AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Section 16 of the Sales of Goods Act and section 73 of the Indian Contract Act.
  • Article 52 of the Rules of the Bombay Cotton Trade Association
  • Section 16 of the Sale of Goods Act or Section 73, Contract Act.
  • 204 (Canada). 21. Section 10(2) of the arbitration Act
  • SECTION 14 ARBITRATION ACT 1940
  • ARBITRATION ACT 1940
  • Order 41 Rule 33, Code of Civil Procedure. 50.
  • section 10(2) of the Indian Arbitration Act.
  • Order 41 rule 33, Code of Civil Procedure
  • SECTION 29 ARBITRATION ACT
  • Section 10(2), Arbitration Act
  • O. 41 rule 33, C.P.C.
  • Order 41 Rule 33
  • O. 41 Rule 33
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Section 16 of the Sales of Goods Act and section 73 of the Indian Contract Act.
  • Article 52 of the Rules of the Bombay Cotton Trade Association
  • Section 16 of the Sale of Goods Act or Section 73, Contract Act.
  • 204 (Canada). 21. Section 10(2) of the arbitration Act
  • SECTION 14 ARBITRATION ACT 1940
  • ARBITRATION ACT 1940
  • Order 41 Rule 33, Code of Civil Procedure. 50.
  • section 10(2) of the Indian Arbitration Act.
  • Order 41 rule 33, Code of Civil Procedure
  • SECTION 29 ARBITRATION ACT
  • Section 10(2), Arbitration Act
  • O. 41 rule 33, C.P.C.
  • Order 41 Rule 33
  • O. 41 Rule 33
Smart Summary

Factual and Procedural Background

This arbitration arose from a contract dated February 12, 1964, between the Fertilizer Corporation of India (the Corporation) and Girdler Corporation (later C.I. Girdler Inc., the contractor) for the erection and installation of a Methanol Plant at the Corporation’s Trombay Division in Bombay. The plant was supplied on a turn-key basis with a guaranteed capacity of 100 metric tons of Methanol per continuous 24-hour day. The contract price was 45 million rupees. Performance of the plant was unsatisfactory, failing to meet the guaranteed production capacity, primarily due to repeated failures of the catalyst in the Reformer Furnace.

Following disputes over performance and defects, the Corporation terminated the contract and took possession of the plant in July 1967. Pursuant to the arbitration clause in the contract (Article XIV), arbitrators were appointed by both parties, and an umpire was nominated. The arbitration tribunal, comprising eminent members from three countries, held multiple sessions from 1971 to 1974, issuing an interim award in August 1973 and a final award in February 1974. The Corporation filed objections to the awards under Sections 30 and 33 of the Arbitration Act, 1940, which were dismissed by the learned judge in 1978, prompting the Corporation’s appeal to this court.

Legal Issues Presented

  1. Whether the majority arbitration awards, which were non-speaking and unsigned by the dissenting arbitrator, disclosed any error of law apparent on their face warranting setting aside.
  2. Whether the March 21, 1967 agreement superseded the original contract and defined the rights and duties of the parties, thereby precluding claims for loss of production damages.
  3. Whether the dissenting arbitrator’s detailed note could be considered part of the majority award or used to ascertain the majority’s reasoning.
  4. Whether the respondent was entitled to interest on the decretal amount from the date of decree under Section 29 of the Arbitration Act and whether the court should exercise its discretion under Order 41 Rule 33 of the Code of Civil Procedure to award future interest.

Arguments of the Parties

Appellant's Arguments (Fertilizer Corporation of India)

  • The March Agreement did not supersede the original contract; thus, the contractor was bound to fulfill the original contractual obligations.
  • The Corporation was entitled to damages for loss of production due to fundamental breach and implied warranty of fitness under Section 16 of the Sale of Goods Act and Section 73 of the Indian Contract Act.
  • The dissenting arbitrator’s note should be considered to understand the reasons behind the majority awards, which themselves lacked reasons.
  • The majority awards were flawed and should be set aside for error apparent on the face of the award.

Respondent's Arguments (IDI Management / Contractor)

  • The majority awards, though non-speaking, are final and binding as per Section 10(2) of the Arbitration Act, 1940, and dissenting opinions do not form part of the award.
  • The March Agreement was a full and final settlement, superseding the original contract and precluding claims for loss of production.
  • The court should not interfere with the arbitrators’ findings or attempt to discern their reasoning where none is provided.
  • The discretion to award future interest lies with the trial court, and the appellate court should not exercise powers under Order 41 Rule 33 to award such interest.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union Of India v. A.L Rallia Ram, AIR 1963 SC 1685 Standard for setting aside arbitration awards limited to error apparent on face of award or misconduct. Supported the principle that courts should not disturb arbitral awards unless there is an apparent legal error or misconduct.
Jivrajbhai Ujamshi Seth and others v. Chintamanrao Balaji, AIR 1965 SC 214 Court cannot speculate on arbitrator's reasoning where no reasons are given. Reinforced that absence of reasons in an award does not justify setting it aside.
Bungo Steel Furniture (Pvt.) Ltd. v. Union of India, AIR 1967 SC 378 Similar principle restricting interference with awards. Affirmed limited grounds for challenging arbitral awards.
Upper Ganges Valley Electricity Supply Co. Ltd. v. The U.P. Electricity Board, AIR 1973 SC 683 Reiterated limited judicial review of arbitration awards. Supported finality of arbitral awards barring specified exceptions.
N. Chellappan v. Secretary, Kerala Electricity Board, AIR 1975 SC 230 Mistakes in law or fact in arbitration awards do not invalidate them unless apparent on face of award. Used to support that errors not apparent on face do not vitiate awards.
Rohtas Industries and another, AIR 1976 SC 425 Grounds for setting aside awards limited to error apparent on face or misconduct. Confirmed judicial restraint in interference with arbitration awards.
Champsey Bhara and Co. v. Jivrai Balloo Shipping and Weaving Co., AIR 1923 PC 66 Arbitrators are entitled to their own interpretation; awards stand unless tied to erroneous legal proposition. Applied to uphold majority awards despite absence of reasons and dissent.
Alien Berry and Co. Ltd. v. Union of India, AIR 1971 SC 696 Incorporation of contract or clause in award is by clear finding; mere reference not incorporation. Used to reject argument that documents outside award could be read into it.
Dr. S. Dutt v. University of Delhi, AIR 1958 SC 1050 Example of award set aside for erroneous legal proposition. Distinguished from present case where no such error appeared.
Kalagtan Govt. v. Duff Development Co., (1923) AC 395 Court does not sit in appeal over arbitrator’s construction of contract. Supported principle that mere disagreement is insufficient to set aside award.
Commissioner of Income Tax Assam, Tripura and Manipur v. The Panbari Tea Co. Ltd., AIR 1965 SC 1871 Discretion under Order 41 Rule 33 CPC to adjust rights when necessary due to appeal interference. Applied to hold that such discretion is not to be exercised absent necessity to adjust rights.
T. Atchaih v. Narasingarao, AIR 1978 SC 725 Exercise of Order 41 Rule 33 CPC power only in cases involving setting mutual rights and obligations. Supported refusal to award future interest under this provision where no such adjustment was required.

Court's Reasoning and Analysis

The court analyzed the arbitration awards and the related documents strictly within the confines of the Arbitration Act, 1940, and established judicial principles. It noted that the majority awards were non-speaking and unsigned by the dissenting arbitrator, Mr. B. Sen, whose detailed dissenting note could not be treated as part of the award or as reflecting the majority’s reasoning. The court emphasized that under Section 10(2) of the Arbitration Act, the opinion of the majority prevails and the minority’s views hold no legal weight.

The court examined the March 21, 1967 agreement, which the majority arbitrators considered a full and final settlement superseding the original contract. The court accepted that the tribunal was entitled to this construction and that the Corporation’s claims for loss of production were barred by this agreement, especially given the contract’s exclusion of indirect damages such as loss of profits.

Judicial review was confined to detecting errors apparent on the face of the award or misconduct. The court held that the absence of reasons in the majority awards did not constitute an error or ground for setting aside. It rejected the Corporation’s attempt to import the dissenting arbitrator’s reasoning or extraneous documents (such as Lord Devlin’s letter) into the awards. The court underscored the finality of arbitral awards, noting arbitrators need not give reasons and their decisions are not subject to appeal on merits.

Regarding the claim for interest on the decretal amount, the court found no basis to interfere with the trial judge’s discretion in refusing future interest. It held that the appellate court’s power under Order 41 Rule 33 CPC to modify decrees is to be exercised sparingly and only when necessary to adjust rights as a result of the appeal. Since the appeal was dismissed, no such adjustment was warranted.

Holding and Implications

The appeal of the Fertilizer Corporation of India is dismissed with costs.

The court upheld the majority arbitration awards as final and binding despite their non-speaking nature and the dissent of one arbitrator. The March Agreement was held to supersede the original contract, precluding claims for loss of production damages. The dissenting arbitrator’s note was excluded from consideration as it did not form part of the award. The court reaffirmed the limited scope of judicial review over arbitration awards, emphasizing that awards are not to be set aside for mere errors in construction or absence of reasons unless an error of law is apparent on the face of the award. The discretion to award future interest under Order 41 Rule 33 CPC was not exercised, maintaining the trial court’s decision. This decision does not establish new precedent but reinforces established principles regarding arbitration finality and judicial restraint in interference.

    The Fertilizer Corporation Of India Limited v. I.D.I. Management Inc. Others

    AvadhBehari Rohatgi, J.

    1. This arbitration has been a long drawn out affair. By a contract dated 12-2.1964 between the Fertilizer Corporation of India (the Corporation) and Girdler Corporation, later known as C.I. Girlder Inc. (the contractor), the contractor agreed to erect and instal a Methanol Plant at the Corporations Trombay Division at Bombay of the description and on the terms set out in the said contract. The plant was supplied on a turn-key basis. It was to have a capacity to produce 100 metric tons of Methanol per continuous day of 24 hours with either refinery gas or petroleum naptha as the feed stock. The contractor was to be paid 45 million rupees as the price of the plant.

    2. Article XIV of the said contract contained an arbitration clause which is as follows:

    All disputes and differences between the Contractor and the Corporation shall be referred to arbitration, each party appointing an Arbitrator, and the Two Arbitrators nominating an Umpire, as the first step before consideration of any specific issue referred to them. The decision arrived at unanimously by the two Arbitrators, or on their failure to reach unanimous decision the award of the Umpire shall be accepted as final and binding upon both the parties. The provisions of the Indian Arbitration Act, 1940 shall govern the said arbitration proceedings. The venue of the Arbitration shall be New Delhi. The parties hereby expressly submit to the jurisdiction of the courts at New Delhi for all disputes arising out of the Agreement, the Arbitration proceedings and the enforcement of any award that may be made therein.

    3. The plant was ready for commissioning on December 29, 1965. The performance of the plant was eratic and unsatisfactory. It did not produce the required quantity of hundred metric tons of Methanol per day. This was the main complaint of the Corporation. They said that the Catalyst installed in the Reformer Furnace which was specifically guaranteed under the contract to function satisfactorily for a period of one year had repeatedly failed to perform its function, there being repeated failures and shut downs in the plant. There was considerable correspondence between the parties. On February 16,1967 the contractor notified the Corporation that performance test would be carried out by February 19, 1967. Performance test was given accordingly.

    4. As a result of various discussions and negotiations that took place between the parties certain understandings were arrived at which were recorded in a letter of March 21, 1967 (the March Agreement). In this agreement the outstanding disputes between the parties were defined. The case of the Corporation is that despite the assurances given by the contractor there was a failure of the Catalyst in operation and the performance of the plant was far from satisfactory. It is alleged that there being something basically wrong with the Reformer Furnace, which was a vital part, the plant was not capable of giving sustained production of 100 metric tons per day. As the contractor failed to remedy the defects in the plant the Corporation terminated the contract and took juridical possession of the plant by its letter dated July 8, 1967.

    5. In or about 1967 disputes and differences arose between the Corpora tion and the contractor and in accordance with the said Article XIV the Corporation duly appointed Mr. B. Sen as an arbitrator and the contractor duly appointed Mr. J. Russell Wilson as an arbitrator and the two arbitrators on February 7, 1969 nominated Lord Devlin as Umpire. By a supplemental agreement between the parties made on 1.3.1973 it was provided that the disputes and differences aforesaid should be considered as having always been referred to Lord Devlin, Mr. Russell Wilson and Mr. B. Sen as the three arbitrators, that Lord Devlin should act as the Chairman of the Arbitral Tribunal and that the award or awards should be made in the manner provided in section 10(2) of the Indian Arbitration Act.

    6. This was an eminent Tribunal of Aribtration consisting of members of three countries. Mr. Russell Wilson is a patent attorney of the United States. Mr. B. Sen is a senior advocate of India. Lord Devlin was a law lord in England. They held various sessions between 1971 and 1974. The cost of the arbitration assessed by the Tribunal ran into twelve lacs, parties own expenses being separate.

    7. On October 3, 1969 the Corporation filed a request for arbitration which concluded with four claims (hereinafter called claims I, II, III and IV). On March 14, 1970 the contractor filed the reply which concluded with four claims (hereinafter called counter-claims I, II, III and IV counter-claims III and IV being in the alternative).

    8. In the course of the arbitration proceedings IDI Management, the respondent to this appeal, succeeded to all the rights and liabilities of the contractor under the contract.

    9. The Arbitral Tribunal held 33 sessions on and between May 24, 1971 and March 3, 1973, to take evidence. They required the parties to submit their arguments in writing and also heard oral arguments.

    10. On March 3, 1973 the parties agreed that the Tribunal should make an interim award or awards on certain disputes which were specified in the order dated March 3,1973 made with the consent of the parties. Accordingly the Tribunal made an interim award on August 21, 1973. The material portion of the award is as under:

    AND WHEREAS we have considered all the evidence put before us and the arguments addressed to us and have deliberated thereon AND WHEREAS we have decided to hear oral arguments on Claim II AND WHEREAS a majority of us are agreed upon an award in relation to Claim I and counterclaim I and in the premises Counter claims III and IV do not arise.

    Now we Petrick Devlin and J. Russell Wilson Hereby Award and Declare as follows:

    (1) The Claimants are not entitled under Claim I to a sum to be assessed in respect of lost production and.

    (2) The respondents are entitled under counterclaim I to be paid such sum not exceeding $302, 740, 53 as may be shown to be the out standing balances due to them under the said Contract in dollars as well as in Indian currency.

    IN WITNESS HEREOF we have subscribed our signatures as on the 21st day of August one thousand nine hundred and seventy three.

    Sd/-Lord Devlin.

    Sd/-J. Russell Wilson

    11. It will be seen from the interim award that the claim of the Corporation which was the subject matter of the interim award was the loss of production. They claimed Rs. 471.45 lakhs as damages on account of lost production during the period 9.3.1967 to 31.12.67 and additional period of 18 months, that is, 1.1.68 to 30.6.69 during which the plant failed to give the rated capacity of 100 metric tons of Methanol per day The majority rejected this claim of the Corporation in its entirety.

    12. The counter-claim of the contractor was that, though they had been paid 95 per cent of the price of the plant, the remaining five per cent of the price was not being released to them in spite of the fact that they had done all that was required of them under the contract. The majority allowed this claim of the contractor. In substance this was the decision of the majority in their interim award. Mr. B. Sen did not concur with the majority and therefore did not sign the award.

    13. After the Interim Award the Tribunal held six sessions on and between February 5 and 17, 1974 to hear further arguments and to take evidence upon all other claims and matters remaining in the arbitration. The Corporation abandoned Claim IV and were given leave to add three further claims. The contractor abandoned counter-claim No. II. On the remaining disputes the majority made the final award on February 16, 1974. The material portion of the final award is in these terms:

    AND WHEREAS we have considered all the evidence put before us and the arguments addressed to us and have deliberated thereon AND WHEREAS a majority of us are agreed upon an Award or Awards in relation to all the said Claims and matters NOW WE PATRICK LORD DEVLIN and J. RUSSELL WILSON HEREBY AWARD TO THE CLAIMANTS:

    (a) In satisfaction of Claim II A Rs. 1,06,121 with interest there on from 8 July 1967.

    (b) In satisfaction of claim II C Rs. 2,58,069 with interest there on from 5 August 1967, and.

    (c) In satisfaction of Claim III Rs. 2,35,306 with interest from 31 July 1969.

    All such interest to be at the rate of 6 per cent, per annum and to run until the date of the award.

    AND WE DECLARE that, save as afore said, the Respondents are not liable upon any of the Claims.

    AND WE AWARD to the Respondents in satisfaction of counter claim 1 US $ 302,600,50 with interest thereon at 6 per cent annum from 8 July 1967 until the date of this award.

    14. From this final award it will be seen that the Corporations claims were allowed in respect of the specific items: Claim IIA for the Quenchoot, claim IIC in respect of Catalyst, Claim III on accounting. In respect of the contractors claim they were awarded US $ 3026000,50 with interest. In the Interim Award it was held that the contractor was entitled under counter claim I to be paid such sum not exceeding $ 302,740,53 as may be shown to be the outstanding balance due to them under the said contract. This counterclaim I was now in the final award quantified as US $ 302,600,50 which the contractor was held entitled to receive from the Corporation. This was in the main the balance 5 per cent of the price of the plant which the Corporation had refused to release on account of unsatisfactory performance of the plant.

    15. The final award, as was the interim award, was the decision of the majority consisting of Lord Devlin and J. Russell Wilson. Mr. B. Sen did not agree with the majority. Nor did he sign the interim and the final awards. He issued a dissenting note dated 16.2.1974 giving reasons as to why he did not agree with the majority awards, interim and final. This note, unlike the majority awards, is a detailed document of 32 pages setting out his reasons why he was not concurring with the majority.

    16. In 1974 the contractor made a petition before learned judge on the original side of this court under Section 14 of the Arbitration Act 1940 (the Act stating that the award dated 16.2.74 be made a rule of the court. The arbitrators filed both the interim award dated August 21, 1973 and the final award dated 16-2.1974. On notice being given the Corporation on 26.10.74 filed objections to the award, both interim and final, under Sections 30 and 33 of the Act. The Corporation raised a large number of objections to the majority awards.

    17. Prithvi Raj J. by his order dated April 14, 1978 dismissed the objections of the Corporation. He made the awardsinterim as well as finala rule of the court and passed a decree in terms thereof. From his order the Corporation appeals to this court.

    18. The majority awards are non-speaking awards. In his separate dissenting note dated 16.2.1974. Mr. B. Sen has given his reasons for differing from the majority. The Corporation relies heavily on Mr. B. Sens note in order to attack the majority awards. On behalf of the Corporation it is contended that the note of Mr. B. Sen dated 16.2.1974 is a minority award and it can be looked at for the purpose of finding the reasons of the majority awards.

    19. The opinion of Mr. B. Sen formed the principal topic of dis cussion and submitted as a ground for setting aside the majority awards. I cannot agree with this submission. The majority arbitrators refrained front giving reasons for their awards, which they had every right to do. The minority arbitrator, Mr. B. Sen, is a well known and reputed member of the legal profession. He gave reasons for his dissent. That he did so can only be attributed to an honest and understandable desire on his part to indicate to his colleagues where and now he differed from them: and of course to give those interested the same information. The reasons which he has given cannot be said to be reasons of the majority. Mr. B. Sens reasons are minority reasons as such form no part of the award.

    20.The awards clearly state that they are the awards of the majority. Only Lord Devlin and Mr. J. Russell Wilson signed the awards. Mr. B Sen did not sign. He was a dissenting member. In his dissenting note he disagrees with the view of the majority. But that is neither here nor there. The dissenting opinion of Mr. B. Sen simply shows, what everybody knows, that there are two sides to every question. Like the two sides of a coin. That there can be different and differing points of view on every conceivable question under the sun is all that the note of Mr. B. Sen shows. But no value can be attached in law to his dissenting opinion. The awards of the majority will prevail. (See Hollandand Couper v. Cityof Vagcouver, (1959) 19 DLR (2d) 404 (Canada) and YarrowsLtd. v. C.N.Steamship Co. Ltd, (1951) 2 DLR 204 (Canada).

    21. Section 10(2) of the arbitration Act says that the opinion of the majority will prevail. The majority is a term signifying greater number. Section 10(2) is based on the theory of numbers. It requires counting of heads. If there are arbitrators, two will have the deciding voice because they constitute the majority. The remaining one will be in a minority. The opinion of the minority cannot be looked at for any purpose. The award with which the law is concerned is the award of the majority.

    22. The majority awards, as I have said, are non-speaking awards. The majority has not given any reasons for their decision.

    23. The two outstanding and substantial disputes raised before the arbitrators were these: (1) the claim of the Corporation for the loss of production and (2) the claim of the contractor with regard to the balance 5 per cent of the plant. The majority rejected the Corporations claim for lost production without giving any reasons. Counsel for the contractor drew our attention to Article X of the contract which provided that neither party would be liable to the other for any loss of profit or for any similar indirect damages. He also called our attention to the March Agreement which narrowed down the disputes between the parties. From the March Agreement one thing is quite clear. And it is this that the Corporation accepted the plant. It says, FCI accepts the Methanol Plant which specifically fulfilled its Naptha per formance guarantee during the performance test held during the period beginning at 1200 hours on March 4, 1967 and ending at 1200 hours on March 9, 1967. Thereafter it refers to a few outstanding disputes which required to be resolved. The contractor in his turn agreed to give its attention for suitable remedial measures to the Hot Spot on Waste Heat Boiler and to the design of the Quenchpot. He agreed that he shall remove the defects in the design of the Quenchpot and the Waste Heat Boiler. He also agreed to replace at no cost to the Corporation spare charges of Catalyst used by him in the plant. The Corporation in its turn agreed to pay or arrange to pay Girdler Corporation the outstanding balance due to them under the contract in dollars as well as in Indian currency immediately upon receipt of bank guarantee in its favour. These rights and duties defined by the March Agreement were in full and final settlement of all obligations of the parties as set forth in the contract executed in super session of the agreement dated 12-2.1964.

    24. On the basis of this March Agreement Lord Devlin, the Chairman of the Tribunal, in the course of the arbitration proceedings wrote to the parties a letter dated October 9, 1973 of which the following is an extract:

    It will be apparent from the nature of the Award that the majority of the arbitrators considered that the supplemental agreement of March 21, 1967 defined the rights of the parties as alleged by the respondents. Mr. B. Sens opinion was to the contrary, but he accepts that any further argument must be governed by the majority decision. Accordingly, the oral arguments on the various heads of claim II will be concerned with the rights and duties of the parties under the March Agreement.

    25. Counsel for the Corporation made a two-fold submission. Firstly, he submitted that the majority went wrong in holding that the March Agree ment defines the rights and duties of the parties. He submitted that the original contract of 1964 was not wiped out by the March Agreement and that the contractor was bound to fulfill his obligations under the original contract. He argued that as there was a fundamental breach of the implied term of the original contract that the plant will produce 100 metric tons per day of Methanol, the Corporation was entitled to damages on account of loss of production under Section 16 of the Sales of Goods Act and section 73 of the Indian Contract Act. It appears to me that on a construction of the contract the majority were entitled to come to the conclusion they did. Having accepted the Methanol Plant, as is explicitly stated in the March Agreement, it was not open to the Corporation to make any claim of damages for loss of production. The original contract also did not entitle Corporation to claim remote or indirect damages such as loss of production.

    26. The awards of the majority were attacked on the ground that there was an error apparent on their face. When we pointed out to counsel for the Corporation that the awards of the majority gave no reasons he invited us to read the dissenting note of Mr. B. Sen to find the reasons of the majority. We expressed our inability to accede to this request.

    27. Counsel said that the approach of the majority is disclosed by Mr. B. Sens note. It will, he said, give us a clue to the mind of the majority. The basis of the majority reasoning, he submitted, can be gleaned from Mr. B. Sens note. I do not agree. Neither reasons nor basis nor clue nor approach can be found from the note of Mr. B. Sen. He was in the minority of one. When the majority awards are non-speaking awards we cannot impute to the majority the reasons given by the minority. It will be a strange thing if the minority, can give to the court the reasons of the majority, when the majority has chosen to remain silent. The basis must come from the mind and hand of the maker of the award. There are only two awards and they are the awards of the majority. The dissenting opinion of one arbitrator is not part of the award. under Section 10(2), Arbitration Act the awards of the majority shall prevail.

    28. The March Agreement is a crucial document in this case. The arbitrators realised its importance. The majority took the view that it defined the rights and duties of the parties, as Lord Devlin put it. Mr. B. Sen did not concur with the majority. He thought that the original contract continued to govern the parties and the March Agreement was not a complete repository of the parties rights and duties.

    29. This raises a question of construction in each case, for it has to be decided as a fact whether there was a full and final settlement of all the obligations of the parties and whether there was a supersession of the agreement dated February 12, 1964. By agreement between the parties dated 21.3.1967 the Corporation accepted the promise of something else than the remedy to repudiate, assuming that they were entitled to repudiate on a fundamental breach. There was agreement. There was accord. In a climate of concilia tion a new agreement was executed in March 1967. This March Agreement is a definitive statement of the outstanding disputes and reciprocal promises. The capital importance of this settlement is that the plant was accepted by the Corporation. If the plant has been accepted where is the question of damages for loss of production or profits. The right to claim damages on this score was not reserved. It was given up. This would appear from the express terms of the March Agreement which was a full and final settlement of the old standing disputes.

    30. The March Agreement was a composition settlement. There was mutual surrender on certain points. The parties by this agreement agreed to be bound in supersession of the original agreement. The original cause of action was discharged from the date when the March Agreement was made. The execution of the March Agreement is of central importance in this case. This was the view of the majority whose word is, and must be, final, Were it not so there would be no end to controversy.

    31. The March Agreement was a clear case of accord and satisfaction. The parties put their past behind them. In all amity they chalked out a course of action for the future. In a spirit of give and take the difference were composed on this condition that if certain things are done by each party all disputes will stand settled.

    32.The single question in this case is whether the majority awards disclose an error of law on their face. There is no statement of reasons in the awards. Nor do they incorporate any legal proposition as the basis of the awards. The question whether the majority were right in holding that the March Agreement defined the rights and duties of the parties is not for us to decide. It is not for us to weigh the evidence. That task belonged to the Tribunal. And there can be no doubt that the finding of the Tribunal, which in this case means the majority, should not be disturbed except in cases where there is an error of law on the face of the award or misconduct. As to this there are strong and abundant authorities, e.g.: Union Of India v. A.L Rallia Ram, AIR 1963 SC 1685; JivrajbhaiUjamshi Seth and others v. ChintamanraoBalaji, AIR 1965 SC 214; BungoSteel Furniture (Pvt.) Ltd. v. Unionof India, AIR 1967 SC 378; UpperGanges Valley Electricity Supply Co. Ltd. v. TheU.P. Electricity Board. AIR 1973 SC 683; N.Chellapan v. Secretary,Kerala Electricity Board and another, AIR 1975 SC 230; and RohtasIndustries and another, AIR 1976 SC 425.

    33.The celebrated decision is ChampseyBhara and Co. v. JivraiBalloo Shipping and Weaving Co., AIR 1923 PC 66. Generations of lawyers and judges have paid a respectful tribute to the masterly exposition by Lord Dunedin. This decision has stood for half a century and alone. In the Champsey Bhare case it was held that the arbitrators were entitled to give their own interpreta tion or construction of Article 52 of the Rules of the Bombay Cotton Trade Association and that the finding was not open to review on a motion to set aside the award. The principle enunciated was that the award must stand unless on the face of it the arbitrators had tied themselves down to some legal proposition which was erroneous.

    34.Lord Dunedin in the Champsey Bhara case says that case differs from. Landauerv. Asser,(1905) 2 KB 184 “in an essential particular”. The difference is that in the Landauer case a legal proposition was stated in terms on which the award proceeded while in Champsey case no legal proposition at all is stated as a ground of the award. Lord Dunedin says at p. 69 “to make this equiparate with that of Landauerand Co. v. Asserand Co. (1905) 2 KB 184 the award would have to run somewhat thus:

    In respect of the ground of rejection contained in the letters of the 11th and 25th Nov. and in respect of clause 52 of the Articles, I decide that, etc.

    35. If these words are added in the Champsey award it would have the result of tying the arbitrators down to some legal proposition. If the arbitrator says: On the wording of this clause I hold so and so, then that clause is impliedly incorporated into the award because he invites the reading of it. BlaibarCo. v. LeopoldNewborne (London) Ltd., (1953) 2 Lloyd’s Rep. 427 at p. 429 per Denning LJ).

    36. The other principle Lord Dunedin enunciated is that if in a narra tive a reference is made to a contention of one party, that alone does not open the door to seeing first what that contention is and then going to the contract on which the parties rights depend to see if that contention is sound.

    37. In AlienBerry and Co. Ltd. v. Unionof India, AIR 1971 SC 696 the Supreme Court has said:

    The question whether a contract or a clause of it is incorporated in the award is a question of construction of the award. The test is, does the arbitrator come to a finding on the wording of the contract. If he does, he can be said to have impliedly incorporated the contract or a clause in it whichever be the case. But a mere general reference to the contract in the award is not to be held as incorporating it. The principle of reading contracts or other documents into the award is not to be encouraged or extended. The rule thus is that as the parties choose their own arbitrator to be the judge in the dispute between them, they cannot, when the award is good on the face of it, object to the decision either upon the law or the facts. Therefore even when an arbitrator commits a mistake either in law or in fact in determining the matters referred to him. but such mistake does not appear on the face of the award or in a document appended to or incorporated in it so as to form part of it, the award will neither be remitted nor set aside notwithstanding the mistake.

    38. Applying these principles to this case I find that there is no error in the majority awards because the arbitrators have not tied themselves down to any legal proposition.

    39. This conclusion was countered by counsel for the Corporation by referring us to the letter of Lord Devlin dated October 9, 1973 where he said that the supplemental agreement of March 21, 1967 defined the rights of the parties, and that they, the majority, will be concerned with the rights and duties of the parties under the arch Agreement. The short answer to the argument is that this letter dated Oct. 9, 1973 is not incorporated in the awardsinterim or final. Interim award is dated August 21, 1973. Final award is of February 16, 1974. This letter stands midway between the two dates. it is true that it expresses the view of the majority on an important question but it was signed by Lord Devlin alone. It was not signed by J. Russell Wilson, though it must have been written with his concurrence. But it is no part of the award, Unless it is referred to in the award it cannot be said to be incorporated therein. The principle of reading the contract or other document is not to be encouraged or extended. [Alien Berry and Co. Ltd. v. Union of India, (supra)]. To hold that the language used in the majority awards in the instant case incorporates the documents, such as the original contract of 1964, March Agreement of 1967, Lord Devlin’s letter of Oct. 1973, or so closely connects them therewith that they must be treated as part of the awards, would seem to me personally, with great respect, to make too much out of too little.

    40. The majority have not stated their reasons. We do not know the route of reasoning they took in arriving at their conclusion. It is not open to the Court to attempt to probe the mental process by which the arbitrator has reached his conclusion where it is not disclosed by the terms of the award. In Jivrajbhai Ujamshi Seth (supra) at p. 220 Shah J. said:

    An award may be set aside by the court on the ground of error on the face of the award, but an award is not invalid merely because by a process of inference and argument it may be demonstrated that the arbitrator has committed some misconduct in arriving at his conclusion.

    And again:

    It is not open to the court to speculate, where no reasons are given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion. On the assumption that the arbitrator must have arrived at his conclusion by a certain process of reasoning, the court cannot proceed to determine whether the conclusion is right or wrong.

    JivrajbhaiUjamshi Seth (supra) (p. 220).

    41. Once it is accepted that the court cannot explore the thought processes of the arbitrator how will it ever know what were his reasons for a given conclusion. The award which is the outer expression of the mind of the arbitrator does not give his inner thoughts.

    42. What was referred to the arbitrators were the specific disputes raised by the Corporation against the contractor and contractors disputes against the Corporation. On these the arbitrators gave their findings. They awarded some sums to the Corporation and some to the contractor. They gave a practical decision on merits according to their business sense. The arbitrators have said nothing on fundamental breach, implied warranty of fitness, Section 16 of the Sale of Goods Act or Section 73, Contract Act. These concepts figure prominently in the thinking of Mr. B. Sen as appears from his dissenting note. And it is on these that the Corporation stake their claim But the majority awards are non-speaking awards.

    43. The arbitrators award differs fundamentally from judicial justice that we the judges administer in courts of law. The judges are required in their judgments to give reasons because they have a Court of Appeal set over them. But it is not so with the arbitrator. His ropes and pulleys are different. The foot rules and the set-squares that he uses in arriving at his decisions are different from our known judicial methods. From his decision there is no appeal. The arbitrator is a domestic forum. He may be a lawyer or a layman. A lay arbitrator is not necessarily well versed in law. For that matter no one knows all the law, nor even lawyers and judges. In 1825 Abbot CJ said: God forbid that it should be imagined that an attorney, or a counsel, or even a judge is bond to know all the law. (2 C and P. 113).

    44. An arbitrator is not required to give reasons, He hears both sides and gives his decision. He is not bound by the technical rules of evidence. Nor by any fixed legal procedure. As Lord Halsbury observed in Andrewsv. Mitchel(1930) 74 LJK 339. “We must not insist upon a too minute observance of the regularity of forms among persons who naturally by their education or by their opportunities cannot be supposed to be very familiar with legal procedure, and may accordingly make slips in what is mere matter of form without any interference with the substance of their decisions.” All that is expected of an arbitrator is that he will act impartially. It is presumed that he will do so to the best of his ability. After hearing the injured and the injuring party he gives rough justice of the world. For good or ill, for better or worse, the parties have chosen him and have agreed to be bound by his award. This is why the award is final both on facts and law. Only on the restricted ground stated in sections 30 and 33 of the Act it can be set aside.

    45. Judicial demolition of an award is possible only when some legal proposition is stated in the award and which is erroneous. Two striking examples of erroneous legal propositions on which the awards were set aside are Dr.S. Dutt v. Universityof Delhi, AIR 1958 SC 1050 and Rohtas Industries and another v. Rohtas Industries (supra).

    46. Suppose the majority were wrong in their view that the March Agreement defines the rights and duties of the parties. So what? This is neither misconduct nor an error of law on the face of the award. The award will not be set aside because the arbitrators or the majority of them went wrong in their construction of the contract. Unless the majority in their awards say: On the wording of this clause we hold so and so there is no error on the face of it. Nor is it misconduct to decide a question wrongly. It is not misconduct for the arbitrator to make a mistake of law (Russell on Arbitration 20th ed. p. 423).

    47. Nor is it open to me on this motion to set aside the award only be cause I might myself have come to a different conclusion. The court does not sit in appeal over the decision of the arbitrators. The mere dissent of the court from the arbitrators conclusion on construction is not enough to set aside an award. (KalagtanGovt. v. DuffDevelopment Co., (1923) AC 395). The decision of the arbitrator cannot be set aside by the court only because the court would have come to a different conclusion on a question of construction of the contract. I therefore hold that the awards do not disclose any error of law.

    48. The awards do not set out any reasons. The majority awards are as inscrutable as the face of the sphinx. Nor is there any note appended to the awards by the majority stating the reasons for their judgment involving some legal proposition which is erroneous. The question of construction of contract is a question of law. But whether there was accord and satisfaction is essen tially a question of fact. The question of breach of contract and damages are questions of fact and are in the exclusive domain and province of the arbi trator. Even where an arbitrator makes a mistake either in law or in fact in determining the matters referred, the award is good notwithstanding the mistake. (N. Chellappan v. Secy. Karala State Elec. Board (supra). If the arbitrators arrive at an erroneous finding of fact it is not a ground for setting aside the award. It must be an error or law. It must appear from the award or in some contemporaneous document delivered with the award from which the error of law is apparent e.g, a note appended to the award by the arbitrator stating the reasons for his decision involving some legal proposition which is erroneous. There is nothing of the kind in this case. In my opinion the majority were entitled to come to the conclusion they did and I am unable therefore to set aside the award.

    49. One other question remains to be decided. The respondents claim interest under Section 29 of the Arbitration Act on the decretal amount from the date of the decree till payment. They have filed neither a cross-appeal nor cross- objections. But they invoke the powers of this court under Order 41 Rule 33, Code of Civil Procedure.

    50. The learned Judge has not awarded future interest. I think we ought not to interfere with his discretion. The matter of future interest is in the discretion of the court.

    51. In my opinion Order 41 Rule 33 cannot properly be invoked in the present case. Such a power is to be exercised in exceptional cases when its non-exercise will lead to difficulties in the adjustment of the rights of the various parties. (See RameshwarPrasad and others v. ShambehariLal Jagan-nath and another, AIR 1963 Supreme Court 1901). It is true that Order 41 Rule 33 is expressed in wide terms, but it has to be applied with discretion. It should be applied to cases where interference in favour of the appellant necessitates interference also with a decree which has by acceptance or acquies cence become final, so as to enable the court to adjust the rights of the parties. If the appellate court reaches a conclusion which is inconsistent with that of the court appealed from and in adjusting the right claimed by the appellant it is found necessary to grant relief to a person who has not appealed, the power under O. 41 Rule 33 may properly be invoked. (See Commissionerof Income Tax. Assam. Tripura and Manipur v. ThePanbari Tea Co. Ltd., AIR 1965 SC 1871). As the Supreme Court has said:

    No unrestricted right, however, is conferred by the Rule to reopen decrees which have become final merely because the appellate Court does not agree with the opinion of the court appealed from. (See Commissioner of Income Tax, Assam, Tripura and Manipur (supra).

    52. The cases decided by the Supreme Court show that this power is exercised in cases where as a result of interference in favour of the appellant it becomes necessary to adjust the rights of the other parties; in other words in cases where the question is one of setting mutual rights and obligations. (See T.Atchaih v. Narasingarao,AIR 1978 SC 725).

    53. I do not think the respondent can take recourse to Order 41 Rule 33, Code of Civil Procedure and ask us to modify the decree of the Trial Court by awarding him future interest. The main reason is that we are not interfering in favour of the appellant in this appeal. We are in fact dismissing the appellants appeal. Why should we interfere with the decree of the learned single judge or modify it so as to award interest to the respondent? No rights of the parties are required to be readjusted. We are letting things remain as they are.

    54. Counsel for the contractor referred us to MakkaNarsimlu v. Gunnala Raghunandan Rao, AIR 1977 Andhra Pradesh 374 in support of his contention. In this case it was held that interest could be allowed even though there was no appeal in this regard. With due deference to the learned judges I do not think that it is a proper exercise of the power under O. 41 Rule 33, C.P.C. In view of the Supreme Court judgment I have referred to above I am not prepared to hold that even in a case like the present O. 41 Rule 33 empowers us to award future interest when the learned single judge in his discretion has refused to award. The Andhra Pradesh decision is not in line with the Supreme Court rulings and makes a departure from the established law.

    55. An application for review was made to the learned single judge. He dismissed it on the ground that he was functus officio. In my opinion the respondent is not entitled to future interest. In this view of the matter I think it unnecessary to decide whether an appeal lies and if not, what is its effect? The prayer for future interest is therefore rejected.

    56. For these reasons the appeal of Fertilizer Corporation of India is dismissed with costs.

    Use AI to get other relevant cases.

    Comments

    The Fertilizer Corporation Of India Limited v. I.D.I. Management Inc. Others
    (Mar 1, 1984)