Summary of Judgment (Oral)

Factual and Procedural Background

The petitioner (builder) and respondent (owner) entered into a Collaboration Agreement dated 07.11.2011 concerning a plot of land measuring 1148 square yards in Khasra No. 260, village Bahapur, Tehsil Kalkaji, New Delhi. The agreement envisaged raising a vertical building with two wings. Under the agreement the respondent (owner) was obliged to obtain sanctioned building plans and necessary permissions within 60 days; the petitioner's obligation to pay Rs. 1.50 crore arose only after those approvals. On execution, the petitioner paid Rs. 50 lakh as a security amount. The respondent failed to obtain the sanctioned plan within the stipulated time. On 07.03.2013 the petitioner asked the respondent to act per the agreement. The respondent replied by offering to refund the Rs. 50 lakh by cheque and, by letter dated 22.03.2014, purported to terminate the agreement citing the petitioner's alleged financial incapacity. The petitioner replied on 02.07.2014 refusing the refund, denying any term requiring disclosure of financial credentials, and invoked the arbitration clause.

The petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking protection of the property (situs of the dispute) and restraint against the respondent creating third-party interests pending arbitration. This Court granted an ad interim injunction on 15.07.2014 restraining the respondent from creating third party interests. The respondent applied under Order 39 Rule 4 CPC seeking vacation of the stay and also sought to treat that application as its reply to the Section 9 petition, asserting the petitioner was not financially capable and offering to return the Rs. 50 lakh security.

During proceedings the respondent deposited Rs. 50 lakh with the Registrar General of the Court (kept in FDR) and later sought permission to withdraw that amount.

Legal Issues Presented

  1. Whether the court should grant interim protection under Section 9 of the Arbitration and Conciliation Act, 1996 to preserve the subject-matter (the property) pending arbitral proceedings.
  2. Whether the respondent's contention that Section 52 of the Transfer of Property Act protects the property obviates the need for an order under Section 9.
  3. Whether the respondent's offer to refund or deposit the security amount (Rs. 50 lakh) and the application under Order 39 Rule 4 CPC warranted vacation of the ad interim injunction previously granted.

Arguments of the Parties

Petitioner's Arguments

  • The Collaboration Agreement did not impose any condition requiring the petitioner to disclose financial credentials or experience.
  • The respondent failed to obtain the sanctioned building plan and did not take steps, as required by the agreement, to secure approvals from concerned authorities within 60 days.
  • The petitioner invoked the arbitration clause (letter dated 02.07.2014) and sought protection of the property under Section 9 pending arbitration; he refused the refund of Rs. 50 lakh.

Respondent's Arguments

  • The respondent contended that the petitioner was not financially sound and lacked experience to develop the building, and therefore should not be permitted to develop the property.
  • The respondent offered to refund the Rs. 50 lakh security and by letter dated 22.03.2014 purported to terminate the Collaboration Agreement.
  • The respondent filed an application under Order 39 Rule 4 CPC seeking vacation of the stay and submitted that the deposit of the security (and Section 52 of the Transfer of Property Act) rendered separate interim relief unnecessary.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court proceeded by examining the contractual obligations and the parties' conduct in relation to those obligations:

  1. The Court found there was an existing dispute between the parties arising from the Collaboration Agreement entered into voluntarily.
  2. The Court observed it was undisputed that the Collaboration Agreement did not make performance conditional on the petitioner disclosing financial status or experience.
  3. The Court noted that under the agreement it was the respondent's obligation to obtain the sanctioned plan and requisite permissions before the petitioner's obligation to pay Rs. 1.50 crore would arise, and that there was no contention that the respondent had taken steps to procure those sanctions.
  4. The only substantive contention by the respondent was the petitioner's alleged incapacity to fulfil the agreement; the Court treated this as insufficient to show compliance by the respondent with his own obligations.
  5. On these facts the Court concluded prima facie that the respondent had failed to comply with the terms of the Collaboration Agreement and that an arbitrable dispute existed. The petitioner had invoked the arbitration clause and requested nomination of arbitrators, but the respondent had not proceeded in that direction.
  6. The Court considered the respondent's argument invoking Section 52 of the Transfer of Property Act and rejected it as addressing a different situation; the Court held that Section 9 of the Arbitration and Conciliation Act confers jurisdiction on the Court to pass appropriate orders to protect the subject-matter of arbitration despite the existence of Section 52.
  7. The Court applied the standard interim-relief considerations: existence of a prima facie case in favour of the petitioner, risk of irreparable loss and injury to the petitioner if the respondents were permitted to create third-party interests, and the balance of convenience lying in favour of the petitioner. The Court also noted the risk of multiplicity of litigation if third-party interests were permitted to be created during arbitration.
  8. On that basis the Court confirmed its earlier ad interim injunction of 15.07.2014 and continued restraint on the respondent dealing with the disputed property pending arbitration or until modified by the arbitrator.
  9. Separately, having noted the respondent had deposited Rs. 50 lakh with the Registrar General (kept in FDR), the Court permitted the respondent to withdraw that amount following the grant of protective relief.

Holding and Implications

Holding: The Court's final decision was to CONFIRM THE AD INTERIM INJUNCTION granted on 15.07.2014 and to continue to restrain the respondent, its agents and employees from dealing with, selling, transferring or parting with possession of the plot of land admeasuring 1148 square yards in Khasra No. 260, village Bahapur, Tehsil Kalkaji, New Delhi, until the termination of the arbitration proceedings or until the order is modified by the Arbitrator.

Consequences and implications:

  • The direct effect is that the respondent is restrained from creating any third-party interest in the specified property pending arbitration; this protection remains until the arbitration terminates or the arbitrator modifies the order.
  • The respondent was permitted to withdraw the Rs. 50 lakh previously deposited with the Registrar General; the deposit had been kept in FDR.
  • The Court observed that Section 9 of the Arbitration and Conciliation Act enables the Court to protect the subject-matter of arbitration notwithstanding Section 52 of the Transfer of Property Act. The opinion did not announce or rely upon any new judicial precedent.

The petition was disposed of in accordance with the orders recorded by the Court.

    M/S. Opaque Infrastructure Pvt. Ltd. Petitioner v. M/S. Millennium Realtech Pvt. Ltd.

    JUDGMENT (ORAL)

    1. The present petition has been filed under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) by the petitioner, who was the builder under a Collaboration Agreement dated 07.11.2011 between him and the respondent. The respondent was the owner of plot of land admeasuring 1148 square yards in Khasra No. 260, situated in the revenue estate of village Bahapur, Tehsil Kalkaji, New Delhi. Under this Collaboration Agreement, a vertical building was to be raised comprising of Wing-1 (South West Side) and Wing-2 (North East Side). Under the agreement, it was the obligation of the owner, i.e, the respondent to seek requisite permissions, sanctions and approvals for development on the said plot at his costs and expenses after getting the building plan sanctioned from the concerned authorities. The sanctioned plan was to be obtained within 60 days of the date of execution of this collaboration agreement. As per the terms, the petitioner had paid a sum of Rs. 50 lakhs to the respondent on execution of this Collaboration Agreement. As per clause 5(c) of the said Collaboration Agreement, the petitioner was required to pay a sum of Rs. 1 core 50 lakhs to the owner, i.e, the respondent on his getting the approval/sanction plan of the building approved from the concerned department within 60 days of the signing of this Collaboration Agreement. It is the admitted fact that uptil now, the respondent has not obtained any sanctioned plan of the building from the concerned department. After waiting for about two years, the petitioner wrote a letter dated 07.03.2013 asking the petitioner to act as per the terms of the agreement. The respondent, however, instead of acting as per the terms of the agreement, i.e, obtaining the sanctioned plan, offered to refund the security amount of Rs. 50 lakh to the petitioner and sent the said amount by way of a cheque along with his letter dated 22.03.2014 Vide this letter, the respondent also terminated the Collaboration Agreement as null and void. The ground taken by the respondent in this letter was that the petitioner was not financially sound and had not developed any property and that he had not submitted the requisite documents showing his capability to raise such a construction. The said letter was duly replied by the petitioner vide letter dated 02.07.2014, whereby he refused to accept the refund of the security amount and took the plea that there was no such term or the condition in the agreement that the petitioner was required to submit its financial credentials to the respondent and also invoked the arbitration clause. Thereafter, the petitioner had moved this Court under Section 9 of the Act with the prayer that so long their dispute is resolved by the Arbitrator, the situs of the dispute, i.e, the property should be protected and the respondent be restrained from selling, transferring, or parting with the possession of the disputed property.

    2. This Court vide order dated 15.07.2014 by way of ad interim injunction, restrained the respondent from creating any third party interest in the disputed property.

    3. The respondent filed an application under Order 39 Rule 4 of CPC praying for the vacation of the stay. It has also been requested by the respondent that the said application be considered as their reply to the petition of the petitioner under Section 9 of the Act. In their application, the respondent has submitted that since the petitioners are not financially sound and also have no experience to develop the building, they are not capable of raising the construction on the said property and, therefore, the respondent does not want that the property be developed by them. It is also submitted that the respondent is ready to return the security amount of Rs. 50 lakh to the petitioner.

    4. During the course of arguments on the previous date before this Court, the respondent offered to deposit the security amount of Rs. 50 lakh with the Registrar General of this Court and accordingly, the respondent was allowed to do so and pursuant to that, the respondent had deposited a sum of Rs. 50 lakh as a security with the Registrar General of this Court. The money has been kept in FDR.

    5. Arguments have been heard.

    6. There is no doubt that there exists a dispute between the parties relating to the Collaboration Agreement entered into by the parties voluntarily. There is no dispute to the fact that the Collaboration Agreement was not conditional to the petitioner disclosing his financial status or his experiences. It is also not in dispute that under the agreement, it was for the respondent to obtain the sanctioned plan and all the other requisite permissions from the concerned departments, before the obligation of the petitioner to make the payment of Rs. 1 crore 50 lakh would have arisen. There is also no dispute to the fact that the respondent has no where contended that he took any steps pursuant to the terms and conditions of the Collaboration Agreement, to get the plan sanctioned. The only plea taken is that the petitioner is not capable to fulfil the conditions of the Collaboration Agreement. All these facts clearly show that prima facie it is the respondent who has failed to comply with the terms and conditions of the Collaboration Agreement and that there exists an arbitrable dispute between the parties. It is also clear that despite the petitioner invoking the arbitration clause vide his letter dated 02.07.2014, asking the respondent to nominate the three Arbitrators, the respondent has not moved any further in this direction.

    7. In view of this, I am satisfied that the property, which is the situs of the dispute between the parties, needs to be protected.

    8. At this stage, the learned counsel for the respondent has argued that there is no need to pass a separate order and the property is protected under Section 52 of Transfer of Property Act. However, Section 52 of Transfer of Property Act deals with entirely different situation. Section 9 of the Arbitration and Conciliation Act, despite the existence of Section 52 of the Transfer of Property Act, confers right and jurisdiction upon the Court to pass appropriate order in order to protect the subject matter of arbitration.

    9. In view of this, the petitioner has a prima facie case in his favour and he would suffer an irreparable loss and injury. It is apparent that if the stay is not granted and the respondents are permitted to create third party interest pending arbitral proceedings, it may create multiplicity of litigations. The balance of convenience thus also lies in favour of the petitioner. I hereby confirm my order dated 15.07.2014 and restrain the respondent, its agents and employees from, in any manner, dealing, selling, transferring or parting with possession of the plot of land admeasuring 1148 square yards in Khasra No. 260, situated in the revenue estate of village Bahapur, Tehsil Kalkaji, New Delhi.

    10. The order shall remain effective till the termination of the arbitration proceedings or till the same is modified by the Arbitrator.

    11. At this stage, learned counsel for the respondent makes a request that in view of this order, he may be permitted to withdraw the amount of Rs. 50 lakhs which he had deposited with the Registrar General of this Court. He is permitted to do so. The amount of Rs. 50 lakh be returned to the respondent.

    12. The petition stands disposed of.