Smart Summary

Factual and Procedural Background

Complainants filed complaints before the District Forum and the State Commission against M/s Parsvnath Developers Ltd. ("the Developer") and the Chandigarh Housing Board ("CHB") based on similar tripartite agreements entered into with both parties. The complaints arose from the failure of the Developer and CHB to deliver possession of flats within the stipulated 36 months period as per the Development Agreement dated 06.10.2006 and subsequent Flat Buyer Agreements.

The Developer was awarded the contract by CHB to develop a township named "Parsvnath Pride Asia" on 123.79 acres of land at Rajiv Gandhi Chandigarh Technological Park. Complainants applied for flats and paid substantial amounts as per the allotment and tripartite agreements. However, no construction commenced, and the project was effectively abandoned.

Complainants requested refund of the amounts paid. The District Forum and State Commission allowed the complaints directing the Developer and CHB to refund the amounts with interest and compensation. The Developer and CHB filed appeals and revision petitions challenging aspects of these orders, particularly the rates and liability for interest and compensation.

Legal Issues Presented

  1. Whether the Developer and CHB are jointly liable to refund the amounts deposited by the complainants along with interest and compensation for non-delivery of possession within the stipulated time.
  2. The correct rate of interest payable on the amounts to be refunded.
  3. The liability for payment of compensation under clause 9(c) of the Flat Buyer Agreement for delay in possession.
  4. The effect of the dispute between the Developer and CHB over possession of unencumbered land on the liability towards the complainants.
  5. Whether any forfeiture of earnest money (5%) is justified in the absence of breach by the complainants.

Arguments of the Parties

Developer's Arguments

  • The 36 months completion period under clause 2.2.2 of the Flat Buyer Agreement starts only after the Developer receives unencumbered possession of the project land from CHB.
  • CHB failed to hand over vacant possession of the project site, causing delay in construction.
  • The amount deposited by complainants was held in a joint account with CHB and was not operated by the Developer.
  • Developer is entitled to forfeit 5% of the basic price upon cancellation as per clause 5(a) of the Flat Buyer Agreement.
  • Complainants are not entitled to interest on the refunded amount as they sought refund voluntarily.
  • Liability for compensation should rest with CHB for failure to hand over possession.

Chandigarh Housing Board's Arguments

  • No legal impediment existed for construction on the 123.79 acres of land handed over for residential purposes.
  • The dispute was limited to remaining project land earmarked for commercial use, unrelated to the residential flats.
  • Under clause 9(e) of the tripartite agreement, responsibility to deliver residential units timely lies with the Developer.
  • CHB should not be held liable for compensation for non-delivery of residential units.

Complainants' Arguments

  • Support the orders of the State Commission directing refund with interest and compensation.
  • Argue that no breach of payment terms was committed by them.
  • Assert entitlement to compensation and interest as per the tripartite agreements.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Alok Shanker Pandey vs. Union of India & Ors. (2007) 3 SCC 545 Interest is not a penalty but the normal accretion on capital; in equity, the person holding the money must pay interest as normal accretion on principal amount. The court relied on this precedent to affirm that complainants are entitled to interest on the refunded amounts as normal accretion and not as penalty.

Court's Reasoning and Analysis

The court examined the tripartite Development Agreement and Flat Buyer Agreement, focusing on clauses related to payment, possession, refund, interest, and compensation. It noted that the Developer and CHB jointly held the account where complainants' payments were deposited, evidencing joint liability.

The court found no breach by complainants regarding payment obligations, and held that the Developer and CHB failed to fulfill their contractual obligations by not commencing construction or delivering possession within 36 months.

The court rejected the Developer's contention that the 36-month period commenced only after delivery of unencumbered possession of land, emphasizing that complainants should not suffer due to disputes between Developer and CHB.

Regarding interest, the court interpreted clause 9(d) to mean that if the Developer is unable to deliver the unit, both the Developer and CHB are liable to refund amounts with interest at the SBI term deposit rate applicable on the refund date. The court fixed a uniform interest rate of 9% per annum, aligning with senior citizen fixed deposit rates, to avoid conflicting orders.

For compensation under clause 9(c), the court held the Developer liable to pay Rs.107.60 per square meter (Rs.10 per sq. ft.) per month for delay beyond 36 months, noting the project was abandoned and no construction took place. The court directed interim payment of such compensation subject to final arbitration outcomes.

The court emphasized that the Developer and CHB cannot benefit from their mutual disputes or wrongs, and the complainants' legitimate dues must be protected.

The ratio of refund liability was clarified as 70% by the Developer and 30% by CHB, as per clause 4.2.1 of the Development Agreement, and interim arrangements for refund payments in escrow accounts were detailed.

Holding and Implications

The court disposed of the appeals and revision petitions by:

  • Confirming the joint and several liability of Parsvnath Developers Ltd. and Chandigarh Housing Board to refund the amounts deposited by complainants in the ratio of 70:30 respectively.
  • Directing payment of interest at a uniform rate of 9% per annum on the refunded amounts from respective dates of deposit until refund.
  • Directing the Developer to pay compensation @ Rs.107.60 per sq. mtr. per month for delay in possession beyond 36 months, as an interim relief subject to final arbitration.
  • Mandating that refunds and compensation be paid within three months, failing which penal interest @ 12% per annum shall apply.
  • Ordering that interim refund payments be made through escrow accounts with precise arrangements to ensure proper release to complainants.

No new legal precedent was established; the decision clarifies application of contractual clauses and equitable principles in the context of failed real estate projects and consumer protection claims. The ruling protects consumers from bearing losses due to non-performance by developers and government agencies involved in joint projects.

To access the original judgment, please Sign In or Subscribe.

    M/S. PARSVNATH DEVELOPERS LTD. v. SHAMSHER SINGH SIDHU & ANR.

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    REVISION PETITION NO. 396 OF 2011

    (Against the Order dated 19/11/2010 in Appeal No. 324/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Regd. Office at:, Parsvnath Metro Tower, Near Shahdara Metro Station, Shahdara

    Delhi - 110032

    Delhi ...........Petitioner(s)

    Versus

    1. VINOD KATHURIA & ORS. Residents of Old Vicarage Ellenhall, Stafford, Enland -

    ST216JQ

    2. M/S. ANURADHA KATHURIA, W/O. SHRI VINOD

    KATHURIYA

    Residents of Old Vicrae Ellenhall, Stafford, England -

    ST216JQ

    3. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector -9 Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 170 OF 2011

    (Against the Order dated 29/10/2010 in Complaint No. 21/2009 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    the Managing Director Chandigarh. Chandigarh House Board,8 Jan Marg , Sector-9,

    CHANDIGARH ...........Appellant(s)

    Versus

    1. HARJINDER SINGH & ORS. Harjinder singh S/o sh.Mohinder singh resindent of H.No. 4083,sector 68.S.A.S Nagar Mohali .

    NEW DELHI

    2. PARSVNATH DEVELOPERS LTD.

    parsvnath developers ltd., registered office 6th floor, arunachal building ,19,barakhamba road

    New Delhi

    3. PARASVNATH DEVELOPERS LTD.,

    parsvnath developers ltd SCO No.1,Ist floor,Madhya Marg, CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 255 OF 2012

    (Against the Order dated 29/03/2012 in Complaint No. 1/2012 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Chairman, Sector-9 Chandigarh ...........Appellant(s)

    1

    Versus

    1. RAKESH MALHOTRA & 2 ORS. S/o Mr. S.K. Malhotra, House No.310, sector-37A, Chandigarh

    2. PARSVNATH DEVELOPERS LIMITED

    Through its Director, SCO No. 1, First Floor, Sector-26, Madhya Marg,

    Chandigarh

    3. THE DIRECTOR

    Parsvnath Developers Limited Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhamba Road, NEW DELHI-110001 ...........Respondent(s)

    FIRST APPEAL NO. 259 OF 2012

    (Against the Order dated 02/04/2012 in Complaint No. 09/2012 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Chairman, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. DR. ANIL GOEL & 3 ORS. S/o Shri Inder Kumar Goel, House no. 7, Sector-16A, Chandigarh

    2. DR. POONAM GOEL

    W/o Dr. Anil Kumar Goel, House No. 7, Sector-16A, Chandigarh

    3. PARSVNATH dEVELOPERS lIMITED Through its Branch Manager, SCO No. 1, First Floor, Sector- 26, Madhya Marg,

    Chandigarh

    4. THE MANAGING DIRECTOR

    Parsvnath Developers Limited, Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001 ...........Respondent(s)

    FIRST APPEAL NO. 265 OF 2012

    (Against the Order dated 29/03/2012 in Complaint No. 1/2012 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. Having its Corporate office at: 6th Floor, Arunachal Building, 19, Bara Khamba Road,

    NEW DELHI-110001

    2. M/S. PARSVNATH DEVELOPERS LIMITED, SCO No. 1 , First Floor, Sector-26, Madhya Marg,

    Chandigarh ...........Appellant(s) Versus

    1. RAKESH MALHOTRA & ANR. ...........Respondent(s)

    2

    S/o Shri S.K. Malhotra, R/o House No. 310, Sector-37A, Chandigarh

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh

    FIRST APPEAL NO. 266 OF 2012

    (Against the Order dated 02/04/2012 in Complaint No. 9/2012 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhamba Road, NEW DELHI-110001

    2. M/S PARSVNATH DEVELOPERS LIMITED SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigarh ...........Appellant(s) Versus

    1. DR. ANIL GOEL & 2 ORS. W/o Shri Inder Kumar Goel, R/o House No. 7, Sector-16A, Chandigarh

    2. DR. POONAM GOEL

    W/o Dr. Inder Kumar Goel, R/o House No. 7, Sector-16A, Chanidgarh

    3. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 267 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 69/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO.1, FIRST FLOOR , MADHYA MARG,SECTOR-26, CHANDIGARH-160026

    PUNJAB ...........Appellant(s)

    Versus

    1. NARESH KUMAR BATRA & ANR. S/O LATE SHRI R.P BATRA, PERMANENT RESIDENT OF HOUSE NO. 3067, SECTOR-21-D, CHANDIGARH.

    [PRESENTLY RESIDING AT 19353, PINNACLE COURT,

    SARATOGA, CALIFORNIA, USA-95070] THROUGH MR.

    UMESH BATRA

    2. THE CHAIRMAN, CHANDIGARH HOUSING BOARD,

    , JAN MARG, SECTOR-9, CHANDIGARH-160009 ...........Respondent(s)

    FIRST APPEAL NO. 267 OF 2012

    (Against the Order dated 20/03/2012 in Complaint No. 80/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhamba Road, NEW DELHI-110001 ...........Appellant(s)

    3

    2. M/S. PARSVNATH DEVELOPERS LIMITED. SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigarh

    Versus

    1. JUGNU R. SINGH & 3 ORS. W/o Shri Ravinder Singh, R/o House No. 317, Sector-9D, Chandigarh

    2. MRS. KARANJIN SINGH SHAWNEY

    W/o Shri Ravinder Singh, R/o House No. 317, Sector-9-D, Chandigarh

    3. MS. SHEETAL SINGH

    D/o Shri Ravinder Singh, R/o House No. 317, Sector-9D, Chandigarh

    4. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 268 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 70/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO. 1, FIRST FLOOR, MADHYA MARG, SECTOR-26, CHANDIGARH-160026

    PUNJAB ...........Appellant(s)

    Versus

    1. MEERA MAYER & ANR. W/O MR. MARCO O. MAYER, D/O SHRI RAMESH

    KHOSLA, 1185, PARK AVENUE, APARTMENT 16G, NEW

    YORK (USA)10128 ALSO AT: C/O H NO.27, FIRST FLOOR, SECTOR-5, CHANDIGARH,THROUGH THE

    ATTORNEY,SH. RAMESH G.

    2. CHANDIGARH HOUSING BOARD

    THROUGH ITS PRINCIPAL OFFICER, 8, JAN MARG,

    SECTOR-9, CHANDIGARH-160009 ...........Respondent(s)

    FIRST APPEAL NO. 269 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 73/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO .1,FIRST FLOOR, MADHYA MARG, SECTOR -26, CHANDIGARH -160026.

    PUNJAB ...........Appellant(s)

    Versus

    1. TEJPAL SINGH DHILLON

    S/O SHRI HARNAND SINGH DHILLON, BOTH

    PRESENTLY RESIDING AT 7501, S. TANGLEWILD

    DRIVE, RALEIGHT NC, USA-27613.

    2. PARMIN DER KAUR,

    W/O SHRI TEJPAL SINGH DILLON, RESIDING AT 7501, ...........Respondent(s)

    4

    S.TANGLEWILD DRIVE,RALEIGHT NC,

    USA-27613

    3. THE CHAIRMAN ,

    CHANDIGARH HOUSING BOARD, 8, JAN MARG ,

    SECTOR -9,

    CHANDIGARHB-160009

    FIRST APPEAL NO. 269 OF 2012

    (Against the Order dated 13/03/2012 in Complaint No. 04/2012 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LIMITED & ANR. 6th Floor, Arunachal Building, 19, Barakhamba Road, NEW DELHI-110001

    2. M/S PARSVNATH DEVELOPERS LIMITED, SCO No. 1, First Floor, Sector-26, Madhya marg, Chandigarh ...........Appellant(s) Versus

    1. HARSOHIN KAUR & ANR. D/o Major Mohinder Singh Sarkaria, R/o House No. 39 , the Mall,

    Amritsar

    Punjab

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 270 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 77/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO.1, FIRST FLOOR , MADHYA MARG,SECTOR-26, CHANDIGARH-160026

    PUNJAB ...........Appellant(s)

    Versus

    1. RANJIT SINGH AMRIT

    S/O SHRI HARBANS SINGH AMRIT, E-380, 2ND FLOOR, GREATER KAILASH-II, NEW DELHI-110048 BEING REPRESENTED BY SHRI S.S. GUPTA, R/O H NO. 143, SECTOR-A, CHANDIGARH BEING POWER OF

    ATTORNEY HOLDER.

    CHANDIGARH

    PUNJAB

    2. THE CHAIRMAN, CHANDIGARH HOUSING BOARD,

    8, JAN MARG, SECTOR-9, CHANDIGARH-160009 ...........Respondent(s)

    FIRST APPEAL NO. 271 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 76/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO. 1, FIRST FLOOR, MADHYA MARG, SECTOR-26, ...........Appellant(s)

    5

    CHANDIGARH-160026

    PUNJAB

    Versus

    1. M/S. ISAT NETWORK ENGINEERS PVT. LTD. & ANR. D-24 & 25, INDUSTRIAL AREA-II,

    HARIDWAR,[THROUGH ITS DIRECTOR SH.

    SUDHANSHOO AGGARWAL]

    2. THE CHAIRMAN

    CHANDIGARH HOUSING BOARD, 8, JAN MARG,

    SECTOR-9, CHANDIGARH-160009 ...........Respondent(s)

    FIRST APPEAL NO. 272 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 74/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO NO. 1, FIRST FLOOR, MADHYA MARG, SECTOR-26, CHANDIGARH-160026

    PUNJAB ...........Appellant(s)

    Versus

    1. RANJIT SINGH SHONPAL & ANR. S/O LATE SHRI MEHMA SINGH SHONPAL, R/O 38, WEST HILL, SANDERSTEAD, SUREY,LONDON, U.K.-

    CR20SA

    2. THE CHAIRMAN

    CHANDIGARH HOUSING BOARD, 8, JAN MARG,

    SECTOR-9,

    CHANDIGARH-160009

    PUNJAB ...........Respondent(s)

    FIRST APPEAL NO. 273 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 78/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    6TH FLOOR, ARUNACHAL BUILDING, 19,

    BARAKHAMBA ROAD,

    NEW DELHI-110001 ...........Appellant(s) Versus

    1. MRS. HARBANS KAUR BRAR & ORS. W/O. SHRI DARSHAN SINGH BRAR, BOTH RESIDENTS OF H. NO. 279, SECTOR-10,

    CHANDIGARH

    PUNJAB

    2. MS. JASWINDER KAUR GILL,

    D/O SHRI DARSHAN SINGH BRAR, BOTH RESIDENTS OF H. NO. 279, SECTOR-10, CHANDIGARH

    3. THE CHAIRMAN, CHANDIGARH HOUSING BOARD,

    8, JAN MARG, SECTOR-9, CHANDIGARH-160009 ...........Respondent(s)

    FIRST APPEAL NO. 284 OF 2011

    6

    (Against the Order dated 01/06/2011 in Complaint No. 78/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, JAN MARG, SECTOR-9, CHANDIGARH-160009

    PUNJAB ...........Appellant(s) Versus

    1. HARBANS KAUR BRAR & ORS.

    WIFE OF SHRI DARSHAN SINGH BRAR , H NO. 279,

    SECTOR-10,

    CHANDIGARH-

    PUNJAB

    2. PARSVNATH DEVELOPERS LTD.

    - ...........Respondent(s)

    FIRST APPEAL NO. 289 OF 2012

    (Against the Order dated 13/03/2012 in Complaint No. 4/2012 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Secretary, 8, Jan Marg, Sector-9D, Chandigarh ...........Appellant(s) Versus

    1. HARSOHIN KAUR & 2 ORS. D/o Major Mohinder Singh Sarkaria, R/o House No. 39, The Mall,

    Amritsar

    Punjab

    2. PARSVNATH DEVELOPERS LIMITED,

    Through its Managing Director, Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhamba Road,

    NEW DELHI

    3. THE MANAGER

    Parsvnath Developers Ltd., SCO No. 1, First Floor, Sector-26, Madhya Marg,

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 306 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 4/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Regd.Offce at: Parasvnath Metro Tower, Near Shahdara Metro Station,Shahdara

    Delhi - 110 032

    Delhi ...........Appellant(s)

    Versus

    1. SHAMSHER SINGH SIDHU & ANR. House No.165, Sector-8A Chandigarh

    Chandigarh ...........Respondent(s)

    7

    2. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9 Chandigarh

    Chandigarh

    FIRST APPEAL NO. 307 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 15/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. ...........Appellant(s) Versus

    1. SATISH KUMAR GOYAL & ANR.

    2. CHANDIGARH HOUSING BOARD

    - ...........Respondent(s)

    FIRST APPEAL NO. 308 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 34/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Through:Shri V. Mohan, Company Secretary, Regd.Office at:

    Parasvnath Metro Tower, Near Shahdara Metro Station, SHahdara

    Delhi-110032

    Delhi ...........Appellant(s)

    Versus

    1. BALJEET SWINDER GANDHI & ANR. House No.1046, Sector-2, Panchkula-134112

    -

    2. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector - 9 Chandigarh

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 309 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 39/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Through: Shri V.Mohan, Company Secretary, Regd.Office at. Parsvnath Metro Tower, Near Shahdara Metro Station, Shahdara

    Delhi-110032

    Delhi ...........Appellant(s)

    Versus

    1. ATUL KUKREJA & ANR. E-83, Saket

    New Delhi-110017 Delhi

    2. CHANDIGARH HOUSING BOARD

    8, Jan Marg Sector-9 ...........Respondent(s)

    8

    Chandigarh Chandigarh

    FIRST APPEAL NO. 310 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 44/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    2. M\S PARSAVNATH DEVELOPERS LTD

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDRA MET RO STATION ,SHAHDRA,

    DELHI-110032 ...........Appellant(s) Versus

    1. BINDER PAL MITTAL & ANR.

    2. SH .BINDER PAL MIT TAL

    HOUSE NO.233, SECTOR-7

    PANCHKULA

    HARYANA

    3. CHANDIGARH HOUDING BOARD

    8 ,JANMARG ,SECTOR -9

    CHANDIGARH

    HARYANA ...........Respondent(s)

    FIRST APPEAL NO. 311 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 55/2009 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Through: Shri V. Mohan, Company Secretary, Regd.Office at:

    Parsvnath Metro Tower, Near Shahdara Metro Station,Shahdara Delhi-110032

    Delhi ...........Appellant(s)

    Versus

    1. DEEPAK SARIN & ANR. Green House(Next to Post Office) Nongrim Hills Shillonhg-793003

    2. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9, Chandigarh

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 313 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 15/2009 of the State Commission Punjab)

    1. CHANDIGARH HOUSING BOARD

    SECTOR -9 CHANDIGARH CHANDIGARH ...........Appellant(s) Versus

    1. SATISH KUMAR GOYAL & ORS. BOTH R/O SUBASH IRON STORE ,LOHA BAZAR ,MANDI, GOBINDGARH ...........Respondent(s)

    9

    GOBINDGARH

    PUNJAB

    2. SUSHMA GOYAL

    R/O SUBASH IRON STORE , LOHA BAZAR , NADI

    GOBINDGARH

    GOBIND GARH

    PUNJAB

    3. PARSVNATH DEVELOPERS LIMITED

    THROUGH ITS MANAGING DIRECTOR REGISTERED

    OFFICE , 6TH FLOOR ,ARUNACHAL BUILDING 19 ,

    BARAKHAMBA ROAD

    NEW DELHI

    4. THE MANAGER PARSVNATH DEVELOPERS LTD .

    SCO 1,1ST FLOOR ,MADHYA MARG ,SECT OR-26

    CHANDIGARH

    CHANDIGARH

    FIRST APPEAL NO. 313 OF 2012

    (Against the Order dated 09/05/2012 in Complaint No. 13/2012 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Having its Registered Office at : Parsvnath Metro Tower, Near Shahdara Metro Station, Shahdara ,

    Delhi-110032 ...........Appellant(s)

    Versus

    1. M/S. KUKREJA BUILDERS PVT. LTD. & ANR. 501, Sai Commercial Building, BKS Devshi Marg (Govandi), East Mumbai

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 314 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 39/2009 of the State Commission Punjab)

    1. CHANDIGARH HOUSING BOARD

    THROUGH ITS CHAIRMAN SECTOR -9 CHANDIGARH

    CHANDIGARH

    CHANDIGARH (U.T.0 ...........Appellant(s) Versus

    1. ATUL KUKREJA & ORS. r/o no:1046, sector -2, panchkula haryana

    2. POOJA KUKREJA

    W/O ATUL KUKREJA BOTH R/O E-83,SAKET ,NEW

    DELHI

    NEW DELHI ...........Respondent(s)

    10

    3. PARSAVNATH DEVELOPERS LTD.

    THROUGH ITS MANAGING DIRECTOR REGISTERED

    OFFICE AT ,6TH FLOOR ARUNACHAL BUILDING

    19,BARAKHAMBA ROAD

    NEW DELHI

    4. THE MANAGER RETAIL AND MARKETING

    R/O AT PASARVNATH DEVELOPER LTD . SCO 1,1ST FLOOR ,SECTOR -26,MADHYA MARG

    CHANDIGARH

    FIRST APPEAL NO. 315 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 4/2009 of the State Commission Punjab)

    1. CHANDIGARH HOUSING BOARD

    SECTOR -9 CHANDIGARH CHANDIGARH ...........Appellant(s) Versus

    1. SHAMSHER SINGH SIDHU & ORS. R/o : H.No.165, sector-8A

    CHANDIGARH

    2. M/S. Parsavnath Developers Ltd registered office at 6th floor, arunachal building 19, barakhamba road,

    New Delhi - 110 001 ...........Respondent(s)

    FIRST APPEAL NO. 316 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 34/2009 of the State Commission Punjab)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg , Sector /9S Chandigarh -160009 chandigarh ...........Appellant(s) Versus

    1. BALJEET SWINDER GANDHI & ORS. R/o : House .No.1046, sector -2, panchkula

    haryana

    2. Swindher Singh Gandhi R/o House No. 1046, sector -2, panchkula

    haryana

    3. M/s. Parsavnath Developers Ltd, Company incorporated under the Proivison of the companies act 1956, Regisrered office at 6th floor Arunachal Building 19, Barakhamba Road,

    New Delhi

    4. M/s Parsavnath Developers Ltd, Company incorporated under the Proivison of the companies act 1956, Regisrered office at 6th floor Arunachal Building 19, Barakhamba Road, ...........Respondent(s)

    11

    New Delhi

    FIRST APPEAL NO. 317 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 44/2009 of the State Commission Punjab)

    1. CHANDIGARH HOUSING BOARD

    SECTOR-9 CHANDIGARH CHANDIGARH ...........Appellant(s) Versus

    1. BINDER PAL MITTAL & ORS. H.NO.233 SECTOR-7 PANCHKULA

    PUNJAB

    2. M/S. PARASVNATH DEVELOPERS LTD. 6th FLOOR ARUNACHAL BUILDING 19,BARAKHAMBA ROAD NEW DELHI-110001

    3. Mrs Sushma Mittal W/o Mr Binder Pal Mittal, R/o:House No. 233, Sector -7, Panchkula

    Haryana

    4. Mr. Bharat Mittal S/o:Mr. Binder Pal Mittal , R/o : House No .233, Sector -7 Panchkula

    Haryana

    5. Through its director M/s Parsavnath Developers Ltd. sco 1, 1st floor, Sector -26, Madhya Marg, chandigarh

    Chandigarh

    6. THROUGH ITS MANAGER, ICICI BANK LTD.

    SCO No. 129-130, Ist Floor, Sector - 9-C Chandigarh

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 317 OF 2012

    (Against the Order dated 09/05/2012 in Complaint No. 13/2012 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Chairman, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. M/S. KUKREJA BUILDERS PVT. LTD. & 2 ORS. Through its authorized signatory, 501, Sai Commercial Building, BKS Sevshi Marg (Govandi)

    East Mumbai

    2. PARSVNATH DEVELOPERS LIMITED

    Through its Branch Manager, SCO No. 1, First Floor, Sector- 26, madhya Marg,

    Chandigarh

    3. THE MANAGING DIRECTOR ...........Respondent(s)

    12

    Parsvnath Developerrs Limited, Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhamba Road, New Delhi-110001

    FIRST APPEAL NO. 318 OF 2010

    (Against the Order dated 19/08/2010 in Complaint No. 55/2009 of the State Commission Pondicherry)

    1. CHANDIGARH HOUSING BOARD

    OFFICE AT 8,JANMARG ,SECTOR-9

    CHANDIGARH

    U.T.CHANDIGARH ...........Appellant(s) Versus

    1. DEEPAK SARIN & ORS.

    RESIDENT OF GREEN HOUSE ,NONGRIM HILLS

    SHILLONG

    MEGHALAYA

    2. M/s. Parsavnath Developers Ltd. Company incorporated under companies act 1956, registered office at 6th floor Arunachal Building 19, Barakhamba Road , New Delhi ...........Respondent(s)

    FIRST APPEAL NO. 332 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 69/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector/9-D,

    CHANDIGARH

    PUNJAB ...........Appellant(s) Versus

    1. NARESH KUMAR BATRA & ORS. S/O. Late Shri R.P. Batra, R/o, House No. 3067, Sector-21-D,

    CHANDIGARH

    PUNJAB

    2. PARSVNATH DEVELOPERS LTD,

    through its Director, SCO No. 1, 1st Floor, Madhya Marg, Sector-26,

    Chandigarh

    Punjab

    3. THE DIRECTTOR,

    M/s. Parsvnath Developer Ltd, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    New Delhi-1100001 ...........Respondent(s)

    FIRST APPEAL NO. 333 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 70/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9, Chandigarh, Punjab, through its Principal Officer/Estate Officer ...........Appellant(s) Versus

    13

    1. MEERA MAYER & ORS. W/O Mr. Marco O. Mayyer, D/o Shri Ramesh Khosla, 1185, Park Avenue, Apartment-16-G,

    NEW YORK

    USA-10128

    2. C/o HOUSE NO. 27, FIRST FLOOR, Sector-5, CHANDIGARH, PUNJAB, through the Shri Ramesh Khosla

    3. M/S. PARSVNATH DEVELOPERS LTD, SCO No. 1, First Floor, Madhya Marg, sector-26, Chandigarh- Punjab

    4. M/S PARSVNATH DEVELOPERS LTD., 6th Floor, Arunachal Building, 19, Bara Khambha Road, NEW DELHI-110001 ...........Respondent(s)

    FIRST APPEAL NO. 334 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 73/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9-D, Chandigarh-160009 ...........Appellant(s) Versus

    1. TEJPAL SINGH DHILLON & ORS. S/o Shrim Harnand singh Dhillion, R/O. 7501, S. Tanglewild Drive, Raleight NC, USA 27613

    2. PERMINDER KAUR DHILLION

    W/O TEJPAL SINGH DHILLION, R/o. 7501, S. Tanglewild Drive, Raleight NC, USA 27613

    3. PARSVNATH DEVELOPERS LTD,

    THROUGH its Director, SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh-160026

    4. THE DIRECTOR

    Parsvnath Developers ltd, Registered and Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-01 ...........Respondent(s)

    FIRST APPEAL NO. 335 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 74/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9-D, Chandigarh-160009 ...........Appellant(s) Versus

    1. RANJIT SINGH SONPAL & ORS. S/o Late Shri Mehma Singh Shonpal, R/o 38 West Hill, Sanderstead, Surely, London, U.K.-CR20SA

    2. PARSVNATH DEVELOPERS LTD.,

    through its Director, SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh-160026

    3. THE DIRECTOR

    Parsvnath developers ltd.,Registered and Corporate Office, 6th ...........Respondent(s)

    14

    Floor, Arunachal Building, 19, Bara Khambha Road, New Delhi-110001

    FIRST APPEAL NO. 336 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 76/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOSING BOARD

    8, Jan Marg, Sector-9-D, Chandigarh-160009 ...........Appellant(s) Versus

    1. M/S. ISAT NETWORK ENGINEERS PVT. LTD. D-24, & 25, Industrial Area-II, Haridwar-294-1, Sh. Sughanshoo Aggarwal

    2. PARSVNATH DEVELOPERS LTD.,

    Through its Director, SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh-160026

    3. THE DIRECTOR

    Parsvnath developers ltd.,Registered and Corporate Office, 6th Floor, Arunachal Building, 19, Bara Khambha Road, New Delhi-110001 ...........Respondent(s)

    FIRST APPEAL NO. 337 OF 2011

    (Against the Order dated 01/06/2011 in Complaint No. 77/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9-D, Chandigarh-160009 ...........Appellant(s) Versus

    1. RANJIT SINGH AMRIT & ANR. S/O Late Shri Harbans Singh Amrit, E-380, 2nd Floor, Greater Kailash-II,

    NEW DELHI48-

    2. PARSVNATH DEVELOPERS LTD.

    Through its Managing Director, SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh-160026 ...........Respondent(s)

    FIRST APPEAL NO. 366 OF 2011

    (Against the Order dated 11/08/2011 in Complaint No. 75/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Chairman, 8, Jan Marg, Sector-9-D,Chandigarh Punjab ...........Appellant(s)

    Versus

    1. RAJIV MALHOTRA & ORS. S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53,

    Gurgaon-122011

    2. MRS NAVINDER MALHOTRA

    W/o. Mr. Rajiv Malhotra, S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53, Gurgaon -122011

    3. MR. V.S. MALHOTRA ...........Respondent(s)

    15

    S/o. Late B.R. Malhotra, S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53, Gurgaon-122011

    4. PRASVNATH DEVELOPERS LTD,

    through its Principal officer, 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001

    FIRST APPEAL NO. 370 OF 2011

    (Against the Order dated 25/07/2011 in Complaint No. 56/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001

    2. THE CHAIRMAN

    CHANDIGARH HOUSING BOARD, 8 Jan Marg, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. SUMANT BAKSHI & ANR. 45, Qutab View Apartment, opposite Qutab Hotel, Sahid Jeet Singh Marg,

    New Delhi ...........Respondent(s)

    FIRST APPEAL NO. 371 OF 2011

    (Against the Order dated 11/08/2011 in Complaint No. 75/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001 ...........Appellant(s) Versus

    1. RAJIV MALHOTRA & ORS. S/o Mr. V.S. Malhotra,S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53, Gurgaon-122011

    2. MRS. NAVINDER MALHOTRA

    W/O. Mr. Rajiv Malhotra,S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53, Gurgaon-122011

    3. MR. V.S. MALHOTRA

    S/O Late Mr. B.R. Malhotra, S/o Mr. V.S. Malhotra, Flat 1401, Tower 6 Vipul Belmonte, Golf Course Road, Sector-53, Gurgaon-122011 ...........Respondent(s)

    FIRST APPEAL NO. 372 OF 2011

    (Against the Order dated 20/07/2011 in Complaint No. 3/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001 ...........Appellant(s) Versus

    1. VIKRAM VEER SINGH & ORS. ...........Respondent(s)

    16

    S/o Sh. Harminder Singh, R/O 19, Cool Road, Jyoti Nagar, Jalandhar,

    Punjab

    2. KARNVEER SINGH

    S/O sh. Harminder Singh, R/o 19, Cool Road, Jyoti Nagar, Jalandhar, PUNJAB

    3. THE CHAIRMAN

    CHANDIGARH HOUSING BOARD, 8 Jan Marg, Sector- 9, Chandigarh-160009

    FIRST APPEAL NO. 373 OF 2011

    (Against the Order dated 20/07/2011 in Complaint No. 7/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh-160026 ...........Appellant(s) Versus

    1. VIJAY KUMAR SAGGAR & ANR. S/O Late SH. Vaval Kishore Saggar, Elling Hoists, GT-8, Drammen Norway 3022 and C/O # 1302, D-1, Vasant Kunj, NEW DELHI-1100070

    2. THE CHAIRMAN,

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh- 160009 ...........Respondent(s)

    FIRST APPEAL NO. 374 OF 2011

    (Against the Order dated 25/07/2011 in Complaint No. 56/2010 of the State Commission Chandigarh)

    1. THE CHAIRMAN , CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9,

    Chandigarh

    2. PARSVNATH DEVELOPERS LTD.

    THROUGH ITS DIRECTOR, SCO No. 1, First Floor, Madhya Marg, Sector-26,

    Chandigarh-160026

    3. THE DIRECTOR, PARSVNATH DEVELOPERS LTD.

    REgistered and corporate office, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI-1100001 ...........Appellant(s)

    Versus

    1. SUMANT BAKSHI & ORS. R/o, Qutab View Apartment, Opposite Qutuab Hotel, Sahid Jeet Singh Marg,

    NEW DELHI-

    2. PARSVNATH DEVELOPERS DEVELOPERS LTD.

    - ...........Respondent(s)

    FIRST APPEAL NO. 375 OF 2011

    (Against the Order dated 20/07/2011 in Complaint No. 03/2011 of the State Commission Chandigarh)

    17

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9,through its Principal officer/Estate Officer.

    Chandigarh ...........Appellant(s)

    Versus

    1. VIKRAMVEER SINGH & ORS. S/o Sh. Harminder Singh, R/o 19, Cool Road, Jyoti Nagar, Jalandhar,

    PUNJAB

    2. KARANVEER SINGH

    S/o Sh. Harminder Singh, R/o 19, Cool Road, Jyoti Nagar, Jalandhar,

    PUNJAB

    3. PARSVNATH DEVELOPERS LTD.

    Registered office, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI - 110 001 ...........Respondent(s)

    FIRST APPEAL NO. 376 OF 2011

    (Against the Order dated 20/07/2011 in Complaint No. 7/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9, THROUGH its Pincipal Officer/ Estate Officer

    Chandigarh-160009 ...........Appellant(s) Versus

    1. VIJAY KUMAR SAGGAR & ANR. S/o Late Shri Naval Kishore Saggar, R/o Elling Holsts, GT-8, Drammen Norway-3022 AND 1302,, D-1, Vasant Kunj, NEW DELHI-110070

    2. PARSVNATH DEVELOPERS LTD.

    SCO No. 1, First Floor, Madhya Marg, Sector-26, through its managing Director

    CHANDIGARH

    3. PARSVNATH DEVELOPERS LTD.

    6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001, through Shri Pardeep Jain its Managing Director ...........Respondent(s)

    FIRST APPEAL NO. 377 OF 2011

    (Against the Order dated 26/08/2011 in Complaint No. 27/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    , Jan Marg, Sector-9, Chandigarh-160009, Through its Chairman ...........Appellant(s)

    Versus

    1. APURVA GOSWAMY & ANR. S/O Mr. B.N. Goswamy, R/o House No. 171, Sector-19A, Chandigarh ...........Respondent(s)

    18

    PUNJAB

    2. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001, Through its Managing Director

    3. PARSVNATH DEVELOPERS LTD.

    SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh

    FIRST APPEAL NO. 391 OF 2011

    (Against the Order dated 16/08/2011 in Complaint No. 66/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9, Chandigarh, Through its Chairman/Secretary ...........Appellant(s) Versus

    1. HARTON COMMUNICATION LTD. & ORS. through its Director Vineet Malik, Valley Estate, Mansa Devi Road,

    Panchkula

    2. M/S. PARSVNATH DEVELOPERS LTD., Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi- IInd ADDRESS : SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigargh ...........Respondent(s)

    FIRST APPEAL NO. 392 OF 2011

    (Against the Order dated 16/08/2011 in Complaint No. 67/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, jan Marg, Sector-9, Chandigarh, Through its Chairman ...........Appellant(s) Versus

    1. PANCHKULA AGRO FOODS LTD. & ANR. 79, Industries Area Phase-I, Panchkula, through its Director

    2. M/S. PARSVNATH DEVELOPERS LTD., Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi- ...........Respondent(s)

    FIRST APPEAL NO. 393 OF 2011

    (Against the Order dated 16/08/2011 in Complaint No. 68/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9, Chandigarh, Through its Chairman/Secretary ...........Appellant(s) Versus

    1. ARAVALI ENGINEER PVT. LTD. & ANR. through its Director, Valley Estate Mansa Devi Road,MD Complex,

    Panchkula

    2. M/S PARSVNATH DEVELOPERS LTD., Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-, through its Director ...........Respondent(s)

    FIRST APPEAL NO. 394 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 14/2011 of the State Commission Chandigarh)

    19

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. RAVINDER KAUR & ORS. R/o House No. 558, Sector-36B, Chandigarh

    2. M/S. PARSVNATH DEVELOPERS LTD., Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-

    3. THE MANAGER

    M/S.PARSVNATH DEVELOPERS LTD., SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigargh ...........Respondent(s)

    FIRST APPEAL NO. 395 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 18/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9-B, Chandigarh-160009, Through its Principal Officer/Estate Officer ...........Appellant(s) Versus

    1. BALWANT LAKHBIR SINGH & ORS. S/O. Sh. Balwant Singh Randhawa, R/o 5A, Raw House Surya Vihar, Dundahera

    Gurgaon-12206

    2. MRS. RIPU SINGH

    W/O. Sh. Balwant Singh , R/o 5A, Raw house Surya Vihar, Dundahera, Gurgaon-12206

    3. M/S PARSVNATH DEVELOPERS LTD SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigargh-160026 ...........Respondent(s)

    FIRST APPEAL NO. 397 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 16/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9, Chandigarh, Through its Chairman ...........Appellant(s) Versus

    1. SAT PAUL BANSAL & ORS. R/O. House No. 749, SEctor-8-B,

    CHANDIGARH

    2. M/S. PARSVNATH DEVELOPERS LTD Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road, (through its Managing Director)

    NEW DELHI

    3. THE MANAGER

    M/S PARSVNATH DEVELOPERS LTD.,SCO No. 1, First Floor, Sector-26, Madhya Marg,

    Chandigargh ...........Respondent(s)

    20

    FIRST APPEAL NO. 402 OF 2011

    (Against the Order dated 05/09/2011 in Complaint No. 25/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan marg, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. VIKRAM BABBAR & ORS. S/o Shagan Lal Babbar, R/o House No. 786, Ward No. 3, Krishana Colony, Muktsar

    (Punjab)

    2. SEEMA BABBAR

    W/O Vikram Babbar R/o House No. 786, Ward No. 3, Krishana Colony, Muktsar

    (Punjab)

    3. M/S. PARSVNATH DEVELOPERS LTD., through its Director, SCO No. 1, First Floor, Sector-26, Madhya Marg,

    Chandigargh

    4. THE DIRECTOR, M/S PARSVNATH DEVELOPERS LTD Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road,-

    New Delhi ...........Respondent(s)

    FIRST APPEAL NO. 403 OF 2011

    (Against the Order dated 02/09/2011 in Complaint No. 15/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9, Chandigarh, Through its Chairman ...........Appellant(s) Versus

    1. PRITAM SINGH SETHI & ORS. R/o House No. 558, Sector-36-B,

    CHANDIGARH

    2. MANAGER, M/S. PARSVNATH DEVELOPERS LTD., SCO No. 1, First Floor, Sector-26, Madhya Marg, Chandigargh ...........Respondent(s)

    FIRST APPEAL NO. 413 OF 2011

    (Against the Order dated 02/09/2011 in Complaint No. 15/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001 ...........Appellant(s) Versus

    1. PRITMA SINGH SETHI & ANR. R/O House No. 558, Sector-36-B, Chandigarh

    2. THE CHAIRMAN,

    CHANDIGARH HOUSING BOARD, 8, Jan Marg, Sector -9, ...........Respondent(s)

    21

    CHANDIGARH

    FIRST APPEAL NO. 414 OF 2011

    (Against the Order dated 05/09/2011 in Complaint No. 25/2011 of the State Commission Chandigarh)

    1. PARSVNATH DEVELOPERS LTD.

    6th Floor, Arunachala Building, 19, Barakhmbha Road, NEW DELHI ...........Appellant(s)

    Versus

    1. VIKRAM BABBAR & ORS. S/o. Sh. Shagan Lal Babbar, R/o. House No. 786, Ward No. 3, Krishna Colony, Muktsar,

    PUNJAB

    2. MRS SEEMA BABBAR

    W/o. Mr. Vikram Babbar, R/o. House No. 786, Ward No. 3, Krishna Colony, Muktsar,

    PUNJAB

    3. THE CHAIRMAN

    CHANDIGARH HOUSING BOARD, 8, Jan Marg, Sector-9-B, CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 428 OF 2011

    (Against the Order dated 16/08/2011 in Complaint No. 66/2010 of the State Commission Chandigarh)

    1. PARSVNATH DEVELOPERS LTD.

    6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi ...........Appellant(s)

    Versus

    1. M/S. HARTRON COMMUNICATION LTD. & ANR. Valley Estate, Mansa Devi Road, Panchkula

    2. THE CHAIRMAN / SECRETARY Chandigarh Housing Board, 8, Jan Marg, Sector-9-B, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 429 OF 2011

    (Against the Order dated 16/08/2011 in Complaint No. 67/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001 ...........Appellant(s) Versus

    1. PANCHKULA AGRO FOODS LTD. & ANR. 79, Industrial Area, Phase-I, through its Director Panchkula

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 430 OF 2011

    22

    (Against the Order dated 16/08/2011 in Complaint No. 68/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, New Delhi-110001 ...........Appellant(s) Versus

    1. M/S. ARAVALI ENGINEER PVT. LTD. & ANR. Valley Estate Mansa DEvi Road, MD Coplex, through its Director

    Panchkula

    2. THE CHANDIGARH HOUSING BAORD

    Sector-9, Madhya Marg, Chandigarh

    through its chairman secretary ...........Respondent(s)

    FIRST APPEAL NO. 431 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 14/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhmbha Road, NEW DELHI-110001 ...........Appellant(s) Versus

    1. RAVINDER KAUR & ANR. R/O H No. 558, Sector-36-B

    CHANDIGARH

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 432 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 16/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001 ...........Appellant(s) Versus

    1. SAT PAUL BANSAL & ANR. R/o. H No. 749, Sector-8-B, Chandigarh

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 433 OF 2011

    (Against the Order dated 18/08/2011 in Complaint No. 18/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI-110001 ...........Appellant(s)

    23

    Versus

    1. APURVA GOSWAMY & ANR. Son of Mr. B.N. Goswamy, R/o House No. 171, Sector-19-A, Chandigarh

    2. CHANDIGARH HOUSING BOARD

    - ...........Respondent(s)

    FIRST APPEAL NO. 434 OF 2011

    (Against the Order dated 26/08/2011 in Complaint No. 27/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. 6th Floor, Arunachal Building, 19, Barakhambha Road, NEW DELHI ...........Appellant(s)

    Versus

    1. BALWANT LAKHBIR SINGH & ORS. S/o Sh. Balwant Singh Randhawa, R/o 5A, Row House Surya Vihar,

    Dundahera

    Guragaon-122016

    2. MRS RIPU SINGH.

    W/o Sh. Balwant Lakhbir Singh, R/o 5A, Roaw House Surya Vihar, Dundahera,

    Guragaon-122016

    3. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector 9-B, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 441 OF 2011

    (Against the Order dated 21/09/2011 in Complaint No. 21/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LIMITED 6th Floor, Arunachal Building, 19, Barakhmbha Road, NEW DELHI-110001 ...........Appellant(s) Versus

    1. RANJIT SINGH & ORS. R/O House No. 2090, Sector-15-C,

    CHANDIGARH

    2. MANJIT KAUR

    W/o. Sh. Ranjit Singh, R/O House No. 2090, Sector 15-C,

    CHANDIGARH

    3. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 442 OF 2011

    (Against the Order dated 22/09/2011 in Complaint No. 38/2011 of the State Commission Chandigarh)

    1. M/S. PARVNATH DEVELOPERS LIMITED 6th, Floor, Arunachal Building, 19, Barakhambha Road, ...........Appellant(s)

    24

    NEW DELHI-110001 Versus

    1. MR. INDER KUMAR ARORA & ANR. S/o. Shri Parmanand, R/o L-88, Lajpat Nagar-II,

    NEW DELHI

    2. THE PRINCIPAL OFFICER/ESTATE OFFICER Chandigarh Housing Board, 8, Jan Marg, Sector-9B, CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 443 OF 2011

    (Against the Order dated 20/09/2011 in Complaint No. 43/2011 of the State Commission Chandigarh)

    1. M/S. PARVNATH DEVELOPERS LIMITED 6th Floor, Arunachal Building, NEW DELHI-110001 ...........Appellant(s) Versus

    1. MS. CHANCHAL SONI & ANR. W/o. Shri Lalit Soni, H No. 330, Sector-4, Mansa Devi Comlex, (through Shri Vijay Anannd)General Power of Attorney)

    Panchkula-134 174

    2. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector -9, Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 447 OF 2011

    (Against the Order dated 21/09/2011 in Complaint No. 21/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    office at 8, Jan Marg, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. RANJIT SINGH & ANR. R/o H No. 2090, Sector-15-C, Chandigarh

    2. MANJIT KAUR

    W/o Sh. Ranjit Singh, R/o H No. 2090, Sector-15-C, Chandigarh

    3. M/S. PARSVNATH DEVELOPERS LIMITED Registered &Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI-110001

    4. tTHE MANAGER, M/s Parsvnath Developers Limited, SCO No. 1, First Floor, Madhya Marg, Sector-26,

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 448 OF 2011

    25

    (Against the Order dated 21/09/2011 in Complaint No. 22/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9, through its Chairman Chandigarh ...........Appellant(s) Versus

    1. BALDEV SINGH & ORS. R/o House No. 2090, Sector-15-C, Chandigarh

    2. M/S. PARSVNATH DEVELOPERS LTD. - ...........Respondent(s)

    FIRST APPEAL NO. 449 OF 2011

    (Against the Order dated 22/09/2011 in Complaint No. 38/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    office at 8, Jan Marg, Sector-9-B, Chandigarh ...........Appellant(s) Versus

    1. INDER KUMAR ARORA & ANR. S/o Sh. Parmanand, Resident of L-88, Lajpat Nagar-II, NEW DELHI-

    2. M/S. PARSVNATH DEVELOPERS LIMITED SCO No. 1, First Floor, Madhya Marg, Sector-26, through its Managing Director/Pricipal Officer

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 450 OF 2011

    (Against the Order dated 20/09/2011 in Complaint No. 43/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9 Chandigarh ...........Appellant(s) Versus

    1. MS. CHANCHAL SONI & ORS. W/o Lalit Soni, through Vijay Anand, General Power of Attorney, H No. 330, Sector-4, Mansa Devi Complex, Panchkula-134174

    2. M/S. PARSVNATH DEVELOPERS LIMITED through its Managing Director, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    New Delhi - 110 001

    3. THE MANAGER

    Parsvnath Pride Asia, Chandigarh, SCO No. 1, first Floor, Sector-26, Madhya Marg,

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 477 OF 2011

    (Against the Order dated 12/10/2011 in Complaint No. 45/2011 of the State Commission Chandigarh)

    26

    1. CHANDIGARH HOUSING BOARD

    8, Jan Marg, Sector-9-D, (through its Chairman) Chandigarh-160009 ...........Appellant(s) Versus

    1. SANDEEP SINGH & ORS. S/o Sardar Harjit Singh, IPS, R/o H No. 714, Sector-11-B, Chandigarh-160011

    2. BHAVABDEEP SINGH

    W/o Sandeep Singh, S/o Sardar Harjit Singh, IPS, R/o H No. 714, Sector-11-B,

    Chandigarh

    3. PARSVNATH DEVELOPERS LTD.,

    through its Managing Director SCO No. 1st Floor, Sector-26, Madhya Marg,

    Chandigarh

    4. THE MANAGING DIRECTOR,

    Parsvnath Developers Ltd, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI-1100001 ...........Respondent(s)

    FIRST APPEAL NO. 48 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 24/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. ABHINAV SHARMA & ANR. R/O:37-B,ASHOK NAGAR ,AMBALLA CANTT

    CHANDIGARH

    CHANDIGARH-133001

    2. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR -9,

    CHANDIGARH

    CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 486 OF 2011

    (Against the Order dated 12/10/2011 in Complaint No. 45/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. SCO No. 1, First Floor, Madhya Marg, Sector-26, Chandigarh - 160 026 ...........Appellant(s) Versus

    1. SANDEEP SINGH & ORS. S/o. Sardae Harjit Singh, IPS, Director General of Police (RETD), Punjab, R/o. H No. 714, Sector 11-B, Chandigarh - 160 011 ...........Respondent(s)

    27

    2. MRS. BHAVANDEEP SINGH,

    W/o. Sandeep Singh, R/o H No. 714, Sector-11-B, Chandigarh-160011

    3. THE CHAIRMAN

    Chandigarh Housing Board, 8, Jan Marg, Sector-9, Chandigarh-160009

    FIRST APPEAL NO. 49 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 27/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT : PASARVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI-110032 ...........Appellant(s) Versus

    1. VIJAY AGGARWAL & ORS.

    CHANDIGARH HOUSING BOARD,8,JAN

    MARG,SECTOR-9,

    CHANDIGARH

    CHANDIGARH

    2. Vijay Aggarwal S/o: Major R.Sahai , ressidento f HNo. 854, Sector 15A, Faridabad

    Uttar Pardesh

    3. MONA AGGARWAL

    W/o. Shri Vijay Aggarwal, Resident of H.No. 854, Sector 15A Faridabad

    Chandigarh

    4. Vijay Aggarwal S/o: Major R.Sahai , ressidento f HNo. 854, Sector 15A, Faridabad

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 50 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 29/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. SUDEEP BUDHIRAJ HUF & ANR.

    SHRI SUDEEP BUDHIRAJ HUF THROUGH ITS KARTA

    SUDEEP BUDHIRAJ R/O HOUSE NO.12,SECTOR -2,

    CHANDIGARH

    CHANDIGARH

    2. CHANDIGARH HOUSING BOARD

    8, JAN MARG, SECTOR -9, ...........Respondent(s)

    28

    CHANDIGARH

    CHANDIGARH

    FIRST APPEAL NO. 51 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 37/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. BAIJNATH AGARWALA & SONS (HUF) & ANR. 140/4B N.S.C BOSE ROAD ,TOLLYGUENGE ,

    KOLKATA

    WEST BENGAL -700040

    2. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR -9,

    CHANDIGARH

    CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 517 OF 2011

    (Against the Order dated 08/11/2011 in Complaint No. 11/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Office at 8, Jan Marg, Sector-9, Chandigarh ...........Appellant(s) Versus

    1. PERMINDER WALIA & ORS. W/o Gurbachan Singh Walia,H No. 1033, Sector-69, Mohali

    2. M/S PARSVNATH DEVELOPERS LIMITED, through its Director, SCO No. 1, 1st Floor, Sector-26, Madhya Marg,

    Chandigarh

    3. THE DIRECTOR,

    M/S. PARSVNATH DEVELOPERS LIMITED, Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI-110001 ...........Respondent(s)

    FIRST APPEAL NO. 52 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 38/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. M/S. UAL INDUSTRIES LTD. & ANR. ...........Respondent(s)

    29

    CORPORATE OFFICE ,KOMARK -MANI UDAY ,

    KOLKATA

    WEST BENGAL -700019

    2. CHANDIGARH HOUSING BOARD

    THROUGH THE CHAIRMAN 8,JAN MARG ,SECTOR -9

    CHANDIGARH

    CHANDIGARH

    FIRST APPEAL NO. 528 OF 2011

    (Against the Order dated 17/11/2011 in Complaint No. 72/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Principal Officer, office at 8, Jan Marg, Sector-9, Chandigargh ...........Appellant(s)

    Versus

    1. SANTOSH SINGH TAKHAR & ANR. S/o Sh. Bakhtawar Singh Takhar, R/o House No. 114, Sector- 28-A,

    Chandigarh

    2. M/S PARSVNATH DEVELOPERS LIMITED, Registered & Corporate Office, 6th Floor, Arunachal Building, 19, Barakhambha Road,

    NEW DELHI

    3. MR. KARANVIR SINGH SIBIA

    S/o. Late Sh. Gurbaksh Singh Sibia, R/o. House No. 114, Sector - 28 A

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 529 OF 2011

    (Against the Order dated 09/11/2011 in Complaint No. 51/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through its Chairman, Office at 8, Jan Marg, Sector-9, Chandigarh ...........Appellant(s)

    Versus

    1. HARINDER SINGH & ANR. R/o H No. 289, Sector-10, Panchkula

    Haryana

    2. PARSVNATH DEVELOPERS LTD.

    Managing Director, SCO No. 1, First Floor, Sector-26, Madhya Marg,

    Chandigarh ...........Respondent(s)

    FIRST APPEAL NO. 53 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 39/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Regd office at :Parsavnath Metro Tower, Near Shahdara Metro ...........Appellant(s)

    30

    Station, Shahdara New Delhi

    Versus

    1. PALO SINGH

    Through its POA Holders Shri Daljit Singh R/o:H.No.541, sector 8-B

    Chandigarh

    chandigarh

    2. CHANDIGARH HOUSING BOARD

    - ...........Respondent(s)

    FIRST APPEAL NO. 54 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 40/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. AJMER SINGH JOHAL

    THROUGH P.O.A HOLDER SH.NIRMAL SINGH S/O CHARAN SINGH R/O:COALBIUM COTTAGE

    ,WHITWICK ROAD ,PRESENTLY RESIDING AT

    VILLAGE BARODA KALA ,

    NAWANSAHAR

    PUNJAB ...........Respondent(s)

    FIRST APPEAL NO. 55 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 41/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. NIRMAL SINGH & ANR.

    RESIDING AT VILLAGE BARNALA KALA

    NAWANSHAHER

    PUNJAB

    2. CHANDIGARH HOUSING BOARD

    8, JAN MARG, SECTOR -9,

    CHANDIGARH

    CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 56 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 42/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT:PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA ...........Appellant(s)

    31

    NEW DELHI -110032 Versus

    1. HARBHAJAN SINGH BRAICH & ORS. S/O. SHRI HARNAM SINGH, SMT MOHINDER KAUR BRAICH, W/O. SHRI HARBHAJAN SINGH ,SMT LOVALEEN KAUR RAIR ,W/O SHRI JAGBINDER RAIR ,ALL RESIDING AT :J-25,SOUTH CITY -I

    GURGAON

    HARYANA ...........Respondent(s)

    FIRST APPEAL NO. 57 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 44/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. Regd office at :Parsavnath Metro Tower, Near Shahdara Metro station ,Shahdara

    New Delhi-110032 ...........Appellant(s)

    Versus

    1. KANWALJIT SINGH DHILLON & ANR. residing at :Village Barnala Kala, Nawanshahar

    punjab

    2. CHANDIGARH HOUSING BOARD

    - ...........Respondent(s)

    FIRST APPEAL NO. 58 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 45/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT :PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    DELHI -110032 ...........Appellant(s) Versus

    1. GURJEET SINGH JOHAR & ANR.

    11,CLUB DRIVE ,MG ROAD

    NEW DELHI

    2. CHANDIGARH HOUSING BOARD

    8, JAN MARG, SECTOR 9-B

    CHANDIGARH

    CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 59 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 46/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD.

    REGD OFFICE AT : PARSAVNATH METRO TOWER

    ,NEAR SHAHDARA METRO STATION ,SHAHDARA

    NEW DELHI -110032 ...........Appellant(s) Versus

    1. HARPAL SINGH BRAR & ORS. ...........Respondent(s)

    32

    R/O :5,JANTAR MANTAR ROAD ,

    NEW DELHI

    2. DR.RANJIT SINGH BRAR

    R/O:5,JANTAR MANTAR ROAD

    NEW DELHI

    3. CHANDIGARH HOUSING BOARD

    8, JAN MARG, SECTOR -9,

    CHANDIGARH

    CHANDIGARH

    FIRST APPEAL NO. 63 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 24/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAM MARG, SECTOR/9-D CHANDIGARH - 160009 CHANDIGARH ...........Appellant(s) Versus

    1. ABHINAV SHARMA & ANR. MR. ABHINAV SHARMA,R/o:37/B, ASHOK NAGAR,

    AMBALLA CANTT,

    AMBALA

    PUNJAB - 133001

    2. M/S. PARSAVNATH DEVELOPERS LIMITED

    COMPANY

    INCORPORATED UNDER THE PROIVISIONS OF THE

    COMPANIES ACT 1956,REGISTERED OFFICE AT 6TH

    FLOOR ,ARUNACHAL BUILDING 19,BARAKHAMBA

    ROAD ,

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 64 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 27/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D CHANDIGARH - 160009 CHANDIGARH ...........Appellant(s) Versus

    1. VIJAY AGGARWAL & ORS. R/O:H.NO.854,SECTOR 15-A

    FARIDABAD

    HARYANA

    2. MRS. MONA AGGARWAL

    R/O : H.MP:854, SECTOR 15A

    FARIDABAD

    HARYANA

    3. M/S. PARSAVNATH DEVELOPERS LIMITED ...........Respondent(s)

    33

    REGISTERED OFFICE AT :6TH FLOOR ,ARUNACHAL

    BUILDING ,29, BARAKHAMBA ROAD

    NEW DELHI -110001

    FIRST APPEAL NO. 65 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 27/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D CHANDIGARH -160009

    CHANDIGARH ...........Appellant(s) Versus

    1. SUDEEP BUDHIRAJA HUF

    HOUSE NO .12, SECTOR 2,

    CHANDIGARH

    CHANDIGARH

    2. PARSAVNATH DEVELOPERS LIMITED

    REGISTERED AND CORPORATED OFFICE AT 6TH

    FLOOR ,ARUNACHAL BUILDING 29,BARAKHAMBA

    ROAD

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 66 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 37/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D

    CHANDIGARH

    CHANDIGARH-160009 ...........Appellant(s) Versus

    1. BAIJNATH AGARWALA & SONS (HUF) & ORS. 140/4B ,N.S.C.BOSE ROAD ,TOLLYGUNE

    KOLKATA

    WEST BENGAL -700040

    2. M/S. PARSAVNATH DEVELOPERS LIMITED THROUGH ITS DIRECTOR SCO 1, 1ST FLOOR ,SECTOR -

    26,MADHYA MARG

    CHANDIGARH

    CHANDIGARH

    3. THE DIRECTOR ,PARSAVNATH DEVELOPERS

    LIMITED

    REGISTERED AND CORPORATED OFFICE AT 6TH

    FLOOR ARUNACHAL BUILDING 19, BARAKHAMBA

    ROAD

    NEW DELHI ...........Respondent(s)

    FIRST APPEAL NO. 67 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 38/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD ...........Appellant(s)

    34

    8,JAN MARG , SECTOR /9 -D

    CHANDIGARH

    CHANDIGARH -160009 Versus

    1. UAL INDUSTRIES LTD. & ORS. CORPORATE OFFICE AT KOMARK -MANI UDAY

    ,16,MAYFAIR ROAD ,

    KOLKATA

    WEST BENGAL -700019

    2. PARSAVMATH DEVELOPERS LIMITED

    THROUGH ITS DIRECTOR ,SCO 1,1ST FLOOR ,SECTOR -

    26 ,MADHYA MARG

    CHANDIGARH

    CHANDIGARH

    3. THE MANAGING DIRECTOR ,PASARAVNATH

    DEVELOPERS LIMITED ,

    REGISTERED OFFICE AT 6TH FLOOR ,ARUNACHAL

    BUILDING 19 , BARAKHAMBA ROAD

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 68 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 39/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    R/O: 8 JAN MARG ,SECTOR /9-D

    CHANDIGARH

    CHANDIGARH ...........Appellant(s) Versus

    1. PALO SINGH & ORS.

    THROUGH ITS POWER OF ATTORNEY HOLDERS SH .

    DALJIT SINGH R/O :H.NO:541,SECTOR -8-B

    CHANDIGARH

    CHANDIGARH

    2. PARSAVNATH DEVELOPERS LIMITED

    THROUGH ITS DIRECTOR SCO 1,1ST FLOOR ,SECTOR -

    26,MADHYA MARG ,

    CHANDIGARH

    CHANDIGARH

    3. THE DIRECTOR PASARVANATH DEVELOPERS

    LIMITED ,

    REGISTERED &CORPORATE OFFICE :6 TH FLOOR

    ARUNACHAL BUILDING 19,BARAKHAMBA ROAD

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 69 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 40/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D ...........Appellant(s)

    35

    CHANDIGARH-160009

    CHANDIGARH

    Versus

    1. AJMER SINGH JOHAL & ORS. THROUGH ITS POWER OF ATTORNEY HOLDER R/O

    :COALBOURN COTTAGE ,WHITEWICK ROAD ,MARK

    FIELD QB ,U.K. LEICESTER , LE

    2. PASARVANATH DEVELOPERS LIMITED ,THROUGH

    ITS DIRECTOR

    SCO 1 ,1ST FLOOR ,SECTOR -26, MADHYA MARG ,

    CHANDIGARH

    3. THE DIRECTOR ,PASARVANATH DEVELOPERS

    LIMITED

    REGISTERED AND CORPORATE OFFICE AT 6 TH

    FLOOR ARUNACHAL BUILDING 19, BARAKHAMBA

    ROAD ,

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 70 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 41/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D ,

    CHANDIGARH

    CHANDIGARH-160009 ...........Appellant(s) Versus

    1. NIRMAL SINGH & ORS. R/O :COALBOURN COTTAGE WHITWICK ROAD ,MARK

    FIELD ,LEICESTER ,LE 679 QB,

    UNITED KINGDOM

    2. PARSAVNATH DEVELOPERS LIMITED

    THROUGH ITS DIRECTOR SCO-1 ,1 ST FLOOR ,SECTOR -26 ,MADHYA MARG

    CHANDIGARH

    CHANDIGARH

    3. THE DIRECTOR ,PASARVNATH DEVELOPERS

    LIMITED

    REGISTERED CORPORATE OFFICE AT :6 TH FLOOR

    ARUNACHAL BUILDING 10,KHAMA ROAD

    NEW DELHI ...........Respondent(s)

    FIRST APPEAL NO. 71 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 42/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,jan marg ,sector /9-D chandigarh

    chandigarh ...........Appellant(s) Versus

    36

    1. HARBHAJAN SINGH BRAICH & ORS. R/O :J 25,SOUTH CITY -1,

    GURGAON

    2. M/S LOVALEEN KAUR BARAICH MRS MOHINDER

    KAUR BAIRACH ,MR .LOVALEEN KAUR BAIRACH

    R/O :J25,SOUTH CITY -1,

    GURGAON

    GURGAON

    3. PARSAVNATH DEVELOPERS LIMITED

    SCO1,1ST FLOOR ,SECTOR -26,,MADHYA MARG

    CHANDIGARH

    CHANDIGARH ...........Respondent(s)

    FIRST APPEAL NO. 72 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 44/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JANMARG ,SECTOR /9-D CHANDIGARH -160009

    CHANDIGARH ...........Appellant(s) Versus

    1. KANWALJIT SINGH DHILLON & ORS. R/O :R/O :32,DUNELLAN ROAD ,MILNHSVIE GLASGOW

    G627RE ,

    UNITED KINGDOM

    2. MR.NIRMAL SINGH

    R/O COALBOURN COTTAGE ,WHITEWICK ROAD

    ,MARK FIELD LEICESTER ,LE 679 QB

    UNITED KINGDOM

    3. PARSAVNATH DEVELOPERS LIMITED

    THROUGH ITS DIRECTOR ,SCO 1,1ST FLOOR ,SECTOR -

    26,MADHYA MARG

    CHANDIGARH

    4. THE MANAGING DIRECTOR , PASARVNATH

    DEVELOPERS LIMITED ,

    REGISTERED &CORPORATE OFFICE ,6TH FLOOR

    ARUNACHAL BUILDING 19,BARAKHAMBA ROAD

    NEW DELHI -110001 ...........Respondent(s)

    FIRST APPEAL NO. 73 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 45/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, JAN MARG ,SECTOR /9-D

    CHANDIGARH

    CHANDIGARH-160009 ...........Appellant(s) Versus

    1. GURJEET SINGH JOHAR & ORS. R/O#11,CLUB DRIVE ,M.G.ROAD GHITORONI ...........Respondent(s)

    37

    NEW DELHI -110030

    2. MRS. SUMEET JOHAR

    R/O #11,CLUB DRIVE ,M.G.ROAD ,GHITRONI NEW DELHI -110030

    3. M/S PARSAVNATH DEVELOPERS LIMITED

    6TH FLOOR ARUNACHAL BUILDING 19,

    BARAKHAMBA ROAD

    NEW DELHI

    FIRST APPEAL NO. 74 OF 2011

    (Against the Order dated 27/10/2010 in Complaint No. 46/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8,JAN MARG ,SECTOR /9-D,

    CHANDIGARH

    CAHNDIGARH ...........Appellant(s) Versus

    1. HARPAL SINGH BRAR & ORS. R/O :5,JANTA MANTAR ROAD , NEW DELHI -

    2. PASARVNATH DEVELOPERS LIMITED

    THROUGH ITS DIRECTOR ,SCO 1,1ST FLOOR SECTOR -

    26 ,MADHYA MARG

    CHANDIGARH

    3. RANJIT SINGH

    R/O 5,JANTAR MANTAR ROAD

    NEW DELHI

    4. THE MANAGING DIRECTOR ,PARSAVNATH

    DEVELOPERS LIMITED

    REGISTERED &CORPORATE OFFICE ,6TH FLOOR

    ARUNACHAL BUILDING 19,BARAKHAMBA ROAD ,

    NEW DELHI -110001 ...........Respondent(s)

    REVISION PETITION NO. 1358 OF 2011

    (Against the Order dated 30/09/2010 in Appeal No. 178/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Through it's Secretary, 8 Jan Marg, Sector 9-D Chandigarh ...........Petitioner(s) Versus

    1. SUDHIR SAGAR & ORS. House No. 143, Sector 8-A Chandigarh - 160008

    2. MRS. ARCHANA SAGAR, W/O. MR. SUDHIR SAGAR House No. 143, Sector 8-A

    Chandigarh - 160008

    3. PARSVNATH DEVELOPERS LTD.

    Through Branch Manager, SCO No. 1, 1st Floor, Madhya Marg ...........Respondent(s)

    38

    Chandigarh

    REVISION PETITION NO. 1359 OF 2011

    (Against the Order dated 30/09/2010 in Appeal No. 228/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through it's Secretary, 8 Jan Marg, Sector 9-D Chandigarh ...........Petitioner(s) Versus

    1. SATYA ESTATES & ANR. Through Smt. Satya Jain, Proprietor,]SCO 371-372, Second Floor, Atam Chambers, Sector 35-B

    Chandigarh

    2. PARSVNATH DEVELOPERS LTD.

    Through Branch Manager, SCO No. 1, 1st Floor, Madhya Marg Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 1360 OF 2011

    (Against the Order dated 19/11/2010 in Appeal No. 377/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Through it's Secretary, 8 Jan Marg, Sector 9-D Chandigarh ...........Petitioner(s) Versus

    1. VINOD KATHURIA & ORS. Residents of Old Vicarage Ellenhall, Staffford, Ellenhall, Stafford

    England - ST261JQ

    2. PARSVNATH DEVELOPERS LTD.

    Through Branch Manager, SCO No. 1, 1st Floor, Madhya Marg Chandigarh

    3. MS. ANURADHA KATHURA, W/O. SH. VINOD

    KATHURA

    Residents of Old Vecarage Ellenhall, Stafford England - ST261JQ

    4. PARSVNATH DEVELOPERS LTD.

    Through Branch Manager, SCO No. 1, 1st Floor, Madhya Marg Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3546 OF 2011

    (Against the Order dated 04/08/2011 in Appeal No. 460/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Sector-9D, Through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. CHETAN MITTAL & ORS. S/o Sh Rajinder Kumar Mittal, R/o House No- 235, Sector-21A ...........Respondent(s)

    39

    Chandigarh Chandigarh

    2. Monica Mittal, W/o Shri Chetan Mittal House No-235, Sector-21A

    Chandigarh

    Chandigarh

    3. M/s. Parsvnath Developers Ltd. SCO-1 Madhya Marg, Sector-26, Through its Principal Officer Chandigarh

    Chandigarh

    REVISION PETITION NO. 3547 OF 2011

    (Against the Order dated 25/07/2011 in Appeal No. 462/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Sector-9D, Through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. MUKESH MITTAL & ORS. S/o Sh Rajinder Kumar Mittal, R/o House No-1526, Sector-

    18D

    Chandigarh Chandigarh

    2. Alka Mittal, W/o Shri Mukhesh Mittal R/o House No -1526, Sector-18D Chandigarh

    Chandigarh

    3. M/s. Parsvnath Developers Ltd.. through its Director SCO No-1, Ist Floor Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3567 OF 2011

    (Against the Order dated 25/07/2011 in Appeal No. 437/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Sector-9D, through its Secreatry, Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. AMIT CHOPRA & ANR. S/o Sh. R.K Chopra, 555 Sectro - 18B Chandigarh

    Chandigarh

    2. PARSVNATH DEVELOPERS LTD.

    - ...........Respondent(s)

    REVISION PETITION NO. 3580 OF 2011

    40

    (Against the Order dated 20/07/2011 in Appeal No. 187/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. Through its Director, SCo No.1 First Floor,Madhya Marg, Sector- 26

    Chandigarh

    Chandigarh

    2. The Director, M/S Parsvnath Developers Ltd., 6th floor, Aruncahal building, 19, Barakhamba Road, New delhi - 110001

    Delhi ...........Petitioner(s)

    Versus

    1. SANDEEP CHANANA & ANR. S/o Late Shri Prakash Chand, House No-825, Sector-8 Panchkula

    Haryana

    2. The Chairman/ Principal Officer Chandigarh Housing Board, 8 Jan marg, Sector-9B Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3581 OF 2011

    (Against the Order dated 25/07/2011 in Appeal No. 430/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. Through its Director, SCo No.1 First Floor,Madhya Marg, Sector- 26

    Chandigarh

    Chandigarh

    2. The Director, M/S Parsvnath Developers Ltd., 6th floor, Aruncahal building, 19, Barakhamba Road, New Delhi - 110001

    Delhi ...........Petitioner(s)

    Versus

    1. AMIT CHOPRA & ANR. S/o Shri R.K Chopra, 555, Sector-18B Chandigarh

    Chandigarh

    2. Chandigarh Housing Board 8,jan Marg, Sector - 9 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3607 OF 2011

    (Against the Order dated 25/07/2011 in Appeal No. 423/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. Through its Director, SCI No-1, First Floor,Sector-26 ...........Petitioner(s)

    41

    Chandigarh Chandigarh

    2. The Director,, M/s Parsvnath Developers Ltd.., 6th Floor,Arunachal Building,19 Barakhamba Road, New Delhi - 110001

    Delhi

    Versus

    1. MUKESH MITTAL & ORS. S/o Shri Rajinder Kumar Mittal, R/o House No-1526, Sector018D

    Chandigarh

    Chandigarh

    2. Mrs Alka Mittal, W/o Shri Mukesh Mittal House No-1526, Sector-18D

    Chandigarh

    Chandigarh

    3. The Chairaman, Chandigarh Housing Board 8, Jan Marg, Sector-9

    Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3608 OF 2011

    (Against the Order dated 19/07/2011 in Appeal No. 424/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th Floor,Arunachal Building,19 Barakhamba Road, New Delhi - 110001

    Delhi

    2. The Manager, M/s Parsvnath Developers Ltd.., SCo-1 first floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. DALJIT SINGH BRAR & ORS. S/o Shri Bhajan Singh, R/o H.No-18, Sector-2 Chandiagrh

    Chandiagrh

    2. Smt Narinder Kaur, W/o Shri Daljit Singh Brar, R/o H.No-18, Sector-2

    Chandigarh

    Chandigarh

    3. Smt Narinder Kaur, W/o Shri Daljit Singh Brar, R/o H.No-18, Sector-2

    Chandigarh

    Chandigarh

    4. Chandigarh Housing Board, 8,Jan Marg, Sector-9 ...........Respondent(s)

    42

    Chandigarh Chandigarh

    REVISION PETITION NO. 3620 OF 2011

    (Against the Order dated 19/07/2011 in Appeal No. 461/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Sector-9D, through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. DALJIT SINGH BRAR & ORS. S/o Sh Bhajan Singh, R/o H.No-18, Sector-2 Chandigarh

    Chandigarh

    2. Smt Narinder Kaur, W/o Daljit Singh Brar R/o H.No-18, Sector-2

    Chandigarh

    Chandigarh

    3. Parsvnath Developers Ltd., Through its Director SCO-1, 1st floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh

    4. Parsvnath Developers Ltd.. Through its Director, SCO-1, 1st floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3621 OF 2011

    (Against the Order dated 28/07/2011 in Appeal No. 59/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSE BOARD

    Sector-9D, through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. ROHIT HARMESH GHANARA & ORS. S/o. Col harmesh Ghanara, R/o House No-G-101, Army Flats, Sector-4 mansa Devi Complex

    Panchkula

    Haryana - 134109

    2. Veena Ghanara , W/o Col Harmesh Ghanara R/o House No-G-101, Army Flats, Sector-4, Mansa Devi Complex

    Panchkula

    Haryana - 134109

    3. Parsnath Developers Ltd. Through its Director, SCO-1, 1st floor, madhya Marg, sector - ...........Respondent(s)

    43

    26

    Chandigarh Chandigarh

    REVISION PETITION NO. 3625 OF 2011

    (Against the Order dated 28/07/2011 in Appeal No. 60/2011 of the State Commission Chandigarh)

    1. CHANDIGAH HOUSE BOARD

    Sector-9D , through its Secretary, Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. SANJAY GUPTA & ANR. S/o Sh. J.P Gupta, R/o F-4, South City-1,Near Unitech Country Club

    Gurgoan

    Haryana

    2. Parsvanth Developers Ltd. through its Director, SCO No-1, first floor, Madhya Marg, Sector - 26

    Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3640 OF 2011

    (Against the Order dated 28/07/2011 in Appeal No. 45/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th floor, Arunachal Building, 19, Barakhamba Road, New Delhi

    Delhi

    2. The Manager, M/s Parsvnath Developers Ltd.. SCo-1 First floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. SANJAY GUPTA & ANR. S/o Shri J.P Gupta, R/o F-4, South City-1, Near Unitech Country Club

    Gurgoan

    Haryana

    2. Chandigarh Hosing Board,

    8 Jan Marg, Sector-9 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3641 OF 2011

    (Against the Order dated 28/07/2011 in Appeal No. 46/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. ...........Petitioner(s)

    6th floor, Arunachal Building, 19, Barakhamba Road, New Delhi

    Delhi

    2. The Manager, M/s Parsvnath Developers Ltd.. SCo-1 First floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh

    Versus

    1. ROHIT HARMESH GHANARA & ORS. S/o Col Harmesh Ghanara, R/o No-101, Army Flats, Sector- 4,Mansa Devi Complex

    Panchkula - 134109

    Haryana

    2. Smt. Veena Ghanara, W/o Col Harmesh Ghanara R/o. H.No-G-101 Army flats, Sector-4, Mansa Devi Complex Panchkula - 134 109

    Haryana

    3. Chandigarh Hosing Board,

    8 Jan Marg, Sector-9 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3690 OF 2011

    (Against the Order dated 04/08/2011 in Appeal No. 425/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th floor Arunchal Building, 19 Barakhamba Road New Delhi

    Delhi

    2. The Manager, M/s Parsvnath Developers Ltd.., SCO-1 First Floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. CHETAN MITTAL & ORS. S/o Shri Rajinder Kumar Mittal, R/o House No -235 Sector- 21/A

    Chandigarh

    Chandigarh

    2. Mrs Monica Mittal, W/o Shri Chetan Mittal, House No- 235 Sector-21A

    Chandigarh

    Chandigarh

    3. The Chairaman, Chandigarh Housing Board 8, Jan Marg Sector-9

    Chandigarh

    Chandigarh ...........Respondent(s)

    45

    REVISION PETITION NO. 3691 OF 2011

    (Against the Order dated 24/08/2011 in Appeal No. 431/2010 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. Through its Director, SCO-1 First Floor, Madhya Marg, Sector-

    26

    Chandigarh Chandigarh

    2. The Director, M/s Parsvnath Developers Ltd, 6th floor, Arunachal Building, 19 Barakhamba Road, New Delhi - 110001

    Delhi ...........Petitioner(s)

    Versus

    1. UMED SINGH LAMBA & ANR. S/o Dhri Ram Singh Lamba, R/o VPO Daulatpur, Hissar

    Haryana

    2. The Chairaman, The Chandigarh Housing Board,

    8 Jan Marg, Sector-9 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3692 OF 2011

    (Against the Order dated 02/08/2011 in Appeal No. 129/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th floor Arunchal Building, 19 Barakhamba Road New Delhi

    Delhi

    2. The Manager, M/s Parsvnath Developers Ltd.., SCO-1 First Floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. JASWANT SINGH SANGHERA & ORS. S/o Shri Mohinder Singh, R/o 39 Chigwell Rise, Chingwell Area

    Essex

    U.K

    2. Amrjit Kaur, W/o Shri Jaswant Singh Sanghera (NRI) 39, Chugwell Rise, Chigwell Area

    Essex

    U.K

    3. The Chairaman, Chandigarh Housing Board 8, Jan Marg Sector-9

    Chandigarh

    Chandigarh ...........Respondent(s)

    46

    REVISION PETITION NO. 3701 OF 2011

    (Against the Order dated 02/08/2011 in Appeal No. 114/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9D, Through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. JASWANT SINGH & ORS. S/o Modinder Singh, R/o 39 Chigwell Rise, Chigwell Area Essex

    U.K.

    2. Amarjit kaur,W/o Jaswant Singh Sanghera ( NRI) S/o Mohinder Singh

    39 Chighwell Rise,Chighwell Area Essex

    U.K.

    3. Parsvnath Developers Ltd., Through its Director SCO-1, 1st Floor , Madhya marg, Sector-26, Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3727 OF 2011

    (Against the Order dated 20/09/2011 in Appeal No. 2/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    8, jan Marg, Sector-9D, Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. DEVINDER SINGH MARWAH & ORS. S/o Late balwant Singh, R/o 10 Kumerland Avenue, Goring By sea, Worthing,

    West Sussex

    England

    2. Mrs Balwinder Kaur Marwaha, W/o Devinder Singh Marwaha

    R/o 10 Kumberland Avenue, Goring by sea, Worthing, West Sussex

    England

    3. Parsvnath Developers Ltd Regd & Corporate office., 6th floor Arunachal Building, 19 Barakhamba Road New Delhi

    Delhi

    4. the Director, Parsvnath Developers Ltd.., SCO No-1,1st floor, Madhya Marg, Sector-26, Chandigarh ...........Respondent(s)

    47

    Chandigarh

    REVISION PETITION NO. 3728 OF 2011

    (Against the Order dated 24/08/2011 in Appeal No. 436/2010 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9D, Through its Secreatry Chandigarh

    Chandigarh

    2. M/s Parsvnath Developers Ltd., through its Director, SCo No-1, 1st floor Madhya Marg, Sector-

    26

    Chandigarh Chandigarh ...........Petitioner(s) Versus

    1. UMED SINGH LAMBA & ANR. S/o Shri Ram Singh lamba, R/o VPO Daulatpur Hissar

    Haryana

    2. PARSVNATH DEVELOPERS LTD.

    - ...........Respondent(s)

    REVISION PETITION NO. 3729 OF 2011

    (Against the Order dated 09/09/2011 in Appeal No. 105/2011 of the State Commission Chandigarh)

    1. CHANDIGARH HOUSING BOARD

    Sector-9D, through its Secretary Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. KATAR SINGH & ORS. S/o Sh Gyan Singh Rai, R/o House No-514, Sector-8B Chandigarh

    Chandigarh

    2. Kanwar Inder Singh Rai, S/o Inder Dev Singh Rai, House No-514, Sector-8-B

    Chandigarh

    Chandigarh

    3. Parsvnath Developers Ltd through its Director, SCO-1 1st Floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3826 OF 2011

    (Against the Order dated 20/09/2011 in Appeal No. 02/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th floor Arunchal Building, 19 Barakhamba Road, through its Director ...........Petitioner(s)

    48

    New Delhi Delhi

    2. The Manager, M/s Parsavnath Developers Ltd.., SCo-1, First floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh

    Versus

    1. DEVINDER SINGH MARWAH & ORS. S/o Late balwant Singh, R/o 10 Kumberland Avenue, Goring By Sea, Worthing,

    West - Sussex

    England

    2. Smt Balwinder kaur Marwah, W/o Devinder Singh Marwah R/o 10 Kumberland Avenue, Goring By Sea, Worthing, West - Sussex

    England

    3. Chandigarh Housing Board,

    8 Jan Marg, Sector-9 Chandigarh

    Chandigarh ...........Respondent(s)

    REVISION PETITION NO. 3827 OF 2011

    (Against the Order dated 09/09/2011 in Appeal No. 128/2011 of the State Commission Chandigarh)

    1. M/S. PARSVNATH DEVELOPERS LTD. & ANR. 6th floor Arunchal Building, 19 Barakhamba Road, through its Director

    New Delhi

    Delhi

    2. The Director, M/s Parsvnath Developers Ltd,, SCO-1 First Floor, Madhya Marg, Sector-26 Chandigarh

    Chandigarh ...........Petitioner(s) Versus

    1. KARTAR SINGH RAI & ORS. S/o Shri Gyan Singh Rai, R/o House No-514, Sector-8-B Chandigarh

    Chandigarh

    2. Kanwar Inder Singh Rai, S/o Shri Inder Dev Singh Rai, R/o House No-514, Sector-8-B

    Chandigarh

    Chandigarh

    3. The Chairman, Chanigarh Housing Board, 8, Jan Marg, Sector- 9

    Chandigarh

    Chandigarh ...........Respondent(s)

    49

    BEFORE:

    HON'BLE MR. JUSTICE ASHOK BHAN, PRESIDENT HON'BLE MRS. VINEETA RAI, MEMBER For the Petitioner : M/S. KNM & PARTNERS For the Respondent : MR. SANJIV GUPTA

    (KKR)

    MR. SANJIV GUPTA (KKR)

    MS. RACHANA JOSHI ISSAR

    Dated : 05 Mar 2013

    ORDER

    Complainants/Respondents filed complaints before the District Forum and the State Commission against the Parsvnath Developers Ltd., Appellant/Petitioner herein (hereinafter to be referred to as "the Developer") and the Chandigarh Housing Board, Appellant/Petitioner herein (hereinafter to be referred to as 'the CHB") depending upon the pecuniary jurisdiction of the claim. Complaints were filed based on the same/similar tripartite agreement entered into by the complainants with the Developers and the CHB. District Forum allowed the complaints directing the Developer and the CHB to refund the amount paid by the Complainants along with interest varying from 9% to 12% and compensation varying from Rs.50,000/- to Rs.1,00,000/-. State Commission allowed the complaints directing the Developer and the CHB to refund the amount deposited by the Complainants along with interest @ 7.75% (being the SBI term deposit rate prevalent at the relevant time in terms of clause 9 (d) of the agreement) and compensation @ Rs.107.60 per sq. mtr. (Rs.10/- per sq. ft.) of the super area of the unit per month after the expiry of 36 months of entering into the agreement till the date of payment in terms of clause 9

    (c) of the tripartite agreement. Since the facts and the law points except the compensation and rate of interest involved are the same, all the Appeals and the Revision Petitions are disposed of by a common order.

    Facts are being taken from the First Appeal No. 306 of 2010 titled M/s. Parsvnath Developers Ltd. Vs. Shamsher Singh Sidhu & Anr. FACTS:-

    50

    CHB, Opposite Party No.2 before the State Commission invited bids to implement a project for developing residential/commercial and other related infrastructure at Rajiv Gandhi Chandigarh Technological Park at Chandigarh on the land admeasuring 123.79 acres. The bid sent by the Developer was accepted by the CHB. CHB and the Developer entered into a Development Agreement dated 06.10.06. Developer thereafter widely advertised their project of a township in the name of "Parsvnath Pride Asia", Chandigarh envisaging sale of flats/pent houses to be constructed by them in the township. Complainant/Respondent (hereinafter to be referred to as "the Complainant") applied for allotment of a flat of Category-C, Type-1 vide his application No.A-07282 dated 18.09.07. The total cost of the flat including the amenities was Rs.2,08,50,000/-. Rs.9,81,000/- being 5% of the total sale consideration were paid by the Complainant to the Developer at the time of booking. Developer issued allotment letter dated 28.09.07 followed by a subsequent letter dated 20.10.07 to the Complainant allotting flat No.3/Second Floor, Block No.C4-203 with tentative super area of 2825 sq. ft. for Rs.1,96,33,750/-. Subsequently, Complainant requested the Developer to upgrade the flat to a pent house. Developer acceded to the request and demanded an additional sum of Rs.46,31,500/- which was paid by the Complainant on 6.12.07. A tripartite Flat Buyer Agreement was executed between the Developer, CHB and the Complainant on 25.01.08. As per clause 2(d) of the Flat Buyer Agreement, all the payments towards the sale consideration were to be paid by account pay cheque/Bank Draft in the name of Pasrsvnath Developers Ltd. - CHB Account No.30184417088 payable at Chandigarh. As per clause 4.2.1 of the Development Agreement dated 6.10.06, the amount deposited by the Complainant was to be shared in the ratio of 70:30 between the Developer and the CHB. Further, as per clause 9 (a) of the Flat Buyer Agreement, the construction of the residential units was likely to be completed within a period of 36 months of signing of the Development Agreement, i.e., 6.10.06 between the Developer and the CHB.

    51

    Since there was no intimation from the Developer regarding the status of the project, Respondent on enquiry made by him, learnt that the project had not taken off and no construction had commenced at the site. Complainant requested the Developer to refund the deposited amount to which Developer agreed subject to deduction of Rs.10,00,000/- @ 5% of the basic sale price out of the payment made by the Complainant. Complainant, being aggrieved, filed the complaint before the State Commission.

    Developer, on being served, entered appearance and filed its written statement resisting the complaint, inter-alia, on the grounds; that as per Clause 2.2.2 of the Flat Buyer Agreement, the period of 36 months for completion of the project was from the time when the unencumbered project land was handed over to it; that after signing the Development Agreement on 6.10.06, the CHB handed over 123.79 acres of land to the Developer claiming it to be free from any encumbrance but on erection of fencing around it, the Haryana Government claimed ownership over a part of the land; that vide letters dated 9.2.07 and 12.04.07, CHB informed the Developer that the matter had been resolved with the Haryana Government; that CHB handed over a revised demarcation plan of the land but refused to deliver physical possession of the revised area; that due to non-delivery of unencumbered land the delay occurred in the development of the project; that as per clause 5(a) of the Flat Buyer Agreement, Developer was entitled to forfeit 5% of the basic price in the event of cancellation.

    CHB, on service, put in appearance and filed its separate written statement contesting the complaint on the grounds that as per clause 5(a) of the Flat Buyer Agreement, in the eventuality of cancellation, earnest money being 5% of the basic price was to be forfeited and the balance, if any, was to be refundable without interest; that as per clause 9 (e) of the Agreement, it was the responsibility of the Developer to timely deliver the residential unit to the buyer; that the delay in delivery of possession of the residential unit was attributable to the Developer; that there was no deficiency in service on their part. The State Commission, after considering the material available on record and going

    52

    through the evidence led by the parties, came to the conclusion that the Developer was not entitled to forfeit 5% of the basic price as per clause 5(a) of the tripartite agreement as there was no breach of any condition by the Complainant. State Commission further held that the dispute was between the Developer and the CHB regarding delivery of the possession of unencumbered land for construction of flats for which the Complainant could not be allowed to suffer.

    State Commission allowed the complaint in the following terms:-

    (i) Parsvnath Developers Ltd. and Chandigarh Housing Board jointly and severally are held liable to refund the amounts deposited by the complainants in each complaint case along with interest @ 7.75% p.a. with effect from respective dates of deposit till actual realization;

    (ii) Parsvnath Developers Ltd. shall also pay compensation in each complaint case for not offering the built up flat within 36 months @ Rs.107.60 per sq. mtr. (Rs.10/- per sq. ft.) of the super area of the unit per month from 5.10.2009 (i.e. the last date of completion of the project) till actual realization.

    (iii) The aforesaid directions shall be complied with by the Ops in all these complaints within 30 days from the date the copy of order is received, failing which they shall be liable to pay penal interest @ 12% p.a. on the aforesaid payable amount. State Commission in its order observed thus:-

    "10. We have given our thoughtful consideration to the above points raised on behalf of the parties and have also gone through the relevant terms and conditions of the Development Agreement dated 6.10.06 and Flat Buyer Agreement. Before we proceed further, it is pertinent to mention here that both OPs, i.e. Parsvnath Developers Ltd. and Chandigarh Housing Board have fairly admitted that at the spot the project in terms of the scheme and the agreement could not take off in spite of the expiry of 36 months period within which the possession of the flat was agreed to be handed over. Thus, now the question to be determined before us is as to who is liable to refund the amounts deposited by the complainants and interest thereon as well as compensation. In this regard, both parties have

    53

    made reference to various clauses of the Flat Buyer Agreement which is duly signed by the Complainants, Developers and CHB. Clause-(a) at page -3 of this Agreement goes to show that the Development Agreement had already been signed between OPs, i.e. Parsvnath Developers Ltd. and CHB on 6.10.06 and thereafter developer had also acquired development rights in 123.79 acres of land (project land) which was meant for residential purposes. Meaning thereby, the project was to be completed on or before 5.10.09 but no steps whatsoever are shown to have been taken so far for raising construction thereon.

    11. It is apparent from clause 2(d) that all the payments towards the construction amount including basic price and other charges payable in terms of Scheme of Allotment and the said agreement was to be paid by Account Payee Cheque/bank drafts in the name of Parsvnath Developers Ltd. - CHB A/C No.30184417088 payable at Chandigarh. This indicates that both OPs are jointly holding the account in which the amounts of complainants are lying deposited. No doubt that in the case of any breach of condition or terms of the Agreement by the buyer, the allotment was liable to be cancelled and in that eventuality 5% of the basic price was to be forfeited and the balance, if any, was refundable with interest as laid down in clause 5(a) of the aforesaid tripartite Agreement. Admittedly, there is no breach of any condition of the Agreement committed by any of the complainants regarding payment towards the cost of the flat whereas OPs are proved to have not carried out the terms and conditions in its letter and spirit as required under the Agreement which was duly signed by the parties. Moreover, if there was any dispute between OPs regarding delivery of the possession of the Project land or raising of construction thereon for that complainants cannot be allowed to suffer and at the same time OPs also cannot be allowed to bake benefit of their own wrongs. Thus, it is a clearcut case of deficiency in service on the part of the OPs. It is well established that the Parsvnath Developers Ltd. had constructed a sample flat at the site of the project land which allured the complainants who deposited huge amounts in order to fulfill their dreams of having a same kind of flat. Admittedly, not a single brick has been laid at the spot and the money collected from the buyers in crores is being used by OPs without taking any steps to refund the same to them. All these acts on the part of the OPs further also amount to unfair trade price. In this view of the matter, question of making any deduction while refunding the deposited

    54

    amounts of complainants does not arise.

    12. Now adverting to the clause 9(d) of the Flat Buyer Agreement, therein it was agreed upon between both the parties that if the developer is unable to deliver the unit to the buyer, the Developer and the CHB shall be liable to refund the buyer the amount received from them with interest. The said clause in fact reads as under :-

    "9(d) If as a result of any rules or directions of the Government or if any competent authority delays, withholds, denies the grant of necessary approvals for the project, or if due to any force majeure conditions, the Developer is unable to deliver the unit to the Buyer, the Developer and CHB shall be liable to refund to the buyer the amounts received from the buyer with interest at the SBI Term Deposit Rate at applicable on the date of refund"

    13. Thus, a perusal of the aforesaid clause goes a long way to show that the complainants are entitled to interest over their amounts deposited with Ops at the SBI term deposit rate as applicable on the date of refund. In this regard, a tabulated statement showing latest revised payable terms deposit interest effective from 17.08.10 has been placed on file which indicates that on the term deposit amount for two years to less than three years the interest is 7.75% p.a. which in the given facts and circumstances of the complaints is applicable in all the cases before us."

    Developer as well as CHB, being aggrieved, have filed the separate appeals/Revision Petitions.

    Appeals/Revision Petitions came up for preliminary hearing on 8.09.11. This Commission, after hearing the counsel for the Developer, CHB, Appellants/Petitioners herein and the Complainants, passed the following order:-

    "1. We have heard learned counsel for the parties.

    2. It goes to the credit of the counsel that they have come to the agreement for interim arrangements to be made for refund of the amounts deposited by the original complainants, at least to the extent of the principle amount, though the issue pertaining to interest payable is yet to be determined.

    3. Learned counsel make a statement for following agreed agreement to be made for refund of the principle amount to the

    55

    claimants:

    4. In supercession of earlier interim orders, now it is agreed that M/s Parasvnath Developers will deposit the amount to the extent of 70% in the "ESCROW" account and if any amount is deposited in this Commission, it will be inclusive of such 70% of the amount, which is the liability of the developer to make the payment as per the terms of the Tripartite Agreement. In other words, if in some cases the developer has not deposited 50% of the amount in this Commission then the amount will be deposited in the 'Escrow" account to make deficit of 70% and if 50% amount is deposited in this Commission as per the earlier order, the remaining 20% will be deposited in the 'Escrow" account. Thus the developer will make the entire payment to the extent of 70% in the "Escrow" account or this Commission, as the case may be, so as to arrange for the refund of the principle amounts deposited by the complainants (consumers), which is its liability.

    5. The learned counsel for Chandigarh Housing Board (CHB) seeks time to deposit 30% of the amount in the "Escrow" account, as per the expressed terms of the Tripartite Agreement. So also the developer's counsel seeks time to complete the payment by making the deficit payment or whatever is the remaining amount in order to complete the payment to the extent of 70% for each of the complainant before this Commission in all the matters pending before this Commission.

    6. The learned counsel for the consumers before this Commission has no objection for granting three (3) weeks time for making such deficit payment by the Developer as well as for depositing of 30% of the principle amount by the Chandigarh Housing Board (CHB). Consequently, three weeks time is granted to the parties i.e. the Developer and CHB to deposit their respective parts of the amounts i.e. 70% - 30% in "Escrow" account keeping with the above terms.

    7. The respective consumers will be entitled to get the principle amounts released which are deposited by the developer in this Commission to the extent of their respective shares and also from

    "Escrow" account, with appropriation of the amounts. For example, if the Developer has deposited 50% amount in case of consumer "X" in this Commission, then that amount will be released to the consumer "X" by this Commission and if 20% amount is deposited by the Developer in "Escrow" account and 30% is deposited by the CHB in the "Escrow" account then such consumer "X" will be entitled for payment of that 20% + 30% from the "Escrow" account. So also in the case of Developer and

    56

    if the Developer has not deposited the amount in this Commission, the Developer shall deposit 70% of the amount in

    "Escrow" so as to complete the transaction within three weeks. There will be no further modification in this order and the entire amount to the extent of principle sums shall be released in favour of each of the consumer without any delay. The parties may take note that no further extension of time will be granted for depositing of the amount. The parties to complete pleadings so that the expeditious hearing of the appeals and revisions can take place.

    8. M/s Parasvnath Developers Ltd. shall file tabulated information in tabular form about the amount deposited in each of the case per consumer, with this Commission and the deficit amount to meet bench mark of 50%, if any, which shall be deposited as per the agreement within a period three weeks. The tabular information shall be verified by the Registry as per the accounts so deposited by M/s Parasvnath Developers Ltd. from which account the repayment is required to be made to the complainants and information may be also confirmed from each of the complaint or counsel of the complainant before the amount is so released by the Registry. The Registry, however shall not release any amount deposited by the Chandigarh Housing Board (CHB) in this Commission to any of the consumer because the release of such amount to the extent of 30% is to be made from the "Escrow" account in which the CHB is to deposit such amount to make good of 30% of that account.

    9. The consumers will be entitled to get release of the principle amount of their respective shares from the concerned bank i.e. State Bank of India being "Escrow" agent without any further order and on appropriate identification and completion of the other formalities. The rest of the matter in controversy is pending before the Arbitrator and therefore, the above arrangement is by way of an ad interim relief.

    10. The registry to take stock of the Vakalatnamas and show names of the concerned advocates in the cause list and make comprehensive cause list of all these connected appeals and revisions.

    11. Notice be also issued in all the matters, in which notices have not been already issued.

    12. Stand over to 21-02-2012. Dasti allowed."

    57

    We have heard the Ld. Counsel for the parties at length. Ld. Counsel appearing for the Developer contends that as per clause 2.2.2 of the Flat Buyer Agreement, the period of 36 months for completion of the project was from the time when the unencumbered project land was handed over to the Developer by the CHB; that the CHB has not handed over to the Developer the vacant unencumbered possession of the project site till date; that had the CHB handed over the vacant unencumbered possession of the project site, Developer would have completed the construction of the flats within the stipulated time; that as such the Developer cannot be held liable to pay any compensation to the Complainants; that the amount deposited by the Complainants towards the cost of flat was not with the Developer rather it was lying deposited in the joint account with the CHB and that account was not being operated upon by the Developer; that as per clause 5(a) of the Flat Buyer Agreement, Developer was entitled to forfeit 5% of the basic price in the event of cancellation.

    Ld. Counsel appearing for the CHB contends that there was no legal hitch in raising construction over the area of 123.79 acres of land which was meant for residential purpose only; that the dispute, if any, was with regard to remaining project land which was earmarked for commercial activities; that as per clause 9 (e) of the tripartite agreement, it was the responsibility of the Developer to timely deliver the residential units to the buyers and the CHB cannot be held liable to pay any compensation to the Complainants for non- delivery of the residential units.

    As against this, Ld. Counsel appearing for the Complainants supports the orders passed by the State Commission.

    Facts are not in dispute before us.

    Complainant entered into a tripartite Flat Buyer Agreements with the Developer and the CHB for allotment of a flat. The total cost of the flat including amenities was Rs.2,08,50,000/- and 5% being earnest money to the tune of Rs.9,81,000/- was deposited by the Complainant in the joint account of the Developer and the CHB at the time of

    58

    booking. Vide letters dated 28.09.07 and 20.10.07, Complainant was allotted flat No.3/Second Floor, Block No. C4-203 with tentative super area of 2825 sq. ft. for Rs.1,96,33,75/-. As per clause 9 (a) of the tripartite agreement, the construction of the flats was to be completed within 36 months from the date of signing of the Development Agreement between the Developer and CHB on 6.10.06. As per clause 9 (c) of the tripartite agreement, Developer was liable to pay compensation to the buyers @ Rs.107.60 per sq. mtr. (Rs.10 per sq ft.) of the super area of the unit per month in case the possession of the built up area was not offered to the buyer within a period of 36 months. CHB handed over the possession of 123.79 acres of land to the Developer for raising the construction of the flats. There was some dispute on the land with the Haryana Government which was resolved later on. As the Developer did not/could not take any step to construct the flats on the said land, Complainant requested the Developer to refund the deposited amount. Developer agreed to refund the deposited amount subject to forfeiture of 5% of the basic price in the case of cancellation in terms of clause 5(a) of the tripartite agreement. Complainants, being aggrieved, filed the complaints before the District Forum and the State Commission as per pecuniary jurisdictions. District Forum and State Commission allowed the complaints with a direction to the Developer and CHB to refund the amount along with interest and compensation. Developer and the CHB have filed the present Appeals and the Revision Petitions before us.

    As regards the dispute pertaining to the proportionate share of the Developer and the CHB in the refund of the deposited amounts to the Complainants in the Revision Petitions and the First Appeals, as per clause 4.2.1 of the Development Agreement dated 06.10.06 executed between the Developer and the CHB, it was agreed that 30% of the revenues received in the Escrow account shall be transferred to a designated bank of CHB and correspondingly, the balance 70% shall be transferred to the account of the Developer. As such, in terms of clause 4.2.1 of the Development Agreement, Developer is liable to refund 70% of the deposited amount and the CHB is liable to refund 30% of the deposited

    59

    amount. Developer and CHB in terms of the interim order dated 08.09.11 have deposited the amount in the ratio of 70:30. The amount deposited by the Developer and the CHB in terms of the interim directions issued on 8.09.11, has already disbursed to the Complainants/Respondents.

    Admittedly, the project has been abandoned and the respective counsel appearing for the Developer and the CHB have no grievance against the directions issued by the fora below directing the Developer and the CHB to refund the amounts to the Complainants as per their entitlement. The only dispute which remains between the parties is regarding the payability and liability of the interest and compensation in terms of clause 9(c) and 9(d) of the Flat Buyer Agreement.

    Ld. Counsel appearing for the Developer submits that the Complainants are not entitled to any interest as they sought the refund voluntarily. We do not find any substance in the submission made by the Ld. Counsel for the Developer that the deposited amount should be refunded to the Complainants without any interest. Complainants have been deprived of use of their money for the period the deposited amount remained with the Developer and the CHB and as such they are entitled to get the interest as per clause 9(d) of the tripartite agreement being the normal accretion on the capital. Clause 9 (d) reads as under:-

    "9(d) If as a result of any rules or directions of the Government or if any competent authority delays, withholds, denies the grant of necessary approvals for the project, or if due to any force majeure conditions, the Developer is unable to deliver the unit to the Buyer, the Developer and CHB shall be liable to refund to the buyer the amounts received from the buyer with interest at the SBI Term Deposit Rate at applicable on the date of refund"

    A perusal of the clause 9(d) of the Flat Buyer Agreement reveals that in case the Developer was unable to deliver the units to the buyers, the Developer and the CHB were liable to refund to the buyers the amounts received from them with interest at the SBI

    60

    Term Deposit Rate as applicable on the date of refund. Apart from this, Hon'ble Supreme court of India in "Alok Shanker Pandey vs. Union of India & Ors. (2007) 3SCC 545" has held that interest is not a penalty or punishment at all, but is the normal accretion on capital; that in equity the person keeping the money is required to pay the interest being normal accretion on the principal amount. Relevant observations of the Supreme Court are as under: -

    "It may be mentioned that there is misconception about interest. Interest is not a penalty or punishment at all, but it is the normal accretion on capital. For example if A had to pay B a certain amount, say 10 years ago, but he offers that amount to him today, then he has pocketed the interest on the principal amount. Had A paid that amount to B 10 years ago, B would have invested that amount somewhere and earned interest thereon, but instead of that A has kept that amount with himself and earned interest on it for this period. Hence equity demands that A should not only pay back the principal amount but also the interest thereon to B."

    The District Forum as well as the State Commission in most of the cases while allowing the complaint have directed the Developer and the CHB jointly and severally to pay interest at the rate of SBI term deposit prevalent at the relevant time, i.e. 7.75% p.a. in terms of clause 9 (d) of the Flat Buyer Agreements. However, in some cases it varies from 9% to 12% p.a.

    To avoid the contradiction in the directions given by the District Forum and the State Commission regarding the payment of interest to the Complainants, we modify the orders passed by the fora below and direct the Developer and the CHB to pay interest at the uniform rate of 9% p.a (payable to the senior citizen on Bank fixed deposit at the relevant time) to the Complaints in the ratio of 70:30 from the respective dates of deposit till the date of deposit of the amount by the Appellants/Petitioners in the Escrow Account. Adverting to the point of compensation, Ld. Counsel for the Developer has tried to shift the burden on the CHB by stating that the CHB has failed to hand over the possession of the unencumbered land to the Developer to raise the construction. That had the CHB handed over the possession of the unencumbered land to the Developer, the construction of

    61

    the residential units would have been completed within the stipulated time. As against this, Ld. Counsel appearing for the CHB states that an area of 123.79 acres of land was handed over to the Developer for construction of the residential units. That there was no dispute with regard to the said land and the dispute was regarding the remaining project land which was earmarked for commercial activities. For a dispute between the Developer and the CHB, Complainants cannot be deprived of their legitimate dues which have become payable in terms of clause 9 (c) of the tripartite agreement. The Developer and the CHB cannot be allowed to have the benefit of their own/mutual wrongs. The dispute arising between the Developer and the CHB already stands referred to the Sole Arbitrator appointed by the Hon'ble Supreme Court (Hon'ble Mr. Justice R.V. Raveendran, Retd. Judge of the Supreme Court of India).

    In terms of clause 9 (c) of the Flat Buyer Agreement, the Developer is liable to pay the compensation @ Rs.107.60 per Sq. Mt. (Rs.10 per sq. ft.) of the super area of the unit per month in case the possession of the built up area was not offered to the Buyer within a period of 36 months as stipulated in the tripartite agreement. Clause 9 (c) reads as under:-

    " 9(c) In case of possession of the built up area is not offered to the buyer within a period of 36 months or extended period as stipulated in sub clause (a) above the Buyer shall be entitled to receive from the Developer compensation @ Rs.107.60 per sq. mtr. (Rs.10/- per sf. Ft) of the super area of the unit per month and to no other compensation of any kind. In case the Buyer fails to clear his account and take possession of the unit within 30 days of offer, the Buyer shall be liable to pay to the developer holding charges @ 107.60 per sq. mtrs. (Rs.10 per sq. ft) of the super area of the unit per month in addition to the liability to pay interest to the sellers and other consequences of default in payment."

    Admittedly, the Developer has failed to construct the residential units and hand over the possession of the same to the Complainants. In terms of clause 9 (c) of the Agreement, Developer is liable to compensate the buyers @ Rs.107.60 per sqr. mtrs. (Rs.10 per Sq.ft) of the super area of the unit per month. By way of interim measure, we direct the Developer to pay the compensation to the Complainants in terms of clause 9 (c) of the agreement @ Rs.107.60 per sqr. mtrs. (Rs.10 per Sq.ft) of the super area of the unit per

    62

    month which would be subject to the final outcome of the arbitration proceedings. The orders passed by the State Commission in the original complaints and in the First Appeals arising of the complaint filed before the District Forum stand modified in terms of the directions given above. Any direction either contrary or at variance to these directions stands modified.

    The amount of interest and compensation shall be paid by the Developer and the CHB as directed above within a period of three months from today failing which the amount shall carry interest @ 12% p.a.

    The First Appeals and the Revision Petitions are disposed of in above terms. No order as to costs.

    ......................J

    ASHOK BHAN

    PRESIDENT

    ......................

    VINEETA RAI

    MEMBER

    63