Factual and Procedural Background

The petitioners challenged the order dated 16th March 2011 passed by the Executive Engineer of the Bombay Municipal Corporation, which cancelled the IOD (Intimation of Disapproval) and CC (Completion Certificate) previously granted for construction on property bearing CTS Nos. 153, 153/1 to 3 of Village Malad (East), ‘P’ North Ward. The IOD and CC were initially granted based on a letter dated 23rd January 2009 from the Administrative Officer, Central Ordnance Depot, which gave no objection to the building plans. Subsequently, it was brought to the Corporation's notice that the said letter was not on the defence authority’s record; instead, their record contained a letter dated the same day raising objection to the building plans. The Corporation cancelled the permissions due to two principal reasons: lack of access to the petitioners’ plot and objection from the defence authority citing danger to the defence establishment from the proposed construction. The petitioners relied on a decree from the City Civil Court, Bombay, granting access to the plot, while the respondents contended that the access was insufficient under relevant regulations. The petitioners also argued that without a Notification under section 3 of the Works of Defence Act, 1903, building permission could not be refused on the ground of proximity to a defence establishment. It was agreed that no such Notification is currently in force, as a previously issued Notification was cancelled. The Government of Maharashtra had issued directions requiring no objection from defence authorities before sanctioning building plans near defence establishments, but the court opined that such instructions may lack power absent a statutory Notification under the Works of Defence Act.

Legal Issues Presented

  1. Whether the cancellation of IOD and CC by the Bombay Municipal Corporation was justified given the decree granting access to the petitioners' plot and the absence of a Notification under section 3 of the Works of Defence Act, 1903.
  2. Whether the Government of Maharashtra’s directive requiring no objection from defence authorities for sanctioning building plans near defence establishments has legal effect in the absence of a Notification under the Works of Defence Act.
  3. What procedural steps should be taken regarding the issuance of a Notification under section 3 of the Works of Defence Act, 1903, and reconsideration of building permissions.

Arguments of the Parties

Petitioners' Arguments

  • The decree passed by the City Civil Court, Bombay, grants access to the petitioners’ plot, which should suffice for granting IOD and CC.
  • Building permission cannot be refused on the ground of proximity to a defence establishment unless a Notification is issued under section 3 of the Works of Defence Act, 1903.
  • The Notification relating to the defence establishment was cancelled, so no valid Notification currently exists.

Respondents' Arguments

  • The access granted by the City Civil Court decree is insufficient under D.C Regulations and allied enactments to permit construction.
  • The Government of Maharashtra’s letter directs that no building permission should be granted near defence establishments without no objection from the concerned defence authority.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court examined the grounds for cancellation of the IOD and CC, focusing on the two primary reasons: lack of access and defence authority objections. It acknowledged the decree from the City Civil Court granting access but noted the respondent's contention that such access might not meet regulatory standards. Regarding the objection from the defence authority, the court emphasized that refusal of building permission on this ground requires a valid Notification under section 3 of the Works of Defence Act, 1903, which was not in force as the prior Notification was cancelled. The court further opined that the Government of Maharashtra’s directive cannot override the statutory framework established by the Works of Defence Act. Consequently, the court set aside the impugned order and directed the Executive Engineer to reconsider the matter, specifically to evaluate the adequacy of access and to await any Notification issued under the Works of Defence Act. The court outlined a procedural mechanism for the respondents to seek issuance of a Notification and for the Competent Authority to decide on it within a specified timeframe, emphasizing that no opinion was expressed on whether such Notification should be issued.

Holding and Implications

The court’s final decision was to set aside the order dated 16th March 2011 of the Executive Engineer cancelling the IOD and CC and to direct reconsideration of the matter in light of legal and factual considerations outlined in the judgment.

The respondents are permitted to pursue issuance of a Notification under section 3 of the Works of Defence Act, 1903, and the Competent Authority must decide on this within three months of receiving a proposal. The Executive Engineer must await the outcome of this process before making a fresh order. Until then, the petitioners are restrained from commencing construction based on the previously issued IOD and CC.

This decision affects the parties directly by mandating procedural compliance and reconsideration but does not set any new legal precedent beyond clarifying the necessity of a valid Notification under the Defence Act for refusal of building permissions near defence establishments.

    Lok Holding And Construction Ltd. & Ors. v. Municipal Corporation Of Greater Mumbai & Ors.

    P.C:— At the request of the learned Counsel appearing for petitioners, the name of respondent No. 5 is permitted to be deleted.

    2. Rule, returnable forthwith. Heard finally by consent of the parties.

    3. The petitioners, by this petition, make a grievance against the order dated 16th March 2011 passed by the Executive Engineer of the Bombay Municipal Corporation. By that order, the authority has cancelled the IOD and CC which were granted in favour of the petitioners for construction of building on property bearing CTS Nos. 153, 153/1 to 3 of Village Malad (East), ‘P’ North Ward. It is common ground that IOD and CC were granted in favour of the petitioners after the petitioners produced before the Competent Authority a letter dated 23rd January, 2009 signed by the Administrative Officer, Central Ordnance Depot, giving no objection to the sanction of the building plans submitted by the petitioners.

    4. It appears that thereafter, it was pointed out to the Corporation that the letter dated 23rd January 2009 granting no objection is not on the record of the defence authority. On the contrary, on their record, there is a letter dated 23rd January 2009, but by that letter objection is raised to the sanction of building plans submitted by the petitioners.

    5. We have heard learned Counsel appearing for both the sides. Perusal of the order impugned in the petition shows that the IOD and CC have been cancelled by the Corporation principally for two reasons, firstly access to the plot of the petitioners is not available and secondly an objection is raised by the defence authority for raising construction on the plot on the ground that the structure if raised will cause danger to the defence establishment. So far as the first aspect of the matter is concerned, the learned Counsel appearing for petitioners has pointed out to us that there is a decree passed in favour of the petitioners by the City Civil Court, Bombay granting access to the petitioners' plot where construction is proposed to be made. It was urged on behalf of the respondent-Union of India that the access that is provided by the decree of the City Civil Court, Bombay is not engough according to the D.C Regulations and other allied enactments for grant of permission to the proposed building on the plot in question. So far as the proposed construction being raised near the defence establishment is concerned, the learned Counsel appearing for petitioners pointed out to us that unless there is a Notification issued under section 3 of the Works of Defence Act, 1903, building permission cannot be refused in favour of the petitioners on the ground that there is defence establishment in the vicinity. It was pointed out to us that a Notification in relation to the defence establishment in question was actually issued by the Collector but subsequently that Notification was cancelled. Thus, it is common ground before us that there is no Notification presently in force issued under section 3 of the Works of Defence Act 1903. On behalf of the respondents, reliance was also placed on a letter dated 4th November 2010 issued by the Government of Maharashtra to the Commissioner of Bombay Municipal Corporation directing that while sanctioning building plans in relation to the plot where defence establishment is in the vicinity, building permission should not be granted without obtaining no objection from the concerned authority. In our opinion, as there is a statutory enactment occupying the field, viz. The Works of Defence Act 1903, the Government may not have the power to issue such instructions in respect of defence establishment in Page: 348relation to which there is no Notification as contemplated by the provisions of the said Act Taking overall view of the matter, therefore, in our opinion, following order would meet the ends of justice.

    6. The order passed by the Executive Engineer of the Bombay Municipal Corporation dated 16th March, 2011 challenged in the petition is set aside. The Executive Engineer who has passed the order at Exh.-V’ to the petition is directed to reconsider the matter. The Executive Engineer shall consider whether the access provided to the petitioners by the decree passed by the City Civil Court, Bombay is enough according to the relevant law for grant of IOD and CC to the petitioners. The respondents shall be free to take appropriate steps for getting a Notification in the present case under the Works of Defence Act, 1903 issued, if they are so advised. The respondents may submit a proposal to the Competent Authority in that regard with a copy to the petitioners within a period of four weeks from today. The Competent Authority to whom the proposal may be submitted by the respondents shall consider that proposal in accordance with the provisions of Works of Defence Act, 1903 and grant an opportunity of being heard to the petitioners and any other person who may be entitled for such hearing under the law and decide whether Notification under section 3 of the said Act is to be issued or not. The Competent Authority shall make the order as expeditiously as possible and in any case within a period of three months from the date of receiving the proposal. It is clarified that the Competent Authority is to decide the question whether Notification is to be issued or not on the basis of material produced before that authority only and by this order we have not expressed any opinion whether such a Notification deserves to be issued or not.

    7. The Executive Engineer of the Corporation shall take his decision pursuant to this order only after expiry of the period which we have granted to the Competent Authority for deciding the question of issuing Notification under the Works of Defence Act 1903. In case Notification is issued within the aforesaid period, the Executive Engineer shall go in accordance with the said Notification. In case such a Notification is not issued, the Executive Engineer shall decide the matter in accordance with law and on the basis of material produced before him. Till the Executive Engineer makes a fresh order pursuant to this order, the petitioners shall not carry out any construction on the basis of IOD and CC which have been issued in their favour by the Corporation. Rule is made absolute accordingly with no order as to costs.

    8. Parties to act on the copy of this order duly authenticated by the Associate/Private Secretary of this Court.

    9. Certified copy expedited.

    10. Rule made absolute.