AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Smart Summary

Factual and Procedural Background

This petition under Article 227 of the Constitution of India challenges the order dated 19-2-2013 passed by the trial Court, which allowed an application under section 14 of the Arbitration and Conciliation Act, 1996 (the 1996 Act) filed by respondent No. 1 seeking termination of the mandate of the arbitral tribunal.

The petitioner No. 1, a company incorporated under the Companies Act, 1956, entered into a concession agreement dated 11-4-2003 with respondent No. 1 for construction and maintenance of the Sagar-Damoh-Jabalpur road on a Build-Operate-Transfer (BOT) basis. A State Support Agreement was also executed on 14-4-2003 by the petitioner, respondent No. 1, and the Government of Madhya Pradesh, under which the State Government guaranteed implementation of the concession agreement by respondent No. 1.

Respondent No. 1 rescinded the contract on 12-7-2007 citing delay in completion. Clause 39 of the concession agreement provided for dispute resolution by arbitration under the 1996 Act. The petitioner appointed an arbitrator, and respondent No. 1 appointed another arbitrator; both appointed a presiding arbitrator.

The petitioner filed a statement of claim on 16-7-2011 before the arbitral tribunal. Respondent No. 1 challenged the tribunal’s jurisdiction under section 16 of the 1996 Act, contending that disputes should be adjudicated under the M.P Madhyastham Adhikaran Adhiniyam, 1983 (the 1983 Act), not the 1996 Act. The arbitral tribunal rejected this challenge on 25-6-2012.

Respondent No. 1 then filed an application under section 14 of the 1996 Act before the District Judge, Bhopal, asserting the arbitral tribunal was unable to perform its function. The trial Court initially granted an interim stay but later vacated it. Respondent No. 1 challenged this vacatur under Article 227, and the writ petition was disposed of with directions to expeditiously decide the arbitration case.

Ultimately, the trial Court held on 19-2-2013 that the concession agreement was effectively a works contract and that arbitration under the 1996 Act was invalid; disputes had to be adjudicated under the 1983 Act. The petitioner has approached this Court to quash this order.

Legal Issues Presented

  1. Whether the agreement between the parties is a concession agreement governed by the Arbitration and Conciliation Act, 1996, or a works contract governed by the M.P Madhyastham Adhikaran Adhiniyam, 1983.
  2. Whether the trial Court erred in terminating the mandate of the arbitral tribunal and holding that disputes must be adjudicated under the 1983 Act instead of the 1996 Act.
  3. The applicability and interpretation of arbitration clauses in concession agreements versus works contracts in light of conflicting Supreme Court decisions.

Arguments of the Parties

Petitioner’s Arguments

  • The contract is a concession agreement distinct from a works contract, as defined in the agreement clauses and supported by the parties’ own pleadings.
  • The respondent admitted in pleadings that the contract was a concession agreement, and they cannot now change their stance.
  • The concession agreement expressly provides for dispute resolution under the 1996 Act.
  • Supreme Court decisions establish that where an arbitration clause exists specifying the 1996 Act, disputes must be resolved under that Act, not the 1983 Act.
  • Even if treated as a works contract, since it was repudiated and terminated, disputes fall under the 1996 Act as per Supreme Court precedent.
  • The respondent’s contention that the agreement is a works contract is an afterthought and inconsistent with multiple concession agreements entered into by the respondent that provide for arbitration under the 1996 Act.

Respondent’s Arguments

  • The agreement, read in entirety, is a works contract, which has a broad definition including consultancy services related to the works contract.
  • There was no admission in pleadings about the contract being a concession agreement; any such statement was a drafting error and cannot be binding.
  • Clause 44.3 of the concession agreement provides that after termination, rights and obligations are governed by the 1983 Act.
  • The trial Court’s order does not suffer from any error warranting interference, and the dispute must be adjudicated under the 1983 Act.
  • Reliance on multiple decisions supports the applicability of the 1983 Act and the trial Court’s view.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Electrical Corporation of India v. Secretary, Revenue Department Government of Andhra Pradesh, (1999) 4 SCC 458 Distinction between concession agreement and works contract; arbitration clause applicability Relied upon to support that the contract is a concession agreement and disputes fall under the 1996 Act
V.A Tech Escher Wyass Flovel Ltd. v. M.P State Electricity Board, (2011) 13 SCC 261 Applicability of 1996 Act where arbitration clause exists; 1983 Act applies where no arbitration clause Supported the petitioner’s contention that arbitration under 1996 Act applies
Ravikant Bansal v. M.P Rural Road Development Authority, (2012) 3 SCC 513 Scope of arbitration under 1983 Act when arbitration clause specifies tribunal Used to distinguish when 1983 Act applies
APS Kushwaha v. Municipal Corporation Gwalior, Civil Appeal No. 1888-89/2011 Arbitration clause in contract invokes 1996 Act; works contract disputes otherwise under 1983 Act Held binding on this Court to follow 1996 Act where arbitration clause exists
M.P Rural Road Development Authority v. L.G Choudhary Engineers and Contractors, (2012) 3 SCC 495 Disputes under works contracts are to be referred to tribunal under 1983 Act; divergence on cancellation disputes Discussed but noted that larger Bench has been referred; Court followed earlier binding precedent
Ashok Sadarangani v. Union of India, (2012) 11 SCC 321 Support for arbitration under 1996 Act after repudiation of contract Supported petitioner’s submission on arbitration applicability post-termination
Technogem Consultants Pvt. Ltd. v. General Manager, M.P Rural Development Authority, AIR 2007 NOC 1105 MP Broad definition of works contract including consultancy Relied upon by respondents to argue contract is works contract
D.D Sharma v. Madhya Pradesh Rural Roads Development Authority Etc., AIR 2008 MP 72 Definition and scope of works contract under 1983 Act Used by respondents to support their stance
Jalandhar Improvement Trust v. Sampuran Singh, (1999) 3 SCC 494 : AIR 1999 SC 1347 Admissions in pleadings and their legal effect Respondents cited to deny binding effect of alleged admission
Madan Gopal Kanodia v. Namraj Maniram, (1977) 1 SCC 669 Admissions against law cannot bind parties Respondents relied on to argue drafting error
Surya Dev Rai v. Ram Chander Rai, 2003 (5) MPLJ (S.C) 1 : (2003) 6 SCC 675 : AIR 2003 SC 3044 Applicability of arbitration provisions Relied on by respondents to support 1983 Act applicability
Shalini Shyam Shetty v. Rajendra Shankar Patil, 2010 (4) MPLJ (S.C) 590 : 2010 AIR SCW 6387 Interpretation of arbitration clauses Respondents cited to support their view
Radhey Shyam v. Chhabi Nath, 2009 AIR SCW 4006 Arbitration and dispute resolution principles Used by respondents
Bank of India v. K. Mohandas, (2009) 5 SCC 313 Construction of contract depends on language and intention of parties Applied to interpret the concession agreement
Administrator of the Specified Undertaking of the Unit Trust of India v. Garware Polyester Limited, (2005) 10 SCC 682 Commercial documents must be construed in commercial parlance Applied to interpret the concession agreement and State Support Agreement
Nagindas Ramdas v. Dalpatram Iccharam alias Brijram, (1974) 1 SCC 242 : AIR 1974 SC 471 Binding effect of admissions in pleadings Applied to hold respondent bound by admission of concession agreement
Jabalpur Bus Operators Association v. State of M.P, 2003 (1) MPLJ 513 Earlier Supreme Court decisions by equal benches are binding Applied to hold that earlier decision in APS Kushwaha is binding

Court's Reasoning and Analysis

The Court examined the definitions and provisions of the 1983 Act and the 1996 Act, focusing on whether the agreement qualifies as a “works contract” under the 1983 Act or a concession agreement governed by the 1996 Act. The Court noted that the 1983 Act mandates disputes under works contracts to be referred to a special tribunal irrespective of arbitration clauses, but the definition of “works contract” under the 1983 Act is restrictive and does not encompass detailed design, financing, and operation obligations that are integral to the concession agreement.

The Court analyzed the concession agreement and the State Support Agreement together, finding that the petitioner’s obligations included design, financing, construction, operation, and maintenance of the project road, which is inconsistent with the limited scope of a works contract. The existence of a State Support Agreement and the mode of payment by toll collection further distinguished the concession agreement from a works contract.

The Court gave significant weight to the parties’ own pleadings wherein respondent No. 1 admitted the contract was a concession agreement. It held that such admissions in pleadings are binding and cannot be retracted as an afterthought.

The Court also considered the relevant Supreme Court precedents, giving precedence to the earlier two-Judge Bench decisions, particularly APS Kushwaha, holding that where an arbitration clause exists specifying the 1996 Act, that Act applies over the 1983 Act. It noted that the conflicting later decision in L.G Choudhary is under consideration by a Larger Bench and thus did not override the binding earlier precedent.

Consequently, the Court concluded that the trial Court’s order terminating the arbitral tribunal’s mandate and directing adjudication under the 1983 Act was an error apparent on the face of the record.

Holding and Implications

The Court quashed the impugned order dated 19-2-2013 passed by the trial Court and allowed the writ petition. The dispute between the parties was held to be governed by the Arbitration and Conciliation Act, 1996, and the arbitral tribunal’s mandate was to be continued.

The direct effect of this decision is that the arbitration proceedings under the 1996 Act shall continue, and the parties must resolve their dispute accordingly. No new precedent was set beyond the application and reaffirmation of existing Supreme Court rulings on the interplay between the 1983 Act and the 1996 Act.

    Jabalpur Corridor (India) Pvt. Ltd. And Another v. Madhya Pradesh Road Development Corporation Ltd. And Others

    List of cases referred: 1. Electrical Corporation of India v. Secretary, Revenue Department Government of Andhra Pradesh, (1999) 4 SCC 458 (Para 5) 2. V.A Tech Escher Wyass Flovel Ltd. v. M.P State Electricity Board, (2011) 13 SCC 261 (Paras 5, 16, 17) 3. Ravikant Bansal v. M.P Rural Road Development Authority, (2012) 3 SCC 513 (Paras 5, 16) 4. APS Kushwaha v. Municipal Corporation Gwalior, Civil Appeal No. 1888-89/2011 (Paras 5, 17, 18) 5. M.P Rural Road Development Authority v. L.G Choudhary Engineers and Contractors, (2012) 3 SCC 495 (Paras 6, 17, 18) 6. Ashok Sadarangani v. Union of India, (2012) 11 SCC 321 (Para 6) 7. Technogem Consultants Pvt. Ltd. v. General Manager, M.P Rural Development Authority, AIR 2007 NOC 1105 MP (Para 7) 8. D.D Sharma v. Madhya Pradesh Rural Roads Development Authority Etc., AIR 2008 MP 72 (Para 7) 9. Jalandhar Improvement Trust v. Sampuran Singh, (1999) 3 SCC 494 : AIR 1999 SC 1347 (Para 7) 10. Madan Gopal Kanodia v. Namraj Maniram, (1977) 1 SCC 669 (Para 7) 11. Surya Dev Rai v. Ram Chander Rai, 2003 (5) MPLJ (S.C) 1 : (2003) 6 SCC 675 : AIR 2003 SC 3044 (Para 7) 12. Shalini Shyam Shetty v. Rajendra Shankar Patil, 2010 (4) MPLJ (S.C) 590 : 2010 AIR SCW 6387 (Para 7) 13. Radhey Shyam v. Chhabi Nath, 2009 AIR SCW 4006 (Para 7) 14. Bank of India v. K. Mohandas, (2009) 5 SCC 313 (Para 9) 15. Administrator of the Specified Undertaking of the Unit Trust of India v. Garware Polyester Limited, (2005) 10 SCC 682 (Para 13) 16. Nagindas Ramdas v. Dalpatram Iccharam alias Brijram, (1974) 1 SCC 242 : AIR 1974 SC 471 (Para 15) 17. Jabalpur Bus Operators Association v. State of M.P, 2003 (1) MPLJ 513 (Para 18)

    In this petition under Article 227 of the Constitution of India, the petitioners, inter alia, seek quashment of the order dated 19-2-2013 passed by the trial Court, by which the application under section 14 of the Arbitration and Conciliation Act, 1996 (in short ‘the 1996 Act’) filed by respondent No. 1 seeking termination of mandate of arbitral Tribunal, has been allowed.

    2. The background facts, leading to filing of this petition, briefly stated, are that the petitioner No. 1 is a company incorporated under the provisions of the Companies Act, 1956. The respondent No. 1 invited the tender for construction of Sagar-Damoh-Jabalpur road. The tender submitted by the petitioner No. 1 was accepted and concession agreement dated 11-4-2003 was entered into between the petitioner No. 1 and the respondent No. 1 with regard to construction and maintenance of Sagar-Damoh-Jabalpur road on BOT basis. Thereafter, the petitioner, respondent No. 1 and the Government of Madhya Pradesh entered into a State support agreement on 14-4-2003 under which State Government guaranteed the implementation of terms and conditions of the concession agreement by respondent No. 1. The respondent No. 1 vide letter dated 12-7-2007 rescinded the contract under clause 32.2 of the concession agreement on the ground that the petitioner could not complete the work within the stipulated time. Clause 39 of the concession agreement provides for settlement of the dispute through arbitration under the 1996 Act. After protracted correspondence, the petitioner appointed Mr. R.C Chugh as an arbitrator under clause 39 of the concession agreement whereas the respondent No. 1 appointed one Mr. K. Shankar Narayanan as an arbitrator vide letter dated 9-3-2011. The two nominated arbitrators appointed Mr. K.K Sethi as Presiding Arbitrator in the meeting of the arbitrators which was held on 5-4-2011.

    3. The petitioner filed the statement of claim before the arbitrator on 16-7-2011. The respondent No. 1 raised a preliminary objection under section 16 of the 1996 Act on the ground of limitation and for not exhausting the procedure for amicable settlement prescribed in the agreement. The respondent No. 1 also filed statement of defence and counter-claim before the arbitral tribunal. The matter was heard by arbitral tribunal on 23rd, 24th and 25th June, 2012. The respondent No. 1 filed an application under section 16 of the 1996 Act in which challenge to the jurisdiction of the arbitral tribunal was made on the ground that the dispute between the parties has to be adjudicated under the M.P Madhyastham Adhikaran Adhiniyam, 1983 (hereinafter referred to as ‘the 1983 Act’) and not under the 1996 Act. The arbitral tribunal by order dated 25-6-2012 rejected the application submitted by the respondent No. 1 under section 16 of the 1996 Act and determined the Rules of procedure of arbitration.

    4. The respondent No. 1 thereafter filed an application under section 14 of the 1996 Act before the District Judge, Bhopal on the ground that arbitral tribunal has become de jure and is unable to perform its function. The trial Court vide order dated 27-6-2012 granted interim stay of the proceeding before the arbitral tribunal. The petitioner filed reply to the application for stay. The trial Court vide order dated 28-7-2012 after hearing the parties vacated the ad interim order of stay. The respondent No. 1 in a petition under Article 227 of the Constitution of India challenged the order dated 28-7-2012 passed by the trial Court. The writ petition was disposed of by a Bench of this Court on 3-10-2012 with the direction to the trial Court to expeditiously decide the arbitration case pending before it. Thereafter, the trial Court vide order dated 19-2-2013 inter alia held that a works contract cannot be termed as a concession agreement merely because the mode of payment has been changed. It was further held that the proceeding under the 1996 Act is invalid and the dispute between the parties has to be adjudicated under the 1983 Act. In the aforesaid factual back-drop, the petitioner has approached this Court.

    5. Learned senior counsel for the petitioner while referring to definition clauses of the agreement, namely, clauses 1.1.18 and 1.1.37 as well as clauses 3 and 9 of the concession agreement submitted that there is a difference between the concession agreement and works contract. It is further submitted that the respondent No. 1 itself in paragraph 11(c) in the statement of defence filed before the arbitral tribunal has admitted that the contract in question is a concession agreement therefore, the respondent No. 1 cannot be permitted to change its stand now. In support of his aforesaid submission, learned senior counsel has placed reliance on the Constitution Bench decision of the Supreme Court in Electrical Corporation of India v. Secretary, Revenue Department Government of Andhra Pradesh, (1999) 4 SCC 458. It is further submitted that the concession agreement specifically provides that the dispute between the parties has to be resolved in accordance with the provisions of the 1996 Act. Learned senior counsel while referring to the decision of the Supreme Court in VA Tech Escher Wyass Flovel Ltd. v. M.P State Electricity Board, (2011) 13 SCC 261 and Ravikant Bansal v. M.P Rural Road Development Authority, (2012) 3 SCC 513 submitted that the Supreme Court has held that 1983 Act applies where there is no arbitration clause in the contract, and where the agreement itself mentions that arbitration would be under 1996 Act, then in such a case the dispute has to be adjudicated by the arbitral tribunal under the 1996 Act. Reliance has also been placed on the decision of the Supreme Court in APS Kushwaha v. Municipal Corporation Gwalior (Civil Appeal No. 1888-89/2011).

    6. It was also submitted that even assuming the concession agreement to be a works contract, since the works contract is itself repudiated and is not in existence by virtue of its termination, the dispute between the parties has to be referred to an arbitrator under the 1996 Act in view of decision of the Supreme Court in M.P Rural Road Development Authority v. L.G Choudhary Engineers and Contractors, (2012) 3 SCC 495. It was also urged that though the decision in the L.G Choudhary (supra) has been referred for consideration to a larger Bench, yet the High Court can decide the lis pending before it. In support of the aforesaid submission, learned senior counsel has placed reliance on the decision in the case of Ashok Sadarangani v. Union of India, (2012) 11 SCC 321. Attention of this Court has been invited to several concession agreements executed by the respondent No. 1 up to 2013, in which the clauses clearly stipulate resolution of the dispute under the 1996 Act, whereas in case of works contracts, the clauses in the works contracts provide for resolution of the dispute under the 1983 Act. Lastly it is urged that the stand taken by the respondent No. 1 before this Court that the concession agreement is a works contract is nothing but an afterthought.

    7. On the other hand, learned counsel for the respondents submitted that if the concession agreement is read in its entirety, it would be clear that the same is a works contract and the definition of works contract is vast and inclusive and even the consultancy services in respect of the works contract have been held to be works contract. In this connection reference has been made to the decisions in Technogem Consultants Pvt. Ltd. v. General Manager, M.P Rural Development Authority, AIR 2007 NOC 1105 MP and D.D Sharma v. Madhya Pradesh Rural Roads Development Authority Etc., AIR 2008 MP 72. It was also submitted that in paragraph 11(c) of the reply filed before the arbitral tribunal, in fact, there is no admission. It is a case of drafting error which has been caused inadvertently and in any case there cannot be admission against law. In this regard reference has been made to the decisions in the cases of Jalandhar Improvement Trust v. Sampuran Singh, (1999) 3 SCC 494 : AIR 1999 SC 1347 and Madan Gopal Kanodia v. Namraj Maniram, (1977) 1 SCC 669. It was further submitted that under clause 44.3 of the concession agreement, even after termination of the contract, the rights and obligations of the parties shall be governed by the 1983 Act, and the order passed by the trial Court does not suffer from any error apparent on the face of record warranting interference by this Court in exercise of power under Article 227 of the Constitution of India. Reliance has also been placed on the decisions in Surya Dev Rai v. Ram Chander Rai, 2003 (5) MPLJ (S.C) 1 : (2003) 6 SCC 675 : AIR 2003 SC 3044, Shalini Shyam Shetty v. Rajendra Shankar Patil, 2010 (4) MPLJ (S.C) 590 : 2010 AIR SCW 6387 and Radhey Shyam v. Chhabi Nath, 2009 AIR SCW 4006.

    8. I have considered the respective submissions made by learned counsel for the parties. The 1983 Act is an Act enacted under Entry 13 of List III of Seventh Schedule of the Constitution of India and is a special enactment which provides for the establishment of a Tribunal to arbitrate in disputes to which the State Government or a Public Undertaking wholly or substantially owned or controlled by the State Government is a party and for the matters incidental thereto or connected therewith. Sections 2(d) and (i) of the 1983 Act, which define the expressions “dispute” and “works-contract”, respectively, read as under:

    “2. Definitions, (d) “dispute” means claim of ascertained money valued at Rupees 50,000/- or more relating to any difference arising out of the execution or non-execution of a works contract or part thereof,

    xxx xxx xxx

    2 (i) “works-contract” means an agreement in writing for the execution of any work relating to construction, repair or maintenance of any building or superstructure, dam, weir, canal, reservoir, tank, lake, road, well, bridge, culvert, factory, workshop, powerhouse, transformers or such other works of the Government may, by notification, specify in this behalf at any of its stages, entered into by the State Government or by an official of the State Government or Public Undertaking or its official for and on behalf of such Public Undertaking and includes an agreement for the supply of goods or material and all other matters relating to the execution of any of the said works.”

    Section 7(1) of the 1983 Act provides that either party to a works contract shall irrespective of the fact whether the agreement contains an arbitration clause or not, refer in writing the dispute to the tribunal.

    9. In the light of provisions of 1983 Act, which require parties to refer their dispute mandatorily to the tribunal constituted under the 1983 Act, irrespective of arbitration clause, the singular issue which arises for consideration in the instant petition is whether the concession agreement in question is a works contract as defined under section 2(i) of the 1983 Act, or not. It is well settled in law that construction of contract must depend upon the import of words used and the intention of the parties must be ascertained from the language employed in the contract and the object of the contract. The contract has to be read as a whole in order to ascertain its true meaning [See: Bank of India v. K. Mohandas, (2009) 5 SCC 313]. The Court seeks to give effect to the parties' intention to refer disputes to arbitration and to allow the tribunal full jurisdiction except in cases of hopeless confusion. [See: Russel on Arbitration, Twenty Third Edition Page 68].

    10. In view of aforesaid well settled legal position, the provisions of the concession agreement executed between the petitioner No. 1 and the respondent No. 1 need to be examined. The parties have described the agreement as “concession agreement”. Under the aforesaid agreement, the respondent No. 1 had granted the petitioner concession for a period of 5440 number of days, commencing from the commencement date including the right, licence and authority during the subsistence of the agreement to implement the project and the concession in respect of the project highway. The petitioner was awarded the work of construction and maintenance of 176 kilometres of road forming the part of National Highway No. 37. Clause 9 of the agreement defines the obligations of the petitioner No. 1 whereas clause 10 thereof defines obligations of the respondent No. 1. Clause 39.3.1 provides that any dispute which is not resolved amicably as provided in clause 39.1 and 39.2 shall be finally decided by reference to arbitration by a Board of Arbitrators as per the provisions of the 1996 Act. Clause 44.3 of the Agreement provides that termination of the agreement shall not relieve either party of their obligations or liabilities for the loss or the damage caused to the other party arising out of or caused by acts or omissions of such party prior to the effectiveness of such termination or arising out of such termination.

    11. From perusal of the agreement, it is evident that under the agreement the petitioners are under an obligation to prepare a detailed design, engineering, financing, procurement, construction, operation and maintenance of the project road. Thus, the project is deemed to be leased out to the petitioners for maintenance as well as collection of toll and regular entry and exit taking care of the project road, till the expiry of the concession period. The agreement provides execution of EPC contract and other contracts for execution of the project. The petitioner was also at liberty to employ other contractors for items of works as considered necessary for execution of the project. The petitioner, respondent No. 1 as well as the State Government have entered into an agreement, namely, State Support Agreement on 14-4-2003 in pursuance of the concession agreement. From perusal of the State Support Agreement, it is evident that it forms an integral part of concession agreement. From perusal of clause A-F of the agreement, it is evident that concession agreement has been made part of State Support Agreement. Clause 3 of the aforesaid agreement provides the duties of the Government of Madhya Pradesh whereas clause 4 contains the petitioner's obligation under the agreement. Clause 7 provides for breach and compensation to the petitioner No. 1 respectively by the Government of Madhya Pradesh as well as by the respondent No. 1. Under Clause 8.3 of the agreement, the Government of Madhya Pradesh is made liable to indemnify the petitioner No. 1 for any payment required to be made by it with respect to levy of any local taxes. It is pertinent to mention here that clause 9 of the State Support Agreement also provides that a dispute between the parties shall be resolved as per the 1996 Act.

    12. The expression ‘works contract’ as defined in the 1983 Act has a restricted meaning and has special and limited connotation and the same does not include detailed design, financing and operation of the contract. The works contract is a lump sum contract wherein the contractor has to quote the amount for execution of the work based on details furnished by the employer. There is no necessity for creation of any Escrow Account in works contract. In works contract the payment is made against the running account bills prepared by contractor and submitted to the employer periodically. Whereas in concession agreement, the concessionaire has to utilise and arrange the funds. The concessionaire under the agreement after completion of the construction recovers the amount invested by him for completion of the project by way of toll. No State Support Agreement is executed in case of a works contract whereas the same is executed in a case of concession agreement. It is pertinent to mention here that the petitioner is not liable to pay Value Added Tax, Sales Tax and other taxes under the concession agreement which are payable under the works contract. The aforesaid salient features clearly show that there is distinction between the works contract and concession agreement. As stated supra, the State Support Agreement forms an integral part of concession agreement and both have to be read together. By no stretch of imagination State Support Agreement can be termed as ‘works contract’, and both the aforesaid agreements contain provisions with regard to resolution of dispute under 1996 Act. For this reason also concession agreement cannot be termed as works contract.

    13. It is well settled in law that commercial documents must be construed in a manner as understood in commercial parlance. [See: Administrator of the Specified Undertaking of the Unit Trust of India v. Garware Polyester Limited, (2005) 10 SCC 682] It is pertinent to mention here that admittedly respondent No. 1 has entered into as many as seventeen concession agreements between the period from 7-8-2009 till 8-8-2012 and in each of the concession agreements, the clause provides that the dispute shall be resolved under the 1996 Act. The respondent No. 1 between the period of February, 2009 till October, 2012 has entered into six agreements which are works contracts. The same clearly provide that the dispute between the parties shall be resolved as per the provisions of the 1983 Act. The aforesaid fact goes a long way to show that the respondents have clearly understood the distinction between the works contract and the concession agreement and have consciously chosen the forum provided under the 1996 Act.

    14. In paragraph 11(c) of the statement of claim filed before the arbitral tribunal, the petitioner stated that the contract value of the concession agreement is?. 89.78 Cr. whereas the contract value of EPC contract is Rs. 120 Cr. In this context, the respondent No. 1 in paragraph 11(c) of the statement of defence has stated as follows:

    “That as far as the contents of para 11(c) is concerned it is improper to state that the value of contract was 89.78 Cr. It is submitted that the present is not a work contract but a Concessionair agreement. It is submitted that Concession Agreement was on BOT basis for reconstruction, strengthening widening and rehabilitation of 176 Km road and its operation and maintenance to be executed through concession on build operate and transfer basis concession agreement is the agreement for concession period. The tenders were invited for concession period. The EPC contract means contract or contracts entered into by the concessionaire with one or more contractors for the detailed working, design, engineering, procurement of material and equipment construction. The contract value of such contract is the mutual settlement between EPC contractors and concessionaire and respondent has no role in that. As per agreement prior approval for entering EPC contract has to taken. The higher cost of EPC contract entered by claimant is his own will and respondent are not concerned with that.”

    15. Thus, both the parties have clearly understood the agreement to be a concession agreement and had consciously taken a decision that the dispute between the parties shall be resolved under the 1996 Act. The respondent No. 1 in view of its admission made in paragraph 11(c) of the statement of defence filed before the arbitral tribunal cannot be permitted now to contend that the agreement in question is a works contract, as admission in the pleading stands on a higher footing than evidentiary admission and is fully binding on the party making such an admission. [See: Nagindas Ramdas v. Dalpatram Iccharam alias Brijram, (1974) 1 SCC 242 : AIR 1974 SC 471]

    16. Even assuming that the agreement in question is not a works contract, yet for another reason the dispute between the parties has to be resolved under the provisions of 1996 Act. In V.A Tech Escher Wyass Flovel Ltd. (supra) a two-Judge Bench of Supreme Court held that 1996 Act would apply when there is an arbitration clause, whereas 1983 Act would apply where there is no arbitration clause. In Ravikant Bansal (supra) a two-Judge Bench of the Supreme Court held that where an arbitration clause mentions that arbitration would be goverened by M.P Arbitration Tribunal, in such cases, 1983 Act would apply.

    17. Again a two-Judge Bench of Supreme Court by judgment dated 17-2-2011 in A.P.S Kushwaha (SSI Unit) v. Municipal Corporation, Gwalior [Civil Appeal No. 1888-889 of 2011] while dealing with a dispute arising out of an agreement with regard to maintenance of water supply and electric works in different parts of Gwalior Municipal Corporation area which is also a works contract, while taking note of the judgment of Supreme Court in V.A Tech Escher Wyass Flovel Ltd. (supra) held that if the contract between the parties contains an arbitration clause, the provisions of 1996 Act would apply. However, it is pertinent to mention here that another two-Judge Bench of the Supreme Court in case of L.G Choudhary (supra), inter alia, held that all disputes pertaining to works contract have to be statutorily referred to the Tribunal set up under the 1983 Act. However, there was divergence of opinion with regard to issue whether the dispute regarding cancellation/determination of such works contract can be referred to arbitration under the 1983 Act. In view of the aforesaid divergence of opinion, the matter has been referred for consideration by a Larger Bench and the view taken by in V.A Tech Escher Wyass Flovel Ltd. (supra) has been held to be per incuriam.

    18. It is pertinent to mention here that in the case of L.G Choudhary (supra) the Supreme Court has not taken note of earlier decision rendered by a two-Judge Bench in the case of A.P.S Kushwaha (SSI Unit) (supra). A Special Bench of this Court in the case of Jabalpur Bus Operators Association v. State of M.P, 2003 (1) MPLJ 513 has held that in case of a conflict between decisions of Supreme Court comprising equal number of Judges, decision of earlier Bench is binding. Therefore, the ratio laid down by a two-Judge Bench of Supreme Court in A.P.S Kushwaha (SSI Unit) (supra), which is prior in point of time, is binding on this Court. For this reason also the dispute between the parties has to be referred to the arbitral tribunal under the 1996 Act.

    19. In view of the preceding analysis, it is evident that the order passed by the trial Court suffers from an error apparent on the face of record and, therefore, the same cannot be sustained in the eye of law. The dispute between the parties has to be resolved under the provisions of the 1996 Act. In the result, the impugned order dated 19-2-2013 passed by the trial Court is hereby quashed and the writ petition is allowed. However, there shall be no order as to costs.

    Petition allowed.

    Use AI to get other relevant cases.

    Comments

    Jabalpur Corridor (I... v. Madhya Pradesh Road ...
    (Dec 4, 2013)