Smart Summary

Factual and Procedural Background

This judgment disposes of multiple Letters Patent Appeals (Nos. 510, 633, 740–755, 778–780 of 1986) and Civil Writ Petitions (Nos. 2389, 4122, 4941, 5034 of 1986; 208, 490, 2505, 3892 of 1987; and 1787 of 1988). The Court treated Civil Writ Petition No. 718 of 1986 as the main writ petition and applied observations made in relation to that petition to the others.

The writ petitioners were work-charged employees engaged at the Anandpur Sahib Hydel Project. Minutes of a meeting held on December 17, 1974 (Annexure P.2) recorded a policy decision that work-charged employees in all three branches of the Public Works Department who had completed five years' service and were working against government posts of a regular maintenance nature should be made regular, with effect from April 1, 1975. Subsequent communications by the Chief Engineer to Superintending Engineers conveyed regularisation of such work-charged employees.

The Project was completed in January 1985. Some categories of staff became surplus and their services were terminated, which led to the writ petitions. The petitioners claimed entitlement to regularisation under the 17-12-1974 policy decision and the Chief Engineer's communications. The State responded that petitioners were temporary work-charged employees engaged on a temporary basis; the Project's completion meant surplus staff whose services were terminable under Rule 20(1) read with Rule 3(a) of the certified standing orders for work-charged staff. The State also contended the 1974 policy decision and subsequent communications were not applicable because the petitioners were not engaged against government posts of the regular maintenance nature specified in the minutes.

The learned Single Judge issued directions ordering regularisation from the relevant April 1st following completion of five years' continuous service, computation of seniority across the department, absorption into maintenance jobs on project completion and transfer/absorption of surplus employees while treating Anandpur service as continuous for pay and benefits. The Single Judge relied on Article 226 and on certain precedents in reaching that conclusion.

Legal Issues Presented

  1. Whether the policy decision recorded in the Minutes of the meeting dated 17-12-1974 and the subsequent communications from the Chief Engineer are enforceable by issuance of a writ of mandamus under Article 226 of the Constitution of India.
  2. Whether the writ petitioners (work-charged employees at Anandpur Sahib Hydel Project) are entitled to regularisation and the reliefs directed by the learned Single Judge based on that policy decision and communications.
  3. Whether executive administrative instructions (such as the Minutes and the Chief Engineer's communications) have the force of statutory rules under Article 162 of the Constitution so as to be justiciable.

Arguments of the Parties

Writ Petitioners' (Workers') Arguments

  • The petitioners were work-charged employees engaged at the Anandpur Sahib Hydel Project and, having completed the requisite period of service, were entitled to regularisation in accordance with the policy decision recorded in the Minutes of the meeting dated 17-12-1974 (Annexure P.2).
  • Subsequent communications from the Chief Engineer to Superintending Engineers implementing the policy reinforced that entitlement; therefore the terminations were without legal sanction.

State's Arguments

  • No termination notice was issued with effect from 27-2-1986 as alleged; the petitioners were engaged on a purely temporary basis as work-charged employees.
  • The Project was completed in January 1985 and surplus work-charged employees’ services were no longer required; their services were terminable under Rule 20(1) read with Rule 3(a) of the certified standing orders for work-charged staff on completion of the Project.
  • The policy decision of 17-12-1974 and the Chief Engineer's communications are not applicable to these petitioners because they were not engaged against government posts of a regular maintenance nature in any of the three branches of the Public Works Department.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Dr. Amarjit Singh Ahluwalia v. The State of Punjab and Ors., 1975 S.L.J. 220 In absence of statutory rules regulating recruitment or conditions of service, the State Government may issue administrative instructions providing for recruitment and laying down conditions of service. The Single Judge relied on this decision to treat executive instructions/policy as enforceable; the High Court questioned applicability of this ratio to the present facts.
Union of India v. K. P. Joseph and Ors., 1973 (1) S.L.R. 910 The benefits accruing to ex-military personnel on re-employment relating to conditions of service could be enforced when provided by a general order. The Single Judge relied on this decision; the High Court found difficulty in applying its ratio to the present case.
G. J. Fernandez v. State of Mysore, A.I.R. (1967) S.C. 1753 Administrative instructions not issued under statutory authority or a constitutional provision (Article 162 alone insufficient) are mere administrative instructions and do not have statutory force; breach of such instructions does not confer a right to seek quashing orders from the court. The Court applied this principle and held that the Minutes of the meeting dated 17-12-1974 and the Chief Engineer's communications were administrative instructions without statutory force and therefore not enforceable by writ.
The Tamil Nadu E.D.M. & G.S.S.A. etc. v. State of Tamil Nadu and Ors., 1980 (Unreported S.C.) 285 (V. R. Krishna Iyer J.) Judicial restraint in service jurisprudence; courts should not substitute administrative judgment for the executive except in cases of unconstitutional excess. The Court cited observations to underscore deference to administrative decision-making and to support the view that the court should not convert administrative instructions into enforceable statutory rights.
Piara Singh & Another v. State of Haryana and Ors., 1988 (4) S.L.R. 739 Bench decision cited by counsel to support that a work-charged employee with more than two years' service may be entitled to regularisation (as argued by petitioners' counsel). The Court noted the counsel relied on this decision but observed that the judgment specifically excludes applicability to industrial workers, so it did not support petitioners' case as advanced.
G. Govinda Rajula v. The Andhra Pradesh State Construction Corporation Ltd. and Anr., A.I.R. 1987 S.C. 1801 Equitable directions for absorption/rehabilitation of retrenched employees in appropriate circumstances. The Court followed this decision in ordering that retrenched employees be considered for absorption into other projects or government service according to qualifications and fitness, with specified conditions (six‑month period, age relaxation if necessary, counting Anandpur service for pension if appointed to pensionable jobs, but appointments treated as new for seniority).

Court's Reasoning and Analysis

The Court began by identifying the central legal question as whether the Minutes of the meeting of 17-12-1974 and the Chief Engineer's communications possess the character of executive instructions under Article 162 such that they become enforceable (i.e., have the force of statutory rules) and could be enforced by issuance of writs under Article 226.

The learned Single Judge had interpreted the Minutes as a policy decision enforceable under Article 226 and relied on decisions such as Dr. Amarjit Singh Ahluwalia and Union of India v. K. P. Joseph to support enforceability of executive instructions in the absence of statutory rules. The High Court analysed this reliance and found it difficult to apply the cited ratios to the present facts.

The Court examined Article 162 and explained that it defines the scope of the State's executive power but does not itself confer rule-making authority on the State Government. The Court emphasized that for administrative instructions to have the force of statutory rules they must have been issued under authority conferred by statute or under a constitutional provision that specifically permits rule-making; Article 162 alone does not suffice.

The Court relied on the reasoning in G. J. Fernandez v. State of Mysore, where the Supreme Court held that departmental codes or instructions not framed under statutory authority are mere administrative instructions and do not create rights enforceable by court orders. Quoting and applying that principle, the Court held that the Minutes of 17-12-1974 and the communications of the Chief Engineer are administrative in character and not statutory rules; consequently, breach of those instructions did not confer a legally enforceable right on the petitioners to maintain the writ petitions.

The Court also invoked observations from the Tamil Nadu case to underline the need for judicial restraint in matters of administrative policy and integration of services, noting that courts should not indulge in "fussy forensic monitoring" of administrative choices absent unconstitutional excesses.

Because the petitioners' entire case depended on the alleged policy decision and communications — which the Court held were not justiciable statutory instruments — the petitioners lacked the requisite legal right to support their writs; therefore their claims for regularisation failed on that ground.

Nonetheless, the Court considered equitable relief. Following the Supreme Court decision in G. Govinda Rajula (A.I.R. 1987 S.C. 1801), the Court directed respondents to consider absorption of retrenched employees into other projects or government service in accordance with their qualifications and fitness, with the following procedural safeguards and clarifications:

  • Such absorption should be effected within six months from the date of the judgment.
  • If age-limit relaxation is necessary for appointments, it should be granted before appointment.
  • If retrenched employees are appointed to pensionable posts, the service rendered in the Anandpur Sahib Hydel Project shall be taken into account for pension and other retirement benefits.
  • Any appointment made pursuant to this order shall be treated as a new appointment for purposes of seniority among employees.
  • The relief ordered is without prejudice to any retrenchment compensation or other rights that employees may have under the provisions of the Industrial Disputes Act, 1947; the Act's machinery remains available to the petitioners.

Holding and Implications

Core Ruling: Subject to the reservations noted in the judgment, the appeals filed by the State are allowed and the appeals and writ petitions filed by the workers are dismissed.

Direct consequences and practical implications:

  • The Court held that the Minutes of the meeting dated 17-12-1974 and the Chief Engineer's communications are administrative instructions without statutory force and therefore are not enforceable by writ of mandamus under Article 226.
  • As a result, the petitioners have no legally enforceable right to regularisation based solely on those Minutes and communications; their writ petitions for regularisation were dismissed.
  • As an equitable measure, the Court ordered that retrenched employees be considered for absorption into other projects or government service according to qualifications and fitness within six months, allowed age relaxation where necessary, and permitted counting of Anandpur service for pension if appointed to pensionable posts; appointments under this direction are to be treated as new for seniority.
  • The relief granted is without prejudice to claims under the Industrial Disputes Act, 1947; employees may pursue remedies under that statutory machinery.

The opinion does not purport to lay down a novel rule of law beyond the application of established authorities; the Court applied existing precedent (including G. J. Fernandez and G. Govinda Rajula) to the facts at hand.

    State Of Punjab And Others v. Mehanga Ram And Others

    1. This judgment will dispose of Letters Patent Appeals No. 510, 633, 740 to 755, 778, 779 and 780 of 1986 and Civil Writ Petitions No. 2389, 4122, 4941 and 5034 of 1986, and 208, 490, 2505 and 3892 of 1987 and 1787 of 1988. Letters Patent Appeals No. 510 and 740 to ,755 of 1986 have been preferred by the State against the judgment of the learned Single Judge dated May 30,1986 whereby a writ of mandamus was issued to implement the policy decision adopted in the meeting dated December 17 1974 appended as Annexure P. 2 to the Civil Writ Petition No. 718 of 1986. Letters Patent Appeals No. 633, 778, 779 and 780 of 1986 have been preferred by the workers against the same judgment of the learned Single Judge whereby their writ petitions were dismissed. The other civil writ petitions have been filed by the workers for issuance of writ of mandamus to implement the policy decision adopted in the meeting dated December 17, 1974. The pleadings in all these appeals and the petitions are substantially on the same pattern. We have treated Civil Writ Petition No. 718 of 1986 as the main writ petition. Therefore, for the sake of convenience, we will refer to the pleadings and the Annexures in Civil Writ Petition No. 718 of 1986 and whatever we say in regard to this writ petition (L.P.A. No. 740 of 1986) would apply to all other appeals and writ petitions.

    2. The writ petitioners were working in various capacities in the Anandpur Sahib Hydel Project. They were appointed as work charged employees. A policy decision was taken which was incorporated in the Minutes of the Meeting held on December 17, 1974 (Annexure P. 2). It was decided in the meeting that the work-charged employees in all three branches of the Public Works Department who have completed five years' service or more and are working against the Government Posts of regular nature of maintenance works should be made regular. The decision was to take effect with effect from April 1, 1975 Communications were addressed by the Chief Engineer, Irrigation Works, Punjab to all the Superintending Engineers conveying to regularise the services of work charged employees who completed five years' service as work-charged employee on government post of regular nature. On February 9, 1984, a meeting was held between the chairman of Punjab State Electricity Board, Chief Engineer and the representatives of the Workers in which it is stated that the Chairman of the Punjab State Electricity Board gave an assurance that no worker is to be retrenched from Anandpur Sahib Hydel Project and on the completion of this Project, the surplus workers will be transferred to Mukerian Hydel Project On the completion of Anandpur Sahib Hydel Project. Nargal, various categories of staff became sub plus and their services were terminated giving rise to this writ petition. The writ petitioners maintained that in view of the policy decision taken in the meeting presided over by the Finance Minister, Punjab, held on December 17, 1974 and subsequent communications addressed by the Chief Engineer to the Superintending Engineers, their services ought to be regularised and the termination is without any legal sanction. The State in its reply inter alia pleaded that no termination notice has been issued to any workman working on the Anandpur Sahib Hydel Project with effect from 27-2-1986 including the writ petitioners. The writ petitioners were engaged on Aanandpur Sahib Hydel Project on purely temporary basis as work-charged employees. The Project was completed in January, 1985 and services of surplus work charged employees were no longer required. Their services were terminable as per Rule 20(1) read with Rule 3(a) of the certified standing orders for work-charged staff on Anandpur Sahib Hydel Project on the completion of the Project. The services of the writ petitioners are regulated by the certified standing orders for work-charged staff. The policy decision adopted in the meeting held on December 17,1974 is not applicable to the writ petitioners since they were not engaged as work-charged employees against the government posts of regular nature of maintenance Works in any of the three branches of the Public Works Department The other communications addressed by the Chief Engineer to the Superintending Engineers are also not applicable to the writ petitioners. The learned Single Judge issued the following directions :-

    "(1) to abide by the Government policy decision adopted in the meeting dated 17-12 -1974 presided over by the Finance Minister, Punjab Annexure P-2, and treat the service of the petitioners as on regular basis with effect from 1st of April of the particular year following the date on which each of the petitioners completed continuous service of five years on the post that he is holding;

    (ii) to work out seniority list of all the employees holding posts on work charge basis who are made regular as directed above for the entire department of Public Works, Irrigation, Branch and to absorb them on maintenance jobs on completion of the project concerned on the basis of the seniority.

    (iii) after such absorption, to transfer employees . who are found surplus to other projects which are in progress against existing vacancies or against posts manned by those who are junior to them i e. whose continuous length of service is less;

    (iv) to treat the service of those employees who are transferred to other projects as continous to make it more explict, the service rendered by them on the Anandpur Hydel Project shall count towards pay, seniority and other admissible benefit as regular employees

    (v) Only those employees who stand junior most in the overall seniority of the Punjab P W. D. Irrigation Branch, shall be retrenched from No. 1804 of 1986 and the petitioners in C. W. P. Nos 896, 1354, 1489, 1781 and 1888 of 1985 have admittedly less than five years service to their credit. As such no relief can be granted to them."

    2. The learned Single Judge understood the Minutes of the Meeting as policy decision enforceable under Article 226 of the Constitution of India by issuance of a writ of mandamus. The learned Single Judge was of the opinion that the executive instructions of the Government, in the absence of statutory rules could be enforced by way of writ petition and he relied upon two decisions namely Dr. Amarjit Singh Ahluwalia v. The State of Punjab and Ors., 1975 S. L. J. 220. and Union of India v. K. P., Joseph, and Ors. , 1973 (1) S. L. R. 910. In Dr. Amarjit Singh Ahluwalia's case (supra); the Supreme Court has only held that in the absence of statutory rules, regulating recruitment or conditions of service, the State Government can in the executive power issue administrative instructions providing for recruitment and laying down conditions of service; In K. P. Joseph's case (supra), the Government of India, Ministry of Defence, issued a general order providing for certain benefits to ex-military personnel on re-employment on basis of their length of actual military service. The Apex Court observed that the benefits accruing to ex military personnel on re-employment relates to conditions of service of the employees and could be enforced.

    3. It is difficult to appreciate how the ratio of these two judgments is applicable to the present case. Article 162 of the Constitution provides that executive power of a State "shall extend to the matters with respect to which the legislature of the State has the power to make laws". This article merely indicates the scope of executive power of the State; it does not confer any Rule making power on the State Government. The State can give administrative instructions to its servants how to act in certain circumstances; but that will not make such instructions statutory rules which are justiciable in certain circumstances. In order that such executive instructions have the force of statutory rules it must be shown that they have been issued either under this authority conferred on the State Government by some statute or under some provision of the Constitution providing therefor This matter came up for consideration before the Apex Court in a judgment G. J. Fernandez v. State of Mysore, A, I. R. (1967) S. C. 1753. under the following circumstances "'Tenders were called for construction of right bank masonry dam called 'Hidkal Dam' by the Public Works Department, Irrigation Projects, of the State of Mysore G. J. Fernandez also submitted his tender to the Chief Engineer of the Department. Respondent No. 3 before the Apex Court was another tenderer. The contract was granted by the Major Irrigation Projects Control Board to respondent No. 3. The appellant G. J. Fernandez challenged the grant of contract to respondent No. 3 on two grounds, namely (1) that the rules in the Mysore Public Works Department Cede were no followed; and (2) that there was unequal treatment between the various tenderers which was in Violation of Article 14 of the Constitution."

    4. The High Court negatived both these contentions, with regard to the submission with respect to provision of the Code having rot been followed in the matter of tenders, the question arose whether the Code consisted of statutory rules or not. The High Court of Mysore had held that the so called rules in the Code are not framed either under any statutory enactment or under any provision of the Constitution They are merely in the nature of administrative instructions for the guidance of the department The Apex Court proceeded to consider the question whether the instructions in, the Code have any statutory force and held thus:-

    "It is not in dispute that there is no statute which confers any authority on the State Government to issue rules in matters with which the Code is concerned; nor has any provision of the Constitution been pointed out to us under which these instructions can be issued as statutory rules except Article 162. But as we have already indicated, Article 162 does not confer any authority on the State Government to issue statutory rules. It only provides for the extent and scope of the executive power of the State Government, and that coincides with the legislative power of the State Legislature Thus under Article 162, the State Government can take executive action in all matters in which the Legislature of the State can pass laws. But Article 162 by itself does not confer any rule making power on the State Government in that behalf. We are therefore of opinion that instructions contained in the Code are mere administrative instructions and are not statutory rules. Therefore even if there has been any breach of such executive instructions that does not confer any right on the appellant to apply to the court for quashing orders in breach of such instructions"

    5. Observations made in the same context in The Tamil Nadu E. D. M. & G. S. S. A. etc. v. State of Tamil Nadu and Ors., 1980 Unreported Judgments (S.C ) 285. by V. R. Krishna Iyer J. is useful in this connection :-

    "In Service jurisprudence intergration is a complicated administrative problem where, in doing broad justice to many, some bruise to a few cannot be ruled out. Some play in the joints, even some wobbling, must be left to government without fussy forensic monitoring, since the administration has been entrusted by the Constitution to the Executive, not to the Court Ali life, including administrative life, involves experiment, trial and error, but within the leading strings of fundamental rights, and. absent unconstitutional 'excesses', judicial correction is not right. Under Article 32, this court is the constitutional sentinal, not the national ombudsman. We need an ombudsman but the Court cannot make do."

    6. We do not find that the Minutes of the meeting held on December 17. 1974 and the communications addressed by the Chief Engineer to the Superintending Engineer are in the nature of executive instructions falling within the ambit of Article 162 of the Constitution and thus no writ of mandamus can be issued to the State No right accrues to the writ petitioners to enforce it. Since the entire case of writ petitioners hinges upon the alleged policy decision and on the communications addressed by Chief Engineer to the Superinteding Engineers and this having been held by us to be not justiciable, the writ petitioners' case must fail. They have no right much less legal right for the enforcement of which they can maintain these writ petitions. The other arguments addressed by the learned counsel that the employees of the Anandpur Hydel Project were not similarly treated in other Projects is also of no consequence in view of our answer to the principal question. Mr Nijjar appearing on behalf of the Workers, relied upon a Bench Decision rendered in Piara Singh and anther v. State of Haryana and Ors., 1988 (4) S.L.R. 739. to substantiate his plea that a work-charged employee who has put in more than two years' service is entitled to have his services regularised. The learned counsel did not appreciate that the judgment specifically excludes the applicability to Industrial Workers. However, having regard to the facts and circumstances of the present case, we think that the equitable course is the one that was followed by the Supreme Court in the decision in G. Govinda Rajula v. The Andhra Pradesh State Construction Corporation Ltd and Anr.., A. I. R. 1987 S. C. 1801. Following that decision, we direct the respondents to take the retrenched employees in other Projects or in service of the government according to the qualifications of each of the employees and their fitness. Such absorption of the retrenched employees shall be done within a period of six months from this day. If any relaxation of the age limit is necessary, that shall also have to be done before appointments. The retrenched employees also will be entitled to take into account the service rendered in the Anandpur Sahib Hydel Project in case they are appointed in pensionable jobs for the purpose of pension and other retirement benefits. ' However, it is made clear that any appointment made under this order shall be treated as new appointment for the purpose of seniority among the employees. This relief given is also without prejudice to the retrenchment and any other compensation, they may be entitled to under the provisions of the Industrial Disputes Act, 1947. The Act has set up suitable machinery for the adjudication of disputes which exist or are apprehended between an employer and his workmen. The machanism of the Act is geared to conferment of regulated benefits to workman and resolution, according to a sympathetic rule of law, of the conflicts actual or potential between management and workman. One of the objects of the Act is to regulate conditions of employment. The writ petitioners can approach the appropriate authority for redress of their grievance, if any, before the authorities under the Act. With these observations, subject to reservations the appeals filed by the State are allowed and the appeals and the writ petitions filed by the Workers are dismissed.

    Use AI to get other relevant cases.

    Comments

    State Of Punjab And Others v. Mehanga Ram And Others