Equivalent Citations
citation codes
Case Number
Advocates
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
To access the original judgment, please Sign In or Subscribe.

    GMADA v. Harvinder Kaur Gill

    The appellant/OP (hereinafter referred as OP) has filed the present appeal against the order dated 01.08.2014 passed by the District Consumer Disputes Redressal Forum, SAS Nagar Mohali (hereinafter referred as 'the District Forum') in consumer complaint No.471 dated 01.11.2013, vide which the complaint filed by the respondent/complainant (hereinafter referred as 'complainant') against OP was allowed with a direction to OP to refund First Appeal No.1260 of 2014 2 Rs.4,16,726/- as non-construction fee charged from the complainant along with 9% interest from the date of deposit i.e. 19.03.2013 till the date of payment; to pay Rs.2.00 Lacs as lumpsum compensation for harassment and mental agony including litigation expenses.

    2. Brief facts of the case are that the complainant filed her complaint under Section 12 of the Consumer Protection Act (in short "Act") against OP. She submitted that she applied with the OP for the allotment of free hold residential plot measuring 400 Sq. yards. As per the advertisement dated 10.12.2010 for allotment of free hold residential plot in Sector 80 SAS Nagar Mohali, she took approval from the competent authority and applied for the allotment of free hold residential plot vide application No.2535 under the General Category plot measuring 400 Sq. yards. She deposited an amount of Rs.1,50,000/- along with her application with the OP. The draw for allotment of free hold residential plot was held on 30.03.2001 in which her application No.2535 was selected as one of the successful allottees. OP issued a public notice in the Tribune dated 01.04.2001 showing the list of successful applicants in the draw of lots. After the advertisement on 01.04.2011 by the OP, letter of intent was issued by OP on 30.03.2001, vide which she was informed that she was successful in the draw of lots and as per that letter tentative price of the plot was fixed at Rs.15,00,000/- @ Rs.3,750/- per sq. yards. As per the said letter of intent, she was directed to deposit 15% of the said amount i.e. Rs.2,25,000/- within 60 days from the date of issue of the letter. She deposited 15% of the tentative price of the plot vide receipt No.44, book No.1290 dated 24.05.2001. The draw for First Appeal No.1260 of 2014 3 allotment of residential plots was again held on 16.05.2008 and an allotment letter was issued to her on 25.09.2008 vide Memo No.GMADA/E.O./08/29006. As per this allotment letter, she was allotted plot No.1086-C (corner) in Sector 77 measuring 400 Sq. yards. However, she received another allotment letter vide memo No.GMADA/EO-Supdt-2(1086/77)/2009/2324 dated 02.02.2009 by which the tentative price of the plot in question was raised to an amount of Rs.18,45,937.51@ Rs.3,750/- per Sq. yards, which included additional area of 47.5 Sq.yards in the plot allotted to her. She was directed to deposit a sum of Rs.86,484.38p towards payment of 25% cost of the increased area. She deposited an amount of Rs.86,485/- with OP vide demand draft No.7689700 dated 12.02.2009 vide their receipt dated 17.02.2009. She was directed to pay the remaining amount of Rs.13,84,453.13 in six instalments. As per allotment letter dated 02.09.2009, she was given information that "the allottee shall be required to take possession of the site within 60 days of the issue of allotment letter". In pursuance to that clause, she gave a representation dated 17.02.2009 to OP and demanded possession of the said plot. No reply was given by OP to her letter dated 17.02.2009. Her husband used to visit the office of the OP to enquire about the delay in providing the possession of the allotted plot to her. During the course of his visits, it came to his knowledge that the land in question, where the plot allotted to his wife, was under litigation. She filed an application under RTI Act, on 23.09.2010 and she received a reply from OP. It was submitted that even though she was making regular payment of instalments of the plot allotted to her. First Appeal No.1260 of 2014 4 OP did not handover the possession of the plot to her. She received a letter from OP vide memo No.EO/GMADA/2012/12509 dated 04.04.2012 wherein amount of instalments was mentioned as Rs.2,58,429/- alongwith penalty interest of Rs.9,346/- under col.4 of the said letter, however, no late fee for construction was shown in that letter and total dues were shown as Rs.2,67,775/-. As per this letter, complainant was directed to deposit the demanded amount by 30.04.2012. After depositing the demanded amount of Rs.2,67,775/-, she applied for no due certificate in the month of August, 2012, vide her application dated 31.08.2012. However, OP vide their memo No.EO/GMADA/2012/37201 dated 21.09.2012 demanded an amount of Rs.2,25,222/- towards the non- construction charges and Rs.213/- towards interest on delayed payment. On receipt of the said letter from the OP, she gave a representation to authorities of the OP. She got a computer generated property ledger print out pertaining to her plot, dated 10.10.2012. In the said property ledger, balance as on 10.10.2012, balance due was shown just Rs.213/-. However, she received another letter vide memo No.EO/GMADA/2012/7474 dated 06.11.2012 wherein an amount of Rs.2,70,266/- was demanded towards the non-construction charges till 30.12.2012. She gave a representation to the OP on 20.11.2012 to withdraw the non- construction charges, as the said amount was levied upon her in an arbitrarily and wrongful manner. It was submitted by her that only reason for non-construction of the plot was that a stay order granted by Hon'ble Punjab and Haryana High Court, as communicated to her as per her RTI application. However, no reply was received by her First Appeal No.1260 of 2014 5 on her said representation given on 20.11.2012. She gave another representation to the OP regarding waiving off the non-construction charges, vide her letter dated 11.12.2012. She again took-up her case with the OP vide letter dated 17.02.2013. However, OP vide their memo No.EO/GMADA/2012/3740 dated 14.03.2013 demanded non-construction charges of Rs.4,16,726/- from her and informed her that No Dues Certificate will not be given to her, as there were arrears to be paid by her. However, she was informed vide their memo No.GMADA/EO/2013/11617-18 dated 07.05.2013 that her representation dated 17.02.2013 was not considered and OP authorities, decided not to cancel the demand of Rs.4,16,726/- as non-construction fees from her. Meanwhile OP vide its letter No.GMADA/O.M.A.(B)/2013/6007 dated 02.04.2013 demarcated her property and handed over physical possession to her. She was advised to submit her construction plan for approval. On receipt of letter dated 02.04.2013, she again wrote a letter to OP on the same day requesting them to issue No Dues Certificate, as she had made all the payments pertaining to her allotted plot No.1086 in Sector 77, SAS Nagar. However, GMADA vide their letter No.GMADA/SDO(B)/ 13/13560 dated 30.05.2013 issued permission for occupation/use of and OR OC for one living unit on ground floor only. She again gave a representation, after the receipt of letter from GMADA dated 07.05.2013, wherein her request for waiving off the non-construction charges was declined. On failure to get No Dues Certificate from OP, she filed her complaint before District Forum and made a prayer that directions be issued against OP to refund an excess amount of First Appeal No.1260 of 2014 6 Rs.4,16,726/- along with interest @ 12% towards extension fee/non- construction charges, to pay Rs.2,50,000/- as compensation for mental agony and harassment and to pay Rs.31,000/- as cost of litigation.

    3. Upon notice, OP appeared and filed their written reply and took preliminary objection that the complaint filed by the complainant was not maintainable; there was no consumer dispute; District Forum did not have jurisdiction to decide the matter regarding extension fee and there was no deficiency in service; neither any unfair trade practice was there on its part as alleged in the complaint. It was submitted that the complaint filed by the complainant was barred by time. It was admitted that the plot in question was allotted to the complainant against tentative price of Rs.18,45,937.51p. The said price was fixed on account of allowing the excess area of 47.50 sq.yards. It was admitted that the complainant had given a letter dated 17.02.2009 demanding possession. It was submitted that she did not come back to take the possession of the allotted plot though there was a report submitted by SDO that the possession of the allotted plot was feasible to be delivered to her. It was further admitted that Hon'ble Punjab & Haryana High Court granted stay in respect of land in Sector 76 to 80, as such development work in Sector 77 was not completed. However, regarding grant of stay order by Punjab and Haryana High Court, pertaining to the land falling in Sector 76 to 80, the information was given to her vide their letter No.37211 dated 23.09.2010. It was submitted that as per the terms and conditions of allotment of plot, complainant was to deposit the First Appeal No.1260 of 2014 7 price of the plot as per the allotment letter. But, delivery of possession of plot was not a conditional precedent to deposit the payment of instalment of plot by the complainant. It was submitted that the complainant was liable to pay extension fee on account of failure to raise construction within the stipulated period. The ledger folio consisting of account ledger pertaining to the maintenance of instalments schedule issued to her cannot be considered as evidence against them. It was submitted that extension fee after 30.06.2012 was payable by the complainant, as three years expired on 01.02.2012 from the date of allotment letter. As such, the demand raised by them, vide their letter dated 21.09.2012 and 06.11.2012 was as per rules and regulations. It was also admitted that the complainant had written a letter in response of letter No.7474 dated 06.11.2012 to them, which was received by them on 20.11.2012. It was admitted that though the plot of the complainant was falling in Sector 77 and even when the stay with regard to 102 acres of land falling in Sector 76 to 80 was there, but the plot of the complainant was available to be delivered to her as per the report of SDO. It was further pleaded that the complainant deliberately had not come forward to take possession and wrongly interpreted their letter dated 23.09.2010 to avoid taking of possession and also to avoid payment of extension fee and did not raise construction within the stipulated period. It was further admitted that complainant had given letters dated 20.11.2012 and 11.12.2012. It was also admitted that the complainant had given letter dated 07.02.2013, which was received in their office on 01.03.2013 to waive off the demand of extension fee. First Appeal No.1260 of 2014 8 However, a fresh demand was raised vide memo No.3740 dated 14.03.2013 for a sum of Rs.4,16,726/- payable till 30.06.2013. It was further submitted that complainant was issued occupation certificate for one living unit on ground floor on 30.05.2013. As such, the demand of extension fee was rightly demanded from the complainant to be paid upto 30.06.2013. It was further submitted that the complainant started construction on the plot allotted to her much before the date i.e. 02.04.2013 as alleged in the complaint. It was admitted that the physical measurement and identity of the alleged plot was given to the complainant on 02.04.2013. It was argued that stay which was granted by Punjab & Haryana High Court in Sector 76-80 in SAS Nagar Mohali would not alter the position of allotment of plot to the complainant and period of three years for construction would start from the date of issuance of letter of intent/letter of allotment. It was further agitated that the amount so demanded towards non-construction charges was raised against the complainant as per rules and regulations framed by the GMADA. It was further averred that she was not competent to challenge charging of extension fee before the District Forum and denied other averments pleaded in the complaint and prayed that the demand so raised by OP was justified and prayed that the complaint filed by the complainant be dismissed.

    4. The parties were allowed by the learned District Forum to lead their evidence.

    5. In support of his allegations, the complainant had tendered into evidence her affidavit as Ex.CW1/1 and affidavit of First Appeal No.1260 of 2014 9 Gurpreet Singh, husband of complainant Ex.CW1/2, copies of advertisement dated 10.01.2000 Ex.C-1, approval dated 28.12.2000 Ex.C-2, prospectus Ex.C-3, advertisement dated 01.04.2001 Ex.C-4, letter of intent dated 30.03.2001 Ex.C-5, affidavit Gurbakhish Singh, brother of the complainant Ex.C-6, receipt dated 24.05.2001 Ex.C-7; allocation letter dated 25.09.2008 Ex.C-8, allotment letter dated 02.02.2009 Ex.C-9, receipt dated 17.02.2009 Ex.C-10, letter dated 17.02.2009 Ex.C-11, information from RTI dated 23.09.2010 Ex.C-12, receipts Ex.C-13 to Ex.C-21, letter dated 04.04.2012 Ex.C-22, application received by the OP on 24.08.2012 Ex.C-23, letter dated 19.11.2012 Ex.C-24, application for issuing NOC dated 31.08.2012 Ex.C-25, application dated 15.10.2012 Ex.C-26, memo dated 21.09.2012 Ex.C-27, ledger dated 10.10.2012 Ex.C-28, memo dated 06.11.2012 Ex.C-29, representations dated 20.11.2012, 11.12.2012 and 17.02.2013 Ex.C-30 to C-32, memo dated 14.03.2013 Ex.C-33, receipt dated 19.03.2013 Ex.C-34, letter dated 07.05.2013 Ex.C-35, demarcation certificate dated 02.04.2014 Ex.C-36, letter dated 02.04.2013 Ex.C-37, letter of RTI dated 12.04.2013 Ex.C-38, permission for occupancy dated 30.05.2013 Ex.C-39, legal notices dated 15.06.2013 and 07.08.2013 Ex.C-40 and Ex.C-41 legal and close the evidence. On the other hand, OP had tendered into evidence affidavit of Inderjit Kaur Kang, Estate Officer Ex.OP1/1, copy of letter dated 15.01.2009 Ex.OP/1, report dated 12.01.2009 Ex.OP/2 and office noting dated 02.02.2009 Ex.OP/3 and closed the evidence on behalf of the opposite parties. First Appeal No.1260 of 2014 10

    6. After going through the averments made in the complaint, written version filed by OP, evidence and documents brought on the record and on hearing the counsels of parties, the District Forum allowed the complaint as referred above.

    7. Aggrieved with the order passed by the District Forum, the appellant/OP has filed the present appeal.

    8. We have heard the learned counsel for the parties and have carefully gone through the grounds of appeal and record of District Forum.

    9. Counsel for the OP argued that as per the terms of allotment letter issued along with letter of intent in favour of the complainant. She was bound to follow the terms and conditions of the allotment and she was required to complete construction on plot within three years from the date of issuance of letter of intent and that period expired on 01.02.2012. He further argued that as per Ex.OP-2 feasible plots in Sector 77, SAS Nagar, was given by the Deputy Engineer Public Health Division II, Deputy Engineer Civil-II, Deputy Engineer Electricity and the plot allotted bearing plot No.1086 was not having any incumbrance. As such, the plea taken by the complainant in her complaint that the plot allotted to her was under litigation cannot be relied upon. He argued that even though the stay for the entire land falling in Sector 76-80 Mohali was granted by Punjab and Haryana High Court, even then, the plot which was allotted to the complainant was having all complete formalities such as sewerage and other facilities as per the reports submitted by three departments First Appeal No.1260 of 2014 11

    i.e. Public Health, Civil & Electricity. He further argued that the District Forum had come to a wrong conclusion that the plot which was allotted to the complainant was under litigation and the actual physical possession of the plot was allotted to the complainant only on 02.04.2014. Though as per Ex.OP2, the plot which was allotted to the complainant falls under feasible plots. He further argued that District Forum solely relied upon the exhibit placed on record by the complainant and did not appreciate the evidence placed by OP on the District Forum file. He further argued that the District Forum allowed the complaint and directed the OP to pay back the amount of Rs.4,17,726/- with 9% interest. Awarding of 9% interest amounts to compensation and even then, the District Forum further awarded a sum of Rs.2.00 Lacs as a consolidated compensation for mental harassment and litigation expenses. District Forum acceded its power in allowing two amounts of compensation, which is against the law and prayed that the appeal be accepted.

    10. On the other hand, the counsel for the complainant argued that the complainant went on representing her case with the OP for waiver of non-construction fees, but the OP was adamant to charge the amount. Even though their record speaks that the plot in question was under litigation. He argued that as per Ex.C-27, OP issued a letter of demand vide memo No.EO/GMADA/2012/37201 dated 22.09.2012 demanding Rs.2,25,435/- as non-construction fee. In this letter, there is a note No.1, which states as under :- "1) i/eo fJj ;kfJN fe;/ wkB:'r ndkbs tb'A ;N/ nkovo nXhB j? iK e/;zb j'Jh j? sK fJj B'fN; bkr{ BjhA j't/rk ih." First Appeal No.1260 of 2014 12 Thereafter, he brought our attention to Ex.C-28 dated 10.10.2012, it is a document issued by GMADA pertaining to plot No.1086 of the complainant, wherein it has been mentioned that the plot allotted to the complainant was under litigation. Further more, it was pointed out that in the month of April, 2013, Hon'ble Punjab and Haryana High Court decided the writ petition in favour of GMADA. He further submitted that Estate Officer of GMADA and Chief Administrator of GMADA have filed their affidavits in the Apex Court that possession of 102 acres of land was not taken over by them. On the basis of these affidavits filed by OPs in the Hon'ble Supreme Court of India, the acquisition proceedings pertaining to 102 acres land was quashed. As such, letter No.GMADA/ME/411 dated 19.11.2012, wherein, it is stated that if the plot allottee would not take possession of the plot as per the records of GMADA, then it would be deemed that the possession of the plot has been deemed to be handed over to the allottee. He further argued when there was a stay on the land granted by the Hon'ble Punjab and Haryana High Court and when they were not in possession of the land falling in Sectors 76 to 80 then under what circumstances, can OP raise a demand of non- construction charges from the plot owners and argued that the order so passed by District Forum is correct and needs to be confirmed. .

    11. The main controversy in this appeal pertains to charging of non-construction charges from the date of allotment within three years from the date of allotment letter and whether the demand raised by OP was just as per rules and regulations of the OP. First Appeal No.1260 of 2014 13

    12. In order to decide the controversy, we have perused the letter No.GMADA/ME/Accounts/2013/9611 dated 12.04.2013 Ex.C-38 written by GMADA addressed to the complainant in which it was pointed out that the amount of Rs.18,45,938/- being the cost of the plot was received and there was no due amount payable on the said plot, then the second letter No.GMADA-S.D.O.(B)/13 dated 30.05.2013 pertains to granting of permission for occupation of one living unit on ground floor only. Once, it is on the record that the complainant has completed the construction on her plot, then how a demand can be raised for non-construction charges.

    13. Second point for consideration is that when there is a stay order on the land falling under Sector 76-80, can their letter No. EO/GMADA/2012/37201 dated 22.09.2012 demanding an amount of Rs.2,25,222/- and subsequent letter No.EO/GMADA/2013/3740 dated 14.03.2013 raising a demand of Rs.4,16,726/- was a valid demand? The OP is basing their arguments that as per Ex.C-24, if the allottee does not take the possession of the plot within 60 days from the date of allotment of plot, then the plot would be deemed to be delivered to the allotted under deemed possession clause and thereafter, they are relying upon Ex.OP-2 pertaining to the feasibility report issued by Public Health, Civil Engineering and Electricity Department of GMADA. In the said Ex.OP-2 that plot No.1086 was allotted to the complainant and feasibility of the plot can be completed. However, we have perused Ex.OP No.2, wherein a note has been made that total plot of 16 marlas falling under Sector 77 were to the extent of 140 plots, out of which 54 feasible plots were First Appeal No.1260 of 2014 14 mentioned. In this letter, there is a note that these plots will be considered as feasible with respect to sewerage only. But in the same note No.1, it is mentioned intermittent pumping at 3-4 locations would be required. This report states that storm drainage system will not be functional. It further states that if any sort of stay if granted by any court of law in the area falling under plots be got verified from Land Acquisition Collector, Mohali dated 12.01.2009. From this report also, it is clear even sewerage system and storm drainage system shall not functional as such Ex.C-24 stating that possession will be deemed as given possession within 60 days of issuance of allotment letter cannot be taken as a proof that the plot of the complainant was free from all incumbrances. Even more, we find that the complainant had given a request on 17.02.2009 to provide her physical possession. They are simply arguing a point that it was the duty of the complainant to come back to their office to demand possession. We find that it was rather a duty of the OP to issue a letter after receipt of the request letter to send an intimation letter to the complainant to come present in office for taking over the possession of the plot. No such letter informing the complainant was written by the OP addressed to complainant to take possession after 17.02.2009. Even we have failed to understand how OP would be in a position to deliver the possession of the plot to the complainant when the entire acquisition proceeding consisting of 102 acres falling under Section 77-80 was under stay. Even in their letter Ex.C-27, it is mentioned that if there is a stay on the plot, as such the demand of Rs.2,25,222/- be considered as non-payable demand. First Appeal No.1260 of 2014 15

    14. We further find strength in Ex.C-28 issued by GMADA dated 10.10.2012, wherein it is mentioned that the plot allotted to the complainant was under litigation. Under such circumstances, we find that the order so passed by the District Forum disallowing the raising of the construction charges was rightly justified.

    15. Counsel for the OP argued that District Forum wrongly allowed two types of compensation in favour of the complainant. We find that the interest @9% allowed by the District Forum on the ground that if the amount was not deposited by the complainant with the OP then she would have earned the interest on the said amount, if she was to keep that amount in the bank. Thus, she was deprived from earning the interests on the amount which was deposited by her with the OP amounting to Rs.4,16,726/-. However, the District Forum rightly issued directions to OP to pay compensation of Rs.2.00 Lacs as consolidated compensation for causing harassment, mental agony and towards litigation costs. This amount was awarded by the District Forum in favour of the complainant on the ground that when no physical possession was there with the OP as such they were not justified to raise the demand of Rs.4,16,726/- from the complainant. Thus, forcing the complainant to pay the demanded amount amounted to unfair trade practice and its demand caused mental agony and harassment to the complainant. In order to compensate the complainant, against the OP adopting unfair trade practice, the District Forum awarded the above compensation in favour of the complainant. OP has forced complainant to knock the doors of court First Appeal No.1260 of 2014 16 to seek remedy against their unreasonable demand in an arbitrarily manner.

    16. In view of the above, we do not find any reason to modify the order passed by the District Forum as argued by counsel for OP which is a well reasoned order. Hence, the appeal filed by the appellant/OP is hereby dismissed.

    17. The appellant had deposited an amount of Rs.25,000/- with this Commission at the time of filing this appeal and another amount of Rs.3,08,230/- as per order dated 24.09.2014 passed by this Commission. Both these amounts along with interest accrued thereon, if any, be remitted by the registry to the respondent/complainant by way of a crossed cheque/demand draft after the expiry of 90 days, from the despatch of the order to the parties; subject to stay, if any, by the higher Fora/Court. OP is directed to pay the remaining amount as per directions within 90 days from the date of receipt of the copy of order.

    18. The arguments in this appeal were heard on 16.09.2016 and the order was reserved. Now, the order be communicated to the parties as per rules.

    19. The appeal could not be decided within the statutory period due to heavy pendency of Court cases. (Jasbir Singh Gill) Presiding Member September 22, 2016 (Harcharan Singh Guram) Lb/- Member