  • provisions of Regulation 12 to 15 of the Connectivity Regulations and provisions of Clause 23(5)
  • Section 79(1) (f) of the Electricity Act, 2003
  • Section 56 of the Indian Contract Act, 1876,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of Regulation 12 to 15 of the Connectivity Regulations and provisions of Clause 23(5)
  • Section 79(1) (f) of the Electricity Act, 2003
  • Section 56 of the Indian Contract Act, 1876,
Smart Summary

Factual and Procedural Background

The petitioner, Jayaswal Neco Urja Ltd., filed a petition under Section 79(1)(f) of the Electricity Act, 2003, seeking adjudication of disputes arising from long term open access granted by Powergrid Corporation of India Ltd. (PGCIL) for evacuation of electricity from its proposed thermal power plant in Raigarh District, Chhattisgarh.

The petitioner’s holding company, Jayaswal Neco Industries Ltd., was allocated a captive coal block, with plans to utilize the coal for power generation through a 2×300 MW Thermal Power Plant. The petitioner undertook various statutory clearances and financial arrangements to set up the plant.

On 17 March 2011, the petitioner applied for long term open access (LTA) for 600 MW with PGCIL, submitting the requisite application fees and a bank guarantee. PGCIL granted LTA in August 2011 for 300 MW from July 2014 and another 300 MW from October 2014, subject to signing a long term access agreement and submission of an additional bank guarantee of Rs. 30 crore.

The petitioner delayed signing the LTA agreement citing multiple force majeure conditions, including sub-judice status of captive coal block allocation, pending coal linkage approval, lack of environmental clearance, absence of power purchase agreements, and withdrawal/modification of commitments by the State Government of Chhattisgarh.

PGCIL issued a final notice on 11 March 2014 demanding signing of the LTA agreement by 30 April 2014, failing which the LTA would be cancelled and the bank guarantee could be encashed. The petitioner challenged this notice before the Commission, seeking declarations that the rights under the LTA were frustrated by force majeure, and that the bank guarantee should be returned and not encashed.

The petition and an interim application restraining PGCIL from encashing the bank guarantee were heard and disposed of by the Commission.

Legal Issues Presented

  1. Whether PGCIL is entitled to encash the bank guarantee due to the petitioner’s failure to sign the long term access agreement within the stipulated time.
  2. Whether the petitioner’s claimed force majeure conditions frustrate the rights and obligations under the long term access grant.
  3. Whether the petitioner is entitled to the return of the bank guarantee submitted with the LTA application.

Arguments of the Parties

Petitioner’s Arguments

  • The petitioner is unable to sign the LTA agreement or provide the additional bank guarantee due to force majeure events, including pending Supreme Court decision on coal block allocation, absence of coal linkage, lack of environmental clearance, and failure of power purchase agreements.
  • The initial bank guarantee was meant to demonstrate seriousness and secure damages only if PGCIL suffered loss, which has not occurred as no system was developed or transmission capacity blocked.
  • PGCIL cannot encash or retain the bank guarantee unless there is no force majeure, PGCIL has altered its position detrimentally, and there is no mitigation of loss; none of these conditions are fulfilled.
  • The petitioner relied on the Supreme Court judgment in Satyabrata Ghose v. Mugneeram Bangur & Co. under Section 56 of the Indian Contract Act, 1876, to support the claim of contract frustration.

Respondent’s Arguments

  • Under Clause 23.5(iii) of the Procedure issued under the Connectivity Regulations, the bank guarantee may be encashed if the applicant fails to sign the LTA agreement and furnish the construction phase bank guarantee within the stipulated time.
  • The petitioner was granted multiple extensions but failed to sign the agreement by the final deadline of 30 April 2014.
  • The time for signing cannot be further extended without affecting transmission system planning.
  • The respondent relied on the Commission’s earlier order dated 16 October 2013 in Petition No. 153.MP/2012 to support the entitlement to encash the bank guarantee under the specified circumstances.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Satyabrata Ghose v. Mugneeram Bangur & Co. (1954 SCR 310) Contract frustration under Section 56 of the Indian Contract Act, 1876 The petitioner relied on this precedent to argue that the contract (LTA agreement) was frustrated due to force majeure events making performance impracticable.
Commission’s order dated 16.10.2013 in Petition No. 153.MP/2012 Interpretation of Regulations 12 to 15 of the Connectivity Regulations and Clause 23(5) of the Detailed Procedure regarding encashment of bank guarantees The Commission applied these provisions to conclude that the nodal agency is entitled to encash the bank guarantee if the applicant fails to sign the LTA agreement or furnish required bank guarantees within stipulated time.

Court's Reasoning and Analysis

The Commission examined the provisions of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium term Open Access) Regulations, 2009 (“Connectivity Regulations”) and the Detailed Procedure approved under Regulation 27. It noted that two types of bank guarantees are involved: one submitted with the LTA application and another during the construction phase if transmission system augmentation is required.

The Commission emphasized that the bank guarantee submitted with the application is intended to ensure the applicant’s commitment and to prevent stranding of transmission assets. The bank guarantee can be encashed if the applicant withdraws the application or relinquishes LTA rights before operationalization when augmentation is not required, or if the applicant fails to sign the LTA agreement and furnish the construction phase bank guarantee within the stipulated time.

While the petitioner cited force majeure events, the Commission clarified that the Connectivity Regulations do not prohibit withdrawal of the application, but in such case, the application bank guarantee would be forfeited. The letter granting LTA did not provide for cancellation of LTA on account of delays or abandonment due to force majeure.

The Commission rejected the petitioner’s reliance on the contract frustration doctrine under Section 56 of the Indian Contract Act, holding that the contractual framework under the Connectivity Regulations governs the rights and obligations and the consequences of delay or non-performance.

Consequently, the Commission held that the petitioner is not entitled to a refund of the application bank guarantee, and PGCIL is entitled to encash the bank guarantee in accordance with the regulations and procedure.

Holding and Implications

The petition and interim application are disposed of with the holding that the petitioner is not entitled to the refund of the bank guarantee and that PGCIL may encash the bank guarantee in accordance with the Connectivity Regulations and the approved Detailed Procedure.

The decision directly affects the parties by upholding PGCIL’s right to enforce the bank guarantee due to the petitioner’s failure to sign the LTA agreement within the prescribed time. No broader precedent beyond the application of the Connectivity Regulations and the Detailed Procedure is established by this order.

    Jayaswal Neco Urja Ltd. v. Power Grid Corporation Of India Ltd.

    The petitioner Jayaswal Neco Urja Ltd. has filed this petition under Section 79(1) (f) of the Electricity Act, 2003 for adjudication of the disputes arising out of the long term open access granted by Powergrid, the “Respondent” herein, to the petitioner for evacuation of electricity from its proposed thermal generating plant in the Raigarh District of Chhattisgarh.

    2. The case of the petitioner is that the petitioner's holding company, Jayaswal Neco Industries Ltd. (JNIL) was allocated a captive coal block in the state of Chhattisgarh. JNIL decided to utilize the coal having GCV of 4000 K cal/kg and above in its Sponge Iron plant and the balance coal with GCV below 4000 K cal/kg including coal rejects for generation of power. JNIL proposed to set-up a 2×300 MW Thermal Power Plant at village Hamirpur in the Raigarh District of Chhattisgarh in the name of Raigarh Energy Ltd. which was changed to Jayaswal Neco Urja Ltd., the petitioner in the present petition.

    3. The petitioner has submitted that it entered into a Memorandum of Understanding with the Govt. of Chhattisgarh and Chhattisgarh State Electricity Board for setting up of Thermal Power Plant. The petitioner is also stated to have taken several steps for setting up of the Power Plant such as seeking Environment Impact Assessment Clearance, NoC from Airport Authority of India for construction of chimney, site clearance certificate from Forest department, arrangement of water from Water resources Department, Government of Chhattisgarh, arrangement of funds from the financial institutions like Power Finance Corporation and Rural Electrification Corporation, approval from the Ministry of Coal, Govt. of India for utilization of middlings/rejects for use in the generation of power.

    4. The petitioner also applied for long term open access to PGCIL on 17.3.2011 for 600 MW in accordance with Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium term Open Access) Regulations, 2009 (hereinafter Connectivity Regulations). The application was accompanied by a demand draft of Rs. 6,00,000/- as non-refundable application fees and Rs. 60,00,000 @ Rs. 10,000.MW as bank guarantee in accordance with the Procedure issued under the Connectivity Regulations. This Bank Guarantee is initially for a period of one year which shall be revalidated till the execution of the long term access agreement in case augmentation of the transmission system is required or till operationalisation of long term access in case augmentation of transmission system is not required. PGCIL in its letter dated 5.8.2011 granted long term access to the petitioner for 300 MW from July 2014 and balance 300 MW from October 2014 with validity till July 2034. PGCIL in its letter dated 22.11.2011 provided draft agreement for long term access with System Strengthening between PGCIL and the petitioner and required the petitioner to sign the long term access agreement and submit bank guarantee of Rs. 30 crore. The petitioner extended the validity of the bank guarantee on year to year basis and the present bank guarantee is valid till 15.3.2015 The petitioner has submitted that it is not in a position to sign the long term access agreement due to the following reasons:

    (a) The power project of the petitioner is dependent partly on the captive coal allocation. Since the issue of allocation of captive coal blocks by the Government of India is presently sub-judice before Hon'ble Supreme Court, the mine development work cannot take place until a clear decision is available in the matter.

    (b) On 11.9.2009, the petitioner applied to Ministry of Coal for grant of long term coal linkage/Letter of Assurance for meeting its balance requirement of coal to the tune of 1.10 MPTA, which is still pending and in the absence of coal linkage, the petitioner is not able to get loan and facing liquidity problem in execution of the project.

    (c) The petitioner has achieved most of the milestones. However due to lack of environmental clearance, it is not able to execute the project.

    (d) No long term bidding is coming forth in the last three years by any State Electricity Boards/distribution companies and without the same, the project even though achieve financial assistance may not progress as disbursement will not take place.

    (e) The State Government of Chhattisgarh is withdrawing/modifying the commitments made to the private parties by not executing any PPA as agreed upon at the time signing of MoU. However, as per the financial tie up, the petitioner will have to execute a valid PPA for a quantum of 420 MW (70% of capacity) for getting disbursement of loan, which is also not happening.

    5. The petitioner has submitted that PGCIL has given a notice dated 11.3.2014 asking the petitioner to sign the long term access agreement by 30.4.2014 failing which the long term access would be cancelled as per the Connectivity Regulations. The petitioner has submitted that it is not in a position to sign the agreement for long term access at present as it would be required to give another bank guarantee of Rs. 30 crore which the petitioner is not in a position to arrange due to prevailing uncertainties. The petitioner has submitted that the bank guarantee was for the purpose of bringing seriousness to the application made by the applicant and securing damages payable to PGCIL to compensate for the loss suffered by PGCIL in case of any default on the part of the petitioner. The petitioner has submitted that PGCIL has not suffered any loss as no system has been developed by PGCIL for the petitioner nor the petitioner is blocking the existing transmission system of PGCIL from being utilized by other persons. The petitioner has submitted that the question of PGCIL being entitled to retain the bank guarantee or encash the bank guarantee would arise only if all or any of the following conditions are satisfied. Firstly, there is no force majeure condition which prevents the parties from performing the obligations. Secondly, PGCIL has altered its position to its detriment and incurred substantial cost and expenditure on account of the obligations towards the petitioner. Thirdly, there is no avenue for PGCIL to mitigate the loss or utilize the system created for the petitioner. The petitioner has submitted that none of the above exigencies exist for PGCIL to encash or retain the bank guarantee. Aggrieved by the notice of PGCIL to cancel the long term access, the petitioner has filed the present petition seeking the following prayers:

    “(a) Hold and declare that the rights and obligations of the parties under the letter dated 5.8.2011 issued by PGCIL granting approval for long term access to the petitioner have been frustrated on account of the existence of the force majeure condition in the non-development of the generating station by the petitioner;

    (b) Hold and declare that the respondent is not entitled to invoke or otherwise retain the bank guarantee of Rs. 60 lakhs provided by the petitioner to the respondent;

    (c) Direct the respondent to return the bank guarantee of Rs. 60 lakhs provided by the petitioner in view of prevailing force majeure conditions; in view of prevailing force majeure conditions;

    (d) Pass such other further order(s) as the Hon'ble Commission may deem fit in the facts of the present case.”

    The petitioner has filed the IA along with the petition for an interim relief that pending adjudication of the dispute, PGCIL may be restrained not to encash the bank guarantee.

    6. After notice to the respondent, the main petition and the I.A were taken up for hearing. Learned Counsel for the petitioner submitted that as per the provisions of the Connectivity Regulations, PGCIL can encash the bank guarantee only if the application is withdrawn by the petitioner or the long term access rights are relinquished prior to the operationalization of such right when augmentation of transmission system is not required. Learned counsel submitted that none of these contingencies exist in this case as the petitioner is still willing to complete the project but due to the prevailing uncertainties which are in the nature of force majeure events, the petitioner is not in a position to sign long term access agreement and give further bank guarantee. In this connection, the learned counsel for the petitioner relied upon the judgment of the Hon'ble Supreme Court in Satyabrata Ghose v. Mugneeram Bangur & Co., (1954 SCR 310) and submitted that under Section 56 of the Indian Contract Act, 1876, a contract is frustrated if it is impracticable for the parties to do an act which is required under the contract. Learned counsel submitted that in this case, the petitioner is merely asking not to encash the bank guarantee which is valid till 15.3.2015 as the petitioner is not in a position to sign the long term access due to force majeure conditions.

    7. The representative of the respondent submitted that as per 23.5 (iii) of the “Procedure for making application for grant of long term access to ISTS” issued under the Connectivity Regulations with the approval of the Commission, the bank guarantee may be encashed by the nodal agency, “if the applicant fails to sign the Long Term Access Agreement with CTU or a tripartite agreement with CTU and transmission licensee, as the case may be, and fails to submit appropriate BG for construction phase, within stipulated time as indicated in the intimation letter.” The representative of the respondent submitted that the time for signing the Long Term Access Agreement is being extended from time to time at the request of the petitioner. However, the petitioner was given a final notice on 11.3.2014 to sign the LTA by 30.4.2014 The representative of the petitioner submitted that the time for signing of the LTA cannot be further extended without affecting the transmission system planning. The representative of the petitioner relied upon the order of this Commission dated 16.10.2013 in Petition No. 153.MP/2012 and submitted that the case of the petitioner is covered under decision in the said order and may be accordingly dealt with.

    8. We have considered the submission of the parties. The main issue involved in the petition is whether PGCIL is entitled to encash the bank guarantee on account of the failure of the petitioner to sign the long term access agreement. In our order dated 16.10.2013 in Petition No. 153.MP/2012, we examined the provisions of Regulation 12 to 15 of the Connectivity Regulations and provisions of Clause 23(5) of the Detailed Procedure approved by the Commission in terms of Regulation 27 of the Connectivity Regulations and came to the conclusion that the nodal agency (PGCIL) is entitled to encash the bank guarantee under certain circumstances such as non-signing of LTA or non-furnishing of Bank Guarantee for construction phase. Relevant portion of the said order is extracted as under:

    “10. In accordance with Regulation 12, the application made for LTA is to be accompanied by a Bank Guarantee of Rs. 10,000 per MW in favour of the nodal agency, which shall be kept valid and subsisting till the execution of the LTA Agreement where augmentation of transmission system is required or till the operationalisation of the LTA where augmentation of transmission system is not required. The regulation further provides that Bank Guarantee may be encashed in case the applicant withdraws the application for LTA or LTA rights are relinquished prior to the operationalisation of such rights when augmentation of transmission system is not required. The Bank Guarantee stands discharged with the submission of fresh Bank Guarantee given by the applicant to the Central Transmission Utility, the nodal agency, during construction phase where augmentation of transmission capacity is required. Regulation 13 provides that the nodal agency on receipt of the application for LTA shall carry out the necessary system studies and based on these studies, shall identify the inter-State transmission system required to give LTA to the applicant. Regulation 14 requires the nodal agency to communicate to the applicant, the date from which long-term access shall be granted and an estimate of the transmission charges likely to be payable based on the prevailing costs, prices and methodology of sharing of transmission charges specified by this Commission. Regulation 15 mandates the applicant to sign an agreement for LTA with the Central Transmission Utility, which shall contain the date of commencement of LTA, the point of injection of power into the grid and point of drawal from the grid and the details of dedicated transmission lines, if any, required. Where augmentation of the transmission system is necessary, long term access agreement shall contain the time line for construction of the facilities of the applicant and the transmission licensee, Bank Guarantee required to be given by the applicant, and other details in accordance with the Detailed Procedure.

    11. From the above provisions of the Connectivity Regulations it emerges that there are two types of Bank Guarantees that an LTA applicant is required to furnish to the nodal agency. The first Bank guarantee is required to be given alongwith the application for the LTA @ Rs. 10,000 per MW. If as a result of system studies, it is found that no further augmentation of the transmission system is required, the applicant will be required to sign an LTA Agreement and the Bank guarantee already paid will remain valid till operationalisation of the LTA. If it is found that augmentation of transmission system is required, then the applicant will be required to enter into LTA Agreement, submit a fresh Bank Guarantee for construction period calculated as per Detailed Procedure and the bank Guarantee given earlier alongwith the application for LTA shall stand discharged. Under two circumstances, the Bank Guarantee can be encashed by the nodal agency: firstly, if the applicant withdraws the LTA application; secondly, the long term access rights are relinquished prior to operationalisation of such rights when augmentation of transmission system is not required.

    12. By virtue of Regulation 27 of the Connectivity Regulations, this Commission has approved the Detailed Procedure submitted by the Central Transmission Utility on procedural aspects not adequately covered under these regulations. Clause 23(5) of the Detailed Procedure makes following provisions on encashment of the Bank Guarantee, with an object identical with the object of clause (5) of Regulation 12:

    “The bank Guarantee may be encashed by the nodal agency

    (i) if the application is withdrawn by the applicant or

    (ii) …………………………

    (iii) If the applicant fails to sign the Long Term Access Agreement with CTU or a tripartite agreement with CTU and transmission licensee, as the case may be, and fails to furnish appropriate BG for construction phase, within stipulated time as indicated in the intimation letter.”

    13. Thus in accordance with the Detailed Procedure also, the nodal agency is permitted to encash the Bank Guarantee under certain circumstances such as no signing of LTA or non-furnishing of Bank Guarantee for construction phase.”

    9. In the present case, the petitioner made an application to PGCIL for grant of long term open access on 17.3.2011 for 600 MW accompanied by a demand draft for Rs. 6 lakh as non-refundable application fee and bank guarantee of Rs. 60 lakh in accordance with the provisions of the Connectivity Regulations and the procedure issued thereunder. PGCIL after carrying out the necessary system studies decided to grant long term access to the petitioner subject to certain system strengthening. PGCIL vide its letter dated 5.8.2011 granted long term access to PGCIL for 300 MW from July 2014 and another 300 MW from October, 2014 valid till July 2034. In the said letter it was intimated that transmission system strengthening is required in connection with the long term access granted to the petitioner for which the petitioner has to submit a bank guarantee of Rs. 30 crore at the rate of Rs. 5 lakh/MW for 600 MW. Subsequently, PGCIL vide its letter dated 22.11.2011 supplied draft agreement for long term access to the petitioner for signing and for submitting the bank guarantee of Rs. 30 crore. PGCIL while conveying the grant of LTA also informed that the petitioner shall enter into long term access agreement within 30 days of receipt of the draft agreement. The petitioner has been requesting for extension of time for signing of the long term access agreement which has been granted by the respondent. PGCIL in the 7th JCC meeting of IPPs granted/applied LTOA/LTA in Western Region held on 25.2.2014 has intimated the petitioner that the LTA shall be cancelled, if the LTA agreement is not signed by 30.4.2014 Subsequently, PGCIL vide its letter dated 11.3.2014 has also given a final notice for cancellation of the LTA unless it is signed by 30.4.2014 The said letter is extracted as under:

    “This is with reference to LTA granted to you vide intimation no. C/SEF/TA/11/04 dated 5.8.2011 (subsequently revised vide intimation No. C/SEF/TA/L/W/11/04 dated 13.6.2013) and letter dated 04.09.2013, 15.10.2013, 18.11.2013, 9.12.2013 and 21.02.2014 from our Commercial Department, requesting you to sign LTA Agreement as per provisions of CERC Regulations. It may please be noted that grant of LTA was subjected to signing of LTA Agreement within the time period specified in the LTA grant intimation letter. The signing of the said agreement is long pending despite various reminders from our side.

    In this regard please note that during 7 JCC meeting held on 25.02.2014 in POWERGRID office at Gurgaon, it was decided that if the LTA Agreement is not signed by you by 30.04.2014, the LTA shall be cancelled as per the provisions of CERC Regulations for which M/s Jayaswal Neco shall be solely responsible and for the same, no further notie shall be given.

    In view of the above, it is once again requested to depute your representative for signing the LTA Agreement within time, so as to avoid action for cancellation of LTA.”

    It is clear from the above letter that PGCIL has been pursuing the matter with the petitioner for signing of the long term access agreement and has given the petitioner the last opportunity to sign the agreement by 30.4.2014 failing which LTA will be cancelled. The petitioner has submitted that it is committed to execute the project but due to force majeure conditions on account of non-availability of coal linkage from Ministry of Coal for 1.10 MTPA, lack of environmental clearance, allocation of captive coal block being sub-judice before the Supreme Court, non-materialisation of long term bidding and lack of support from the Govt. of Chhattisgarh for purchase of power from the proposed power plant, the petitioner is not in a position to go ahead with the project and has sought return of the bank guarantee. It is not necessary for us to go into the question whether these events are in the nature of force majeure or not as we are not concerned in this petition about the progress of the generating station of the petitioner. The judgment relied upon by the learned counsel for the petitioner is not of much help as the letter dated 5.8.2011 does not provide that the long term access granted to the petitioner will stand cancelled if the generation project is delayed or abandoned. The Connectivity Regulations does not prohibit an LTA applicant to withdraw its application in case the long term access is not required in the light of the subsequent developments. In that event, the LTA applicant will not be required to sign the long term access agreement and will not be required to pay the Performance Bank guarantee. However, in terms of the Connectivity Regulations and the Procedure issued thereunder, the concerned LTA applicant will be required to forego the application bank guarantee which will be encashed by the nodal agency i.e PGCIL. It needs to be emphasized that the purpose of application bank guarantee is to ensure commitment of the project developers to use the transmission line for which LTA has been sought and to give comfort to PGCIL that the transmission line would not be stranded after it is built. If the LTA applicants are allowed to withdraw their LTA applications without any deterrent in the form of encashment of application bank guarantee, then the LTA applicants will withdraw or cancel their LTA applications at their sweet will at slightest pretext which will severely affect and undermine the transmission planning by PGCIL. The very purpose and spirit of providing for application bank guarantee will be frustrated if the petitioner is allowed refund of the application bank guarantee as prayed for in the petition.

    10. In our view, the petitioner is not entitled for refund of the bank guarantee and PGCIL is at liberty to deal with the bank guarantee in accordance with the Connectivity Regulations and Procedure issued thereunder.

    11. The petition and the IA are disposed of in terms of the above.