Smart Summary

Factual and Procedural Background

The appeal arose from a judgment dated 26-10-1999 rendered by the Delhi High Court in FAO (OS) No. 81 of 1999. The dispute centres on an unconditional “on-demand” bank guarantee that was invoked by the beneficiary on 19-05-1989, indisputably within its validity period. At the beneficiary’s instance, the High Court initially issued an injunction on 29-05-1989 restraining encashment but directed that the guarantee be kept alive; this injunction was confirmed on 23-04-1990 subject to periodic renewals.

The constituent failed to pay renewal charges, and the appellant— a nationalised bank—refused to extend the guarantee after 26-05-1996. The High Court (Single Judge) nevertheless held that, because invocation had taken place during the guarantee’s currency, the Bank remained bound to honour payment. A Division Bench dismissed the Bank’s appeal, describing its stance as undermining public faith in banking institutions. Persisting in its refusal, the Bank approached the Supreme Court.

Legal Issues Presented

  1. Whether an unconditional on-demand bank guarantee, invoked within its validity period, obliges the issuing bank to make payment notwithstanding subsequent non-renewal and earlier court-ordered stays.
  2. Whether the alleged existence of a substituted contract extinguished or affected the Bank’s liability under the original guarantee.

Arguments of the Parties

Appellant Bank’s Arguments

  • A “substituted agreement” between the contracting parties rendered the beneficiary’s invocation of 19-05-1989 ineffective.
  • Because the guarantee was not renewed after 26-05-1996 (owing to non-payment of renewal charges), the Bank was under no obligation to pay.
  • Relied on Union of India v. Kishorilal Gupta & Bros. and Makharia Bros. v. State of Nagaland to contend that contractual substitution or failure to extend a guarantee releases the surety.

Respondents’ Arguments

The opinion does not contain a detailed account of the respondents’ legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Kishorilal Gupta & Bros., AIR 1959 SC 1362; (1960) 1 SCR 493 Parties to a contract may, by mutual agreement, substitute a new contract for the old. The Court held the case inapplicable because no substituted contract affected the unconditional bank guarantee in the present matter.
Makharia Bros. v. State of Nagaland, (2000) 10 SCC 503 Discussed remedies where a contractor fails to furnish or extend a security deposit/bank guarantee. Found factually distinguishable; did not dilute the Bank’s obligation to honour a guarantee already invoked within its validity period.

Court's Reasoning and Analysis

The Supreme Court noted that both the Single Judge and the Division Bench had made concurrent findings that the guarantee was invoked on 19-05-1989 while still valid. Because the guarantee was unconditional and on demand, the Bank’s liability crystallised upon invocation. Subsequent injunctions merely postponed payment; once those injunctions were vacated, only intimation to the Bank was necessary.

The Court rejected the “substituted agreement” argument, stating that the cited decision in Kishorilal Gupta was irrelevant to an already-invoked unconditional guarantee. Similarly, Makharia Bros. concerned a failure to extend a guarantee and did not apply where invocation preceded expiry.

Describing the Bank’s conduct as “untenable and frivolous,” the Court emphasised that public and commercial confidence depends on banks honouring their guarantees. Allowing evasions such as those attempted by the appellant would imperil national and international commerce.

Holding and Implications

Appeal dismissed with costs.

Immediate Effect: The Bank must honour the unconditional guarantee and pay the beneficiary; costs are awarded to Respondents 1 and 2.

Broader Implications: While not establishing a new legal test, the decision reinforces existing jurisprudence that banks must promptly honour unconditional on-demand guarantees once validly invoked, and cannot rely on procedural delays or alleged contractual substitutions to avoid payment.

To access the original judgment, please Sign In or Subscribe.

    Bank Of India v. Nangia Constructions (I) Private Limited And Others

    Dalveer Bhandari, J.— This appeal is directed against the judgment and order dated 26-10-1999 of the High Court of Delhi at New Delhi in FAO (OS) No. 81 of 1999.

    2. The learned Single Judge of the High Court has taken the view that the invocation of bank guarantee was within the validity period of the bank guarantee and the Bank cannot decline to make the payment. The Division Bench in the impugned judgment while dismissing the appeal has clearly observed that the bank guarantee was invoked on 19-5-1989 within the validity period of the guarantee. The bank guarantee was merely renewed under orders of the Court as there was a stay order against encashment of the bank guarantee. Once the stay order was vacated there was no question of any invocation of the bank guarantee. In the instant case, the invocation had already taken place within the validity period. Thereafter, all that was to be done was to intimate the Bank that the stay has been vacated and that now payment had to be made under the bank guarantee.

    3. The Division Bench in great anguish has observed thus:

    “It is surprising that a nationalised bank, which has given an unconditional on demand bank guarantee takes up such a contention. No ground to refuse payment was shown to the lower court or to us. It is surprising that nationalised bank wants to use delays of law in order not to comply with its unconditional obligations under a bank guarantee. The nationalised bank should know that it is such conduct which is adversely affecting the faith of the public in banking institutions and in transaction of bank guarantee.”

    The Court dismissed the appeal with costs.

    4. The nationalised bank despite the concurrent findings of both the courts and such a strong observation of the Division Bench of the High Court has still chosen to file this appeal before this Court. Even before this Court, this is not disputed that the bank guarantee was invoked within the validity period of the bank guarantee.

    5. Mr K.N Bhat, the learned Senior Counsel appearing for the appellant Bank submitted that there was a substituted agreement of contract, therefore, the invocation of the bank guarantee by Respondent 2 on 19-5-1989 was of no consequence.

    6. It may be relevant to mention here that after the bank guarantee was invoked, an application was filed in the Court for stay of payment under the bank guarantee. To that application, the Bank was not a party. Initially, an injunction was granted by the High Court on 29-5-1989. This was on a condition that the bank guarantee should be kept alive. This injunction was confirmed on 23-4-1990 again on the condition that the bank guarantee should be kept renewed. The constituent who had obtained injunction and who was to keep the bank guarantee alive, did not pay the charges of the Bank in respect of renewals of the bank guarantees. Consequently, the appellant Bank refused to renew the bank guarantee after 26-5-1996. Thus, the beneficiary of the bank guarantee took out an application wherein the following prayer was made:

    “In the circumstances it is, therefore, most humbly and respectfully prayed that the petitioner be directed to extend the bank guarantee for an initial period of one year and the petitioner be directed to continue to extend the bank guarantees and furnish the same to the respondent at least fifteen days before the expiry till the disputes are finally adjudicated upon by arbitration and on the failure of the petitioner to renew the bank guarantees as aforesaid the respondent may be permitted to encash the above bank guarantee.”

    7. As the question was whether the bank guarantee was to be renewed, notice was issued to the appellant Bank to remain present in the Court. This was in order to find out whether they would be willing to renew the bank guarantee. The appellant Bank appeared and made it clear to the Court that they were not ready to renew the bank guarantee as according to them the charges are not being paid.

    8. The appellant Bank has reiterated the same argument before this Court that since the bank guarantee has not been renewed, therefore, the Bank is under no obligation to pay the amount under the bank guarantee.

    9. Learned counsel for the appellant has placed reliance on two judgments of this Court, on Union of India v. Kishorilal Gupta & Bros. AIR 1959 SC 1362, (1960) 1 SCR 493 and Makharia Bros. v. State of Nagaland (2000) 10 SCC 503.

    10. In Kishorilal Gupta AIR 1959 SC 1362, (1960) 1 SCR 493 this Court has held that it was well settled that the parties to an original contract could by mutual agreement enter into a new contract in substitution of the old one. There is no quarrel with this proposition. The parties are always at liberty to enter into a fresh contract but this case has no application to the facts of the present case.

    11. In Makharia Bros. (2000) 10 SCC 503 the question was:

    “7. … what was [the State's] remedy against the contractor when the contractor failed to furnish the security deposit in cash or, in lieu thereof, by a bank guarantee. The State could not have filed a suit requiring the contractor to do these things for it as it would have been tantamount to asking for a decree of specific performance, a decree which would have been incapable of enforcement if the contractor was unable or unwilling to pay out money or put a bank in funds to provide a bank guarantee. When the contractor declined to extend the terms of the bank guarantee, the proper course for the State was to terminate the contract on the ground of breach of the terms thereof as aforestated, make a claim for damages and recover on the bank guarantee, if necessary by filing a suit.”

    We are afraid that even this case is of no help to the appellant because the facts of the instant case are quite different. Admittedly, the bank guarantee has been invoked during the validity period of the bank guarantee. The bank guarantee was unconditional on demand bank guarantee. The Bank was bound to honour its commitment and pay the amount of guarantee.

    12. It is unfortunate that a nationalised bank is finding excuses for refusing to make the payment on totally untenable and frivolous grounds. The Division Bench was fully justified in making observations regarding the conduct of the nationalised bank. The entire trust, faith and confidence of people depends on the conduct and credibility of the nationalised bank. In the present day world, the national and international commercial transactions largely depend on bank guarantees. In case the banks are permitted to dishonour their commitments by adopting such subterfuges, the entire commercial and business transactions will come to a grinding halt. This principle has been reiterated in large number of cases by this Court. We do not deem it appropriate to burden this judgment by reiterating all those judgments.

    13. This appeal being devoid of any merit is accordingly dismissed with costs to be paid to Respondents 1 and 2.

    Civil Appeal No. 3592 of 2008 [Arising out of SLP (Civil) No. 3644 of 2007]

    14. Leave granted.

    15. In view of our aforesaid decision, this appeal is also dismissed with costs.

    Use AI to get other relevant cases.

    Comments

    Bank Of India v. Nangia Constructions (I) Private Limited And Others
    (May 15, 2008)