    North Eastern Electric Power Corporation Ltd. v. Assam State Electricity Board, Guwahati

    1. Heard Shri J. Barkakati, Director (T) for the petitioner and the representatives of the respondents present at the hearing.

    2. The petitioner shall submit by 6.5.2005 the clarifications to explain delay of 84 months in commissioning of the station along with necessary documents/information, with copy to respondents. While furnishing the clarifications as above, the following shall be specifically be brought out, namely:

    (a) Chronology of events,

    (b) Efforts made by project authorities to reduce/avoid delay,

    (c) Details of the project cost quoted by the lowest bidder Mitsubishi and negotiated project cost along with price level, and

    (d) Reasons for delay of 43 months during construction after placement of orders in May 1992 and efforts made by project authorities to avoid delay.

    2. List this petition on 7.6.2005

    Use AI to get other relevant cases.

    Comments

    North Eastern Electric Power Corporation Ltd. v. Assam State Electricity Board, Guwahati
    (Apr 7, 2005)