AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 11(6) of the 1996 Act
  • Section 11 of the 1996 Act
  • Section 11, 1996 Act
  • Section 11(6), 1996 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11(6) of the Arbitration and Conciliation Act, 1996
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 11(6) of the 1996 Act
  • Section 11 of the 1996 Act
  • Section 11, 1996 Act
  • Section 11(6), 1996 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11(6) of the Arbitration and Conciliation Act, 1996
Smart Summary

Factual and Procedural Background

The Union of India awarded Contract No. CEBTZ-14/95-96 to M/s Master Construction Company on 17 September 1995 for construction of operational and technical buildings at Bhatinda. The first and second phases were scheduled for completion by 20 July 1996 and 20 January 1997 respectively, but the contractor ultimately completed the work on 31 August 1998. A completion certificate issued on 9 September 1999 was followed by the contractor’s execution of several “no-claim certificates” (3 April, 28 April and 4 May 2000). The final bill was signed on 4 May 2000 and paid on 19 June 2000; a bank guarantee of Rs 21,00,000 was released on 12 July 2000.

On the very day the bank guarantee was released, the contractor withdrew the “no-claim certificates” and lodged new claims. The Chief Engineer (Bhatinda Zone) rejected these claims on 13 July 2000, prompting the contractor to demand appointment of an arbitrator on 10 September 2000. No appointment having been made, the contractor filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 before the Civil Judge (Senior Division), Bhatinda on 10 January 2001; that application was dismissed on 6 January 2003, and the High Court dismissed the ensuing writ petition on 20 May 2004.

The contractor’s special leave petition was disposed of by the Supreme Court on 3 January 2006, directing that the Section 11 application be placed before the Chief Justice of the Punjab & Haryana High Court. On 8 December 2006, the Chief Justice directed that “all disputes” be referred to arbitration and appointed a retired Chief Justice as sole arbitrator. The present appeal, by special leave, challenges that order.

Legal Issues Presented

  1. Whether any arbitrable dispute survived after the contractor voluntarily issued “no-claim certificates” and accepted final payment, thereby discharging the contract.
  2. Whether, assuming a dispute survived, the Chief Justice was obliged under Section 11(6) of the 1996 Act to appoint an arbitrator strictly in accordance with Condition 70 of the contract.

Arguments of the Parties

Appellants’ Arguments (Union of India)

  • The “no-claim certificates” and acceptance of final payment demonstrated accord and satisfaction; hence no arbitrable dispute exists.
  • Even if arbitration was permissible, the Chief Justice should have respected the contractual mechanism (Condition 70) and appointed an engineer-officer arbitrator rather than an outsider.

Respondent’s Arguments (Contractor)

  • The “no-claim certificates” were executed under financial duress and coercion because payment was otherwise withheld; therefore a genuine dispute exists that must be decided by an arbitral tribunal.
  • Relied heavily on National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267, and also cited NTPC Ltd. v. Reshmi Constructions, (2004) 2 SCC 663 and Ambica Construction v. Union of India, (2006) 13 SCC 475 to contend that questions about voluntariness of discharge vouchers are for the arbitrator.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 Defines the scope of the Chief Justice’s power under Section 11 and categorises cases involving “no-claim certificates”, including exceptions where discharge bars arbitration. Relied on extensively; the Court placed the present case within the exception where a voluntary discharge bars arbitration.
NTPC Ltd. v. Reshmi Constructions, (2004) 2 SCC 663 Illustrates circumstances where coercion may render a discharge voucher ineffective. Cited by the respondent; the Court distinguished the present facts, finding no evidence of coercion.
Ambica Construction v. Union of India, (2006) 13 SCC 475 Similar to Reshmi Constructions; recognises arbitrability despite discharge where coercion is alleged. Cited by the respondent; not found applicable because coercion was not prima facie established.
A line of earlier cases surveyed in Boghara Polyfab (e.g., Kishorilal Gupta 1959; Naihati Jute Mills 1968; Damodar Valley 1974; BHEL 1982; L.K. Ahuja 1988; Nav Bharat Builders 1994; P.K. Ramaiah 1994; Nathani Steels 1995; Indian Drugs & Pharmaceuticals 1996; Ajmer Singh Cotton 1999; Jayesh Engineering 2000; SBP & Co. 2005; Nipha Exports 2006; Sehtia Shoes 2008) Collectively examine the effect of accord and satisfaction and the Chief Justice’s jurisdiction under Section 11. Referred to indirectly through the Court’s detailed discussion of Boghara Polyfab; they inform the principles applied but were not analysed individually.

Court's Reasoning and Analysis

The Court first undertook an in-depth review of Boghara Polyfab, extracting the principle that the Chief Justice, when seized of a Section 11 application, must examine—at least prima facie—whether a discharge voucher was executed voluntarily or under coercion. If the discharge appears voluntary and credible, no arbitration need be ordered.

Applying that benchmark, the Court scrutinised the contractor’s own certificates, which unequivocally stated that all dues had been settled “in full and final satisfaction” and that no further claims subsisted. The contractor raised no protest until after the bank guarantee was released nearly a month later. The Court found “nothing to suggest” financial duress: the allegation was “a bald plea… lacking in credibility.”

Given these facts, the Court classified the case within the exception identified in Boghara Polyfab—where a clear, voluntary discharge bars arbitration. It therefore ruled that no arbitrable dispute existed. Having reached this conclusion, the Court considered it unnecessary to address the subsidiary issue concerning the proper mode of appointing an arbitrator under Condition 70.

Holding and Implications

Appeal Allowed – Order of the Chief Justice dated 8 December 2006 set aside.

Consequently, the contractor’s application under Section 11(6) stands dismissed and no arbitral reference will ensue. Each party bears its own costs. The judgment underscores that the mere assertion of coercion is insufficient; a credible prima facie case is required before parties are put to the expense of arbitration. While reaffirming the framework in Boghara Polyfab, the decision does not establish a new legal standard but clarifies its practical application in discharge-voucher scenarios.

To access the original judgment, please Sign In or Subscribe.

    Union Of India And Others v. Master Construction Company .

    R.M Lodha, J.— Leave granted. This appeal, by special leave, arises from the order dated 8-12-2006 passed by the Chief Justice of the Punjab and Haryana High Court in the proceedings under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short “the 1996 Act”) whereby he held that all disputes between the parties to the contract have to be referred to arbitration and appointed Mr M.S Liberahan, retired Chief Justice of Andhra Pradesh High Court, as sole arbitrator to decide the disputes between the parties.

    2. The respondent, M/s Master Construction Company (for short “the contractor”) was awarded a contract (CA No. CEBTZ—14/95-96) on 17-9-1995 by the first appellant, Union of India for the work, “provisions of OTM accommodation and certain essential technical buildings” to be erected and installed at Bhatinda. The first phase of the work was to be completed by 20-7-1996 and the second phase by 20-1-1997. The agreement between the parties made IAFW—2249 an integral part of the contract. Condition 70 thereof provided mode for resolution of disputes and differences between the parties through arbitration.

    3. The work is said to have been completed by the contractor, albeit belatedly, on 31-8-1998. The completion certificate was issued on 9-9-1999. The contractor furnished no-claim certificates on 3-4-2000, 28-4-2000 and 4-5-2000 and the final bill was signed on 4-5-2000. The payment of the final bill was released to the contractor on 19-6-2000. Thereafter, the bank guarantee amounting to Rs 21,00,000 was also released on 12-7-2000. Immediately after release of the bank guarantee, on that very day i.e 12-7-2000, the contractor wrote to the appellants withdrawing “no-claim certificates”, it also lodged certain claims.

    4. The Chief Engineer, Bhatinda Zone, Bhatinda (Appellant 3 herein) vide his letter dated 13-7-2000 declined to entertain the claims of the contractor on the ground that the final bill has been accepted by the contractor after furnishing the “no-claim certificates” and no claim under the contract remained. The contractor vide its letter dated 10-9-2000 requested the Engineer-in-Chief, Army Headquarters, Kashmir House, New Delhi (Appellant 2 herein) to refer the disputes between the parties for resolution to the arbitrator. The contractor stated in that letter that if the arbitrator was not appointed within 30 days from the date of request, it may be constrained to seek the remedy as may be available under the law.

    5. As no arbitrator was appointed by the appellants despite the request made in the letter dated 10-9-2000, the contractor made an application under Section 11 of the 1996 Act before the Civil Judge (Senior Division), Bhatinda on 10-1-2001. The application, after contest, was dismissed by the Civil Judge, Senior Division, Bhatinda on 6-1-2003. Not being satisfied with the order dated 6-1-2003, the contractor challenged that order by filing a writ petition before the High Court of Punjab and Haryana. The Division Bench of the High Court heard the parties and by its order dated 20-5-2004 dismissed the contractor's writ petition.

    6. The contractor challenged the High Court's order by filing a special leave petition before this Court. This Court disposed of the special leave petition on 3-1-2006 (2011) 12 SCC 357 by directing that the application filed by the contractor under Section 11 of the 1996 Act shall be placed before the Chief Justice of the Punjab and Haryana High Court, for appropriate order thereon. This Court, consequently, set aside the orders of the High Court and the lower court. It was then that the Chief Justice of the Punjab and Haryana High Court decided the application filed by the contractor under Section 11(6) of the 1996 Act and passed the order impugned in the present appeal.

    7. Mr Brijender Chahar, learned Senior Counsel for the appellants made two-fold submission:

    (i) that no arbitrable dispute existed between the parties as full and final payment has been received by the contractor voluntarily after submission of “no-claim certificates” and the final bill, and
    (ii) that, in any case, the Chief Justice in exercise of his power under Section 11(6) ought to have given due regard to the arbitration clause and appointed the arbitrator in terms thereof.

    8. Ms Indu Malhotra, learned Senior Counsel for the contractor, on the other hand, vehemently contended that the whole case of the contractor from the very beginning had been that “no-claim certificates” were given by the contractor under the financial duress and coercion as the appellants had arbitrarily withheld the payment. She would submit that the issue whether “no-claim certificates” were given voluntarily or under financial duress, is an issue which must be decided by the arbitrator alone and it is for this reason that the Chief Justice, in the proceedings under Section 11(6), has referred the disputes between the parties to the arbitrator. In this regard, she heavily relied upon a recent decision of this Court in National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 She also referred to two earlier decisions of this Court, namely, NTPC Ltd. v. Reshmi Constructions, Builders and Contractors (2004) 2 SCC 663 and Ambica Construction v. Union of India (2006) 13 SCC 475.

    9. That IAFW—2249 was made an integral part of the contract between the parties and Condition 70 thereof provided for mode of resolution of disputes and differences between the parties through arbitration is not in dispute. Condition 70 (arbitration clause) reads as under:

    “70. Arbitration.—All disputes, between the parties to the contract (other than those for which the decision of the CWE or any other person is by the contract expressed to be final and binding) shall, after written notice by either party to the contract to the other of them, be referred to the sole arbitration of an engineer officer to be appointed by the authority mentioned in the tender documents.
    Unless both the parties agree in writing such reference shall not take place until after the completion or alleged completion of the works or termination or determination of the contract under Conditions 55, 56 and 57 hereof:
    Provided that in the event of abandonment of the works or cancellation of the contract under Conditions 52, 53 or 54 hereof, such reference shall not take place until alternative arrangements have been finalised by the Government to get the works completed by or through any other contractor or contractors or agency or agencies:
    Provided always that commencement or continuance of any arbitration proceeding hereunder or otherwise shall not in any manner militate against the Government's right of recovery from the contractor as provided in Condition 67 hereof.
    If the arbitrator so appointed resigns his appointment or vacates his office or is unable or unwilling to act due to any reason whatsoever, the authority appointing him may appoint a new arbitrator to act in his place.
    The arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties, asking them to submit to him their statement of the case and pleadings in defence.
    The arbitrator may proceed with the arbitration, ex parte, if either party, in spite of a notice from the arbitrator fails to take part in the proceedings.
    The arbitrator may, from time to time with the consent of the parties, enlarge the time up to but not exceeding one year from the date of his entering on the reference, for making and publishing the award.
    The arbitrator shall give his award within a period of six months from the date of his entering on the reference or within the extended time as the case may be on all matters, referred to him and shall indicate his findings, along with sums awarded, separately on each individual item of dispute.
    The venue of arbitrator shall be such place or places as may be fixed by the arbitrator in his sole discretion.
    The award of the arbitrator shall be final and binding on both parties to the contract.
    If the value of the claims or counterclaims in an arbitration referred exceeds Rs 1 lakh the arbitrator shall give reasons for the award.”

    10. The controversy presented before us does not concern the existence of arbitration agreement but it relates to whether after furnishing “no-claim certificates” and the receipt of payment of final bill, as submitted by the contractor, any arbitrable dispute between the parties survived or the contract stood discharged.

    11. Before we turn to the factual aspect, it is appropriate to carefully consider the decision of this Court in Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 at some length as the learned Senior Counsel for the contractor placed heavy reliance on it. In Boghara Polyfab (P) Ltd. (2009) 1 SCC 267, this Court surveyed a large number of earlier decisions of this Court, namely, Union of India v. Kishorilal Gupta & Bros. AIR 1959 SC 1362, Naihati Jute Mills Ltd. v. Khyaliram Jagannath AIR 1968 SC 522, Damodar Valley Corpn. v. K.K Kar (1974) 1 SCC 141, BHEL v. Amar Nath Bhan Prakash (1982) 1 SCC 625, Union of India v. L.K Ahuja (1988) 3 SCC 76, State of Maharashtra v. Nav Bharat Builders 1994 Supp (3) SCC 83, P.K Ramaiah & Co. v. NTPC 1994 Supp (3) SCC 126, Nathani Steels Ltd. v. Associated Constructions 1995 Supp (3) SCC 324, Indian Drugs & Pharmaceuticals Ltd. v. Indo Swiss Synthetics Gem Mfg. Co. Ltd. (1996) 1 SCC 54, United India Insurance v. Ajmer Singh Cotton & General Mills (1999) 6 SCC 400, Jayesh Engg. Works v. New India Assurance Co. Ltd. (2000) 10 SCC 178, SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618, National Insurance Co. Ltd. v. Nipha Exports (P) Ltd. (2006) 8 SCC 156 and National Insurance Co. Ltd. v. Sehtia Shoes (2008) 5 SCC 400.

    12. With regard to the jurisdiction of the Chief Justice/his designate in the proceedings under Section 11 of the 1996 Act, this Court culled out the legal position in SCC para 51 of the Report as follows: [Boghara Polyfab (P) Ltd. case (2009) 1 SCC 267]

    “51. The Chief Justice/his designate exercising jurisdiction under Section 11 of the Act will consider whether there was really accord and satisfaction or discharge of contract by performance. If the answer is in the affirmative, he will refuse to refer the dispute to arbitration. On the other hand, if the Chief Justice/his designate comes to the conclusion that the full and final settlement receipt or discharge voucher was the result of any fraud/coercion/undue influence, he will have to hold that there was no discharge of the contract and consequently, refer the dispute to arbitration. Alternatively, where the Chief Justice/his designate is satisfied prima facie that the discharge voucher was not issued voluntarily and the claimant was under some compulsion or coercion, and that the matter deserved detailed consideration, he may instead of deciding the issue himself, refer the matter to the Arbitral Tribunal with a specific direction that the said question should be decided in the first instance.”

    13. The Bench in Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 in SCC paras 42 and 43 (p. 291), with reference to the cases cited before it, inter alia, noted that there were two categories of the cited cases; (one) where the Court after considering the facts found that there was a full and final settlement resulting in accord and satisfaction, and there was no substance in the allegations of coercion/undue influence and, consequently, it was held that there could be no reference of any dispute to arbitration and (two) where the Court found some substance in the contention of the claimants that “no-dues/claim certificates” or “full and final settlement discharge vouchers” were insisted and taken (either in printed format or otherwise) as a condition precedent for release of the admitted dues and thereby giving rise to an arbitrable dispute.

    14. In Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 the consequences of discharge of the contract were also considered. In SCC para 25 (p. 284), it was explained that when a contract has been fully performed, then there is a discharge of the contract by performance and the contract comes to an end and in regard to such a discharged contract, nothing remains and there cannot be any dispute and, consequently, there cannot be reference to arbitration of any dispute arising from a discharged contract. It was held that the question whether the contract has been discharged by performance or not is a mixed question of fact and law, and if there is a dispute in regard to that question, such question is arbitrable.

    15. The Court in Boghara Polyfab case (2009) 1 SCC 267, however, noted an exception to this proposition. The exception noticed is that where both the parties to a contract confirm in writing that the contract has been fully and finally discharged by performance of all obligations and there are no outstanding claims or disputes, courts will not refer any subsequent claim or dispute to arbitration. Yet another exception noted therein is with regard to those cases where one of the parties to the contract issues a full and final discharge voucher (or no-dues certificate, as the case may be) confirming that he has received the payment in full and final satisfaction of all claims, and he has no outstanding claim. It was observed that issuance of full and final discharge voucher or no-dues certificate of that kind amounts to discharge of the contract by acceptance or performance and the party issuing the discharge voucher/certificate cannot thereafter make any fresh claim or revive any settled claim nor can it seek reference to arbitration in respect of any claim.

    16. In SCC para 26 (pp. 284-85), this Court in Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 held that if a party which has executed the discharge agreement or discharge voucher, alleges that the execution of such document was on account of fraud/coercion/undue influence practised by the other party, and if that party establishes the same, then such discharge voucher or agreement is rendered void and cannot be acted upon and consequently, any dispute raised by such party would be arbitrable.

    17. In SCC para 24 (p. 284) in Boghara Polyfab (P) Ltd. (2009) 1 SCC 267, this Court held that a claim for arbitration cannot be rejected merely or solely on the ground that a settlement agreement or discharge voucher has been executed by the claimant. The Court stated that such dispute will have to be decided by the Chief Justice/his designate in the proceedings under Section 11 of the 1996 Act or by the Arbitral Tribunal.

    18. In our opinion, there is no rule of the absolute kind. In a case where the claimant contends that a discharge voucher or no-claim certificate has been obtained by fraud, coercion, duress or undue influence and the other side contests the correctness thereof, the Chief Justice/his designate must look into this aspect to find out at least, prima facie, whether or not the dispute is bona fide and genuine. Where the dispute raised by the claimant with regard to validity of the discharge voucher or no-claim certificate or settlement agreement, prima facie, appears to be lacking in credibility, there may not be a necessity to refer the dispute for arbitration at all.

    19. It cannot be overlooked that the cost of arbitration is quite huge—most of the time, it runs into six and seven figures. It may not be proper to burden a party, who contends that the dispute is not arbitrable on account of discharge of contract, with huge cost of arbitration merely because plea of fraud, coercion, duress or undue influence has been taken by the claimant. A bald plea of fraud, coercion, duress or undue influence is not enough and the party who sets up such a plea must prima facie establish the same by placing material before the Chief Justice/his designate. If the Chief Justice/his designate finds some merit in the allegation of fraud, coercion, duress or undue influence, he may decide the same or leave it to be decided by the Arbitral Tribunal. On the other hand, if such plea is found to be an afterthought, make-believe or lacking in credibility, the matter must be set at rest then and there.

    20. In light of the above legal position, we now turn to the facts of the present case. At the time of receiving payment on account of the final bill, the contractor executed the certificate in the following terms:

    “(a) I/we hereby certify that I/we have performed the work under the condition of Contract Agreement No. CEBTZ-14/95-96, for which payment is claimed and that I/we have no further claims under CA No. CEBTZ-14/95-96.
    (b) Received rupees two lakh fifteen thousand one hundred seventy-eight only. This payment is in full and final settlement of all money dues under CA No. CEBTZ-14/95-96 and I have no further claims in respect of CA No. CEBTZ-14/95-96.”
    (emphasis supplied by us)

    21. The contractor also appended the following certificate:

    “It is certified that I have prepared this final bill for claiming entire payment due to me from this contract agreement. The final bill includes all claims raised by me from time to time irrespective of the fact whether they are admitted/accepted by the Department or not. I now categorically certify that I have no more claim in respect of this contract beyond those already included in this final bill by me and the amount so claimed by me shall be in full and final satisfaction of all my claims under this contract agreement. I shall however, receive my right to raise claim to the extent disallowed to me from this final bill.”

    22. The above certificates leave no manner of doubt that upon receipt of the payment, there has been full and final settlement of the contractor's claim under the contract. That the payment of final bill was made to the contractor on 19-6-2000 is not in dispute. After receipt of the payment on 19-6-2000, no grievance was raised or lodged by the contractor immediately. The authority concerned, thereafter, released the bank guarantee in the sum of Rs 21,00,000 on 12-7-2000. It was then that on that day itself, the contractor lodged further claims.

    23. The present, in our opinion, appears to be a case falling in the category of exception noted in Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 (p. 284, para 25). As to financial duress or coercion, nothing of this kind is established prima facie. Mere allegation that no-claim certificates have been obtained under financial duress and coercion, without there being anything more to suggest that, does not lead to an arbitrable dispute. The conduct of the contractor clearly shows that “no-claim certificates” were given by it voluntarily; the contractor accepted the amount voluntarily and the contract was discharged voluntarily.

    24. We are, thus, unable to sustain the order of the Chief Justice in the proceedings under Section 11(6) of the 1996 Act. In view of our finding above, it is not necessary to consider the alternative submission made by the Senior Counsel for the appellants that the Chief Justice in exercise of his power under Section 11(6) ought to have appointed the arbitrator in terms of the arbitration clause and the appointment of Mr M.S Liberahan, retired Chief Justice of the Andhra Pradesh High Court, was not in accord with the arbitration agreement.

    25. The appeal is, accordingly, allowed. The impugned order dated 8-12-2006 passed by the Chief Justice of the High Court of Punjab and Haryana is set aside. The parties shall bear their own costs.