Factual and Procedural Background

The appellant contractor was awarded a contract dated 25-02-1987 for constructing residential and non-residential buildings at the Central Excavation Training Institute (CETI) for Rs 68,91,589. The contractor alleges that delays due to the respondent’s failure to supply final drawings, cement, other materials, and water postponed completion until 01-04-1989. Because the respondent allegedly delayed preparing and sanctioning the final bills, disputes arose and were referred to a sole arbitrator.

On 30-10-1999 the arbitrator allowed various monetary claims, including water charges and plaster of Paris, and awarded simple interest at 15% per annum from six months after completion (01-04-1989) until payment, with an escalation to 18% if payment was not made within three months of the award. Payment was not made within that period.

The respondent challenged the award before the First Additional District Judge, Sidhi. While upholding the award on merits, that court reduced interest to 12% per annum from 31-10-1999 until payment. Both parties appealed. The High Court of Madhya Pradesh reduced interest further to 10% per annum and set aside the awards for water charges and plaster of Paris. The present civil appeals challenge the High Court’s decision.

Legal Issues Presented

  1. Whether the High Court and the District Court were justified in interfering with the arbitrator’s award of 15% interest (escalating to 18%) and substituting it with 10% simple interest.
  2. Whether the High Court erred in setting aside the arbitrator’s award granting Rs 1,68,890.25 towards water charges.
  3. Whether the High Court correctly denied the arbitrator’s award for the cost of plaster of Paris.

Arguments of the Parties

Appellant's Arguments

  • The arbitrator’s detailed and reasoned award should not have been disturbed by the courts below.
  • Contract clauses 5(a) and 5(b) placed the responsibility for supplying water on the respondent; hence the award of water charges was proper.
  • The arbitrator rightly allowed reimbursement for plaster of Paris based on contractual documents.
  • Reduction of the interest rate by the lower courts was contrary to the contractual terms and the arbitrator’s findings.

Respondents' Arguments

  • The High Court correctly rejected the claims for water charges and plaster of Paris and properly reduced the rate of interest.
  • No substantial question of law arose warranting interference by the Supreme Court.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court limited the controversy to the rate of interest and the two disputed heads of claim. It observed that the arbitrator’s rate of 15% had been reduced to 10% by the High Court. Finding no convincing reason to upset that determination, the Court affirmed the 10% rate, but preserved the original period fixed by the arbitrator—namely, from 01-04-1989 until payment.

On the merits of the water-charges claim, the Court examined the general terms and conditions of the contract and agreed with the arbitrator that the Department was contractually obliged to supply water. Consequently, the High Court’s deletion of the award for Rs 1,68,890.25 was unjustified and required reinstatement.

Conversely, the Court found no error in the High Court’s rejection of the plaster-of-Paris claim and let that aspect of the judgment stand.

Holding and Implications

Appeals partly allowed and disposed of.

  • Interest fixed at 10% per annum on all sums awarded, calculable from 01-04-1989 until the date of payment.
  • The arbitrator’s award of Rs 1,68,890.25 for water charges is restored.
  • The disallowance of the plaster-of-Paris claim is upheld.
  • No order as to costs.

The decision provides final resolution of monetary entitlements between the parties without establishing new precedent beyond applying contractual obligations and confirming the courts’ limited scope to vary arbitral awards.

To access the original judgment, please Sign In or Subscribe.

    Nand Contractors And Engineers Through G.D Ahuja v. Northern Coalfield Limited And Another

    K.S.P Radhakrishnan, J.— Leave granted. We may take up the civil appeal arising out of Special Leave Petition (C) No. 24337 of 2009 as a lead case which arises out of a common judgment dated 14-11-2007 of the High Court of Madhya Pradesh at Jabalpur. In the first three appeals, we are concerned with the claim on interest alone and, in the other two appeals, the question involved is with regard to the claim for interest, water charges and the cost of plaster of Paris.

    2. The appellant was awarded the work relating to the construction of residential and non-residential buildings at Central Excavation Training Institute (CETI) vide work order dated 25-2-1987 for an amount of Rs 68,91,589. The appellant submits that for want of final drawings and delay in the supply of cement and other construction materials, including supply of water, the work was delayed, but completed on 1-4-1989 and handed over the buildings to the respondent. There was delay on the part of the respondents in preparing and sanctioning the final bills which gave rise to various disputes and ultimately the matter was referred to the sole arbitrator. The arbitrator passed an award dated 30-10-1999 on the claims made by the appellant including claims for water charges and plaster of Paris. So far as the claim for interest is concerned, the arbitrator awarded simple interest @ 15% per annum from six months of the date of completion i.e 1-4-1989 on all the amounts awarded till the date of payment. Further, it was also ordered that in case the payment was delayed beyond three months of the date of the award, interest be paid @ 18% per annum from the date of payment. No payment was made within three months from the date of the award. Hence, according to the appellants, as per the award he was entitled for 15% interest from six months of the date of completion i.e 1-4-1989 on the amounts awarded by the arbitrator till the date of payment.

    3. The award passed by the arbitrator was challenged by the respondent before the First Additional District Judge, Sidhi who did not upset the award on merits, but modified the interest awarded by the arbitrator and substituted with 12% per annum simple interest from the date of the award i.e 31-10-1999 till the date of payment. Aggrieved by the said order, appeals were preferred by the appellant before the High Court. The High Court disposed of all the appeals, reducing the interest to 10% per annum. The High Court has also set aside the award on the claim for water charges and plaster of Paris. Being aggrieved by the judgment, as already stated, these appeals have been preferred by the appellant.

    4. We have heard Shri Rohit Arya and Shri Mahabir Singh, learned Senior Counsel, appearing for the appellant and respondents, respectively. Mr Rohit Arya, learned Senior Counsel submitted that the High Court as well as the District Court were not justified in interfering with the well-considered award passed by the arbitrator. The learned Senior Counsel submitted that the reasons stated by the High Court are incorrect and contrary to the terms of contract as well as documents produced before the arbitrator. The learned Senior Counsel submitted that the arbitrator was justified in allowing the claim of water charges to the tune of Rs 1,68,890.25. Reference was also made to Clauses 5(a) and 5(b) of the general conditions applicable to the contract and submitted that it is the responsibility of the respondents to supply the water at their costs. The learned Senior Counsel also submitted that the claim for plaster of Paris was rightly allowed by the arbitrator and there was no reason to interfere with the same.

    5. Shri Mahabir Singh, learned Senior Counsel appearing for the respondents, on the other hand, submitted that there is no reason to interfere with the judgment of the High Court which has rightly rejected the claims on water charges and plaster of Paris and also reduced the rate of interest. Further, no question of law arises for consideration in these appeals.

    6. We are of the view that the dispute between the parties lies in a narrow compass. We find that the arbitrator has awarded simple interest @ 15% per annum from six months of the date of completion i.e 1-4-1989 on the amounts awarded till the date of payment. The High Court thought it fit to reduce the rate of interest to 10% per annum, which we find no reason to disturb. The period for which the arbitrator has awarded the interest will remain the same. The appellant, therefore, would be entitled to get interest at the rate of 10% per annum from 1-4-1989 till the date of payment.

    7. We are of the view that the High Court was not justified in interfering with the amount awarded in respect of the water charges which comes to Rs 1,68,890.25. Going by the general terms and conditions of the contract, in our view, the Department was bound to supply water, so found by the arbitrator, in our view, rightly. Therefore, that part of the award of the arbitrator, with regard to the water charges, is upheld. However, the High Court, in our view, rightly denied the claim with regard to plaster of Paris, therefore, it is not interfered with.

    8. The appeals are disposed of accordingly, subject to the above modification of the judgment of the High Court. However, there will be no order as to costs.