Factual and Procedural Background

By notification dated 20.8.1985, under section 4 of the Land Acquisition Act, an area of 15.42 acres in village Khera Gajju, Tehsil Rajpura, District Patiala, was acquired for construction of the S.Y.L. Canal. Subsequently, 0.97 acre more was acquired in the same village for the same purpose. The Land Acquisition Collector, by award dated 5.8.1987, fixed compensation at Rs. 62,000 per acre for Chahi and Rs. 35,000 per acre for Gair Mumkin.

On reference under Section 18, the Additional District Judge, Patiala, evaluated land abutting either side of the Rajpura–Chandigarh road (via Banur–Zirakpur) up to a depth of 150 feet at Rs. 1,50,000 per acre; Chahi and Gair Mumkin were evaluated at Rs. 1,00,000 and Rs. 60,000 per acre respectively. The State of Punjab filed Regular First Appeals Nos. 2926 and 2927 of 1993; the claimants filed Cross-objection No. 35-CI of 1994 in RFA No. 2926 of 1993. This judgment disposes of those matters arising from the common award dated 8.10.1993.

Legal Issues Presented

  1. What is the correct valuation of the acquired land abutting the Rajpura–Chandigarh road up to a depth of 150 feet (i.e., whether the valuation awarded by the trial court should be maintained or varied)?
  2. Whether the landowners are entitled to an increase in compensation to reflect price rise between a prior notification/award and the present acquisition (specifically, application of a 12% per annum escalation between the dates of two notifications) in view of the precedent cited.
  3. Entitlement to statutory benefits under the amended provisions of Sections 23(1-A), 23(2) and 28 of the Land Acquisition Act.

Arguments of the Parties

Landowners / Objectors' Arguments

  • The court was reminded that, when dealing with an earlier notification dated 13.12.1982, land abutting the same road up to 150 feet depth had been valued at Rs. 1,50,000 per acre in RFA No. 2807 of 1987 decided on 31.8.1989.
  • Because the present notification was issued after a period of 34 months from that earlier notification, the landowners contended they were entitled to a necessary increase of 12% per annum for price rise between the two notifications, relying on authorities including Inder Singh v. State of Punjab, 1988 (2) P.L.R 190.

The opinion does not record detailed opposing arguments by the State in the text provided.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Inder Singh v. State of Punjab, 1988 (2) P.L.R 190. Cited for entitlement to increase in compensation to reflect price rise (12% per annum) between dates of two notifications/awards. The Court followed the law laid down in Inder Singh and granted enhanced compensation to the cross-objectors accordingly.
RFA No. 2807 of 1987 decided on 31.8.1989 Referenced as a prior evaluation of land abutting the road at Rs. 1,50,000 per acre for the earlier notification dated 13.12.1982. The Court treated that prior valuation as the baseline relied upon by the landowners and, in conjunction with Inder Singh, used it to justify an increased rate for the present acquisition.

Court's Reasoning and Analysis

The Court confined its consideration to valuation of the acquired land up to the specified depth of 150 feet and not to the two classifications of land (Chahi and Gair Mumkin) as separate issues for this determination. It accepted the landowners' position that a prior decision (RFA No. 2807 of 1987) had fixed the comparable land at Rs. 1,50,000 per acre for an earlier notification.

Relying on the precedent of Inder Singh v. State of Punjab, the Court accepted that where there is a gap between notifications/awards, an upward adjustment (here, argued as 12% per annum) to reflect price rise is appropriate. The Court found this argument to have force and applied the principle from Inder Singh to increase the compensation figure for the cross-objectors.

The Court also addressed statutory benefits by holding the cross-objectors entitled to benefits under the amended provisions of Sections 23(1-A), 23(2) and 28 of the Act. It provided administrative relief by allowing two months to cure deficiency in Court fee.

Holding and Implications

Core Ruling: The Court allowed the cross-objections and dismissed the appeals by the State of Punjab.

Specific orders and immediate consequences on the parties:

  • The compensation for the acquired land of the cross-objectors was fixed at Rs. 2,01.000/- (two lacs one thousand) per acre.
  • The cross-objectors were held entitled to the statutory benefits of the amended provisions of Sections 23(1-A), 23(2) and 28 of the Land Acquisition Act.
  • The cross-objectors were allowed two months' time to make up the deficiency in the Court fee.
  • The appeals filed by the State of Punjab were dismissed with no order as to costs; the cross-objections were allowed with proportionate costs.

The opinion does not state that it establishes any new broader legal precedent beyond applying the law as stated in Inder Singh and the referenced prior decision; its effect is to adjust compensation and grant statutory benefits and costs as described above.

    State Of Punjab v. Gulzar Singh .

    N.C Jain, J. (Oral) — This judgment of mine would dispose of Regular First Appeal Nos. 2926 and 2927 of 1993 and Cross-objection No. 35-CI of 1994 in Regular First Appeal No. 2926 of 1993, as they arise out of a common award of the Additional District Judge, Patiala, dated 8.10.1993 Vide notification dated 20.8.1985, issued under section 4 of the Land Acquisition Act (hereinafter referred to as ‘the Act’) an area of 15.42 acres of land situated in village Khera Gajju, Tehsil Rajpura District Patiala, was acquired for the construction of S.Y.L Canal, Subsequently more land i.e measuring 0.97 acre was acquired in the same village and for the same purpose. The Land Acquisition Collector by his award dated 5.8.1987, awarded the compensation at the following rates:—

    (1) Chahi at the rate of Rs. 62,000/- per acre

    (2) Gair Mumkin at the rate of Rs. 35,000/- per acre.

    On reference under Section 18 of the Act, the learned Additional District Judge, Patiala, by the award which is under challenge before this Court, has evaluated the land abutting on either side of the road connecting Rajpura with Chandigarh via Banur-Zirakpur upto the depth of 150 feet at the rate of Rs. 1,50,000/- per acre. Chahi and Gair Mumkin land has been evaluated at Rs. 1,00,000/- and Rs. 60,000/- per acre respectively. State of Punjab has filed the regular First Appeal No. 2926 and 2927 of 1993 whereas the claimants have filed the Cross-objections No. 35-CI of 1994 in Regular First Appeal No. 2926 of 1993.

    2. This Court is concerned with the valuation of the acquired land upto the depth of 150 feet as has been mentioned above and not for two kinds of land. The learned counsel for the landowners/objectors has argued that this Court while dealing with the notification dated 13.12.1982 evaluated the land abutting on either side of the road connecting Rajpura with Chandigarh via Banur and Zirakpur upto the depth of 150 feet, at the rate of Rs. 1,50,000/- per acre in RFA No. 2807 of 1987 decided on 31.8.1989 The learned counsel has further argued that since the land in question was acquired by present notification after a period of 34 months, the Landowners in the present acquisition are entitled to necessary increase of 12% p.a for the price rise between the dates of two notifications in view of the law laid down in several judicial pronouncements including Inder Singh v. State of Punjab, 1988 (2) P.L.R 190.

    3. The argument has got force. Following the law laid down in Inder Singh's case (supra), I hereby grant compensation for the acquired land of the cross-objectors at the rate of Rs. 2,01.000/- (two lacs one thousand) per acre. The cross-objectors are also held entitled to the grant of statutory benefits of the amend provisions of Sections 23(1-A), 23(2) and 28 of the Act. They are also allowed two months time to make up the deficiency in the Court fee. In consequence of the observations made above the appeals filed by the State of Punjab are dismissed with no order as to costs, whereas the Cross-objections filed by the Cross-objectors in Regular First Appeal No. 2926 of 1993 are allowed with proportionate costs.

    Ordered accordingly.

    Use AI to get other relevant cases.

    Comments

    State Of Punjab v. Gulzar Singh .
    (Aug 25, 1994)