  • proved.6. S. 11 of the Sale of Goods Act
  • S. 11 of the Sale of Goods Act,
  • S. 20 of the Sale of Goods Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • proved.6. S. 11 of the Sale of Goods Act
  • S. 11 of the Sale of Goods Act,
  • S. 20 of the Sale of Goods Act
Smart Summary

Factual and Procedural Background

The plaintiff, a mill, filed a suit for recovery of Rs. 18,500 as damages for breach of contract against the defendant. The contract, allegedly concluded on 30th March 1972, involved the defendant's representative submitting a written tender to purchase 500 bags of E. 30 sugar at Rs. 262 per bag, which the plaintiff accepted. The defendant deposited Rs. 5,000 as an advance but failed to pay the balance by the stipulated date. The plaintiff sent telegrams requesting payment and delivery, to which the defendant responded with assurances but later repudiated the contract on the ground that it was not concluded. The plaintiff sold the sugar at a lower price, claiming a loss. The trial court found no concluded contract and dismissed the suit. The plaintiff appealed against this decision.

Legal Issues Presented

  1. Whether the defendant committed a breach of contract as alleged by the plaintiff?
  2. Whether the plaintiff is entitled to claim damages, and if so, what amount?
  3. What relief is the plaintiff entitled to?

Arguments of the Parties

Appellant's Arguments

  • The trial court erred in holding that no concluded contract existed on 30th March 1972.
  • The tender (Ex. A2) and subsequent correspondence establish a concluded contract for the purchase of 500 bags of sugar at Rs. 262 per bag.
  • The deposit of Rs. 5,000 by the defendant evidences the contract's validity.
  • The telegram dated 8th April 1972 (Ex. A3) indicates the defendant agreed to pay by 10th April and take delivery thereafter.
  • The contract was concluded on 30th March 1972, with only payment and delivery postponed, and thus cannot be considered incomplete or inchoate.

Respondent's Arguments

  • There was no concluded contract on 30th March 1972 as alleged.
  • The defendant never agreed to take delivery before 30th April 1972.
  • No specific agreement existed for payment of the full price by 10th April 1972.
  • The plaintiff unilaterally fixed the time for payment and delivery after tender acceptance.
  • No consensus existed on payment and delivery timings, so no breach occurred.
  • The defendant reserved the right to recover the Rs. 5,000 advance.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court analyzed the evidence and found that the plaintiff failed to prove a concluded contract existed as of 30th March 1972. The tender submitted by the defendant's representative (Ex. A2) did not specify the time for payment or delivery, and there was no documentary or oral evidence establishing an agreement on these terms. The court emphasized that a contract of sale is not complete unless there is agreement on the time for payment and delivery. The plaintiff's unilateral fixation of payment and delivery dates and subsequent cancellation of the contract was not justified. Under Section 11 of the Sale of Goods Act, time for payment is not prima facie essential unless stipulated otherwise, and here no such stipulation existed. Further, Section 20 of the Sale of Goods Act was considered: property in specific goods passes to the buyer when the contract is made, regardless of postponed payment or delivery. However, since no notice was given before resale and the plaintiff treated the goods as its own, this indicated absence of a concluded contract. The court concluded that either no contract existed or the plaintiff breached the contract first by terminating it unilaterally.

Holding and Implications

The appeal is dismissed.

The court upheld the trial court's finding that no concluded contract existed between the parties as alleged, and consequently no breach by the defendant was established. The plaintiff is not entitled to damages. No costs were awarded. This decision directly affects the parties by denying the plaintiff’s claim and affirming the defendant’s position. No new precedent was established by this ruling.

    The National Co-Operative Sugar Mills Ltd., Through The Special Officer, Alanganallur v. Messrs, Albert And Co, Rep. By Its Partner, S. Albert

    Ramanujam, J.

    1. The plaintiff in O. S. No. 336 of 1973 on the file of the Sub Court, Madurai, who has failed in that court, is the appellant herein.

    2. The appellant Mill filed the suit for recovery of a sum of Rs. 18,500, as damages for the breach of a contract which it had entered into with the defendant on 30th March 1972. The appellant's ease as set out in the plaint is that on 30th March 1972, the defendant's representative attended the Sales Committee meeting held by the plaintiff at Madurai District Central Cooperative Bank Ltd., Madurai, for fixing the price of sugar and gave a written tender on that day to purchase 500 bags of E. 30 sugar at 262 per bag. The said tender was accepted by the plaintiff and that acceptance was duly communicated to the defendant's representative who deposited then and there a sum of Rs. 5,000 representing Rs. 10 per bag as advance, agreeing to pay the balance of of the sale price by 10th April 1972, and take delivery of the entire 500 bags of E. 30 sugar thereafter. Since the defendant did not remit the balance of sale consideration till 8th April 1972, a telegram was sent by the plaintiff to the defendant calling upon the defendant to remit the balance of the cost of sugar before 10th April 1972, and lift the goods before 20th April 1972. The defendant in his reply telegram assured the remittance shortly. Thereafter the plaintiff extended the time for payment and for performance of the contract by the defendant till 20th April 1972, and the defendant was asked to perform his part of the contract by 20th April 1972. But the defendant by a telegram through his lawyer on 29th April 1972, repudiated the contract on the ground that the contract is not a concluded contract and therefore, the defendant is not bound to pay the sale consideration. Subsequently the price of sugar had fallen and the plaintiff had sold the sugar at a price ranging from Rs. 215 to Rs. 217 per bag exclusive of excise duty and therefore, the plaintiff has been put to a loss at the rate of Rs. 47 per bag and the total loss suffered by the plaintiff as a result of the defendant's breach of the contract is Rs. 23,500. Deducting a sum of Rs. 5,000 paid as advance by the defendant, the balance of 18,500 is payable by the defendant as and by way of damages for his breach of contract.

    3. The defendant resisted the suit contending that there was no concluded contract between the plaintiff and defendant on 20th March 1972, as alleged in the plaint, that the defendant never agreed to take delivery of the goods before 30th April 1972, that there was no specific agreement to remit the full price on or before 10th April 1972 and that the fixing of time for payment of the price and for taking delivery of the goods has been done unilaterally by the plaintiff long after the defendant submitted his tender and the same was accepted. Thus according to the defendant, there was no consensus between the parties as to the time for payment of the balance of sale consideration and as to the time for taking delivery and, that there is no question of the defendant committing breach of the contract which has not been duly concluded. The defendant also reserved his right to recover the advance amount of Rs. 5,000 paid by him to the plaintiff.

    4. On these pleadings the court below set out the following three issues for consideration—

    1. Whether It is true that the defendant has committed breach of contract as alleged by the plaintiff?

    2. Is the plaintiff entitled to claim damages? If so to what amount?

    3. To what relief?

    Under issue No. 1, the Court below held that since there was no concluded contract between the plaintiff and the defendant on 30th March 1972, under Ex.A2, the tender given by the defendants representative, there is no question of any contract and in view of the said finding on issue No. 1, the rest of the issues were found against the plaintiff and the suit was dismissed.

    5. In this appeal the learned counsel for the plaintiff-appellant contends that the Court below is in error in holding that there is no concluded contract established on the materials on record and that in fact Ex. A.2 the tender submitted by the defendant's representative, and the subsequent correspondence between the parties clearly establish the fact that there was a concluded contract on 30th March 1972, between the plaintiff and the defendant to purchase 500 bags of E. 30 sugar at the rate of Rs. 262 per bag and that it is only in pursuance of such-completed contract a sum of Rs. 5,000 was deposited by the defendant. It is pointed out that Ex.A3, the telegram which was sent on 8th April 1972 would clearly indicate that the defendant agreed to pay for the goods for the purchase of which he has submitted the tender on 10th April 1972 and take delivery of the same, and but for such an agreement the telegram would not have referred to the date 10th April 1972. It is also pointed out by the learned counsel that on 30th March 1972 itself the contract has been concluded and only the payment of the price and delivery of the goods have been postponed and therefore, the contract cannot be inchoate or incomplete. In this case, Ex. A2 which is the tender submitted by the defendant's representative to purchase 500 bags of E. 30 suger at the price of Rs. 262 per bag does not refer to the time for payment of the price though the plaintiff would say that the tender was accepted and the defendant was asked to pay the price and take delivery of the goods on 10th April 1972. There is, however, no document in support thereof. Admittedly, the communication by the plaintiff accepting the tender of the defendant is oral and there is no document by which the plaintiff has communicated the time for payment of the price and for taking delivery of the goods to the defendant. Curiously, no oral evidence also has been adduced in this case either by the plaintiff or by the defendant Apart from the submission of the tender and its acceptance, that there was a further discussion as to the time for delivery and for payment of the price should have been brought to light at least in the oral evidence. It cannot be disputed that it is the plaintiff who has come forward with a specific case that on 30th March 1972, the defendant agreed to pay the sale consideration and take delivery of the goods on 10th April, 1972, and therefore, it is for him to establish that fact by adducing concrete and positive evidence. However, the plaintiff has felt satisfied itself by producing Ex. A2, the tender submitted by the defendant's representative. As already stated, the tender is silent as to the time for payment of the price and for taking delivery of the goods. A contract of sale cannot be said to be complete unless the parties to the contract have agreed as to the time for payment of the sale price and for taking delivery of the goods. It is true under Ex. A 3 the plaintiff has called upon the defendant to pay the sale price before 10th April 1972, and make arrangements to take delivery of the goods by 20th April 1972. But unless there is an earlier agreement between the parties as to the time for payment of the price and for taking delivery of the goods the plaintiff cannot unilaterally fix the time for payment of the goods and for taking delivery of the same and cannot cancel the contract again unilaterally after the defendant has committed default in payment of the price and taking delivery of the goods as called upon within the date fixed by the plaintiff. On the materials on record, we cannot say that the plea of the plaintiff that the defendant agreed to pay the price and take delivery of the goods by 10th April 1972, has been proved.

    6. S. 11 of the Sale of Goods Act says, unless a different intention appears from the terms of the contract, stipulations as to the time of payment are not deemed to be the essence of a contract of sale. Even if the time for payment is fixed under the contract that cannot be taken prima facie to be the essence of the contract of sale as contemplated by S. 11 of the Sale of Goods Act, unless there is a stipulation to the contrary in the contract itself. The time cannot be taken to be the essence of the contract in a case where the contract itself does not stipulate the time for payment of the price, It is well established that it is only in cases where the time is the essence of the contract the vendor can cancel the contract for non-payment of the price within the time stipulated. In this case in Ex. A 2, the defendant has not fixed any time for payment of the price and this shows that the time is not the essence of the contract and thus the plaintiff who has chosen to cancel the contract as the defendant has not paid the sale consideration within the time stipulated by him unilaterally is not entitled to cancel the contract. This is one of the reasons given by the court below for non-suiting the plaintiff.

    7. There is also a further aspect to be taken note of in this case. S. 20 of the Sale of Goods Act proceeds on the basis that in a case where there is an unconditional contract for the sale of specific goods in a deliverable state, the property in the goods passes to the buyer when the contract is made, and it is immaterial whether the time of payment of the price or the time of delivery of the goods, or both, is postponed. In this ease, Ex.A2, the tender submitted by the defendant's representative does not refer to the time for payment of the price and the time for taking delivery of the goods. However, according to S. 20 the property In goods should be taken to have passed to the defendant and the plaintiff will be entitled to claim only unpaid vendor's lien; but the plaintiff in this case has not proceeded on that basis. Admittedly, no notice has been given before the resale of the sugar which the defendant failed to take delivery in pursuance of the contract and the plaintiff has admittedly sold the consignment of 500 bags of E. 30 sugar treating the stocks as its own. This also will show that the contract is not a concluded one as contended by the plaintiff-appellant. Thus on a due consideration of the matter we hold that the plaintiff is not entitled to claim damages, firstly on the ground that there was no concluded coo tract and as such there could not have been any breach thereof committed by the defendant, and secondly on the ground that even assuming that there was a concluded contract the materials on record would show that it was the plaintiff who has committed the breach by terminating the contract taking the time as the ground that the defendant did not pay the price and take delivery of the goods by 20th April 1972.

    8. For the foregoing reasons this appeal has to be dismissed, and is therefore, dismissed. Under the circumstances, there will be no order as to costs.