AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Section 37(1) of the Arbitration and Conciliation Act, 1996,
  • Section 9(1) of the Arbitration and Conciliation Act, 1996.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Section 37(1) of the Arbitration and Conciliation Act, 1996,
  • Section 9(1) of the Arbitration and Conciliation Act, 1996.
Smart Summary

Factual and Procedural Background

This matter arises from FAO(OS) (COMM) 2/2017, an appeal under Section 37(1) of the Arbitration and Conciliation Act, 1996 against a judgment and order dated 09.11.2016 of a Single Judge dismissing the appellant's application for interim relief. The dispute stems from a main contract between Uttrakhand Urban Sector Development Agency (UUSDA) and M/s JITF Water Infrastructure Private Limited dated on or about 10.12.2014, under which respondent no.1 sub-contracted work to the appellant by an agreement dated 28.06.2015. The appellant furnished two bank guarantees (Rs. 3,76,25,000 and Rs. 6,09,88,271.30). The Single Bench refused to restrain the respondent from encashing those bank guarantees. Separate procedural applications in the cause included a caveat (Caveat Pet. No. 4/2017), an exemption application (CM No. 117/2017), an application for condonation of delay of seven days in filing the appeal (CM No. 115/2017) and other interlocutory applications (CM Nos. 116/2017 and 118/2017).

Legal Issues Presented

  1. Whether the invocation of unconditional bank guarantees by the beneficiary can be restrained by the court pending arbitration or adjudication, and on what legal principles such restraint is permissible.
  2. Whether the appellant's pleaded allegations (including alleged fraud in paragraph 7.1 of the Section 9 petition) suffice to establish a prima facie case of egregious fraud or irretrievable injustice to justify interdiction of the bank guarantees.
  3. Whether the appeal alleging wrongful invocation of the bank guarantees should succeed and interim relief be granted (including ordering deposit of invoked proceeds in court registry).
  4. Whether delay of seven days in filing the appeal should be condoned.
  5. Procedural: whether the caveat stands discharged and whether exemption from filing is allowed.

Arguments of the Parties

Appellant's Arguments

  • The respondent wrongfully invoked the bank guarantees despite the principal employer (UUSDA) not having invoked bank guarantees furnished to it by the respondent.
  • Particulars of alleged fraud were pleaded (paragraph 7.1 of the Section 9 petition) and therefore the invocation should be restrained.
  • Orders should be passed directing the respondent (who had already invoked the bank guarantees) to deposit the proceeds in the registry of this Court.

Respondent's Arguments

The opinion does not contain a detailed account of the respondent's legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Svenska Handelsbanken v. Indian Charge Chrome: (1994) 1 SCC 502 Supports the principle that bank guarantees cannot be interdicted except upon establishment of prima facie egregious fraud and irretrievable injustice. The court relied on this precedent to affirm that interdiction of bank guarantees is permissible only in rare cases of egregious fraud/irretrievable injustice and found the appellant had not established such a case.
U.P Cooperative Federation Limited v. Singh Consultants and Engineers Pvt. Ltd.: (1988) 1 SCC 174 Reinforces the settled law limiting circumstances in which invocation of bank guarantees may be restrained. The court cited this authority as part of the settled law upholding the Single Bench's approach that restraint requires strong equitable grounds, which were not made out by the appellant.

Court's Reasoning and Analysis

The court analyzed the appeal by reiterating established principles regarding bank guarantees: (i) a bank guarantee is an independent contract between the issuing bank and the beneficiary and is ordinarily unconnected to underlying disputes between contracting parties; (ii) interdiction of a bank guarantee is permissible only in rare cases involving fraud specifically connected to the invocation, irretrievable injustice, or special equity; (iii) if invocation is not in terms of the guarantee, restraint may be possible, but that factual situation was not pleaded here.

The court examined the appellant's pleadings, noting that particulars of alleged fraud in paragraph 7.1 of the Section 9 petition did not disclose fraud in the invocation of the guarantee. The appellant's contention that invocation was wrongful because UUSDA had not invoked respondent's guarantees was rejected because the guarantees did not condition invocation on the principal employer's action. The court also observed there were no pleadings that, if invocation were ultimately found wrongful, the appellant would be unable to recover the proceeds (i.e., no showing of irretrievable injustice).

The court further held that it could not indirectly achieve what it could not do directly: since it could not restrain invocation, it could not order the beneficiary to deposit proceeds to achieve the same result. The Single Bench's reliance on the cited precedents and its conclusion were endorsed as correctly applying the law.

Holding and Implications

APPEAL DISMISSED.

Direct consequences: the order dismissing the application for interim relief (refusing to restrain encashment of the bank guarantees) is upheld; the appellant's request to direct deposit of proceeds in court registry was rejected; the ancillary applications mentioned in the order have become infructuous and stand disposed of. The court stated its observations were prima facie and would not affect the arbitration proceedings. The opinion does not indicate that it sets any new legal precedent beyond affirming the settled law described above.

To access the original judgment, please Sign In or Subscribe.

    Teyma India Private Limited v. Jitf Water Infrastructure Private Limited & Anr. S

    Indira Banerjee, J. (Oral)

    Caveat Pet. No. 4/2017

    1. Since the caveator has put in appearance through counsel, the caveat stands discharged.

    CM No. 117/2017

    2. Exemption allowed, subject to all just exceptions.

    3. The application stands disposed of.

    CM No. 115/2017 (delay)

    4. This is an application seeking condonation of delay of 7 days in filing the appeal. For the reasons stated in the application, the delay of about 7 days in filing the appeal is condoned.

    5. The application stands disposed of.

    FAO(OS) (COMM) 2/2017 and CM Nos. 116/2017 (stay) and 118/2017 (for permission to file additional documents)

    6. This appeal filed under Section 37(1) of the Arbitration and Conciliation Act, 1996, is against a judgment and order dated 09.11.2016 passed by the learned Single Bench dismissing the application of the appellant for interim relief.

    7. By the judgment and order impugned, the learned Single Bench rejected the prayer of the appellant for orders restraining the respondent from encashing a bank guarantee furnished by the appellant in favour of the respondent-JITF Water Infrastructure Private Limited.

    8. On or about 10.12.2014, Uttrakhand Urban Sector Development Agency (“UUSDA”) entered into a contract with the respondent no. 1, M/s JITF Water Infrastructure Private Limited, for engineering, procurement, construction, supplying, laying, testing and commissioning of water supply distribution system for 19 geographic zones in Dehradun.

    9. The contract, hereinafter referred to as the main contract, provided for sub-contract of the contractual work. On or about 28.06.2015, the respondent no. 1 entered into a contract dated 28.06.2015 with the appellant whereby the respondent no. 1 sub-contracted the contract job to the appellant on back to back basis.

    10. In terms of the agreement between the respondent and the appellant, the appellant was required to furnish a bank guarantee which the appellant duly furnished for an amount of Rs. 3,76,25,000/-. The bank guarantee is referred to as the first bank guarantee. The appellant issued a second bank guarantee for an amount of Rs. 6,09,88,271.30 which is referred to as the second bank guarantee, as required in terms of the sub-contract.

    11. It appears that several disputes arose between the respondent no. 1 and the appellant with regard to the execution of the sub-contract, with which we are not concerned at this stage.

    12. It is well settled that the bank guarantee constitutes an independent contract between the bank which issues the bank guarantee and the beneficiary of the bank guarantee. A bank guarantee, and more particularly an unconditional bank guarantee, is in no way concerned with the underlying disputes between the party at whose instance the bank guarantee has been furnished and the beneficiary of the bank guarantee.

    13. It is well settled that an order restraining the invocation of a bank guarantee can only be passed in rare cases of fraud in relation to the bank guarantee, in cases of irretrievable injustice, or where special equity exists in favour of the person at whose instance the bank guarantee has been furnished. Fraud must be in connection with the invocation of the bank guarantee.

    14. If the invocation of a bank guarantee is not in terms of the bank guarantee, invocation may be restrained. However, this is not a case where it can be said that invocation is not in accordance with terms of the bank guarantee. In fact, it is not even the case of the appellant, that the invocation is not in accordance with the bank guarantee. Particulars of alleged fraud allegedly committed by the respondent no. 1 have been pleaded in paragraph 7.1 of the petition filed before the learned Single Bench under Section 9(1) of the Arbitration and Conciliation Act, 1996. The pleadings in paragraph 7.1 do not disclose any act of fraud in the matter of invocation of the bank guarantee.

    15. It has strenuously been argued on behalf of the appellant that the respondent no. 1 acted wrongfully in invoking the bank guarantees when the Uttrakhand Urban Sector Development Agency had not invoked the bank guarantees furnished by the respondent to Uttrakhand Urban Sector Development Agency. Unfortunately, however, it was not a condition of the bank guarantees that invocation thereof would be subject to invocation by Uttrakhand Urban Sector Development Agency of the bank guarantees furnished to them.

    16. Principles of irretrievable injustice and special equity can be invoked only in case of apparent illegality coupled with a situation where the party furnishing a bank guarantee would never be able to recover the proceeds of the bank guarantee. At least, there are no pleadings to the effect that in the event the bank guarantee is invoked and if ultimately, the invocation is held to be wrongful, the appellant would never be able to recover the proceeds from the respondent.

    17. The learned Single Bench has rightly held:

    “The law relating to interdiction of bank guarantees is now well settled; the same cannot be interdicted unless the party seeking interdiction is able to establish a prima facie case of egregious fraud and irretrievable injustice. (See: Svenska Handelsbanken v. Indian Charge Chrome: (1994) 1 SCC 502 and U.P Cooperative Federation Limited v. Singh Consultants and Engineers Pvt. Ltd.: (1988) 1 SCC 174).”

    18. It may also be pertinent to refer to the following observation of the learned Single Bench.

    “The reliance placed by the petitioner on the letter dated 30.06.2016 sent by respondent no. 1 to the principal employer is also not determinative of the dispute between the parties. It is relevant to note that the said response clearly stated that it was “without prejudice”. Further, the said response was issued by the respondent no. 1 to dissuade the principal employer from taking action that the principal employer proposed to take against respondent no. 1. While respondent no. 1 was defending the issue regarding delays and poor work with the principal employer, it also informed the petitioner as to the said controversy, which directly related to the subject contract between respondent no. 1 and the petitioner.

    19. It is also not in dispute that the principal employer has terminated the contract with respondent no. 1, inter alia, alleging poor performance.”

    20. The learned counsel appearing on behalf of the appellant submitted that orders may be passed directing the respondent who has already invoked the bank guarantee to deposit the proceeds in the registry of this Court. It is, however, well settled that what cannot be done directly cannot be done indirectly. If the Court cannot restrain the invocation of the bank guarantee, the Court cannot indirectly restrain the beneficiary of the bank guarantee from enjoying the proceeds of the bank guarantee. We find no grounds to interfere with the order under appeal. The appeal is dismissed.

    21. It is made clear that any observations in this order are prima facie observations which will not sway the arbitration proceedings in any manner.

    22. Since the appeal is dismissed, the applications mentioned herein have become infructuous, and shall stand disposed of.

    23. Dasti.