K.C PURI, J. (ORAL)
Challenge in this revision petition is to the judgment/order dated 30.03.2002 passed by Shri Jaspal Singh, Additional District Judge, Firozpur, vide which appeal preferred by the contractor now respondent against the judgment/order dated 09.06.1998 passed by Shri D. R. Arora, Civil Judge (Senior Division), Firozpur, was accepted.
Briefly stated, M/s Sohan Lal Vipan Parkash (hereinafter referred to as “the Contractor”) filed application under Section 20 of the Indian Arbitration Act before the Court of learned Civil Judge (Senior Division), Firozpur, for appointment of arbitrator to decide the dispute between the parties. The case of contractor now respondent is that contractor is a firm. Vide order dated 12 of 27.6.1989, the contractor was given work of urgent repair of door and windows in the staff quarters at Phagwara, Goraya, Phillaur and Ladhowal. There was condition that the work may be stopped at any time by the Executive Engineer after giving seven days notice in writing and further that in case of any dispute regarding the agreement, the matter would be referred to a person to be nominated by the General Manager of Northern Railway. The contractor started the work but the respondents did not allow it to complete the same and the contractor was asked to remove the material from the workshop vide two different letters dated 18.5.1990 and 18.6.1990 and ultimately, Union of India issued order bearing No. 770.W/108-09 dated 28.10.1991 intimating that the contract has been rescinded vide order dated 17.8.1990 It was further intimated that the work has been further entrusted to some other party at the expenses of contractor amounting to Rs. 21,399/-. Prayer was made for referring the matter to arbitrator.
The petition was contested by Union of India taking preliminary objections that notice under Section 80 CPC is not served; the petition is not maintainable. It is further pleaded that contractor filed suit for mandatory injunction which was withdrawn with permission to file fresh suit and as such, the present petition is barred under Order 2 Rule 2 CPC. The factum of allotment of work was admitted. It is pleaded that contractor has not started the work and he was requested to fulfill the contractual obligations by various letters including letter dated 08.01.1990 Ultimately, the contract was rescinded vide letter dated 17.08.1990 on the ground that the material used by the contractor was defective and of inferior quality. A penalty of Rs. 21,399/- was imposed on account of excess amount paid to the other contractor.
The trial Court framed the following issues:—
1. Whether the applicant firm is a registered firm and Sohan Lal is one of the registered partners of the applicant firm? OPA
2. Whether there is any dispute between the parties referable to the Arbitrator under the agreement arrived at between the parties? OPR
3. Whether the applicant had not served the respondents with a notice u/s 80 CPC? OPR
4. Whether the petition is barred under Order 2 Rule 2 CPC? OPR
5. Relief.
In order to prove its case, the contractor firm tendered some documents and closed the evidence. On the other hand, defendants failed to lead any evidence and their evidence was closed by order.
Learned trial Court returned the findings on Issues No. 1 to 3 in favour of petitioner, whereas Issue No. 4 was decided against the petitioner holding that petition is time barred and the petition was dismissed.
Feeling dissatisfied with the judgment dated 09.06.1998 passed by Shri D. R. Arora, Civil Judge (Senior Division), Firozpur, the contractor filed appeal. The said appeal was accepted by Shri Jaspal Singh, Additional District Judge, Firozpur vide judgment dated 30.03.2002, holding that point of limitation has to be dealt with by the arbitrator.
Feeling dissatisfied with the said judgment dated 30.03.2002, Union of India has preferred the present revision petition.
The short controversy raised in present petition is the point of limitation. The trial Court reached to the conclusion that application of contractor is time barred in as much as the same has been filed after more than three years. The Appellate Court accepted the appeal and held that the factum of limitation has to be decided by the arbitrator.
I have heard both the sides and have gone through the records of the case at length.
The appellate Court has not decided the appeal in right perspective. The trial Court relied upon various authorities that application for arbitration cannot be maintained after the period of limitation under Article 137 of Limitation Act, 1963 (hereinafter referred to as “the Act”). The Hon'ble Apex Court in authority “S. Rajan v. State of Kerala” AIR 1992 SC 1918 has held that application under Section 20 of the Arbitration Act can be maintained keeping in view Article 137 of the Act.
In the present case, it is not disputed that contract was rescinded on 17.08.1990 The present petition was filed on 25.04.1996 i.e after more than 5 years. The limitation, as per authority S. Rajan's case (supra) for filing application is three years under Article 137 of the Act.
So, in view of above discussion, the appellate Court has committed error in leaving the point of limitation at the hands of arbitrator. More so, when apparently application under Section 20 of the Arbitration Act is time barred.
Learned counsel for respondents is fair enough to concede that there is no application for condonation of delay in filing the application under Section 20 of the Arbitration Act.
Consequently, the revision petition stands accepted and the judgment of appellate Court dated 30.03.2002 stands set-aside and judgment dated 09.06.1998 passed by learned Civil Judge(Senior Division), Firozpur, stands restored.
In view of peculiar circumstances, the parties are left to bear their own expenses.