AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • National Rural Employment Guarantee Act (NREGA) and Jawaharlal Nehru Urban Renewal Mission (JNNURM). (e)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • National Rural Employment Guarantee Act (NREGA) and Jawaharlal Nehru Urban Renewal Mission (JNNURM). (e)
Smart Summary

Factual and Procedural Background

The complainants entered into identical agreements with the opposite party for the purchase of residential flats in the Burgandy project being developed by the opposite party in Sector 96 to 98, Noida, Uttar Pradesh. The agreed price for each flat was Rs. 3,84,86,994/-. Possession was contractually to be offered within 30 months from the receipt of the duly signed terms and conditions, with allotments made in October 2010, thus possession was due by April 2012. Clause 5(v) of the allotment letter provided for compensation of Rs. 10/- per sq. ft. per month for any unreasonable delay beyond the stipulated date.

The complainants alleged that despite paying over 95% of the sale consideration, possession was not offered and construction remained incomplete. They sought directions for immediate delivery of possession, compensation beyond the contractual amount, interest at 18% per annum on amounts paid, and damages for mental harassment and agony.

The opposite party resisted the complaints, relying on contractual terms limiting liability to Rs. 10/- per sq. ft. per month compensation and justifying delays due to various reasons previously considered by the Commission.

Legal Issues Presented

  1. Whether the opposite party is obligated to deliver possession of the flats within the stipulated contractual period.
  2. Whether the complainants are entitled to compensation beyond the contractual rate of Rs. 10/- per sq. ft. per month for delay in possession.
  3. Whether interest at the rate of 18% per annum is payable on amounts paid by the complainants due to delay in possession.
  4. Whether compensation for mental harassment and agony can be awarded to the complainants in addition to monetary compensation.
  5. Whether the complaints are maintainable before this Commission given the flat cost is less than Rs. 1 crore.

Arguments of the Parties

Opposite Party's Arguments

  • Liability for delay is limited to contractual compensation of Rs. 10/- per sq. ft. per month as per the allotment letter.
  • Delay in possession was due to factors beyond control, including scarcity of labour and materials, economic recession, impact of social schemes (NREGA and JNNURM), shortage of water and raw materials, and environmental restrictions.
  • Due to the flat cost being less than Rs. 1 crore, the complaint is maintainable only before the concerned State Commission, not this Commission.
  • Even if compensation beyond contractual terms is considered, it should be limited to payment of market rent of the flats or comparable accommodation.

Complainants' Arguments

  • Having paid the full price, complainants have a right to possession and are suffering financial loss due to inability to occupy the flats.
  • Market rent is not an adequate compensation as complainants may not be residing in rented accommodation or the rented accommodation may differ in size, specifications, locality, and amenities.
  • Proof of market rent is difficult since lease deeds may be unregistered or unavailable.
  • Mental harassment and agony caused by delay and inability to live in their own home despite payment should be compensated.
  • The satisfaction of living in one's own house cannot be equated with living in rented premises, regardless of similarity in size or locality.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Satish Kumar Pandey & Anr. Vs. M/s. Unitech Ltd., Consumer Case No. 427/2014 Delay in possession and entitlement to compensation including interest at 12% per annum and additional compensation beyond contractual clauses. The Commission rejected the opposite party's grounds for delay and ordered delivery of possession by a stipulated date, payment of compensation at 12% interest from 36 months after agreement date, and enhanced compensation at 18% interest for further delay.
Santosh Johari & Ors. Vs. Unitech Ltd., Consumer Case No. 429/2014 Similar principles on delay, compensation, and maintainability of complaints before this Commission irrespective of flat cost. The Commission again rejected delay justifications and issued directions similar to Satish Kumar Pandey, including possession delivery deadline, interest compensation, and litigation costs.

Court's Reasoning and Analysis

The court examined the identical grounds of delay raised by the opposite party, including economic and regulatory challenges, and found these insufficient to absolve the opposite party of liability. The Commission relied heavily on its prior decisions in Satish Kumar Pandey and Santosh Johari, which had comprehensively rejected similar defenses and established a framework for compensation and possession delivery deadlines.

The court acknowledged the complainants' submissions on the inadequacy of market rent as compensation, recognizing the unique mental and financial impact of delayed possession beyond mere rental losses. It highlighted the difficulty in proving market rent and the qualitative difference between owning and renting a home.

Given the absence of a revised possession schedule from the opposite party, the court granted a reasonable extended timeline of two years to complete construction and deliver possession. It directed payment of compensation in the form of simple interest at 12% per annum from the date possession was due until delivery or the new deadline, with enhanced interest at 18% per annum for any further delay beyond the deadline. The court also awarded litigation costs.

Holding and Implications

DISPOSED OF

The court ordered the opposite party to offer possession of the flats by 31.10.2017 and to pay compensation in the form of simple interest at 12% per annum from 16.04.2013 until possession is offered or 31.10.2017, whichever is earlier. The compensation interest due until 31.12.2015 must be paid in three equal instalments by specified dates, with subsequent payments monthly. If possession is not offered by 31.10.2017, the opposite party shall pay interest at 18% per annum for each day of delay beyond that date. Additionally, Rs. 5,000/- is to be paid as litigation cost in each case.

The decision directly affects the parties by enforcing possession deadlines and compensation payments but does not establish new legal precedents beyond reaffirming prior Commission rulings. It underscores the Commission's stance on holding developers accountable for delays and providing meaningful compensation beyond nominal contractual amounts, recognizing the broader impact on flat buyers.

To access the original judgment, please Sign In or Subscribe.

    Diwakar Mishra v. Unitech Hi-Tech Developers Ltd.

    JUSTICE V.K.JAIN, PRESIDING MEMBER (ORAL) The complainants entered into identical agreements with the opposite party, for purchase of residential flats in a project known as Burgandy, which the opposite party is developing in Sector-

    96 to 98 of Noida of Uttar Pradesh. The price of the flat booked by the complainants with the opposite party was agreed at Rs. 3,84,86,994/- each in all the three Consumer Complaints. As per clause 5 of the allotment letter issued to the complainants, the possession was to be offered to them within 30 months from the receipt of the duly signed terms and conditions by the allottees. The allotments to the complainants were made in October, 2010. The possession, therefore, was required to be offered to them in April, 2012. Clause 5(v) of the allotment letter provided for payment of compensation @ Rs. 10/- per sq. ft. per month of Super Area by the opposite party in case of any unreasonable delay in offering the apartment for interiors/fit outs beyond the stipulated date.

    2. The grievance of the complainants is that despite they having paid more than 95% of the agreed sale consideration to the opposite party, the possession has not been offered to them and in fact the construction of the flats is still far from complete. The complainants are, therefore, before this Commission, seeking a direction to the opposite party to deliver possession of the flats booked by them at the earliest and pay suitable compensation instead of a notional contractual amount of Rs. 10/- per sq. ft. per month. They are also seeking interest @ 18% per annum on the amount paid by them to the opposite party, besides compensation for mental harassment and agony.

    3. The complaints have been resisted by the opposite party on several grounds including that considering the terms and conditions agreed between the parties, in the event of delay their liability is restricted to payment of compensation @ Rs. 10/- per sq. ft. per month of the Super Area for the period offer of the possession is delayed. The opposite party has also sought to justify the delay in offering possession, on several grounds which have already been the subject matter of the consideration by this Commission in a number of cases.

    4. In Satish Kumar Pandey & Anr. Vs. M/s. Unitech Ltd., Consumer Case No. 427/2014 and connected matters decided by this Commission on 08.06.2015, the complainants had booked apartments with the opposite party, M/s. Unitech Ltd. in a complex known as Vistas, which it was developing in Sector- 70 of Gurgaon. The possession of the apartments was agreed to be delivered to the buyers within 36 months from the date of their respective agreements. Since possession was not offered to them nor was the construction complete in terms of the buyers agreement, the complainants approached this Commission, seeking delivery of possession of the flat agreed to be sold by them or in the alternative payment of current market value of the flat, which was stated to be at Rs. 10,000/- per sq. ft. They also sought compensation for loss of rental income to them with effect from the stipulated date of possession, compensation as per the contractual agreement entered between the parties and compound interest @ 18% per annum with effect from the stipulated date of possession. The complaints were resisted by the opposite party, M/s. Unitech Ltd. on several grounds. The aforesaid grounds were incorporated in para 2 and 3 of the decision which reads as under:-

    2. The complaints have been resisted by the OP on several grounds though it has admitted the agreement for sale of apartments to them. It is also stated in the reply that though the possession of the apartments was proposed to be delivered to the purchasers within 36 months, the said date could be extended if the completion of the project was delayed due to non-availability of essential building material, water supply, slow down, civil commotion and other reasons beyond the control of the opposite party. It is claimed that :- (a) Real Estate Industry is adversely affected due to local and national economic conditions, (b) There is recession in the economy resulting in the availability of labour and raw-materials becoming scarce. (c) Common-wealth games organised in October 2010 resulted in extreme shortage of labour in the NCR region. (d) There was shortage of labour due to implementation of social schemes like National Rural Employment Guarantee Act (NREGA) and Jawaharlal Nehru Urban Renewal Mission (JNNURM). (e) There was extreme shortage of water in NCR region, which was further accentuated due to orders of Punjab and Haryana High Court stopping of use of ground water for construction activities. (f) There was shortage of bricks due to restrictions imposed by Ministry of Environment and Forest on brick klins. (g) There was shortage of sand due to mining having been suspended in Aravali Hill Range.

    3. It is also claimed in the reply that in view of clause 4.c.ii) of the agreement, the opposite party is required to pay only the compensation @5/- per sq. ft. per month for the delay in offering possession. Yet, another plea taken in the reply is that since the cost of the flat was less than 1 crore, the complaint is maintainable only before the concerned State Commission and not before this Commission.

    5. Rejecting the grounds on which the complaints were opposed, this Commission directed as under:-

    (a) The opposite party shall deliver possession of the respective flats of the complainants to them on or before the last date stipulated in its letter dated 27.05.2015; (b) The opposite party shall pay to (i) the original allottees and (ii) to those who acquired the allotment by way of repurchase, within one year of the date of the initial Agreement of their respective flats, compensation in the form of simple interest at the rate of 12% per annum with effect from 36 months from the date of the initial Agreement till the date possession is delivered to them. The interest payable till 31.08.2015 shall be paid by 10.09.2015, in three equal instalments, by the 10 of each month i.e. by 10 July, 2015, 10th th August, 2015 and 10 September, 2015. Thereafter, compensation in the form ofth th interest, in terms of this order, shall be paid on monthly basis by the 10 of eachth succeeding month. (c) Such of the complainants, who acquired allotment of the flat by way of repurchase more than one year after the date of the initial allotment of their respective flats, shall be paid compensation by way of simple interest at the rate of 12% per annum, with effect from

    36 months from the date of repurchase by them, till possession is delivered to them. They will also be paid compensation at the rate of Rs.5/- per square foot of the super area of their respective flat for the period between 36 months from the date of the initial Buyers Agreement of their respective flats and 36 months from the date of repurchase of the flat by them. (d) The increase in service tax with effect from 01.06.2015 shall be borne by the opposite party, in all these cases. (e) If the opposite party fails to deliver possession by the last date stipulated in its letter dated 27.05.2015, it shall pay compensation to all the complainants in the form of simple interest at the rate of 18% per annum, for each day there is delay, beyond the date stipulated in the said letter dated 27.05.2015, in delivering possession to the complainants. (f) The opposite party shall pay Rs.5,000/- as the cost of litigation in each complaint.

    6. Similar complaints against Unitech Ltd. came up for consideration of this Commission in and connected cases,Santosh Johari & Ors. Vs. Unitech Ltd., Consumer Case No. 429/2014 decided on 08.06.2015. The grounds on which the above referred complaints were resisted are given in para 2 and 3 of the decision and read as under:-

    2. The complaints have been resisted by the OP on several grounds though it has admitted the agreement for sale of apartments to them. It is also stated in the reply that though the possession of the apartments was proposed to be delivered to the purchasers within 36 months, the said date could be extended if the completion of the project was delayed due to non-availability of essential building material, water supply, slow down, civil commotion and other reasons beyond the control of the opposite party. It is claimed that :- (a) Real Estate Industry is adversely affected due to local and national economic conditions, (b) There is recession in the economy resulting in the availability of labour and raw-materials becoming scarce. (c) Common-wealth games organised in October 2010 resulted in extreme shortage of labour in the NCR region. (d) There was shortage of labour due to implementation of social schemes like National Rural Employment Guarantee Act (NREGA) and Jawaharlal Nehru Urban Renewal Mission (JNNURM). (e) There was extreme shortage of water in NCR region, which was further accentuated due to orders of Punjab and Haryana High Court stopping of use of ground water for construction activities. (f) There was shortage of bricks due to restrictions imposed by Ministry of Environment and Forest on brick klins. (g) There was shortage of sand due to mining having been suspended in Aravali Hill Range.

    3. It is also claimed in the reply that in view of clause 4.c.ii) of the agreement, the opposite party is required to pay only the compensation @5/- per sq. ft. per month for the delay in offering possession. Yet, another plea taken in the reply is that since the cost of the flat was less than 1 crore, the complaint is maintainable only before the concerned State Commission and not before this Commission.

    7. Repelling the contentions advanced by the learned counsel for the opposite party, this Commission disposed of the complaint with the following directions:- (a) The opposite party shall deliver possession of the respective flats of the complainants to them on or before the last date stipulated in its letter dated 27.05.2015; (b) The opposite party shall pay to (i) the original allottees and (ii) to those who acquired the allotment by way of repurchase, within one year of the date of the initial Agreement of their respective flats, compensation in the form of simple interest at the rate of 12% per annum with effect from 36 months from the date of the initial Agreement till the date possession is delivered to them. The interest payable till 31.08.2015 shall be paid by 10.09.2015, in three equal instalments, by the 10 of each month i.e. by 10 July, 2015,th th

    10 August, 2015 and 10 September, 2015. Thereafter, compensation in the form ofth th interest, in terms of this order, shall be paid on monthly basis by the 10 of eachth succeeding month. (c) Such of the complainants, who acquired allotment of the flat by way of repurchase more than one year after the date of the initial allotment of their respective flats, shall be paid compensation by way of simple interest at the rate of 12% per annum, with effect from 36 months from the date of repurchase by them, till possession is delivered to them. They will also be paid compensation at the rate of Rs.5/- per square foot of the super area of their respective flat for the period between 36 months from the date of the initial Buyers Agreement of their respective flats and 36 months from the date of repurchase of the flat by them. (d) The increase in service tax with effect from 01.06.2015 shall be borne by the opposite party, in all these cases. (e) If the opposite party fails to deliver possession by the last date stipulated in its letter dated 27.05.2015, it shall pay compensation to all the complainants in the form of simple interest at the rate of 18% per annum, for each day there is delay, beyond the date stipulated in the said letter dated 27.05.2015, in delivering possession to the complainants. (f) The opposite party shall pay Rs.5,000/- as the cost of litigation in each complaint.

    8. The present complaints have been resisted on those very grounds, which this Commission has already rejected in Satish Kumar Pandey & Anr. (Supra) and Santosh Johari & Ors. (Supra) by way of detailed order and therefore those grounds need not to be expressly dealt with in this order.

    9. During the course of arguments, it was contended by the learned senior counsel for the opposite party that even if this commission is of the view that contractual compensation will not meet the end of justice, the complainants are not entitled to more than the market rent of the flats which they had booked with the opposite party or a similar flat in a nearby locality. The learned counsel for the complainants on the other hand submits that if the complainants is not residing in a rented accommodation but continues to live in an accommodation which is otherwise not suitable to him solely because of the accommodation booked by him having not been offered in time, it will cause a financial loss to him, since despite having paid the price of the flat in which they wanted to live they are unable to do the same. He further states that even if somebody is living in a rented accommodation, that may not necessarily be of the same size and specifications and/or may not be situated in the same locality in which the accommodation booked by him is to be constructed by the opposite party. He further submits that accommodation in which the flat buyer is compelled to live on account of failure of the opposite party to offer possession within the agreed period may not have the same facilities and amenities which the opposite party has agreed to provide in the flat booked by the flat buyer. He also submits that in case the flat buyer is not living in a rented accommodation it may not be possible for him to prove the prevailing market rent since no one would be willing to handover his lease paper to the flat buyer and not every lease deed would be a registered instrument since the lease deed of less than one year do not require registration. He also highlights the mental agony and pain of a person who despite having paid his life time earnings to the builder and in some cases having taken loan on interest is unable to realise his dream of living in a house of his choice. He also submits that the mental satisfaction of living in ones own house cannot be compared to that of living in a rented accommodation even if it has same size and specifications and is situated in the same or a comparable locality.

    10. Be that as it may, considering all the facts and circumstances of the case including the contentions advanced by the learned counsel for the complainants and the previous decision of this Commission, I am of the view that the present complaints should be disposed of in the lines of the previous decisions of this Commission in Satish Kumar Pandey & Anr. (Supra) and Santosh Johari & Ors. (Supra). However, considering that in these complaints, the opposite party has not come out with a revised schedule for offering possession of the apartments to the complainants, the opposite party can be given a reasonable time of two years to complete the construction.

    11. For the reasons stated hereinabove, the complaints are disposed of with the following directions:-

    (i) The opposite party shall offer possession of the flats booked by the complainants to them on or before 31.10.2017.

    (ii) The opposite party shall pay to the complainants, compensation in the form of simple interest @ 12% per annum w.e.f. 16.04.2013 till the date on which possession is offered to them or till 31.10.2017, whichever be earlier. The interest payable till 31.12.2015 shall be paid in three equal instalments. The first instalment shall be paid by 10.01.2016, the second instalment by 10.02.2016 and the third instalment by 10.03.2016. The compensation in the form of interest for the period w.e.f. 01.01.2016 shall be paid on monthly basis by the 10 of each succeeding month.th

    (iii) If the opposite party fails to offer possession by 31.10.2007, it shall pay compensation to the complainants in the form of simple interest @ 18% per annum for each day there is delay, beyond 31.10.2017, in offering possession to the complainants.

    (iv) The opposite party shall also pay Rs. 5,000/- as cost of litigation in each case. ......................J

    V.K. JAIN PRESIDING MEMBER