  • Section 13(2) of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security and Interest Act, 2002 (hereafter the Act)
  • Rule 2(a) of the Security Interest Rules.9.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Section 13(2) of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security and Interest Act, 2002 (hereafter the Act)
  • Rule 2(a) of the Security Interest Rules.9.
Smart Summary

Summary of the Opinion delivered by Dipankar Datta, J.

Factual and Procedural Background

The borrower (first petitioner in W.P. 4 of 2010) obtained credit facilities from respondent no.1 (the bank). Properties of respondent nos. 3 and 4 (M/s. Bansilal Credit Pvt. Ltd. and M/s. Akhil Orchards Pvt. Ltd., petitioners in W.P. 6 of 2010 and W.P. 3 of 2010 respectively) were mortgaged in favour of the bank by deposit of title deeds. The borrower defaulted in repayment; its cash credit account was classified as a “non-performing asset” (NPA). An authorized officer of the bank issued a demand notice dated 9 September 2009 under Section 13(2) of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (the Act), calling upon payment of Rs. 10,28,74,036.24 within 60 days.

The borrower asked to operate a current account with the bank on the condition that 20% of deposits be retained and transferred to the cash credit account; the bank consented by letter dated 16 September 2009. Small sums (Rs. 45,000/-, Rs. 20,000/-, Rs. 10,000/-) were transferred to the cash credit account but a large outstanding (in excess of Rs. 9.5 crore) remained unpaid. The bank informed the borrowers and the mortgagors of its intention to enforce securities after the 60-day period.

Writ petitions by the borrower, Bansilal and Akhil were filed on 4 January 2010. Identical interim orders were passed on 6 January 2010 permitting affidavits, listing the matters for final hearing, restraining coercive steps against the petitioners (while permitting symbolic possession) and allowing parties to act on xeroxed copies. Affidavits were exchanged. The matters were dismissed for default on 3 August 2010 for non-appearance but were restored with interim orders on 18 August 2010.

The bank filed applications on 14 May 2012 to vacate the interim orders. The court proposed hearing the petitions finally since affidavits had been exchanged; parties agreed and the matters were taken up for consideration.

Legal Issues Presented

  1. Whether the classification of the cash credit account as a “non‑performing asset” and the consequent issuance of the demand notice under Section 13(2) of the Act suffered from jurisdictional error in view of the Reserve Bank of India (RBI) guidelines (specifically clause 4.2.4) and the Andhra Pradesh High Court decision in Sravan Dall Mill (P) Ltd. v. Central Bank of India (AIR 2010 A.P. 35).
  2. Whether the bank, by permitting operation of the borrower’s current account and retaining/transferring 20% of deposits to the cash credit account, effectively waived the demand notice or otherwise caused the account to be upgraded from NPA (i.e., whether part payments or the agreed retention resulted in declassification or waiver).
  3. Whether the officer who issued notices under Sections 13(2) and 13(4) of the Act was an “authorized officer” competent to take action under the Act (challenge based on the definition in Rule 2(a) of the Security Interest Rules).

Arguments of the Parties

Petitioners' Arguments (as advanced by Mr. Chakraborty)

  • The notices were affected by gross jurisdictional error since, under RBI guidelines (clause 4.2.4) and the Andhra Pradesh High Court decision in Sravan Dall Mill, deposits made after issuance of the demand notice should have entitled the borrower to declassification of the cash credit account from NPA to a standard account.
  • Allowing the current account to be operated (and retaining/transferring a portion to the cash credit account) amounted to waiver of the demand notice and cessation of the account’s NPA status.
  • The officer who issued the notices was not the authorized officer competent to take action under the Act, in view of the definition of “authorized officer” in Rule 2(a) of the Security Interest Rules.

Bank's Arguments (as advanced by Mr. Saha)

  • The writ petitions were not maintainable in law or on facts and should be summarily dismissed.
  • No jurisdictional error was committed by the authorized officer; the RBI guidelines were not violated and part payments of a trivial amount (circa Rs. 80,000) did not entitle the borrower to declassification of an account with an outstanding in excess of Rs. 9.5 crore.
  • The demand notice could not be treated as waived unless the entire amount specified in the notice was paid; part payments did not constitute waiver.
  • The officer who issued the notices was of the rank of Chief Manager and was competent to initiate proceedings under the Act; this was substantiated by a supplementary affidavit filed with leave of the Court.
  • For the contention on maintainability, reliance was placed on two Supreme Court decisions: United Bank of India v. Satyawati Tondon ((2010) 8 SCC 110) and Kanaiyalal Lalchand Sachdev v. State of Maharashtra ((2011) 2 SCC 782).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sravan Dall Mill (P) Ltd. v. Central Bank of India, AIR 2010 A.P. 35 (Andhra Pradesh High Court) Suggested principle that deposits made after issuance of a Section 13(2) demand notice may lead to declassification/upgradation of the account (relied upon by petitioners). The Court held that this decision did not lay down any law that would persuade it to accede to the petitioners' contentions; reliance upon Sravanlal was regarded as without merit.
United Bank of India v. Satyawati Tondon, (2010) 8 SCC 110 (Supreme Court) Relied on by the bank to support the submission that writ petitions challenging proceedings under the Act are not maintainable (i.e., supports non‑maintainability argument). The Court found substance in the bank's reliance on this decision and, on that basis, concluded that the writ petitions were not maintainable.
Kanaiyalal Lalchand Sachdev v. State of Maharashtra, (2011) 2 SCC 782 (Supreme Court) Relied on by the bank to support non‑maintainability of the writ petitions. The Court treated this authority as supporting the bank’s maintainability submission and, in conjunction with other reasons, held the writ petitions not maintainable.

Court's Reasoning and Analysis

The court proceeded through the following analytical steps, applying the Act, the RBI guidelines and the evidence on record:

  1. The Court observed that the petitioners never disputed that the borrower owed a sum in excess of Rs. 10 crores on the date the Section 13(2) demand notice was received. The account was classified as an NPA leading to the issuance of the demand notice.
  2. The petitioners had not pointed to any statutory provision or RBI guideline that would demonstrate that issuance of the demand notice was illegal because the jurisdictional fact for issuing it did not exist. Consequently, the Court rejected the contention that the jurisdictional fact for issuance under Section 13(2) was lacking.
  3. On the effect of part payments and the arrangement to retain 20% of current account deposits (resulting in transfers totalling about Rs. 80,000), the Court applied the scheme of the Act: the Act grants the defaulter 60 days to clear the liability or raise an objection. If the full amount specified in the demand notice is not paid within that period, the account remains an NPA and the secured creditor is entitled to initiate action (including possession) under Section 13(4).
  4. The Court examined RBI guideline clause 4.2.4 which provides that upgradation from NPA to “standard” arises only if arrears of interest and principal are paid by the borrower. The Court concluded that the guideline does not contemplate upgradation on part payment; full payment of arrears is the condition for upgradation under the guideline.
  5. Consequently, the Court held that the small transfers did not entitle the borrower to any upgradation nor did they amount to waiver by the bank of its right to proceed under the demand notice. The Court reiterated that waiver cannot be inferred merely because certain payments had been credited to the account.
  6. Regarding competence of the issuing officer, the Court considered the supplementary affidavit filed by the bank and was satisfied that the Chief Manager had initiated the proceedings and was competent to do so. Therefore, the challenge to the officer’s authority failed.
  7. The Court accepted the bank’s contention (supported by Supreme Court authorities relied upon by the bank) that the writ petitions were not maintainable and concluded that the writ petitions must be dismissed on that ground as well.

Holding and Implications

The writ petitions are dismissed and the interim orders dated 6 January 2010 are vacated.

Direct consequences and procedural effects explicitly stated in the opinion:

  • The writ petitions stand dismissed and the applications filed by the bank to vacate the interim orders are disposed of.
  • There shall be no order as to costs.
  • The petitioners are not precluded from invoking the remedy under Section 17(1) of the Act in future, if occasion arises.
  • The Court refused the prayer for stay made by the petitioners' counsel.
  • An urgent photostat certified copy of the order, if applied for, was to be furnished at an early date.

The opinion does not discuss any broader legal implications or establish a new precedent beyond the direct rulings above.

    Nik-Nish Retail Pvt. Ltd. & Anr. v. Union Bank & Ors.

    The Judgment of the Court was delivered by

    Dipankar Datta, J.:— Issues of fact and law in these three writ petitions and connected applications being common, they were heard together and shall stand disposed of by this common judgment and order.

    2. The first petitioner in W.P 4 of 2010 (hereafter the borrower) obtained credit facilities sanctioned by the respondent no. 1.bank (hereafter the bank). Properties of the respondent nos. 3 (M/s. Bansilal Credit Pvt. Ltd.) and 4 (M/s. Akhil Orchards Pvt. Ltd.), who are the petitioners in W.P 6 of 2010 and W.P 3 of 2010 respectively were mortgaged by deposit of title deeds in favour of the bank. The borrower having failed and neglected to repay its debt to the bank, its cash credit account was classified as ‘non-performing asset’ and a demand notice dated September 9, 2009 in terms of Section 13(2) of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security and Interest Act, 2002 (hereafter the Act) was issued by the authorized officer of the bank. The borrower was called upon to pay a total sum of Rs. 10,28,74,036.24 within 60 days, failing which the bank would have no other option but to enforce the securities created in its favour as indicated therein.

    3. The borrower as well as Bansilal and Akhil neither cleared their liability nor made any representation countering the demand notice; instead, the borrower approached the bank with a request to operate a current account maintained by it by retaining 20% of the deposits and permitting withdrawal of the balance as per its requirement. The bank by its letter dated September 16, 2009 permitted operation of the current account, as requested by the borrower, and informed it that the retained amount would be transferred to the cash credit account. In pursuance of such arrangement, Rs. 45,000/-, Rs. 20,000/- and Rs. 10,000/- were transferred to the cash credit account. No effort worth the name was, however, made by the borrower to clear its liability in full in response to the demand notice and a staggering figure in excess of Rs. 9.5 crore remained unpaid. The bank having waited for 60 days to expire from date of issuance of the demand notice informed the borrower as well as Bansilal and Akhil of its intention to enforce the securities by taking possession of the same for recovery of the secured debt.

    4. It was at this stage that these three writ petitions were presented before this Court, inter alia, by the borrower, Bansilal and Akhil on January 4, 2010. Upon hearing learned advocates for the parties, three separate but identical orders dated January 6, 2010 were passed. The order passed on the writ petition filed by the borrower reads as follows:

    “Having heard learned Advocates appearing for the parties and considering the facts and circumstances of the case, I am of the opinion that issues raised in this writ petition should be decided finally on affidavits.

    Therefore, liberty is granted to the respondents to file affidavit-in-opposition in relation to this writ petition within two weeks from date; reply thereto, if any, may be filed within a week thereafter. Let this matter be listed as ‘For Hearing’ three weeks hence.

    Let there also be an interim order restraining the respondents from taking any coercive step against the petitioners or in respect of the assets of the said petitioners until further order, although the said respondents will be at liberty to take symbolic possession of the mortgaged property.

    All parties are to act on a xerox signed copy of this order on the usual undertakings.”

    5. The bank and the respective writ petitioners exchanged their affidavits. The writ petitions were listed before this Court on August 3, 2010. Since no one had appeared despite second call, the writ petitions were dismissed for default. The same have since been restored together with the interim orders by an order dated August 18, 2010.

    6. On May 14, 2012, the bank filed separate applications for vacating the interim orders passed on January 6, 2010. While hearing these applications, I proposed to the parties that the writ petitions may be heard finally since the affidavits had been exchanged. Parties having agreed to such proposal, the writ petitions were taken up for consideration.

    7. Three points were urged by Mr. Chakraborty, learned advocate while assailing the impugned notices dated October 9, 2009 and December 9, 2009.

    8. Firstly, he submitted that the notices suffer from gross jurisdictional error in that the cash credit account in question could not have been classified as ‘non-performing asset’ in terms of the guidelines of the Reserve Bank of India. He referred to clause 4.2.4 of the said guidelines as well as a Bench decision of the Andhra Pradesh High Court reported in AIR 2010 A.P 35 [Sravan Dall Mill (P) Ltd. v. Central Bank of India] in support of his contention that the borrower was entitled to have its cash credit account declassified from a ‘non-performing asset’ to a standard account, in view of the deposits made after issuance of the demand notice under Section 13(2) of the Act. Secondly, he submitted that the cash credit account ceased to be a ‘non-performing asset’ once the bank allowed the current account to be operated resulting in waiver of the said demand notice. Thirdly and finally, it was contended that the officer of the bank who had issued the notices under Section 13(2) and 13(4) of the Act was not the authorized officer competent to take action against the petitioners in terms of the Act in view of the definition of authorized officer in Rule 2(a) of the Security Interest Rules.

    9. Answering the contentions raised on behalf of the petitioners, Mr. Saha, learned advocate for the bank urged that the writ petitions are not maintainable either in law or on facts and deserved to be summarily dismissed. According to him, no jurisdictional error had been committed by the authorized officer of the bank in proceeding against all the petitioners in terms of the provisions contained in the Act. The guidelines of the Reserve Bank have not been violated and the borrower could not have legitimately expected to have the cash credit account declassified from a ‘non-performing asset’ to a ‘standard account’ only because Rs. 80,000/- and odd had been retained by the bank in terms of the request of the borrower, leaving an outstanding of Rs. 9.5 crore. It was further contended by him that until and unless the entire amount specified in the demand notice is paid and the liability cleared, there is no question of waiver of such demand notice and the contention raised in this regard by his adversary is without merit. Lastly, he referred to the supplementary affidavit filed on behalf of the bank, in terms of leave granted by this Court by order dated June 15, 2012, to substantiate his contention that the officer who issued the notices impugned in the writ petitions is of the rank of Chief Manager and, therefore, was competent to initiate proceedings under the Act.

    10. In support of his submission that the writ petitions are not maintainable, Mr. Saha relied on the decisions of the Supreme Court reported in (2010) 8 SCC 110 (United Bank of India v. Satyawati Tondon) and (2011) 2 SCC 782 (Kanaiyalal Lalchand Sachdev v. State of Maharashtra). He, accordingly, prayed for dismissal of the writ petitions.

    11. Having heard learned advocates for the parties, I find substance in the submission of Mr. Saha and have no option but to hold that the writ petitions are not maintainable in law.

    12. The respective petitioners never disputed that a sum in excess of Rs. 10 crores was due and payable by the borrower on the date the demand notice under Section 13(2) of the Act was received by them. The account of the borrower in respect of such debt was classified as ‘non performing asset’, leading to issuance of the demand notice. Reference has not been made to any statutory provision or guideline of the Reserve Bank to demonstrate that issuance of the demand notice was illegal because the jurisdictional fact for issuing it did not exist. I am thus unable to accept Mr. Chakraborty's submission that the jurisdictional fact for issuing the notice under Section 13(2) of the Act was not satisfied.

    13. Now, the request of the borrower to operate the current account was accepted by the bank on terms that 20% of any amount credited in the current account would have to be retained and the same would be transferred to the cash credit account. This arrangement resulted in a paltry sum of Rs. 80,000/- being transferred to the cash credit account, leaving a sum in excess of Rs. 9.5 crore being due and payable to the bank. Question is whether the borrower by virtue of such retention and transfer was entitled to upgradation of the status of the cash credit account to ‘non NPA category’ or not and further as to whether it constituted waiver of the bank to proceed with the demand notice or not.

    14. I have no hesitation to hold that the borrower was not entitled to have the status of the account upgraded, and that there was no waiver on the part of the bank to proceed against the petitioners. The scheme of the Act envisages grant of 60 days time to the defaulter for clearance of the liability or to raise objection. Even if the defaulting party falls short of paying Rs. 1/- of the amount specified in the demand notice within the permitted period, its account would still be a ‘non-performing asset’ and continue to be treated as such and the secured creditor is, in the circumstances, entitled to initiate further action in terms of provisions of the Act including taking measures to take possession of the secured assets after the period of 60 days has expired if no objection is received in the meantime or the objection to the demand notice has been overruled. Question of waiver does not and cannot arise simply because certain payments had been credited in the cash credit account. The period of 60 days is the time limited for clearing the liability and if the liability does not stand cleared, notwithstanding part payment the secured creditor is well within its right to exercise power conferred by Section 13(4) of the Act. The contention, accordingly, stands overruled.

    15. On perusal of the guidelines of the Reserve Bank, it does not appear that the same comes to the rescue of the borrower. Clause 4.2.4, to which reference has been made by Mr. Chakraborty, reads thus:

    “4.2.4 Upgradation of loan accounts classified as NPAs

    If arrears of interest and principal are paid by the borrower in the case of loan accounts classified as NPAs, the account should no longer be treated as non-performing and may be classified as ‘standard’ accounts. With regard to upgradation of a restructured/rescheduled account which is classified as NPA contents of paragraphs 4.2.14 and 4.2.15 will be applicable.”

    16. Upgradation of a loan account that is classified as ‘non-performing asset’ as ‘standard’ would arise only if the arrears of interest and principal are paid by a borrower. The guidelines do not contemplate that part payment of arrears of interest and principal would lead to upgradation of status. The decision in Sravanlal (supra) does not lay down any law that would persuade me to hold in favour of the petitioners. Submission advanced by Mr. Chakraborty placing reliance thereon appears to be wholly without merit.

    17. Adverting to the supplementary affidavit filed on behalf of the bank, I am convinced that the Chief Manager had initiated proceedings and he was competent to do so in view of the office held by him. Initiation of the proceedings does not, therefore, appear to be vulnerable on any count.

    18. The writ petitions stand dismissed. Interim orders dated January 6, 2010 are vacated. In view of the above, the applications stand disposed of. There shall be no order as to costs.

    19. Needless to observe, dismissal of the writ petitions shall not preclude the petitioners to invoke the remedy provided by Section 17(1) of the Act if occasion therefor arises in future.

    Urgent photostat certified copy of this order, if applied for, shall be furnished to the applicant at an early date.

    Later

    Prayer for stay made by Mr. Chakraborty, learned advocate for the petitioners is considered and refused.