AMICUS AI
Citation Codes
Neutral Citations
1994 INSC 599
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 132(5), Section 132(11), Section 132(12) of the Income Tax Act
  • Article 226 of the Constitution
  • Section 13(1) of the Act
  • Section 13(3) of the Act
  • Sections 344 and 345 of the Bombay Municipal Corporation Act
  • sub-section (2) of Section 13 of the Act
  • Section 346 of the Bombay Municipal Corporation Act
  • Sub-section (3) of Section 13 of the Act
  • Section 13(4) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(2) of the Act
  • Section 13 of the BMRDA Act
  • Section 13 of the Bombay Metropolitan Region Development Act, 1974
  • Section 13 of the said Act
  • Section 13(3) of the BMRDA Act
  • Bombay Metropolitan Region Development Act, 1974 (Maharashtra Act No. IV of 1975)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • statute
  • Section 13(3) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(2) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(bb) of the Bombay Rents, Hotel and Lodging House Rates Control Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
1994 INSC 599
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 132(5), Section 132(11), Section 132(12) of the Income Tax Act
  • Article 226 of the Constitution
  • Section 13(1) of the Act
  • Section 13(3) of the Act
  • Sections 344 and 345 of the Bombay Municipal Corporation Act
  • sub-section (2) of Section 13 of the Act
  • Section 346 of the Bombay Municipal Corporation Act
  • Sub-section (3) of Section 13 of the Act
  • Section 13(4) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(2) of the Act
  • Section 13 of the BMRDA Act
  • Section 13 of the Bombay Metropolitan Region Development Act, 1974
  • Section 13 of the said Act
  • Section 13(3) of the BMRDA Act
  • Bombay Metropolitan Region Development Act, 1974 (Maharashtra Act No. IV of 1975)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • statute
  • Section 13(3) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(2) of the Bombay Metropolitan Region Development Authority Act, 1974
  • Section 13(bb) of the Bombay Rents, Hotel and Lodging House Rates Control Act
Smart Summary

Factual and Procedural Background

In 1974, Gokak Patel Volkart Ltd. submitted a plan to the Municipal Corporation of Greater Bombay to demolish two tenant-occupied houses at 124-126 Wodehouse Road, Colaba, Bombay, and construct a thirty-storeyed building using a Floor Space Index (FSI) of 2.45. An Intimation of Disapproval (IOD) was issued on 13-9-1974 that required eviction of tenants and a “No Objection” certificate from the Housing Commissioner.

Meanwhile, the Bombay Metropolitan Region Development Authority Act, 1974 came into force on 26-1-1975. Section 13 empowered the Bombay Metropolitan Region Development Authority (BMRDA) to regulate developments likely to affect the metropolitan region. A notification dated 10-6-1977 capped FSI at 1.33. Because the proposed building exceeded that limit, the Company applied on 14-7-1977 for permission under Section 13(2). The application, received on 15-7-1977, was refused on 8-9-1977 (within sixty days). The Company appealed and on 23-2-1978 the State Government allowed the appeal, whereupon a commencement certificate issued on 31-3-1980.

Residents of Colaba challenged the State Government’s order. On 5-4-1984 the Bombay High Court quashed both the State Government’s order and BMRDA’s 1977 refusal, directing BMRDA to reconsider the application. BMRDA again rejected the application on 19-9-1984. The Company both appealed to the State Government (16-10-1984, still pending) and filed a writ petition contending that, because more than sixty days had elapsed after the High Court’s judgment, permission should now be deemed to have been granted. A Division Bench accepted that contention, holding that a “deemed permission” arose and thus set aside BMRDA’s second refusal.

The present civil appeals were brought by the authorities against that Division Bench decision.

Legal Issues Presented

  1. Whether the High Court ought to have entertained the Company’s writ petition when an alternative statutory appeal was not only available but actually pending.
  2. Whether, after an initial refusal within sixty days is quashed on appeal, the expiry of sixty days from the date of remand triggers the “deemed permission” clause in Section 13(3) of the BMRDA Act.
  3. Whether the statutory sixty-day limit in Section 13(3) applies only to the first decision on an application or also to any subsequent decision passed pursuant to appellate or High Court directions.

Arguments of the Parties

Appellant’s Arguments (Authorities)

  • The writ petition was not maintainable because the Company had an adequate, pending statutory appeal; therefore, the High Court should have declined jurisdiction.
  • The deemed-permission fiction in Section 13(3) arises only when no order is passed within sixty days of the original application. An order was in fact passed on 8-9-1977, so the fiction never arose.
  • When an order passed within limitation is quashed on appeal, the statute does not require the fresh order to be passed within the same sixty-day period; Pooran Mall governs this situation.

Respondent Company’s Arguments

  • Because the earlier refusal was quashed, it was as though no order existed; therefore, failure to take a fresh decision within sixty days after the High Court’s judgment resulted in deemed permission.
  • Reliance was placed on Shree Chamundi Mopeds to emphasise the legal effect of quashing (as distinct from merely staying) an order.
  • The subsequent refusal dated 17-9-1984, purportedly under Section 13(3), was thus without jurisdiction and void.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Shree Chamundi Mopeds Ltd. v. Church of South India Trust Assn., (1992) 3 SCC 1 Quashing an order restores the status quo ante; staying an order merely suspends its operation. Respondent relied on it, but the Court held that although the 1977 refusal was quashed, an order had nonetheless been passed within sixty days, so the deeming provision never arose.
Director of Inspection (Investigation) v. Pooran Mall, (1975) 4 SCC 568 Statutory time limits apply to the initial order; fresh orders passed pursuant to appellate directions are not bound by the original limitation period. Formed the core rationale for rejecting the deemed-permission argument; the Court adopted this principle to hold that the 60-day limit did not apply to the second decision required after remand.
R. v. Paddington Valuation Officer, (1966) 1 QB 380 Relationship between certiorari and mandamus; effect of quashing administrative lists. Cited by the Company; the Court distinguished it as not supportive of the Company’s case.
R. v. Cotham ex parte William, (1898) 1 QB 802 Mandamus lies only where no valid act has been performed. Referenced within the Paddington discussion; not determinative of the instant appeal.
Supdt. of Taxes v. Onkarmal Nathmal Trust, (1976) 1 SCC 766 Governmental laches can invalidate belated action even where earlier restraint orders existed. Distinguished; Court found no laches because an order had been timely passed in 1977.

Court's Reasoning and Analysis

1. Alternative Remedy: The Supreme Court first held that the writ petition should not have been entertained because the Company had an efficacious statutory appeal pending. The existence and prior invocation of that remedy made recourse to Article 226 inappropriate.

2. Deemed Permission: Interpreting Section 13(3), the Court reasoned that the deeming provision is triggered only when the Metropolitan Authority fails to decide within sixty days of receiving the application. In this case, the Authority decided on 8-9-1977—well within sixty days of 15-7-1977—so the statutory fiction never arose.

3. Effect of Quashing: Quashing the 1977 order did not retroactively erase the fact that a timely decision had been made; it merely required a fresh decision. Nothing in Section 13 resets the sixty-day clock upon remand. The Court drew direct support from Pooran Mall, which held that statutory deadlines attach only to the initial order.

4. Reasonable Time on Remand: Because the High Court’s 1984 remand imposed no time-limit, the Authority’s duty was to act within a reasonable period, not within another sixty-day statutory window. Consequently, the refusal dated 19-9-1984 was within jurisdiction.

5. Distinction from Citations Relied on by Company: The Court distinguished Shree Chamundi Mopeds and Paddington Valuation Officer, explaining that those cases did not alter the statutory scheme of Section 13(3) when an initial, timely order exists.

Holding and Implications

Appeal Allowed – High Court judgment dated 15-6-1994 set aside.

Immediate Effect: The “deemed permission” theory accepted by the High Court is overturned; the respondent Company cannot rely on Section 13(3) to assert automatic approval of its 30-storey plan. The appellant authorities are free to proceed in accordance with law, and the Company’s statutory appeal against the 19-9-1984 refusal remains the proper forum for redress. No costs were awarded.

Broader Implications: The decision confirms that (i) statutory time-limits for administrative decisions apply only to the first determination, and (ii) quashing an order does not automatically trigger deeming provisions or restart limitation periods. It reinforces judicial restraint where adequate statutory remedies exist, but does not create new precedent beyond applying settled principles.

To access the original judgment, please Sign In or Subscribe.

    Bombay Metropolitan Region Development Authority, Bombay v. Gokak Patel Volkart Ltd. And Others

    Sen, J.— Leave granted.

    2. On 28-5-1974, Gokak Patel Volkart Ltd, submitted a plan for construction of two houses at premises Nos. 124-126 Wodehouse Road, Colaba, Bombay, to the Municipal Corporation of Greater Bombay. The said two houses were occupied by tenants. The plan was for construction of a thirty-storeyed building utilising Floor Space Index (for short FSI) of 2.45 of the said plot.

    3. The Development Control Rules existent at the relevant time permitted construction of building on the FSI of 2.45 under R-8 FSI zone in which the above property was situated. The plan was approved by the Corporation and on 13-9-1974 Intimation of Disapproval (IOD) was granted to the Company under Section 346 of the Bombay Municipal Corporation Act. It was stipulated in the IOD that no work should be started unless the existing structures proposed to be removed were in fact removed. It was also stated in the IOD that it was given exclusively for the purposes of enabling the party to proceed further with arrangements of obtaining “No Objection” Certificate from the Housing Commissioner under Section 13(bb) of the Bombay Rents, Hotel and Lodging House Rates Control Act. In pursuance of the IOD granted by the Corporation, the Company initiated proceeding for eviction of the tenants from the existing structures on the property in question. Ultimately in August 1979, the tenants were evicted and old structures were demolished. In the meantime, in 1975, the State Legislature of Maharashtra enacted the Bombay Metropolitan Region Development Act, 1974 (Maharashtra Act No. IV of 1975) to provide for the establishment of an authority for the purpose of planning, coordinating and supervising the proper, orderly and rapid development of the areas falling within that region. The said Act came into force with effect from 26-1-1975. Section 13 of the Act provides:

    “13. (1) Notwithstanding anything contained in any law for the time being in force, except with the previous permission of the Authority, no authority or person shall undertake any development within the Metropolitan Region of the type as the Metropolitan Authority may from time to time specify, by notification published in the Official Gazette, and which is likely to adversely affect the overall development of the Metropolitan Region.
    (2) Any authority or person desiring to undertake development referred to in sub-section (1) shall apply in writing to the Metropolitan Authority for permission to undertake such development.
    (3) The Metropolitan Authority shall, after making such inquiry as it deems necessary and within 60 days from the receipt of an application under sub-section (2), grant such permission without any conditions or with such conditions as it may deem fit to impose or refuse to grant such permission. If such permission is not refused within 60 days as aforesaid, it shall be deemed to have been granted by the Authority.
    (4) Any authority or person aggrieved by the decision of the Metropolitan Authority under sub-section (3), may, within 30 days, appeal against such decision to the State Government, whose decision shall be final.”

    4. The Metropolitan Authority, in exercise of powers under sub-section (1) of Section 13 of the said Act, published in the Official Gazette a notification dated 10-6-1977 providing, inter alia, that no construction or reconstruction of any building including addition to any existing building shall be carried out so as to have a Floor Space Index exceeding 1.33

    5. As a result of the provisions of Section 13(1) of the Act and the notification dated 10-6-1977, a person desiring to undertake development in contravention of the notification had to apply in writing to the authority for permission to undertake such development. The authority could grant permission without any condition or with such conditions as it thought fit or refuse to grant such permission. This has to be done within 60 days from the receipt of the application under sub-section (2) of Section 13. If the permission was not refused within the aforesaid period of 60 days under sub-section (3) of Section 13, such permission should be deemed to have been granted by the authority.

    6. In view of the above developments, on 14-7-1977, Gokak Patel Volkart Ltd. (hereinafter described as “the respondent-Company”), applied to the Bombay Metropolitan Region Development Authority (hereinafter described as ‘BMRDA’) under Section 13(2) of the Bombay Metropolitan Region Development Authority Act, 1974 (hereinafter referred to as ‘the Act’) for permission to undertake the above development with the FSI of 2.45 The said application was received by the BMRDA on 15-7-1977. The permission was refused by the Metropolitan Authority under Section 13(3) of the Act on 8-9-1977. The respondent-Company preferred an appeal to the State Government under Section 13(4) of the Act on 19-9-1977 which was allowed by the State Government on 23-2-1978. Accordingly, the respondent-Company was given a commencement certificate under Sections 344 and 345 of the Bombay Municipal Corporation Act on 31-3-1980.

    7. Soon thereafter a writ petition was filed by the residents of Colaba challenging the above order of the State Government under Section 13(3) of the Act allowing the appeal of the respondent-Company against the order of the Metropolitan Authority. By a judgment dated 5-4-1984 passed by the Bombay High Court, the order of the State Government as well as the order passed by the Metropolitan Authority under Section 13(3) of the Act rejecting the application of the respondent-Company were set aside with a direction to the Administrator of the Municipal Corporation of Greater Bombay to consider the application afresh and pass appropriate orders.

    8. The material part of the order was as under:

    “Accordingly, the petition succeeds and the impugned order dated 23-2-1978 passed by Minister for Housing and BMRDA is set aside and so also the order passed by Respondent 3 rejecting the application and which was communicated to Respondent 4 on 8-9-1977. Respondent 3 is directed to reconsider the application dated 14-7-1977 filed by Respondent 4 under sub-section (2) of Section 13 of the Act, in accordance with the observation made in this judgment and pass appropriate orders. Respondent 3 shall pass the orders as expeditiously as possible.”

    9. The Metropolitan Authority took up the application of the respondent-Company under Section 13(3) of the Act for reconsideration in pursuance of the above order of the Court and by the order dated 19-9-1984 rejected the application under Section 13(3). Against that, the respondent-Company filed appeal on merits before the State Government on 16-10-1984 which is still pending.

    10. On the very next day, the writ petition was also filed in the High Court of Judicature at Bombay by the respondent-Company, challenging the order of the Metropolitan Authority passed under Section 13(3) rejecting the application of the respondent-Company under Section 13(2) of the Act on the ground that in the facts and under the circumstances of the case and in view of the lapse of sixty days stipulated in Section 13(3) of the Act, permission was deemed to have been granted to the respondent-Company by the Metropolitan Authority and in that view of the matter, the order of rejection passed under Section 13(3) was illegal and without jurisdiction.

    11. The Division Bench of the Bombay High Court upheld the contention of the Company and held that permission must be deemed to have been granted to construct the building according to the plan in view of the fact that such permission had not been refused within 60 days as required by sub-section (3) of Section 13 of the Act. In coming to this decision the Division Bench took note of the following facts. The judgment in the earlier writ petition had been delivered on 5-4-1984 by which order of the Metropolitan Authority passed under Section 13(3) had been set aside. There was a direction to pass a fresh order, that direction was not carried out at all. BMRDA applied for certified copy of the judgment on 18-4-1984; on 24-5-1984 the Company communicated the operative part of the order dated 5-4-1984 to BMRDA. The Executive Committee of the BMRDA sat on 18-7-1984 and again on 24-7-1984 and finally decided to reject the application of the respondent-Company under Section 13(2) of the Act on 17-9-1984. The BMRDA had no jurisdiction to pass any order under Section 13(3) of the Act on 17-9-1984, as the requisite period of 60 days provided by under Section 13(3) had expired by that time. It was held by Division Bench that the order dated 17-9-1984 refusing to grant permission passed by the Authority was illegal. The said order was passed beyond the statutory period of 60 days, therefore, permission shall be deemed to have been granted by the Authority in terms of Section 13(3) of the Act.

    12. The contention of the appellant in this appeal is that in the first place the writ petition should not have been entertained. The writ petitioner had an adequate alternative statutory remedy. The writ petitioner had in fact already taken advantage of alternative remedy provided by the statute and had preferred an appeal against the judgment of the Tribunal. While the said appeal was pending the writ petitioner invoked the writ jurisdiction of the Bombay High Court praying more or less the same remedy as was prayed in the appeal.

    13. We are of the view that the point taken by the appellant is of substance. This is a case, where there is not only the existence of an alternative remedy but the writ petitioner actually had availed of that remedy. The writ petitioner's appeal before the statutory authority was pending. In that view of the matter this writ petition should not have been entertained.

    14. The second point urged by Mr Salve is also of substance. The respondent had applied to BMRDA for permission to undertake the development work with the FSI of 2.45 under sub-section (2) of Section 13 of the Act. That application was received by the BMRDA on 15-7-1977. The application was rejected by an order passed on 8-9-1977 within the requisite period of 60 days from the receipt of the application as laid down in sub-section (3) of Section 13. The statutory fiction of deemed permission arises only if there is a failure on the part of the Metropolitan Authority to pass an order within 60 days of the receipt of the application. No question of this time-limit arises when the Appellate Authority quashes the order and directs a fresh order to be passed. In such a situation there cannot be any question of passing an order within 60 days from the receipt of the application under sub-section (2) of Section 13. The application was received by the Metropolitan Authority on 15-7-1977. In order to accept the contention of the respondent it has to be deemed that the receipt of the application was on the date of the judgment which was passed on 5-4-1984 or any subsequent date. There is nothing in the wording of sub-section (3) of Section 13 justifying such a construction.

    15. Mr Nariman appearing on behalf of the Company drew our attention to the decision of this Court in the case of Shree Chamundi Mopeds Ltd. v. Church of South India Trust Assn. (1992) 3 SCC 1 A distinction was drawn between quashing an order and stay of operation of an order. It was explained in that judgment that quashing of an order resulted in restoration of the position as it stood on the date of passing of the order. The stay of the operation of the order, however, did not lead to such results.

    16. It is true that the order dated 17-9-1984 after being quashed did not remain in suspended animation. That would have been the case, had the order been merely stayed. That, however, does not mean that the Metropolitan Authority had failed to pass an order within 60 days of the receipt of the application.

    17. As a matter of fact, the application received by the Metropolitan Authority on 15-7-1977 was disposed of by an order dated 8-9-1977 within the requisite period of 60 days. Therefore, there is no question of the deeming provision coming into operation in this case at all. The order passed by the Metropolitan Authority may have been quashed by the High Court but the fact remains that an order was actually passed within the requisite period of time. The deeming provision would have come into operation only if no order was passed within 60 days of the receipt of the application on 15-7-1977.

    18. After the High Court quashed the order passed by the Metropolitan Authority on 17-9-1984, a fresh order had to be passed under the direction of the Court and not on the basis of any fresh application. This fresh order could not have possibly been passed within 60 days of the receipt of the application on 15-7-1977. The High Court could have fixed a time-limit for passing a fresh order. If such a time-limit had been fixed, the Metropolitan Authority had to pass an order within that period. But in this case no time-limit was fixed by the High Court. Therefore, the Metropolitan Authority had to pass a fresh order within a reasonable time.

    19. It is well settled that when the statute lays down the period of limitation for passing an order that requirement is fulfilled as soon as an order is passed within that period. If the order is set aside on appeal and the appellate order directs a fresh order to be passed then there is no requirement of law that the consequential order to give effect to the appellate order must also be passed within the statutory period of limitation. This proposition of law is well settled.

    20. In the case of Director of Inspection of Income Tax (Investigation) v. Pooran Mall (1975) 4 SCC 568, (1974) 96 ITR 390 this Court repelled the contention that the Income Tax Officer had no jurisdiction to pass an order under Section 132(5) of the Income Tax Act when the order initially passed by him within the period of limitation had been set aside by the appellate authority. It was held in that case that the period of time fixed for passing an order under Section 132(5) applied only to the initial order and not to any subsequent order that may have to be passed under the direction given by a statutory authority or by a court in a writ proceeding. It was observed:

    “Even if the period of time fixed under Section 132(5) is held to be mandatory that was satisfied when the first order was made. Thereafter, if any direction is given under Section 132(12) or by a court in writ proceedings, as in this case, we do not think an order made in pursuance of such a direction would be subject to the limitations prescribed under Section 132(5). Once the order has been made within ninety days the aggrieved person has got the right to approach the notified authority under Section 132(11) within thirty days and that authority can direct the Income Tax Officer to pass a fresh order. We cannot accept the contention on behalf of the respondents that even such a fresh order should be passed within ninety days. It would make the sub-sections (11) and (12) of Section 132 ridiculous and useless. It cannot be said that what the notified authority could direct under Section 132 could not be done by a court which exercises its powers under Article 226 of the Constitution. To hold otherwise would make the powers of courts under Article 226 wholly ineffective. The court in exercising its powers under Article 226 has to mould the remedy to suit the facts of a case.”

    21. Mr Nariman next drew our attention to the decision of the Court of Appeal in the case of R. v. Paddington Valuation Officer (1966) 1 QB 380, (1965) 2 All ER 836. In particular we were referred to the judgment of Salmon, L.J wherein it was observed:

    “I am not altogether satisfied that there would be any power to grant mandamus and keep the 1963 valuation list in force by the simple expedient of postponing certiorari until after a new list had been prepared. No doubt it would be convenient, if possible, to follow this course, were the appeal to be allowed; indeed grave inconvenience, if not chaos would follow if the 1956 valuation list were to be revived which both the appellants and respondents at first agreed would be the inevitable result of allowing the appeal. It may be that mandamus can be granted without certiorari, but mandamus cannot be granted if there is a valid valuation list in being. It is not enough that the valuation officer should have prepared the list badly or even very badly. In such a case, he could not be ordered by mandamus to correct his mistakes or make a new list. In order for mandamus to lie, it must be established that he has prepared the list illegally or in bad faith, so that in effect he has not exercised his statutory function at all and that accordingly there is in reality no valid list in existence: R. v. Cotham ex parte William (1898) 1 QB 802. Accordingly, it seems to me that a finding that the list is null and void is necessarily implicit in an order of mandamus.”

    22. We fail to see, how the respondents can derive any support for their case from these observations of Salmon, L.J That was a case where it was found that the valuation officer had prepared a valuation list of 31,656 dwellings at Paddington erroneously. There was a prayer for certiorari to quash the list altogether. There was also another prayer for a writ of mandamus directing the valuation officer to prepare a new list. Lord Denning, M.R held that if the valuation list was entirely quashed there will be chaos. Therefore, the existing list could remain until it was replaced by a new list, when the new list was prepared the old list will be quashed by writ of certiorari. Lord Denning was of the view that certiorari was not a necessary prerequisite to mandamus.

    23. Lord Salmon, L.J did not express any final opinion on the controversy. It was observed:

    “Having regard to the view, however, that I take of the facts, the point as to whether the 1963 list could be temporarily kept alive were mandamus to issue does not arise for decision and I express no concluded opinion upon it.”

    24. In the case before us the decision taken by Metropolitan Authority on the application of the respondent has been quashed. Direction has been given to dispose of the application afresh. This direction does not make any sense unless in reality there was an earlier order dealing with the application made by the respondent. It cannot be said that the Metropolitan Authority had not passed any order, erroneously or otherwise, within 60 days of the receipt of the application. The order that was passed may have become null and void in law but the fact of the matter is that an order had actually been passed, otherwise there would have been no question of issuance of a writ of certiorari for quashing of that order.

    25. In the case of Supdt. of Taxes v. Onkarmal Nathmal Trust (1976) 1 SCC 766, 1975 Supp SCR 365 this Court dealt with the question whether a notice under Section 7(2) of the Assam Taxation (On Goods Carried by Road or Inland Waterways) Act, 1961 was valid. The prescribed period of limitation under the Act was two years from the expiry of the relevant period. There was a difference of opinion on this point. The majority view was that the State was guilty of laches even though the State was restrained by an order from taking any action under the Act. The State did not pray for modification of the order. The State followed the policy of inactivity. Therefore, the notice under Section 7(2) issued in that case was held invalid.

    26. In the instant case, there is no question of any inactivity. The appellant had passed an order within 60 days, which was ultimately quashed by the High Court. The deeming clause under Section 13(3) comes into operation only when the Metropolitan Authority fails to pass an order within a period of 60 days from the receipt of the application. But if an order is passed and that order is quashed by the appellate authority or by the High Court, the deeming clause does not become operative straightaway. The appellate order will now hold the field and fresh order will have to be passed in terms of the order of the appellate authority or the Court.

    27. The last contention of Mr Nariman was that the impugned order dated 17-9-1984 had been passed under Section 13(3) of the BMRDA Act. The Metropolitan Authority had no jurisdiction to pass any order dealing with the application made by the respondent under any other provision except Section 13(3). If the order is not under Section 13(3) then the respondent will have no right to appeal against that order.

    28. There can be no dispute about this preposition. The consequential order passed by the Metropolitan Authority after it was quashed by the High Court must be treated as an order under Section 13(3) of the Act for the purpose of appeal and the limitation must be counted from the date of the fresh order. But that does not answer the question whether the time-limit for passing an order under sub-section (3) of Section 13 will apply to the fresh order which will now have to be passed. That question has been answered in the case of Pooran Mall (1975) 4 SCC 568, (1974) 96 ITR 390 referred to earlier in the judgment.

    29. In the premises this appeal is allowed. The judgment under appeal dated 15-6-1994 is set aside. The appellant will be at liberty to proceed in accordance with law. There will be no order as to costs.

    Civil Appeals Nos. 9153-54 of 1994 [Arising out of SLPs (C) Nos. 15942 & 15982 of 1994]

    30. Leave granted.

    31. In view of our judgment in Civil Appeal No. 9152 of 1994 [arising out of SLP (C) No. 14848 of 1994], the above appeals are also allowed. There will be no order as to costs.