Smart Summary

Factual and Procedural Background

The petitioner challenged the judgment and order dated 28.8.2015 passed by the learned District Judge-3, Satara in Misc. Civil Appeal No. 115/2015. The District Judge had allowed the appeal preferred by the original defendants, quashing and setting aside the judgment and order dated 2.5.2015 passed by the learned Civil Judge, Junior Division, Phaltan in R.C.S No. 13/2015. The suit concerned specific performance of a contract documented in a Visar Pavati dated 16.8.1999. The defendants undertook not to object to specific performance if the petitioner succeeded, stating they had made constructions on the property and would remove them if ordered. The petitioner contended that the trial court rightly granted temporary injunction in his favor based on prima facie case, balance of convenience, and irreparable loss. The District Judge, however, noted the plaintiff delayed instituting the suit until after defendants demolished an old house and began new construction, and found no material showing plaintiff’s steps after execution of the Visar Pavati.

Legal Issues Presented

  1. Whether the petitioner was justified in seeking specific performance of the contract evidenced by the Visar Pavati dated 16.8.1999.
  2. Whether the delay by the petitioner in instituting the suit affected the entitlement to interim relief such as temporary injunction.
  3. Whether the District Judge erred in interfering with the discretionary order of the trial court granting temporary injunction.
  4. Whether the powers under Article 227 of the Constitution of India were properly invoked in this case.

Arguments of the Parties

Petitioner’s Arguments

  • The trial court correctly found a prima facie case in favor of the petitioner and that the balance of convenience and irreparable loss supported granting a temporary injunction.
  • On 16.8.1999, Defendant No. 1 accepted Rs. 80,000 and executed the earnest receipt (Visar Pavati), agreeing to partition and sell his share upon payment of balance consideration.
  • The petitioner was always ready and willing to perform his contractual obligations.
  • Allowing the defendants to proceed with construction on the suit property would frustrate the petitioner’s claim for specific performance.
  • The District Judge erred in interfering with the trial court’s discretionary order.

Defendants’ Arguments

  • Defendants undertook not to object to specific performance if the petitioner succeeded in the suit.
  • They had made substantial constructions on the property and would remove them if ordered.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court examined the material on record and noted that the plaintiff instituted the suit for specific performance based on the Visar Pavati dated 16.8.1999. The District Judge observed there was no material indicating what steps the plaintiff took after execution of the Visar Pavati until the plaintiff issued a notice on 23.1.2012, and the suit was filed only after defendants demolished an old house and commenced new construction. The court referred to Section 46 of the Indian Contract Act, 1872, which requires performance within a reasonable time when no time is specified. The court found no material showing plaintiff’s promptness in enforcing the contract. Given the delay and the District Judge’s acceptance of the defendants’ undertaking protecting the petitioner’s interest, the court found no ground to interfere with the District Judge’s order under Article 227 of the Constitution of India.

Holding and Implications

The petition under Article 227 of the Constitution of India is dismissed.

The direct effect of this decision is the dismissal of the petitioner’s challenge to the District Judge’s order allowing the defendants’ appeal and quashing the trial court’s order. The District Judge’s order included protection of the petitioner’s interests through the defendants’ undertaking. No new precedent was established by this decision.

    Mushtaq Mahibub Shaikh v. Vijay Mahadev Suryawanshi And Ors.

    R.G Ketkar, J.:— Heard Mr. Milind Deshmukh, learned Counsel for the petitioner, at length.

    2. By this Petition under Article 227 of the Constitution of India, the petitioner has challenged the judgment and order dated 28.8.2015 passed by learned District Judge-3, Satara in Misc. Civil Appeal No. 115/2015. By that order, learned District Judge allowed the appeal preferred by the original defendants and quashed and set aside the judgment and order dated 2.5.2015 passed by the learned Civil Judge, Junior Division, Phaltan below Exhibit-5 in R.C.S No. 13/2015.

    3. Learned District Judge accepted the undertaking of the defendants that they will not object specific performance of the contract in the event of the petitioner, hereinafter referred to as plaintiff, succeeding in the suit for specific performance on the ground that the they made construction by spending huge amounts and if ordered they will remove the construction which is subject matter of Visar Pavati dated 16.8.1999

    4. Mr. Deshmukh submitted that after considering the material on record, the learned trial Judge held that the plaintiff has made out prima facie case and the balance of convenience lies in his favour. The plaintiff will suffer irreparable loss and hardship if temporary injunction is not granted in his favour. He submitted that on 16.8.1999 defendant No. 1 after accepting Rs. 80,000/- executed earnest receipt in the presence of witnesses. Defendant No. 1 agreed to get his share partitioned and thereafter execute sale deed by accepting the balance consideration. The plaintiff was and is all along ready and willing to perform his part of the contract. He submitted that if the defendants proceed with the construction over the suit property, it will frustrate the claim of specific performance made by the plaintiff in the suit. As against this, learned District Judge committed serious error in interfering the discretionary order passed by the learned trial Court.

    5. I have considered the submissions advanced by Mr. Deshmukh. I have also perused the material on record. As noted earlier, the plaintiff has instituted the suit for specific performance of the document dated 16.8.1999 which is styled as ‘Visar Pavati’. Learned District Judge has observed in paragraph-6 that there is no material on record to indicate what steps the plaintiff has taken after execution of Visar Pavati on 16.8.1999 For the first time, the plaintiff issued notice dated 23.1.2012 Learned District Judge also noted that the suit was instituted only after the defendants demolished the old house and commenced new construction. There is no explanation as to why the plaintiff did not file suit within a reasonable period from the date of execution of the Visar Pavati. Section 46 of the Indian Contract Act, 1872 reads thus:

    “46. Time for performance of promise, where no application is to be made and no time is specified.— Where, by the contract, a promisor is to perform his promise without application by the promisee, and no time for performance is specified, the engagement must be performed within a reasonable time.

    Explanation.—The question “what is a reasonable time” is, in each particular case, a question of fact.”

    6. Prima facie, there is no material on record to show that what steps the plaintiff has taken after execution of visar pavati on 16.8.1999 It is only after the defendants demolished the old house and started construction of new house, the plaintiff has instituted the suit. In view thereof, I do not find that any case is made out for invocation of powers under Article 227 of the Constitution of India, more so when the learned District Judge has protected the interest of the plaintiff after accepting the undertaking in terms of clause-3 of the operative part of the impugned order. Hence, Petition fails and the same is dismissed.