AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section (13) of the Report dated 24.02.2015 filed by the Court Commissioner
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section (13) of the Report dated 24.02.2015 filed by the Court Commissioner
Smart Summary

Factual and Procedural Background

Civil Appeal No. 5470 of 2004, filed by M/s. Saket Housing Ltd., was dismissed by the Supreme Court on 7 May 2013 after it found “enormous deviations” from the sanctioned plan in the construction of a multi-storeyed building in Patna. Demolition of all construction beyond the sanctioned plan was ordered and that decision attained finality.

Flat owners subsequently instituted Writ Petition (Civil) No. 337 of 2013 seeking recall of the demolition order. On 9 July 2014 the Court dismissed the writ petition as “absolutely misconceived,” but fixed compensation of ₹6,000 per sq. ft. of carpet area for affected occupants and appointed former Chief Justice S.N. Jha as Court Commissioner to ascertain individual entitlements. The builder, respondent no. 4, was directed to furnish a bank guarantee of ₹25 crores, later partially encashed to fund compensation and costs.

Multiple Interlocutory Applications were filed and dismissed, with the Court reiterating that no further relief could be granted after disposal of the writ petition. The Commissioner was instructed to submit reports, one of which included recommendations for possible compounding/regularisation of certain portions of the building. Petitioners (flat owners) proposed sealing or treating a full floor as a “mezzanine” to save additional flats. The Patna Municipal Corporation (PMC) opposed the proposal, citing excessive Floor Area Ratio (FAR), increased height, and violations of safety and Airport Authority of India guidelines.

The present order considers the Commissioner’s final report, the petitioners’ proposals, and PMC’s objections, and issues final directions.

Legal Issues Presented

  1. Whether the Court should reopen the question of compounding or regularising any portion of the unauthorised construction—particularly by treating a complete floor as a “mezzanine”—notwithstanding its earlier final order of demolition.
  2. Whether the compensation rate of ₹6,000 per sq. ft. fixed on 9 July 2014 should be revised.

Arguments of the Parties

Petitioners/Flat Owners

  • Requested sealing or demolition of the so-called mezzanine floor so that the resulting FAR reduction could allow regularisation of additional flats.
  • Sought a direction to the Court Commissioner to calculate which owners’ areas could be saved if the mezzanine floor was excluded from FAR calculations and compounded under an earlier PMC order dated 24 February 2000.

Patna Municipal Corporation

  • Rejected the notion that the contested level was a mezzanine; asserted it was a full first floor covering 100 % of the ground-floor area, contrary to by-laws permitting a mezzanine only up to one-third of ground-floor area.
  • Emphasised that the sanctioned plan was for G + 6 floors, whereas G + 9 floors were built, increasing height from 21 m to 31.05 m and raising FAR to 5.459 (sanctioned FAR = 2.99).
  • Highlighted safety concerns and violation of Airport Authority of India height restrictions; therefore contended that no part of the illegal construction should be compounded and the entire unauthorised portion must be demolished.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court examined the Commissioner’s report and PMC’s objections. It expressly rejected paragraphs 13–14 of the Commissioner’s report recommending fresh consideration of compounding on the ground that the issue was “a closed chapter” after dismissal of both the civil appeal and the writ petition. Permitting compounding would, in the Court’s view, convert an admitted illegal construction into a legal one, contrary to its earlier final judgments.

The Court noted the extensive statutory violations—excess FAR, excessive height, lack of Airport Authority clearance—and agreed with PMC that the structure could not be partially salvaged through administrative indulgence. Consequently, it adhered strictly to its demolition mandate.

While refusing any modification to the demolition directive, the Court revisited compensation. Recognising the passage of time and probable escalation in costs, it enhanced the compensation payable to affected flat owners from ₹6,000 to ₹7,000 per sq. ft. of carpet area, payable within six weeks. Occupants are required to vacate within one month thereafter.

Holding and Implications

Demolition confirmed; compensation enhanced.

The Court reaffirmed its 7 May 2013 and 9 July 2014 orders, directed PMC to demolish all unauthorised structures within four months, and raised compensation to ₹7,000 per sq. ft. for each affected flat owner. Flat owners must vacate promptly, and PMC must file a compliance report. The ruling emphasises that once demolition of illegal construction is finally ordered, subsequent pleas for regularisation or compounding will not be entertained, underscoring strict judicial intolerance toward flagrant building violations.

To access the original judgment, please Sign In or Subscribe.

    Babita Badasaria & Ors. Petitioner(S) v. Patna Municipal Corporation & Ors. (S)

    1. This matter has been placed before us by the Office along with an Office Report for directions.

    2. Civil Appeal No. 5470 of 2004, filed by M/s. Saket Housing Ltd., was dismissed by this Court on 7-5-2013, after noting the fact that there was enormous deviation from the sanctioned plan in construction of multi-storeyed building. At that point of time this Court observed as follows:

    “There being enormous deviations from the sanctioned plan in constructing the multi-storeyed building, after following the due process of law, construction beyond sanctioned plan was directed to be demolished by the Patna Regional Development Authority. Deviation is shocking and can be undertaken only by such person who considers himself to be law unto himself. One of the deviations is that against sanction of 24 flats in 6 floors at the rate of 4 flats per floor, 9 floors have been constructed having 6 flats every floor.”

    3. Accordingly this Court had directed for demolition of the said unauthorized construction dismissing the civil appeal and that order has attained finality. Thereafter, a writ petition, being Writ Petition (Civil) No. 337 of 2013 was filed by the petitioners/owners of the residential flats in Santosha Complex, claiming themselves to be the owners of the portion which was directed to be demolished. This Court refused to recall the orders so passed for demolition of the unauthorized construction and directed M/s. Saket Housing Ltd. (respondent No. 4) to deposit a sum of Rs. 25 crores or furnish the Bank Guarantee in the Registry of this Court. Steps were taken accordingly in the matter. Subsequent thereto, the said writ petition was disposed of by this Court by an order dated July 9, 2014 when this Court was pleased to dismiss the writ petition holding that the writ petition was absolutely misconceived and passed the following order:

    “Having heard learned counsel for the parties and in the facts and circumstances of the case, we are of the opinion that ends of justice shall be met by directing payment @ Rs. 6,000/- per sq. ft. to the persons who shall be affected on account of the demolition. Those persons shall be entitled to have the amount @ Rs. 6,000/- per sq. ft. of the carpet area, i.e., the area transferred to individuals and not the common area.

    4. For ascertaining the carpet area of each of the persons, we appoint Mr. Justice S.N. Jha, former Chief Justice of the Rajasthan High Court, as the Commissioner.

    5. The Patna Municipal Corporation shall within one week furnish to the Commissioner the area/flats to be demolished in terms of the Order dated 7.05.2013 passed in Civil Appeal No. 5470 of 2004. The Commissioner shall ascertain through the agency of his choice the carpet area in possession of each of the persons going to be affected by the demolition. He will not decide inter se disputes between rival claimants. In such cases he will determine the carpet area. On such report, the Registry of the Court will earmark sum calculated on the aforesaid basis and deposit in an interest bearing account. The amount along with interest shall be disbursed to the person establishing the right before a Court of competent jurisdiction. As regards others, on the report of the Commissioner, the Registry of this Court shall disburse the amount calculated on the aforesaid basis to all those persons given by the Commissioner. The Commissioner may indicate the amount one would be entitled calculated on aforesaid basis.

    6. The functionaries of the Patna Municipal Corporation and the State Government shall provide to the Commissioner all facilities as required by him. Within four weeks of the payment, all those persons shall vacate the premises in their occupation and hand it over to the Patna Municipal Corporation. In cases having inter se dispute between rival claimants, they shall also vacate the same within four weeks of submission of the report and shall not wait for the disbursement of amount. In case any one of them does not do so, he will be evicted by using force.

    7. Immediately thereafter all concerned will act in accordance with the directions given by this Court in its Order dated 7.05.2013 passed in Civil Appeal No. 5470 of 2004.

    8. After the disbursement of the amount, as aforesaid, left over amount, if any, shall be returned to respondent No. 4.

    9. The Bank guarantee(s) furnished by respondent No. 4 be encashed and the disbursement, as aforesaid, be made. The encashed amount be deposited in an interest bearing account and the disbursement be made from that from time to time. At the first instance, one of the Bank guarantees, i.e., Rs. 15 Crore be encashed.

    10. We fix the fee of the Commissioner @ Rs. 2 lac per sitting and that shall be disbursed from the amount already deposited by respondent No. 4.

    11. For the present, a sum of Rs. 10 lac be disbursed to Mr. Justice S.N. Jha forthwith. Rest of the fee be paid to him whenever asked for.

    12. All these exercise including demolition be completed within a period of ten weeks.

    13. We make it clear that any deviation in carrying out this order shall be viewed seriously.

    14. The writ petition is disposed of with the directions aforesaid.”

    15. In view of the disposal of the writ petition, all the I.As. which were filed till then, were disposed of without any order. Subsequently, further I.As., being I.A. Nos. 7-14 & 15 were filed which were disposed of by the following order passed on 13.8.2014:

    “Reference may be made to the Order dated 9.7.2014 whereby this Court very categorically held that after the Writ Petition was finally disposed of, no further orders need be passed on the I.As. We are of the same view that after disposal of the Writ Petition, I.As. should not be entertained. Hence, all I.As. are hereby dismissed.

    16. However, if the petitioners have any grievance with regard to measurement etc., they may approach the Commissioner and put their grievance.”

    17. Subsequent thereto, I.A. No. 16 was filed which was also disposed of on 8.9.2014, clarifying the order dated 13.8.2014, to the extent that the word “Commissioner” used in the last but one line to the order shall refer to “Ld. Court Commissioner”. Thereafter, I.A. No. 17 was filed for condonation of delay in renewing the Bank Guarantee which was allowed by order dated 28.11.2014.

    18. Thereafter, Office Report for directions was placed before this Court and an interim report was submitted by the learned Court Commissioner and on 22.02.2015 this Court requested the learned Court Commissioner to submit the final report on or before 9.03.2015 and the Bank Guarantee was extended for another 10 weeks.

    19. Parties, thereafter, prayed for report of the learned Court Commissioner to be furnished to them and on such prayer, an order was passed on 6.04.2015 to provide copies of the reports of the learned Court Commissioner to all the learned counsel appearing for the parties in the matter.

    20. Thereafter, a proposal was filed before this Court by the petitioners and the matter was adjourned from time to time. The Patna Municipal Corporation was also directed to consult the Engineers and give suggestions with regard to the suggestions placed by the parties before this Court.

    21. The proposals which were given on behalf of the petitioners/flat owners were as follows:

    “(A) Direct permanent sealing/demolition of the mezzanine floor so that the FAR so released can be made available to the flat owners/petitioners by considering the second floor as the first floor and in the same way, considering the seventh floor as the sixth floor;

    (B) Direct the Ld. Court Commissioner to work out the number of flat owners whose areas can be saved in view of the fact that the mezzanine floor is sealed and is not being utilized towards the FAR and also in terms of compounding vide order of the Vice-Chairman, Patna Municipal Corporation dated 24.02.2000, which has become final after the dismissal of the builder's Civil Appeal No. 5470 of 2004 by this Hon'ble Court vide its judgment dated 07.05.2013.”

    22. Patna Municipal Corporation filed its response to the proposal dated 31.8.2015 filed by the petitioners and it was further submitted before us that the proposals given by the petitioners cannot be accepted and the same should be rejected by this Court in their entirety. It is submitted on behalf of the Municipal Corporation that the so called Mezzanine Floor, which is actually the First Floor of the building, be completely sealed and not be counted as a floor, has no merit. It was further submitted on behalf of the Municipal Corporation that it is not possible to accept the suggestion of the petitioners as the Mezzanine Floor is a complete floor built over 100% of the Ground Floor. As per the rules, a Mezzanine Floor can only be one if it is over 1/3 of the Ground Floor area. Therefore, the said proposal is not accepted by the Municipal Corporation Authorities. It is further contended that the building was sanctioned for Ground and six floors (G+6 floors). The height of the building is important because if the proposal of the petitioners is accepted, then the building will be Ground+7 Floors or more with one floor (the so called Mezzanine Floor) which is not being counted. It is further pointed out that the sanctioned plan is G+6 Floors and it may not be safe to allow it to rise over the number of floors for which the foundation has been laid by the Builder - Respondent No. 4. Accordingly, it is submitted that it would not be safe to allow compounding of any part of the construction of the building. It is further submitted that in case of sealing of the Mezzanine Floor, it is necessary to monitor the same in the future. It is further stated that it may not be proper to do so on account of the severe deviation in the Floor Area Ratio (FAR), which in the building is 5.459 as against the sanctioned FAR of 2.99, further the height of the Building was illegally increased from the sanctioned height of 21 metres to 31.05 metres. Instead of G+6 Floors, the Builder has constructed G+9 Floors. It is further submitted that it is also contrary to the notification and guidelines issued by the Airport Authority of India as the height of the building was increased by the Builder to beyond 23 metres without any sanction or approval of the Airport Authority of India. It is further submitted that it would not be possible to demolish the so called Mezzanine Floor. In these circumstances, it is submitted on behalf of the Patna Municipal Corporation that the illegal construction should be demolished.

    23. We have considered the Report of the Patna Municipal Corporation filed before this Court. We have also duly considered the Report dated 24.02.2015 filed by the Court Commissioner. However, we do not accept part of the Report which has been specifically stated as follows:

    “(13) In any case, I am inclined to think that as the Builder was pursuing the legal remedies - by way of appeal before the Appellate Tribunal or the writ petition/LPA before the High Court - bona fide, the issue of compounding should not be treated as a closed option. If it is allowable under the bye-laws of the PRDA/PMC, the Hon'ble Court may give a fresh look at the same if it results in regularization of a few flats of the owners who purchased them bona fide from their hard-earned money and are now on the verge of being displaced.

    (14) To conclude the discussions, I would respectfully recommend that while the offer of compounding may be allowed, the option of removal of the floor claimed to be mezzanine or the First Floor by either side - may be considered. A favourable decision on these two points may save two full floors i.e. 14 flats of bona fide purchasers, without compromising the FAR parameters. It may be mentioned that de hors the question of FAR, height of the building is not in issue. It may also be mentioned that three flats out of seven flats on the top floor - facing imminent demolition, belong to the Builder themselves.”

    24. After the final report, any suggestion which has been given by the Court Commissioner only to make an illegal construction as a legal construction by compounding the same by paying compounding fee, is totally unacceptable to us. In our opinion, the issue of compounding is a closed chapter as the writ petition as well as the appeal have already been dismissed by this Court. In these circumstances, we do not find any reason to change our mind and allow to keep this illegal construction which is contrary to law. We have already expressed our views in our order passed at the time of disposal of the writ petition. In these circumstances, we do not intend to pass any further order in this matter. We only direct that steps shall be taken by the respondent authorities/Patna Municipal Corporation in the matter in terms of our order dated 9 July, 2014 passed in the said writ petition.

    25. We, however, make it clear that at the time of disposal of the writ petition, we had directed payment at the rate of Rs. 6,000/- per sq. ft. to the persons who shall be affected on account of the demolition. Since the matter is concluded today, we enhance the said rate from Rs. 6,000/- per sq. ft. to Rs. 7000/- per sq. ft.. We further direct that all the flat owners will get their compensation and such compensation shall be paid within a period of six weeks from date and they will vacate the premises in their occupation, to give effect to the order so passed by us, within a period of one month thereafter.

    26. We further direct that the Patna Municipal Corporation shall demolish the unauthorized structures within a period of four months and thereafter shall file a compliance report before this Court.

    Use AI to get other relevant cases.

    Comments

    Babita Badasaria & Ors. Petitioner(S) v. Patna Municipal Corporation & Ors. (S)
    (Mar 10, 2016)