AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 39 Rules 1 and 2 of the Code of Civil Procedure
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 39 Rules 1 and 2 of the Code of Civil Procedure
Smart Summary

Factual and Procedural Background

The appellant–plaintiff instituted a suit for declaration and injunction in respect of certain immovable property. Two interlocutory applications under Order 39 Rules 1 & 2, Code of Civil Procedure, sought to (1) restrain the respondents from alienating the suit property and (2) prevent any change in its nature during pendency of the suit. The trial court appointed an Advocate Commissioner to verify the status of construction on the property. Relying on the Commissioner’s report and accompanying photographs—which indicated that extensive construction had already been completed at considerable cost—the trial court refused to grant interim injunction. Instead, it imposed three conditions concerning deposit of the property’s balance value, furnishing of bank guarantees, and disclosure obligations toward prospective purchasers.

On appeal, the High Court of Andhra Pradesh affirmed the refusal of injunction but struck down the first two conditions imposed by the trial court. The appellant challenged these concurrent orders before the Supreme Court through the present special leave petitions.

Legal Issues Presented

  1. Whether the courts below erred in refusing interim injunction restraining the respondents from further construction or alienation of the suit property.
  2. Whether substantial construction has in fact been carried out on the suit property, justifying the refusal of injunctive relief.
  3. Whether the conditions imposed by the trial court (and partly set aside by the High Court) were sustainable.

Arguments of the Parties

Appellant-Plaintiff’s Arguments

  • Relied on portions of the Advocate Commissioner’s report to contend that no construction had been undertaken on the suit property.
  • Maintained that, in the absence of substantial construction, an injunction was necessary to preserve the property’s status quo pending trial.

Respondent-Defendants’ Arguments

  • Drew the Court’s attention to other parts of the Commissioner’s report and produced recent photographs showing significant, costly construction already completed.
  • Argued that the trial court and High Court correctly denied injunction because the equities now favoured allowing continued use of the property, subject to the suit’s ultimate outcome.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court found it necessary to ascertain the actual, current status of the suit property before ruling on the merits of the special leave petitions. Noting conflicting representations by counsel regarding the extent of construction, the Court formed a prima facie opinion that additional factual verification was essential “to do complete justice.” Accordingly, it framed five specific factual queries concerning:

  1. Presence and location of constructions on different blocks.
  2. Nature and extent of such constructions.
  3. Whether the constructions qualify as “substantial.”
  4. Completion status of any blocks and readiness of flats for occupation.
  5. Other relevant local features.

To answer these questions, the Court appointed Shri Ram Krishna Prasad, Advocate, as Commissioner, directing him to inspect the site, give prior notice to all parties, and submit a report within a specified timeline. The Court emphasised that the matter would thereafter be considered solely on the basis of this report and that no further oral hearing would be granted.

Holding and Implications

INTERIM ORDER: The Supreme Court appointed an Advocate Commissioner to inspect the suit property and report on specified factual issues by 27-7-2009; the matter is listed for consideration of the report on 28-7-2009. Respondents must bear travel expenses and pay the Commissioner’s remuneration of Rs 30,000 by 24-7-2009.

Implications: The order does not dispose of the special leave petitions but temporarily pauses adjudication pending factual clarification. It preserves the status quo while ensuring that the Court will have reliable, contemporaneous evidence before deciding whether to grant or deny interim injunctive relief. No new legal precedent is set at this stage; the effect is confined to the parties and the ongoing suit.

    Ece Industries Limited (1) v. S.P Real Estate Developers Private Limited And Another

    Order

    1. The instant special leave petitions arise from an appellate order of the High Court of Andhra Pradesh at Hyderabad, by which the High Court had affirmed the order of the Second Additional City Civil Judge at Hyderabad refusing to grant an order of injunction till the disposal of the suit which has been filed by the appellant-plaintiff for declaration and injunction.

    2. In the aforesaid suit, two applications for injunction under Order 39 Rules 1 and 2 of the Code of Civil Procedure were filed by the appellant-plaintiff. The relief that was prayed for in one of the applications for injunction was to restrain the respondents from alienating the suit property including the structures coming up thereon and the other for injunction over the suit property from changing the nature thereof pending disposal of the suit.

    3. While deciding the said applications for injunction, an Advocate Commissioner was appointed by the trial court to find out the extent of construction raised by the respondent-defendants in the suit property in view of the fact that there was a denial on the part of the appellant-plaintiff that there was no construction at all. The Advocate Commissioner appointed by the trial court submitted his report, which is already on record.

    4. While deciding the applications for injunction, the said report was taken into consideration by the trial court and as per that report and also as per the photographs produced by the Advocate Commissioner, the trial court was prima facie of the view that construction work was undertaken and completed which had required the respondents to invest crores of rupees.

    5. The trial court, considering this fact that substantial construction has already been completed, had refused to grant an order of injunction in favour of the appellant-plaintiff from making any construction in the suit property and, accordingly, the applications for injunction were rejected with the following conditions:

    “(1) That the respondents shall deposit the balance value of the property, which comes to around Rs 28,00,000 into court within one month.
    (2) That it shall furnish bank guarantee for the value of the unrealised post-dated cheques, and pay/deposit the value of four cheques, which were dishonoured, within one month from today.
    (3) That the respondents shall not claim equities over the construction made in the land and they are bound by the decision in the suit. The respondents shall furnish the particulars of the prospective buyers of the residential units in advance to the competent authority/urban land ceiling, and it must be made clear to the prospective buyers that their purchases are subject to the result of the suit by making a ‘specific recital’ in the agreement of sale or sale deed, as the case may be.”

    6. Aggrieved by the order of the trial court, the appeals were preferred before the High Court of Andhra Pradesh at Hyderabad, which by the impugned order, had affirmed the order of the trial court on the question of construction in the suit property, but set aside the conditions imposed by the trial court being Clauses 1 and 2 of the order of the trial court. It is these concurrent orders, which are now under challenge before us in these special leave petitions.

    7. Before us, both the learned Senior Counsel appearing for the parties had drawn our attention to the report of the Advocate Commissioner.

    8. Mr Nariman, learned Senior Counsel appearing for the appellant-plaintiff, sought to argue after taking us to the report of the Advocate Commissioner that no construction has been made in the suit property whereas Dr. Singhvi, learned Senior Counsel appearing on behalf of the respondent-defendants, after taking us to some of the portions of the Advocate Commissioner's report and also by producing recent photographs to show substantial constructions already made in the suit property, sought to argue that the appellate court was fully justified in affirming the order of the trial court holding that substantial construction has been made in the suit property for which the respondents have invested huge sum of money.

    9. After hearing the learned counsel for the parties and after going through the Commissioner's report, we are of the prima facie view that before deciding this special leave petition finally on merits, it would be proper in order to do complete justice to find out the actual position of the suit property i.e:

    (i) Whether constructions have been made on the different blocks of the suit property and how many blocks are still remaining vacant?
    (ii) If constructions have been made, what is the nature and extent of such constructions?
    (iii) Whether such constructions can be said to be substantial constructions or not.
    (iv) Whether constructions have been completed in some blocks of the suit property and the flats constructed in such blocks are ready for use and occupation.
    (v) Also to see the local features.

    To find out the aforesaid, we appoint Shri Ram Krishna Prasad, a learned advocate of this Court, who will visit the suit property in course of this week by giving prior notice to both the sides and submit a report on the abovementioned items by next Monday i.e on 27-7-2009. The matter will be placed again for consideration of the said report on 28-7-2009. We make it clear that there will be no further hearing in the matter.

    10. The entire expenses of the learned Advocate Commissioner for visiting the site and coming back to Delhi, shall be met by the respondents and the remuneration of the Commissioner shall also be borne by the respondents, which is assessed at Rs 30,000 to be paid in course of this Friday i.e 24-7-2009.

    Use AI to get other relevant cases.

    Comments

    Ece Industries Limited (1) v. S.P Real Estate Developers Private Limited And Another
    (Jul 23, 2009)