HONBLE MR. JUSTICE V.K. JAIN, PRESIDING MEMBER (ORAL)
1. The complainant in CC No. 207/2014 booked a residential flat with the opposite party being flat no. 1901 measuring 440 sq. ft. of carpet area in a project known as Rupji Arena, which the opposite party was developing in Lower Parel, Mumbai. The parties entered into an agreement dated 14.12.2010, incorporating their respective obligations in respect of the aforesaid transaction. The total consideration of the flat was agreed at Rs. 1,08,00,000/-. The complainant paid Rs. 10455600/- comprising more than 95% of the total cost of the flat, to the opposite party, between October 2010 to 15.03.2013. As per clause 10 of the aforesaid agreement, subject to the purchaser making full payment due under the said agreement, the opposite party was to give possession of the flat to the complainant by 30.06.2013.
2. Vide letter dated 10.06.2013, the opposite party cancelled the agreement dated 14.12.2010 on the ground that while visiting its office, the complainant had damaged the office sofa and chair on which he was sitting by putting blade marks on them. While doing so, the opposite party claimed to be exercising the power conferred upon it by clause 33 of agreement to sale dated 14.12.2010. The complainant protested against the aforesaid cancellation and then he approached this Commission by way of this complaint seeking the following reliefs: (a) That this Honble Forum be pleased to declare that the opposite party is guilty of deficiency in service and direct the opposite party to rectify the defects in its services as builder and developer with directions to the opposite party to hand over possession of flat being Flat No. 1901, admeasuring 440 sq. ft. carpet area, equivalent to 40.83 sq. mtrs. being flat no. 1901 on the 19 floor of the proposed tower to be constructed onth the said project known as Rupji Arena or in such reasonable time this Honble Commission may deem fit and proper by accepting balance consideration of Rs. 3,55,500/-. (b) The alternative to the above and in the event this Honble Commission comes to the conclusion that it is not possible for the opposite parties to handover possession of the same, for any reasons whatsoever, then in that event this Honble Commission be pleased to direct the opposite party to execute agreement in respect of any other flat of the same dimensions in the said project and handover possession of the same by obtaining Occupation Certificate and Building Certificate from the concerned authorities against receipt of balance consideration of Rs. 3,55,500/-. (c) In the alternative to the above and in the event of this Honble Commission comes to the conclusion that it is not possible for the opposite party to handover possession of flat as demanded vide paragraph 5 and 6 of the above complaint then in that event this Honble Commission be pleased to direct the opposite party to pay to the complainant an amount of Rs. 1,04,55,600/- together with 21% interest p.a. from the date of respective payments till realization of the complainants claim to enable the complainant to acquire suitable residential premises elsewhere and to hand over quiet, vacant and peaceful possession of the said flat no. 1901, admeasuring 440 sq. ft. carpet area, equivalent to 40.83 sq. mtrs. being flat no. 1901 on the 19 floor of theth proposed tower to be constructed on the said project known as Rupji Arena, by obtaining Occupation Certificate and Building Certificate from the concerned authorities against receipt of balance consideration; (d) That pending the hearing and final disposal of the above complaint, this Honble Forum be pleased to invoke the provisions of Section 13(3B) of the Consumer Protection Act and grant injunction restraining the opposite parties, its partners, Directors, servants and agents and/or any other person or persons claiming by under or through it from creating any third party interest in respect of the said flat no. 1901, admeasuring 440 sq. ft. carpet area, equivalent to 40.83 sq. mtrs. being flat no. 1901 on the 19 floor of the proposed tower to be constructed on the said project known asth Rupji Arena earmarked for the complainant under Registered Agreement dated 14.12.2011; (e) That this Honble Forum be pleased to direct the opposite party to pay damages of Rs. 50,00,000/- to the complainants on account of mental torture and mental agony suffered by him and also on account of deficiency in service, more particularly set out in the particulars of claim at Exhibit QQ hereto; (f) For costs of Rs. 1,00,000/- towards prosecuting the above complaint be provided for.
3. The complaint has been resisted by the opposite party on several grounds but the learned counsel for the opposite party states on instructions that they are ready to revoke cancellation and hand over the possession of the flat to the complainant subject to payment of outstanding dues stated in para 7 of the reply affidavit filed by them.
4. The complainant in CC No. 94/2015 also booked a residential flat with the opposite party being flat no. 2201 admeasuring 440 sq. ft. of carpet area in the aforesaid project known as Rupji Arena, for a total consideration of Rs. 1,32,00,000/- and the parties entered into an agreement dated 24.01.2013, incorporating their respective obligations in respect of the aforesaid transaction. As per clause 10 of the aforesaid agreement, the possession was to be delivered to the complainant by 31.12.2013. The aforesaid complainant made a total payment of Rs. 1,31,15,000/- to the opposite party. Vide letter dated 01.08.2014. The opposite party demanded a sum of Rs. 373491/- from the aforesaid complainant towards her contribution in the premium/charges alleged to have been demanded from the opposite party by Bombay Municipal Corporation. The complainant made payment of Rs. 1,25,000/- out of the aforesaid amount but did not make the balance payment. The opposite party then terminated the sale agreement invoking clause 21 of the said agreement. The complainants protested against the said termination and then approached this Commission by way of this complaint seeking the following reliefs: (a) That this Honble Forum be pleased to declare that the opposite party is guilty of deficiency in service and direct the opposite party to rectify the defects in its services as builder and developer with directions to the opposite party to hand over possession of flat being Flat No. 2201, admeasuring 440 sq. ft. carpet area, equivalent to 40.88 sq. mtrs. being flat no. 1901 on the 22 floor of the proposed tower to be constructed onnd the said project known as Rupji Arena or in such reasonable time this Honble Commission may deem fit and proper by accepting balance consideration of Rs. 85,000/-. (b) That pending the hearing and final disposal of the above complaint, this Honble Forum be pleased to invoke the provisions of Section 13(3B) of the Consumer Protection Act and grant injunction restraining the opposite parties, its partners, Directors, servants and agents and/or any other person or persons claiming by under or through it from creating any third party interest in respect of the said flat no. 2201, admeasuring 440 sq. ft. carpet area, equivalent to 40.88 sq. mtrs., on the 22 floor ofnd the proposed tower to be constructed on the said project known as Rupji Arena earmarked for the complainant under Registered Agreement dated 23.01.2013; (c) That this Honble Forum be pleased to direct the opposite party to pay damages of Rs. 50,00,000/- to the complainants on account of mental torture and mental agony suffered by him and also on account of deficiency in service, more particularly set out in the particulars of claim at Exhibit O hereto; (d) For costs of Rs. 10,00,000/- towards prosecuting the above complaint be provided for.
5. CC No. 94/2015 was also opposed on several grounds but the learned counsel for the opposite party states on instructions that they have no difficulty in handing over the possession of the flat to the complainants subject to the premium and/or charges/security deposits etc. demanded from them vide letter dated 01.08.2014, alongwith interest on that amount.
6. In CC No. 207/2014, the following amounts have been demanded from the complainant: (a) Dues as per agreement Rs. 3,44,400/- (b) BMC Premium Rs. 3,73,495/- (c) Service Tax Rs. 2,05,273/- (d) MVAT Rs. 1,11,735/- (e) Legal Charges Rs. 15,000/- (f) Shares Rs. 251/- (g) Registration of Society Rs. 1,251/- (h) Proportionate share of taxes Rs. 19,800/-
(i) Electricity Meter Deposit Rs. 8,000/- (j) Penalty as per clause no. 8 Rs. 2,67,913/-
7. The learned counsel for the complainant states that he is disputing only the demand towards Bombay Municipal Corporation premium and penalty as per clause no. 8 of the agreement and is not disputing the remaining charges demanded by the opposite party. Therefore, we are required to examine the correctness only of the aforesaid two demands.
8. Clause 20 of the sale agreement reads as under:
20. It is agreed that in case, any amount by way of premium and/or charges, security deposits, etc. are demanded by the Municipal Corporation of Greater Mumbai and/or the Bombay Electricity Supply and Transport Undertaking and/or State Government before granting water or electric or drainage connections or as and by way of betterment charges or development taxes or on any other account or any payment of similar nature becoming payable by the developers the same shall be paid by the purchaser/s or reimbursed by the purchaser/s to the developers in case already paid by the developers. After separate meters are provided for the individual premises, the purchaser/s shall pay the charges for electricity and/or water according to the readings shown by the meters fixed for the said premises. It is agreed that until the separate water and/or electric meters are provided in the said premises, the purchaser/s shall pay such amount in respect of charges for electricity and water consumed as may be determined by the developers without any objection. In our opinion, the aforesaid clause requires the purchaser to pay only such amount if any, which was demanded by the Municipal Corporation of Greater Mumbai and/or the Bombay Electricity Supply & Transport Undertaking and/or State Government after execution of the sale agreement. The aforesaid clause does not include in its ambit any amount demanded and/or paid by way of premium and/or charges, security deposits etc. before execution of the sale agreement and the share of the purchaser in such premium and/or charges/deposits is supposed to have been included in the sale consideration agreed between the parties. In other words, the aforesaid clause relates to future demands if any by Municipal Corporation of Greater Mumbai and/or BEST/State Government and not to any past demands irrespective of whether paid or not paid by the builder.
9. There is no evidence before us to show that any amount by way of premium/charges, security deposits etc. was demanded by Municipal Corporation of Greater Mumbai and/or the Bombay Electricity Supply & Transport Undertaking and/or State Government, from the opposite party, after execution of the sale agreement between the parties to the complainant. In the absence of proof of any such demand post execution of the sale agreement, we are unable to uphold the aforesaid demand made by the opposite party. Consequently, we hold that the amount demanded by the opposite party towards additional premium/charges alleged to have been paid to Bombay Municipal Corporation is not sustainable either in CC No. 207/2014 or in CC No. 94/2015.
10. As regards the demand of penalty/interest in terms of clause 8 of the sale agreement, we are of the considered view that wherever there was delay on the part of the complainant in making payment of the sale consideration to the opposite party, they must necessarily pay interest at the rate agreed by them in the sale agreement. Since they have agreed to pay interest @ 21% per annum on the delayed payment, the interest so calculated, must necessarily be paid by them since they have deprived the opposite party of the use of that amount with effect from the due date. A perusal of the computation filed by the opposite party shows that a sum of Rs. 259858/- is due from the complainants towards penalty/interest on the delayed payment. The complainant in CC No. 207/2014 is required to make the aforesaid payment to the opposite party.
11. The next question which arises for our consideration is as to by which date the possession of the flats should be delivered to the complainants. The learned counsel for the opposite party states on instructions that though the construction is likely to be completed by the end of May 2016, they will need some more time to obtain the occupancy certificate and it will not be possible for them to obtain the said occupancy certificate before October 2016. In these circumstances, we dispose of these complaints with the following directions: (1) The complainants in CC No. 207/2014 will be liable to pay to the opposite party, on receipt of intimation from the opposite party that the construction is complete in all respects and occupancy certificate has been applied for. (2) The complainant in CC No. 94/2014 is not liable to pay any additional amount to the opposite party. (3) The opposite party shall complete the construction in all respects, obtain the occupancy certificate and deliver possession of the flats booked by the complainants to them immediately after obtaining the occupancy certificate. This entire exercise will be completed at the earliest possible and in any case, not later than 31.10.2016. (4) The opposite party shall pay compensation in the form of simple interest @ 12% per annum, on the entire amount paid to it by the complainants from the agreed date of possession till the date the possession is actually delivered to the complainants in compliance of this order after obtaining the occupancy certificate. The opposite party shall be entitled to adjust from the compensation payable to the complainant in CC No. 207/2014, the amount which the said complainant is required to pay to it in terms of this order. The aforesaid compensation shall be paid at the time of handing over possession of the flats to the complainants. (5) The opposite party shall pay Rs. 10,000/- each as cost of litigation in both the complaints. (6) If any contractual amount is due from the complainant in CC No. 94/2015 to the opposite party, that amount can be adjusted by the opposite party out of the compensation payable to the complainants. ......................J
V.K. JAIN PRESIDING MEMBER ...................... DR. B.C. GUPTA MEMBER