Mr. Deb, learned counsel has further submitted that both the trial court and the appellate court have concurred that a strong prima facie case has been unfolded by the plaintiff. This Court may not interfere with such finding as to the prima facie case by invoking its supervisory jurisdiction when there is no patent illegality or failure in exercise of jurisdiction.
[7] As regards the ground of objection as to non-compliance of the provisions of the Legal Metrology Act, Mr. Deb's submission is two-pronged. He has submitted that there was/is no such challenge before the courts below. Thus, such contention at this stage may not be entertained by this Court. He has further submitted that interpretation as advanced by Mr. Bhowmik, learned senior counsel in respect of Section 11 is highly laboured and beyond the scheme of the Legal Metrology Act inasmuch as the object of the Legal Metrology Act is to establish and enforce the standards of weights of measures, regulate trade and commerce in weights, measures and other goods which are sold or distributed by weight, measure or number and for matters connected therewith or incidental thereto. He has submitted that unless there is element of sale in relation to the goods the legal metrology cannot have any relevance. According to him, Section 2(g) of the said Act clarifies that in relation to the mandatory technical and legal requirements the legal metrology has the object of ensuring public guarantee from the point of view of security and accuracy of the weight and measurement. He has further submitted that even Section 11 of the said Act is confined to its operation to any goods, things or service. Thus, those provisions cannot have any application as to the enforceability of the agreement in question. Finally, Mr. Deb, learned counsel has referred a decision of the apex court in Smt. Sohbatdei v. Deviplal, reported in (1972) 3 SCC 495. The decision is in the context of application of Section 29 of the Contract Act. The apex court held that if the content of the agreement is capable of being certain there cannot be any application of Section 29 of the Contract Act. Probably Mr. Deb, learned counsel appearing for the respondent No. 1 has pressed this decision to support his contention that reading of the agreement along with its schedule would not leave any space for uncertainty of that extent which would render the agreement void. He has finally submitted that the balance of convenience and inconvenience and danger of suffering injury in addition to existence of a strong prima facie case have correctly led the courts below in granting the injunction in favour of the plaintiff.
[8] Having scrutinized the records so placed along with the petition and on a meticulous reading of the agreement, this Court cannot accept the submission made by Mr. Bhowmik, learned senior counsel for the reason that the plaintiff and the defendants recorded their agreement for creation of the path as demised in the schedule of the agreement. The description of the pathway may be termed cumbersome but it cannot be said that the description is so vague that it is incapable of being made certain. Moreover, what has been submitted by Mr. Bhowmik, learned senior counsel as regards the import of Legal Metrology Act, this Court has failed to persuade itself to its logical depth whether a person privy to the agreement can be allowed to raise such technical objection after executing the agreement. However, this observation is wholly tentative. The defendant No. 1, the petitioner herein shall be at liberty to raise such objection in the trial, if he so desires for appropriate consideration.
[9] Having held so, this Court finds no merit in this petition and accordingly, the same is dismissed. The order of temporary injunction delivered in Civil Misc. 10 of 2013, arisen from T.S 06 of 2013 by the Civil Judge, Sr. Division, South Tripura is affirmed. However, there shall be no order as to costs.