AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Maharashtra Restoration of Lands to Scheduled Tribes Act, 1974 (hereinafter referred to as the Act)
  • S. 84-C of the Bombay Tenancy and Agricultural Lands Act, 1976
  • Scheduled Tribes Order (Amendment) Act, 1976,
  • S. 3(1) of the Restoration Act.
  • S. 3 of the Restoration Act
  • Scheduled Tribes Act, 1974
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Maharashtra Restoration of Lands to Scheduled Tribes Act, 1974 (hereinafter referred to as the Act)
  • S. 84-C of the Bombay Tenancy and Agricultural Lands Act, 1976
  • Scheduled Tribes Order (Amendment) Act, 1976,
  • S. 3(1) of the Restoration Act.
  • S. 3 of the Restoration Act
  • Scheduled Tribes Act, 1974
Smart Summary

Factual and Procedural Background

This petition challenges the Maharashtra Revenue Tribunal's order dated 22-1-1992 which upheld the Tahsildar, Yavatmal's direction to restore land transferred by Respondent 2, Bablu Kolam. The Tahsildar, acting in suo motu proceedings under the Restoration of Lands to Scheduled Tribes Act, 1974 ("the Act"), concluded that lands purchased by the petitioners were liable to be restored to the tribal transferor. Because the tribal transferor was not prepared to deposit the costs of land and improvements, the Tahsildar held the land should vest in the Government from the date of his order.

Key factual points (as stated in the opinion):

  • Both petitioners purchased agricultural land from Respondent 2 Bablu on 9-4-1972; lands are in Survey No. 1 of Village Ghoti.
  • On 29-8-1975 Respondent 2 applied for restoration under Section 36 of the Maharashtra Land Revenue Code; Tahsildar rejected this application on 31-5-1976 concluding Respondent 2 was not a tribal for Yavatmal district (the 5-6-1968 notification did not apply there).
  • On 1-2-1978 the Additional Tahsildar initiated suo motu proceedings under the Restoration Act and concluded lands were liable to be restored to Respondent 2; because Respondent 2 would not deposit costs, the Tahsildar held the land should vest in the Government.
  • The petitioners appealed to the Maharashtra Revenue Tribunal, which dismissed the appeal by judgment dated 22-1-1992. The present writ petition challenges that Tribunal judgment.

Legal Issues Presented

  1. Whether under Section 3 of the Restoration of Lands to Scheduled Tribes Act, 1974 the Collector/Tahsildar's suo motu power to initiate proceedings is subject to any time limit, or whether such proceedings may be lawfully initiated "at any time".
  2. Whether Respondent 2 (Bablu Kolam) was required to be a member of a Scheduled Tribe on the date of the transfer (9-4-1972) for the transfer to be liable to restoration under the Act.

Arguments of the Parties

Petitioners' Arguments (as reported)

  • Mr. Bhuibhar, counsel for the petitioners, contended that the suo motu proceedings were barred for being initiated after an unreasonable delay. He argued that where a statute does not prescribe a time for initiation of suo motu proceedings, such power must be exercised within a reasonable time and relied on the Supreme Court decision in Mohd. Kavi Mohd. Amin v. Fatmabai Ibrahim (1997 6 SCC 71) for that proposition.
  • The petitioners also contended that Respondent 2 was not a tribal on the date of purchase (9-4-1972) because the Kolam tribe was notified as a Scheduled Tribe for the first time on 27-7-1977 (the opinion states "27-7-1997" in the text provided). On this basis they argued the transaction was not one "between a Tribal transferor and a non-tribal transferee" and hence not covered by the Act.

Respondents' / State's Arguments (as reported)

  • The Assistant Government Pleader submitted that Section 3 of the Act expressly empowers the Collector to initiate suo motu proceedings "at any time" and therefore there is no limitation or requirement to act within a conventional "reasonable time".
  • The counsel for Respondent 2 supported the view that the suo motu power could be exercised at any time and (as later recorded in the opinion) their arguments, together with the Assistant Government Pleader's, were held to be well founded.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mohd. Kavi Mohd. Amin v. Fatmabai Ibrahim, 1997 6 SCC 71 Where a statutory provision (S. 84-C of the Bombay Tenancy and Agricultural Lands Act, 1976, in that case) does not prescribe a time for initiating suo motu proceedings, the power must be exercised within a reasonable time; the Supreme Court there set aside suo motu proceedings held not to be within a reasonable time. The Court distinguished this precedent: S. 3 of the Restoration Act explicitly authorizes the Collector to act "at any time", unlike the provision construed in Mohd. Kavi. Therefore the principle in Mohd. Kavi (importing a conventional reasonable-time limitation) did not apply to S. 3 as it positively enabled action at any time.
Lingappa Pochanna Appelwar v. State of Maharashtra, 1985 1 SCC 479 Characterisation of the Restoration Act as an instrument of distributive justice and remedial legislation to correct unconscionable transfers from tribals to non-tribals; legislative intent to restore property to weaker sections. The Court relied on these observations to support a liberal construction of Section 3, emphasizing the remedial, distributive purpose of the Act and concluding the legislature intended robust suo motu powers to protect tribals.
Kashibai v. State of Maharashtra, 1993 2 Mah LJ 1168 Division Bench observation that for the purposes of Section 3(1) of the Restoration Act protection is conferred upon "tribals as defined in the said Act" and that the status required by S.3 is that of a tribal as defined in the Act (not necessarily being a scheduled tribe on the date of transfer). The Court relied on this Division Bench view to reject the petitioners' contention that Respondent 2 had to be a Scheduled Tribe on the date of transfer. Applying Kashibai, the Court held the petitioners' challenge on this ground unsustainable and dismissed the petition.
Tukaram Laxman Gandewar v. Piraji Dharmaji Sidarwar, 1989 Mah LJ 815 Earlier decisions interpreted to require that the person claiming to be a tribal must bear that character on the date of transfer (as cited in Kashibai). Referenced in the opinion as part of prior case-law that was discussed and effectively distinguished by the Division Bench in Kashibai; the Court in the present opinion followed the Kashibai reasoning rather than the earlier Tukaram approach.
Chhotelal Bansilal Awasthi v. State of Maharashtra, 1990 Mah LJ 766 Earlier Single Judge decision following the view that tribal status must exist on the date of transfer (as discussed in Kashibai). Referenced as part of the body of precedents considered in Kashibai; the Court in the present opinion preferred the Kashibai Division Bench interpretation over the earlier Single Judge view.

Court's Reasoning and Analysis

The Court analyzed the questions by closely reading Section 3 of the Restoration of Lands to Scheduled Tribes Act, 1974. The reasoning proceeded in these principal steps (as stated in the opinion):

  1. Textual construction of S. 3: The Court noted that S. 3 expressly provides that the Collector may act "either suo motu at any time, or on the application of a Tribal transferor made within three years from the commencement of this Act". From a plain reading the words "at any time" positively enable initiation of suo motu proceedings without temporal limitation. The Court drew a distinction between a provision that omits a time-limit and one that expressly authorizes action "at any time".
  2. Distinction from Mohd. Kavi: Because S. 3 contains the explicit phrase "at any time", the Court distinguished the Mohd. Kavi decision (which dealt with a provision that did not prescribe any time-limit) and held that the usual concept of "reasonable time" applicable where no time is prescribed could not be automatically imported into S. 3.
  3. Legislative intent and remedial purpose: The Court examined the object and purpose of the Restoration Act — to protect tribals from exploitation and to restore lands sold by tribals between 1-4-1957 and 6-7-1974. Citing the remedial and distributive justice character of the legislation (drawing on Lingappa Pochanna Appelwar), the Court held that the Act's purpose supported a broad suo motu power exercisable "at any time".
  4. Contextual indication of legislative tolerance for delay: The Court noted that the limitation period for filing an application under S. 3 had been extended by the legislature from three years to thirty years in 1991. The Court treated this legislative amendment as indicative that the concept of reasonable time, if to be read into the Act at all, should be much longer (in the "region of thirty years") than an ordinary "reasonable time".
  5. On the issue of tribal status at date of transfer: The Court relied on the Division Bench decision in Kashibai v. State of Maharashtra, which held that S. 3 confers protection upon "tribals as defined in the Act" and that the status required by S. 3 does not have to be the tribal's status on the date of transfer. Applying Kashibai, the Court rejected the petitioners' contention that Respondent 2 had to be a Scheduled Tribe on 9-4-1972 for the Act to apply.
  6. Conclusion of analysis: The combination of textual interpretation ("at any time"), the remedial objective of the statute, the legislative amendment extending limitation to thirty years, and authoritative precedent (Kashibai) led the Court to conclude that the suo motu proceedings were lawfully initiated and that Respondent 2's claim was maintainable under S. 3.

Holding and Implications

Holding: The Court held that Section 3 of the Restoration of Lands to Scheduled Tribes Act authorizes the Collector/Tahsildar to initiate suo motu proceedings "at any time" and therefore the suo motu proceedings in this case were not barred by delay. The Court further held, following the Division Bench in Kashibai, that it is not necessary for the person claiming restoration to have had scheduled-tribe status on the date of the transfer for S. 3 to apply. Accordingly, the petition was dismissed and the Rule was discharged.

Direct consequences for the parties: The decision upholds the Tahsildar's and the Maharashtra Revenue Tribunal's orders that the lands in question are liable to be restored to the tribal transferor (and, because the transferor did not deposit costs, that the lands should vest in the Government as per the earlier administrative direction). The petitioners' challenge was rejected.

Broader implications: The Court emphasized a liberal construction of remedial protection afforded to tribals by the Restoration Act and accepted a broad temporal reach for suo motu proceedings under S. 3. The opinion relies on existing precedents and interpretations (notably Lingappa and Kashibai) to interpret legislative purpose; the Court did not record the creation of a new legal principle beyond these interpretative conclusions.

Administrative note recorded in the judgment: The Court granted the petitioners' prayer for a stay of the operation of this judgment for a period of six weeks from the date of the judgment.

    Vimlabai And Another Petitioners v. State Of Maharashtra And Another S

    The Judgment of the Court was delivered by

    S.A Bobde, J.— This petition challenges the order dated 22-1-1992 passed by the Maharashtra Revenue Tribunal upholding the direction of the Tahsildar, Yavatmal, to restore the land transferred by Respondent 2 Bablu Kolam. The Tahsildar in suo motu proceedings under the Maharashtra Restoration of Lands to Scheduled Tribes Act, 1974 (hereinafter referred to as “the Act”) came to the conclusion that the lands purchased by the petitioners were liable to be restored to the tribal transferor. However, since the tribal transferor was not ready to deposit the costs of the land and improvements, the Tahsildar held that the land should vest in the Government with effect from the date of the said order.

    2. The facts, in brief, are:

    Both the petitioners purchased agricultural lands from Respondent 2 Bablu on 9-4-1972. The lands are situated in Survey No. 1 of Village Ghoti.

    3. On 29-8-1975 the 2nd respondent applied for restoration of the said lands under S. 36 of the Maharashtra Land Revenue Code. These proceedings were rejected on 31-5-1976 by the Tahsildar, Yavatmal. The Tahsildar came to the conclusion that the 2 respondent was not a tribal since the notification dated 5-6-1968 under which Kolam was recognized as Scheduled Tribe did not apply to Yavatmal district.

    4. Thereafter on 1-2-1978 the Additional Tahsildar commenced the suo motu proceedings under the Act and came to the conclusion that the lands were liable to be restored to the 2 respondent. However, since the 2 respondent was not ready to deposit the costs of the land and improvements, the Tahsildar held that the land should vest in the Government with effect from the date of the said order. Against the order of the Tahsildar, the petitioner preferred an appeal before the Maharashtra Revenue Tribunal. That Tribunal has dismissed the appeal by the judgment dated 22-1-1992 which is impugned in this writ petition.

    5. Mr Bhuibhar, learned counsel for the petitioners firstly contended that the suo motu proceedings for restoration of land are barred since they were not initiated within a reasonable time. According to the learned counsel, the power to initiate suo motu proceedings is undisputable. The submission is that since no time is prescribed by S. 3 of the Act for initiation of the suo motu proceedings, the proceedings must be initiated within a reasonable time. The learned counsel relies on the decision of the Supreme Court in Mohd. Kavi Mohd. Amin v. Fatmabai Ibrahim 1997 6 SCC 71. That was a case where the Supreme Court took the view that S. 84-C of the Bombay Tenancy and Agricultural Lands Act, 1976 does not prescribe any time for initiation of the proceedings. Therefore, in view of the settled position of law that wherever a power is vested in a statutory authority without prescribing any time-limit, such power should be exercised within a reasonable time. The Supreme Court took the view that the suo motu enquiry initiated in September 1973 to set aside a transfer which took place in December 1972 was not within a reasonable time. Their Lordships, therefore, set aside the suo motu proceedings on the ground that the power was not exercised by the Mamlatdar within a reasonable time. In the present case, it is undisputed that the Act came into force on 1-11-1975 and the suo motu proceedings commenced on 1-2-1978, i.e within three years of the commencement of the Act. The learned Asstt. Government Pleader argued to the contrary and submitted that under S. 3 of the Act, the Tahsildar has the power to initiate proceedings at any time.

    6. The first question, therefore, that arises for my consideration is whether under S. 3 of the Act any time is provided for initiation of suo motu proceedings or whether the said proceedings can be initiated at any time. The relevant part of S. 3 reads as under:

    “3. (1) Where due to transfer—

    (a) the land of a Tribal transferor is held by a non-Tribal transferee, or

    (b) the land acquired in exchange by a Tribal transferor is less in value than the value of the land given in exchange,

    and the land so transferred is in possession of the non-Tribal transferee, and has not been put to any non-agricultural use on or before the 6th day of July 1974, then, notwithstanding anything contained in any other law for the time being in force, or any judgment, decree or order of any court, Tribunal or authority, the Collector either suo motu at any time, or on the application of a Tribal transferor made within three years from the commencement of this Act shall, after making such inquiry as he thinks fit, direct that—

    (i) the lands of the Tribal transferor and non-Tribal transferee so exchanged shall be restored to each other; and the Tribal transferor, or as the case may be, the non-Tribal transferee shall pay the difference in value of improvements as determined under cl. (a) of sub-s. (4), or

    (ii) the land transferred otherwise than by exchange be taken from the possession of the non-Tribal transferee, and restored to the Tribal transferor, free from all encumbrances, and Tribal transferor shall pay such transferee and other persons claiming encumbrances the amount determined under cl. (b) of sub-s. (4):

    Provided that, where land is transferred by a Tribal transferor in favour of a non-Tribal transferee before the 6 day of July, 1974, after such transferee was rendered landless by reason of acquisition of his land for a public purpose, then only half the land so transferred shall be restored to the Tribal transferor.”

    It is clear from a plain reading of the aforesaid section that the time to initiate suo motu proceeding is not limited. The section states that they may be initiated at any time. This, in my view, is different from a situation where the section merely does not prescribe the time for initiation of suo motu proceedings. In other words, there is a difference between a provision which omits to prescribe the time for initiating proceedings and a provision which positively enables the initiation of the proceedings at any time. The latter must be construed to specifically enable the Tahsildar to initiate suo motu proceedings at any time. Thus, the provision in question is different from the provision construed by the Supreme Court in the aforesaid case.

    7. Even otherwise, having regard to the intent and purpose of S. 3 of the Act, it appears that the legislature intended to enable the initiation of proceedings at any time. The Restoration of Lands to Scheduled Tribes Act, 1974 was enacted specifically to protect the tribals from exploitation by non-tribals in the matter of transfer of lands. In fact, this Act was enacted in addition to the provisions for protection of lands for tribals contained in the Maharashtra Land Revenue Code. It is obvious that special provisions have been made for restoration of lands to Scheduled Tribes because the tribals are traditionally not literate and susceptible to exploitation in the matter of their rights in lands. The Act is intended to restore the lands sold by the tribals in favour of non-tribals between the period 1-4-1957 and 6-7-1974 upon payment of the purchase prices originally received by the tribals and on certain other terms and conditions stipulated in the Act. It is to enforce this objective of the Act that the legislature has conferred a suo motu power which may be exercised by the Collector at any time. Having regard to the context of the text, I am of view that the words “any time” must be given full effect to and must be taken to have conferred power on the Collector to initiate proceedings at any time without any limitation. In any case, the usual concept of reasonable time cannot be imported while construing the provisions of this law. It is noteworthy that the limitation for preferring an application for restoration of lands in the very same S. 3 has been amended from three years to thirty years by the legislature in the year 1991. If at all the concept of reasonable time is to be incorporated into this provision, it would be somewhere in the region of thirty years as indicated by the legislature itself.

    8. The Restoration of Lands to Scheduled Tribes Act, 1974 has been enacted as a major distributive justice. In Lingappa Pochanna Appelwar v. State of Maharashtra 1985 1 SCC 479 the Supreme Court made the following observations regarding law: (SCC p. 493, para 16)

    “16. The present legislation is a typical illustration of the concept of distributive justice, as modern jurisprudence knows it. Legislators, Judges and administrators are now familiar with the concept of distributive justice. Our Constitution permits and even directs the State to administer what may be termed as “distributive justice”. The concept of distributive justice in the sphere of law-making connotes, inter alia, the removal of economic inequalities and rectifying the injustice resulting from dealings or transactions between unequals in society. Law should be used as an instrument of distributive justice to achieve a fair division of wealth among the members of society based upon the principle: ‘From each according to his capacity, to each according to his needs.’ Distributive justice comprehends more than achieving lessening of inequalities by differential taxation, giving debt relief or distribution of property owned by one to many who have none by imposing ceiling on holdings, both agricultural and urban, or by direct regulation of contractual transactions by forbidding certain transactions and, perhaps, by requiring others. It also means that those who have been deprived of their properties by unconscionable bargains should be restored their property. All such laws may take the form of forced redistribution of wealth as a means of achieving a fair division of material resources among the members of society or there may be legislative control of unfair agreements.”

    The Supreme Court further observed: (SCC p. 494, para 18)

    “18. The impugned Act is nothing but a remedial measure in keeping with the policy of the State for rendering social and economic justice to this weaker section of the society. The taking of their lands may have been done by way of transfer under the ordinary laws in various ways. The processes and forms of law were apparently followed. But the result has been devastating. As a result of such unequal transactions which were grossly unconscionable and unjust, the tribals lost their lands to non-tribals and were rendered landless. It is implicit in the nature of the legislation that the law regards such transactions as unconscionable and oppressive, and directs restoration of the property to the tribal transferor treating the transfer to be non est. It is axiomatic that a contract is liable to be set aside due to inequality of bargaining power, if someone without independent advice, enters into a contract on terms which are very unfair or transfers property for a consideration which is grossly inadequate when his bargaining power is grievously impaired by reason of his own need or circumstances, or by his own ignorance or infirmity, coupled with undue influences or pressures brought to bear on him by or for the benefit of the other.”

    9. Bearing the aforesaid observations in view, it is not possible to accept the contention on behalf of the petitioners that the suo motu proceedings must be commenced within a reasonable time, as ordinarily understood in law. Rather in the context of this legislation, it would be appropriate to hold that the concept of reasonable time must be construed very liberally to defend the object of the statute and would be in the region of about 30 years as is indicated by the legislature. The arguments of the learned Assistant Govt. Pleader and the learned counsel for Respondent 2 are well founded.

    10. The next contention raised on behalf of the petitioners is that Respondent 2 was not a tribal on the date on which the petitioners purchased the land from him, i.e on 9-4-1972. According to the learned counsel for the petitioners, it is necessary for a transaction to be covered by the Act that the transaction should be between a Tribal transferor and non-tribal transferee. In the petitioner's submission, since Respondent 2's tribe Kolam was notified as Scheduled Tribe for the first time on 27-7-1997 under the Scheduled Tribes Order (Amendment) Act, 1976, the lands purchased by the petitioners are not liable to be restored to the tribals, in this case to the Government by virtue of S. 5-A of the Act. This submission would have been acceptable but for the observations of the Division Bench of this Court in Kashibai v. State of Maharashtra 1993 2 Mah LJ 1168. In that case, the Division Bench of this Court made the following observations: (Mah LJ p. 1184, para 36)

    “36. The learned counsel for the appellants had, however, strenuously urged before us relying upon the judgment of the Division Bench in Tukaram case Tukaram Laxman Gandewar v. Piraji Dharmaji Sidarwar, 1989 Mah LJ 815 as well as the judgments of the learned Single Judge in Chhotelal Bansilal Awasthi v. State of Maharashtra 1990 Mah LJ 766 following the same that the person claiming to be tribal must bear on the date of transfer the character of a tribal i.e of the scheduled tribe recognized under the Scheduled Tribes Order issued under Art. 342 of the Constitution of India, which is applicable on the date of transfer. It is no doubt true that for the purposes of S. 36-A of the Code, the tribal must have that character on the date of transfer because obviously such transfer sought to be effected by him requires the permission of the Collector under sub-s. (1) thereof. However, there cannot be any parity of reasoning to apply the same ratio in interpreting S. 3(1) of the Restoration Act. As referred to by us hereinabove reading of S. 3 of the Restoration Act shows that it confers protection upon the tribals as defined in the said Act. It is their land which is sought to be restored to them, if it was transferred by them during the period from 1-4-1957 to 6-7-1974. The right is thus conferred upon the tribals as defined under the said Act. It has nothing to do with what status he held when actually the transaction was entered into by him.”

    11. Thus the Division Bench has held that the earlier view of the Court that if a person is notified as a tribal subsequently and was not a tribal on the date of transaction, then he is not entitled to have the land restored to him, is not correct. In the circumstances, the petition is liable to be dismissed. Rule is discharged.

    12. At this stage, Mr Bhuibhar, learned counsel for the petitioners, prays for stay of this judgment in view of the fact that the petitioners have been in possession of the lands for the last thirty years. This judgment shall stay as prayed for and will not operate for a period of six weeks from today.