Factual and Procedural Background

This opinion arises from an action instituted by a contractor (Seth Prem Chand Satram Das) seeking enforcement of an award made by an arbitrator under an arbitration clause in a supply contract with the Central Public Works Department (CPWD) for supply of bricks to the Sindri Fertiliser project.

The CPWD invited tenders (23 September 1945). The plaintiff's tender was accepted (letter dated 1 November 1945) and a contract was executed for supply of bricks with a delivery schedule. The plaintiff asserts he manufactured bricks and kept them ready pursuant to the schedule but that the CPWD failed to remove them, causing losses (including land acquisition, increased wages, rain-damage to bricks, suspension of his brick-making business and claimed interest).

The plaintiff submitted claims to the department; the Chief Engineer refused payment and the matter was referred to arbitration under the contract. Mr. Dixon, Superintending Engineer, acted as arbitrator and, after hearing, issued an award dated 1 May 1949 in the first suit (and another award dated 8 May 1949 in the related suit).

The plaintiff sued to enforce the award. The trial court (learned Subordinate Judge) set aside part of the award (claim no. 6 in the first suit) and otherwise entered a decree in terms of the award. The Union (defendant/appellant) appealed. The Court of Appeal heard two related miscellaneous appeals (Nos. 252 and 253 of 1950) arising from two suits (Nos. 27 and 34 of 1949) and decided them together, modifying the decrees by excluding certain claims as set out below.

Legal Issues Presented

  1. Whether the arbitrator's award is vitiated by an error of law apparent on the face of the award in respect of specified claims (in the first suit: claims nos. 3, 4, 8, 13 and 17).
  2. Whether the arbitrator had jurisdiction to decide claims that were not originally included in the contractor's bill submitted to the Chief Engineer (notably the claim for interest brought during arbitration).
  3. Whether awards based on moral or implied obligations (as distinct from contractual obligations) are within the arbitrator's jurisdiction and thus sustainable.

Arguments of the Parties

Appellant's (Union of India) Arguments

  • The award in respect of claims nos. 3, 4, 8, 13 and 17 is illegal and ought to be set aside because an error in law is apparent on the face of the award (submission of Mr. Lal Narain Sinha).
  • The appellant conceded that claims which do not exhibit an apparent illegality should stand; the appellant did not seek remittal to the arbitrator if an error was found because each claim is separable and self-contained.
  • Specifically, the Union contested the arbitrator's legal basis for awarding compensation based on a moral or implied obligation (claim no. 4) and contested arbitrator jurisdiction over a claim for interest that was not originally submitted to the department (claim no. 17).

Plaintiff's (Contractor's) Contentions — as presented in the opinion

  • The contractor performed his contractual obligations and made ready the bricks for delivery according to the contract schedule; failure by the department to remove bricks caused losses including the need to acquire land, additional wages, destruction of bricks by rain, and suspension of his brick-making business.
  • The contractor submitted claims under multiple heads (eighteen claims before the arbitrator) totaling Rs. 2,01,371 including interest; he sought enforcement of the award made by the arbitrator in his favour.
  • Before the arbitrator the contractor presented written claims and argument on the several heads; the arbitrator heard the parties and made awards on individual claims (some wholly or partially allowed).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Saleh Mahomed v. Nathoomal (also cited as Saleh Mahomed Timer Dossal v. Nathoomal Kessamal) Authority for the proposition that an arbitrator's decision can be challenged for "judicial misconduct" when a mistake in law is visible on the face of the award. The court cited it as support for the principle that an error of law apparent on the face of an award is a ground for interference with an arbitrator's award.
Hodgkinson v. Fernie Sets out that arbitrators are sole and final judges of law and fact except where award results from corruption/fraud or where a question of law necessarily arises on the face of the award or accompanying papers. The court relied on Hodgkinson to explain the limited circumstances in which courts may interfere with an award — specifically where an error of law appears on the face of the award.
Champsey Bhara & Co. v. Jivraj Balloo Spinning and Weaving Co., Ltd. Defines "error in law on the face of the award" as a legal proposition found in the award or an incorporated document (e.g., an appended note) which is the basis of the award and is erroneous. Used to clarify that when an arbitrator states a legal proposition as the basis for the award, a court can examine and set aside the award if that legal proposition is erroneous on its face.
F.R. Absalom, Ltd. v. Great Western (London) Garden Village Society, Ltd. Distinguishes ordinary references (where courts can interfere if an error of law appears on the face of the award) from references of specific questions of law (where courts will not interfere even if an error of law is manifest). The court invoked the distinctions articulated by Lord Russell and Lord Wright in this case to frame the boundary between reviewable and non-reviewable arbitrator determinations.
British Westinghouse Electric & Mfg. Co. v. Underground Electric Ry. Co. of London, Ltd. Listed among authorities on the limits of judicial interference with arbitration awards (contextual authority supporting the summary of law). Appears in the court's summary list of leading authorities that define when awards can be attacked for errors apparent on the face of them.
Government of Kelantan v. Duff Development Co., Ltd. Listed as one of the authorities relevant to the principle that errors apparent on the face of an award may attract court interference (contextual authority). Included by the court in the list of cases illustrating the established principles about the finality of arbitrator decisions and the exceptions to that finality.

Court's Reasoning and Analysis

General legal framework applied: The court reviewed established authorities on arbitration law (including the Indian Arbitration Act, 1940 and earlier case law) to state the governing principle: an arbitrator is generally the final judge of law and fact, but courts may set aside an award where there is corruption/fraud or an error of law apparent on the face of the award — particularly where the arbitrator has enunciated a legal proposition or given reasons that reveal the error. The court also noted the distinction between a general reference to arbitration (open to challenge for errors of law on the face of the award) and a specific question of law submitted as such (not open to such review).

The court then examined the arbitration clause in extenso (clause 14) to determine the scope of matters referred to the arbitrator and whether the arbitrator exceeded jurisdiction or made errors of law apparent on the face of the award in relation to the disputed claims.

Claim-by-claim analysis (first suit):

  • Claim no. 3 (purchase of 10 bighas of land): The arbitrator awarded Rs. 2,000 less Rs. 715 (i.e., Rs.1,285). The court observed the arbitrator held Rs. 200 per bigha was reasonable but gave no further reasons. The court found no error apparent on the face of the award and upheld it, noting the appellant was ordinarily expected to remove bricks and the contractor was compelled to acquire land for stacking because of non-removal.
  • Claim no. 4 (additional wages due to non-availability of ration and cloth): The arbitrator, after finding the department was not contractually bound, nonetheless held there was a "moral and implied obligation" on the CPWD to provide facilities for rations at controlled rates and awarded compensation (Rs. 30,000). The court concluded the arbitrator misdirected himself in law by imposing a moral/implied obligation (outside contractual liability) and therefore the illegality was apparent on the face of the award; the award as to this head was set aside.
  • Claim no. 8 (loss of 47 lacs of kuchcha bricks destroyed by rain): The arbitrator found entitlement to compensation for 36 lacs of bricks and awarded Rs. 30,600. The court found no illegality apparent on the face of the award and maintained it.
  • Claim no. 13 (loss due to suspension of brick manufacturing business): The arbitrator awarded Rs. 15,000, finding the contractor's approaches were jammed with government bricks and he could not supply customers. The court noted the arbitrator fixed liability without detailed reasons but found no error of law apparent on the face of the award and therefore upheld it.
  • Claim no. 17 (interest at 6% p.a. for two years): The court observed that the contractor did not claim this interest in his original bill submitted to the Chief Engineer and raised it first during arbitration. The Executive Engineer appearing for the Union did not appear to have submitted to arbitrator jurisdiction on this question. The court concluded the claim for interest was not one of the matters referred to arbitration and that the arbitrator therefore lacked jurisdiction to entertain it; the award as to interest was set aside.

Related second suit (Misc. Appeal no. 253 of 1950): The court described similar facts and arbitration procedure in a separate but factually similar suit (Seth Thawardas Pherumal). There the arbitrator had awarded a substantial sum (Rs. 2,35,346-6-0) against a claim of a higher amount. The appellant contested several claims (nos. 2, 5, 8 and 17). The opinion records the appeals were heard together and that the ultimate disposition modified decrees in both appeals by excluding certain claims (see result below).

Holding and Implications

Core Ruling: Appeals allowed in part; specific heads of the arbitrator's awards set aside where the award showed an error of law apparent on its face or where the arbitrator lacked jurisdiction.

Direct consequences for the parties (as stated in the opinion):

  • In the first appeal (Misc. Appeal no. 252) the decree of the lower court was modified by excluding claims nos. 4 and 17 (these heads of the award were set aside by the appellate court).
  • In the second appeal (Misc. Appeal no. 253) the decree of the lower court was modified by excluding claims nos. 5, 8 and 17 (these heads were set aside in that appeal).
  • As a result of the modifications, the appeals were allowed in part and the parties were directed to bear their own costs in each case.

Broader implications: The opinion applies established principles concerning the limited scope of judicial interference with arbitration awards — specifically reaffirming that courts may set aside awards where an error of law is apparent on the face of the award or where the arbitrator lacks jurisdiction to decide matters not submitted to him. The court did not purport to lay down a new rule of law; it applied existing authorities to the facts before it.

Disposition recorded in the text: "In the result, the appeals are allowed in part... In the circumstances, the parties will bear their own costs in each case." The opinion concludes with "Appeals partly allowed." (Chatterji, J. concurs.)

    Union Of India v. Seth P.S Das

    Lakshmikanta Jha, C.J:— This is an appeal by the defendant (the Union of India) in a suit instituted by the plaintiff-respondent for the enforcement of an award given by an arbitrator appointed under an arbitration clause in an agreement between the parties which provided for settlement of all disputes arising between them.

    The Central Public Works Department invited tenders for the manufacture and supply of four crores of bricks on the 23rd September, 1945, for what is known as the Sindri Fertiliser project. Seth Prem Chand Satram Das, the plaintiff in the present suit, was one of the persons who offered to manufacture and supply bricks at certain rates. His tender was accepted by the Superintending Engineer, Bihar Central Circle, by his letter dated the 1st November, 1945, and he was given a contract for the supply of 1½ crores of bricks at his tender-rates. A deed of agreement was executed and signed by the plaintiff and the Additional Chief Engineer, New Delhi, on behalf of the appellant and a delivery schedule was appended showing the number of bricks to be supplied by the plaintiff month by month from January to May, 1946.

    The case of the plaintiff is that he performed his part of the contract and kept bricks in readiness for supply according to the schedule appended to the contract. But for certain reasons the bricks were not removed from the kiln sites, though they were manufactured and made ready for delivery, as required by the delivery schedule, and this caused, according to the plaintiff, serious dislocation in the manufacture of bricks. His case is that he had to acquire 10 bighas of land at the rate of Rs. 200 per bigha which included the cost of preparing and levelling the land for the stacking of the bricks of which delivery could not be taken. It is not disputed that the plaintiff was paid, at the contract rate, the full price of the bricks which he was ordered to manufacture, but his case is that he suffered loss on various counts by reason of the defendant's failure to remove the bricks according to the agreement. He therefore submitted his claims under various heads and submitted a bill to the Chief Engineer for the reimbursement of the losses suffered by him. The Chief Engineer refused to make any payment on account of any loss. Thereupon the plaintiff applied for arbitration according to the arbitration clause of the agreement. It appears from the Additional Chief Engineer's letter that he appointed Mr. Dixon, the Superintending Engineer of the Circle, as the arbitrator and the plaintiff was asked to submit his case to the arbitrator on the date to be fixed by him. The plaintiff accordingly submitted his claims in writing to Mr. Dixon, for his decision, and preferred his claims under eighteen heads. A sum of Rs. 1,65,893 was claimed by the plaintiff before the arbitrator under different heads and a further sum was also claimed by way of interest at 6 per cent, per annum for two years; in all Rs. 2,01,371 was claimed by the plaintiff before the arbitrator, including interest.

    No objection was filed in writing on behalf of the appellant, but the Executive Engineer appearing before the arbitrator on behalf of the Central Public Works Department objected to the claims orally. Mr. Dixon, after hearing the parties, awarded a sum of Rs. 1,20,560-9-0 as against the plaintiff's claim of Rs. 2,01,371, by his order dated the 1st May 1949, and directed the amount to be paid on or before the 1st June 1949, failing which interest at 6 per cent per annum from the 1st June 1949, was to be 3 paid by the appellant.

    The plaintiff filed the present suit for enforcement of the award and prayed that the award be accepted and a decree passed in terms of the award. The suit was contested and the objection of the Union was only in respect of claims nos. 3, 4, 6, 8, 13 and 17. The award regarding claim no. 6 relating to sale tax was set aside, but the rest of the award was affirmed. With this modification the learned Subordinate Judge directed a decree to be made in terms of the award.

    The dispute before us is now confined only to claims nos. 3, 4, 8, 13 and 17, which are as follows:

    “Claim no. 3.—Payment for the purchase of an additional ten bighas of land for stacking bricks—Rs. 1,285 (i.e, Rs. 2,000 less Rs. 715 already paid).

    Claim no. 4.—Payment on account of additional wages paid to labourers because of non-availability of ration and cloth—Rs. 87,215-10-0.

    Claim no. 8.—Payment for the loss of 47 lacs of kuchcha bricks which were destroyed by rain—Rs. 40,537.

    Claim no. 13.—Payment for loss sustained as the result of brick fields not being freed for lease to intending lessees and suspension of brick manufacturing business—Rs. 25,000.

    Claim no. 17.—Payment of interest at 6 per cent per annum for 2 years on account of delay in settling dues.”

    The contention of Mr. Lal Narain Sinha, for the Union, is that the award in respect of all these five items is illegal and ought to be set aside because the error in law is apparent upon the face of the award. He, however, concedes that the plaintiff is entitled to a decree according to the award for the claims in respect of which there is no illegality in the award apparent on the face of it. He does not want us to remit the award to the arbitrator for reconsideration in case we are satisfied that there is an error apparent on the face of the award in respect of any of the claims. Nor is it necessary to do so because the award in respect of each claim is self-contained and separable. Even if the award in respect of any claim be held to be bad, the rest of it can be maintained without any prejudice to either party. The point for our consideration, therefore, is whether the award is bad in law in respect of any of the five claims mentioned above.

    Domestic tribunal was not unknown to India Statutory recognition was given to it during the British rule and now the whole law on the subject has been incorporated in the Indian Arbitration Act, 1940. With the growth of trade in India it has become almost a regular practice with the businessmen to insert an arbitration clause in almost every agreement providing for settlement of all disputes by an arbitrator. Whenever a dispute is submitted to an arbitrator, his decision becomes final. The arbitrator is constituted the sole and final judge of all questions, both of law and of fact. The decision of an arbitrator, though sacrosanct, can be challenged for his “judicial misconduct”, which does not necessarily imply moral turpitude, but may consist “in making a mistake in law, and letting it be visible on the face of his award”: Saleh Mahomed v. Nathoomal(1). The test for the determination of judicial misconduct of the arbitrator has been laid down in a number of cases.

    In Hodgkinson v. Fernie(2), which is a leading case on the point, Williams, J. stated the grounds on which an award can be successfully assailed. In that case the allegation of the plaintiff was that his ship had been run down owing to the negligent navigation of the defendant's ship. At the trial a verdict was entered for the plaintiff for damages. The amount of damages was referred to be assessed by an arbitrator. The arbitrator awarded a lump sum. The defendant sought to show by affidavit that the arbitrator had included an item which ought to have been rejected. It was held that the award could not be interfered with because there was no error on the face of the award. Williams, J. stated the law thus:—

    “The law has for many years been settled, and remains so at this day, that, where a cause or matters in difference are referred to an arbitrator, whether a lawyer or a layman, he is constituted the sole and final judge of all questions both of law and fact…… The only exceptions to that rule, are, cases where the award is the result of corruption or fraud, and one other, which though it is to be regretted is now, I think, firmly established, viz., where the question of law necessarily arises on the face of the award, or upon some paper accompanying and forming part of the award. Though the propriety of this latter may very well be doubted, I think it may be considered as established.”

    In Champsey Bhara and Company v. Jivraj Balloo Spinning and Weaving Company, Limited which was a case under the Indian Arbitration Act, 1899, Lord Dunedin, on a review of the decisions of the English courts, stated the law thus:—

    “An error in law on the face of the award means, in their Lordships' view, that you can find in the award or a document actually incorporated thereto, as for instance a note appended by the arbitrator stating the reasons for his judgment, some legal proposition which is the basis of the award and which you can then say is erroneous.”

    At another place he stated:—

    “The question of whether an arbitrator acts within his jurisdiction is, of course, for the Court to decide, but whether the arbitrator acts within his jurisdiction or not depends solely upon the clause of reference. It is, therefore, for the Court to decide in this case whether the dispute which has arisen is a dispute covered by rule 13 of the Association. It clearly is so, because it is undoubtedly a dispute arising out of or in relation to a contract made subject to the rules and regulations of the Cotton Trade Association. Now that clause refers to the arbitrator the whole question whether it depends on law or on fact, with the exception only of dispute as to quality.”

    The principle enunciated in this case was followed and reaffirmed by the Privy Council in Saleh Mahomed Timer Dossal v. Nathoomal Kessamal. It is not profitable to examine other cases relevant to the point because the case-law bearing on the question was examined by the House of Lords in F.R Absalom, Ltd. v. Great Western (London) Garden Village Society, Limited. The learned Law Lords on a review of the case-law bearing on the point stated the law in clear and unambiguous terms. Lord Russell of Killowen observed at page 607:—

    “It is, I think, essential to keep the case where disputes are referred to an arbitrator in the decision of which a question of law becomes material distinct from the case in which a specific question of law has been referred to him for decision. I am not sure that the Court of Appeal has done so. The authorities make a clear distinction between these two cases, and as they appear to me they decide that in the former case the Court can interfere if and when any error of law appears on the face of the award, but that in the latter case no such interference is possible upon the ground, that it so appears that the decision upon the question of law is an erroneous one.

    In the same case Lord Wright enunciated the law thus:—

    “The rule in truth applies to the ordinary case where in the words of Lord Dunedin in (1923 Appeal Cases 488 at page 489), the submission refers ‘to the arbitrator the whole question whether it depends on law or on fact’. To be contrasted with such cases there is the special type of case where a different rule is in force, so that the Court will not interfere even though it is manifest on the face of the award that the arbitrator has gone wrong in law. This is so when what is referred to the arbitrator is not the whole question, whether involving both fact or law, but only some specific question of law in express terms as the separate question submitted; that is to say, where a point of law is submitted as such, that is, as a point of law, which is all that the arbitrator is required to decide, not fact being, quoad that submission, in dispute.”

    The law as to how far finality attaches to the decision of an arbitrator may be summarised thus. The award if baldly stated—without giving any reason for it—cannot be assailed even if it be against fact or repugnant to law. In other words, the award is not open to judicial review. But if a reference to arbitration be made generally and not specifically, and the arbitrator enunciates a proposition of law and states his own view of the law as a ground of his award, such an award is open to attack in a court of law and is liable to be set aside if there be an error of law apparent on the face of it. So also, if the arbitrator construes a document and gives his own construction or interpretation of the document as a reason for the award, it is open to the court to examine the reason and set aside the award if the error in the construction is apparent on the face of the award. If, however, a reference is made specifically and a dispute relating either to fact or to law is submitted to the arbitrator for his decision, his award cannot be challenged even if there be an error of fact or law, or both, apparent on the face of the award: see Hodgkinson v. Fernie, British Westinghouse Electric and Manufacturing Company, Limited v. Underground Electric Railway Company of London, Limited, Government of Kelantan v. Duff Development Company, Limited(3), Champsey Bhara and Company v. Jivraj Bdlloo Spinning and Weaving Company, Limited, Saleh Mahomed Umer Dossal v. Nathoomal Kessamal, and F.R Absalom, Ltd. v. Great Western (London) Garden Village Society, Limited.

    Bearing in mind the principles already enunciated, we have to examine the legality of the award with reference to the arbitration clause and other relevant clauses of the agreement and see for ourselves whether there is any error in law apparent on the face of the award. In order to appreciate the argument at the bar on the question raised before us it is necessary to quote here in extenso the arbitration clause of the agreement which runs as follows:—

    “14. Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specification and instructions hereinbefore mentioned and as to quality of materials or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, specification, instructions, orders, or these conditions, or otherwise concerning the supplies whether arising dining the progress of delivery or after the completion or abandonment thereof shall be referred to the arbitration of the Superintending Engineer of the Circle for the time being in the manner provided by law relating to arbitration for the time being in force who after such investigation as he may think proper shall deliver his award which shall be final, conclusive and binding on all parties to this contract.”

    Claim no. 3.

    The dispute in respect of claim no. 3 involves a question arising out of or relating to the contract. It was, therefore, within the competence of the arbitrator to take cognizance of the point in question. He considered the argument on either side and recorded his finding in these terms:—

    “I hold that Rs. 200 per bigha was a reasonable price, the claim of the contractor for Rs. 2,000 less Rs. 715 (already paid) is therefore awarded.”

    It does not appear that there is any error apparent on the face of the award. The arbitrator has held without assigning any reason in support of his award that the contractor is entitled to Rs. 2,000 less Rs. 715 Therefore, the award cannot be interfered with.

    The arbitrator, while dealing with the argument on behalf of the contractor on this point, referred to the argument advanced on behalf of the parties with respect to claim no. 1 in which reference has been made to the agreement. It does not appear that he has referred to any term of the agreement as a matter of construction to fix the liability of the appellant. He seems to have referred to the agreement to understand the nature and origin of the dispute, and in so doing he has not committed any error of law. But even assuming that the arbitrator construed the agreement and has based his award on the construction of it, it does not appear that he committed any error. The appellant was in ordinary course of business expected to remove the bricks according to the schedule. The contractor was compelled to acquire the land for the stacking of the bricks on account of the non-removal of the bricks by the appellant. Therefore, the award on this point is unassailable. The order of the learned Subordinate. Judge is, therefore, confirmed and the award upheld.

    Claim no. 4.

    On account of certain restrictions local labour was not available to the contractor. He had to import coolies from the Central Provinces and the United Provinces for the manufacture of bricks and had to incur extra cost for procuring supply of food for the coolies. It appears that there was certain correspondence between the contractor and the Central Public Works Department in this connection, and the arbitrator seems to be of the view that the responsibility for making available controlled rations for the coolies was accepted by the Central Public Works Department. On account of this and other reasons the arbitrator decided that the appellant is liable to pay to the contractor Rs. 30,000 to make good the loss which the contractor suffered. There is nothing in the agreement to show that the appellant was under any contractual obligation to supply rations for the coolies at controlled rates. In fact the arbitrator himself found that the appellant was not bound to compensate the contractor on this account. His finding is:

    “From the point of view of contractual obligations therefore the department was not bound to compensate the contractor for any losses on this account.”

    In view of this finding the arbitrator misdirected himself in law in holding further

    “there was a moral and implied obligation on the part of the C.P.W.D to see that the contractor was given the necessary facilities to purchase rations at the controlled rates, and that this should have been arranged prior to arrival of the contractor's men”

    and awarding compensation. The arbitrator's, jurisdiction was to fix contractual and not moral liability. The illegality, therefore, is apparent on the face of the award and it is open to us to set aside the award under this head. It is accordingly set aside.

    Claim no. 8.

    The contractor preferred a claim for the price of 47 lacs of kuchcha bricks which had been destroyed by rain. His case was that the destruction of these kuchcha bricks resulted from the jamming of the kilns as a result of a breakdown in the brick removal arrangements which was the responsibility of the department. The Executive Engineer, on behalf of the appellant, maintained that the removal of bricks from kiln area was not a contractual obligation and that, in any case, only 45 lacs of bricks had been destroyed. The arbitrator on a consideration of the arguments on either side recorded his finding thus:

    “I hold that the contractor is entitled to compensation and award payment for 36 lacs of bricks at 8/8 per cent, i.e, Rs. 30,600.”

    There is no illegality on the face of the award. Therefore, it cannot be assailed. The award in respect of this claim is, therefore, good and is accordingly maintained.

    Claim no. 13.

    The contractor claimed damage for the loss in his business arising on account of the non-removal of the bricks by the appellant from the kiln area within a reasonable time. The arbitrator was satisfied on the merits of the case that the contractor was unable to manufacture any bricks and supply the same to his customers because the approaches to land surrounding his kilns were jammed with stacks of Government bricks, and his finding is

    “I hold that the contractor is entitled, to compensation on this matter and award payment to him of Rs. 15,000;”

    From the finding of the arbitrator it is clear that he has fixed the liability without giving any reason in support of his view. Therefore, there is no error of law apparent on the face of the award and it cannot be assailed.

    Claim no. 17.

    The arbitrator has allowed interest from the 31st March, 1947 to the 20th April 1949, i.e, for a period of 24 months and 20 days, at the rate of 6 per cent, per annum. The contractor did not include any claim for interest for this period in his bill originally submitted to the Chief Engineer, Central Public Works Department. The claim was preferred before the arbitrator for the first time during the progress of the arbitration proceeding, and the Executive Engineer, appearing on behalf of the Union, does not seem to have submitted to the jurisdiction of the arbitrator to decide this question. In the circumstances, it cannot be said that the claim for interest was one of the matters referred to arbitration. The arbitrator, therefore, in my opinion, had no jurisdiction to entertain this claim and the award in this respect must accordingly be set aside.

    Miscellaneous Appeal no. 253 of 1950.

    This appeal arises out of suit no. 34 of 1949. It was heard by us along with Miscellaneous Appeal no. 252 of 1950, which arises out of suit no. 27 of 1949. Both the suits were heard together by the trial court and are governed by the same judgment. We have also heard these two appeals together, but for the sake of convenience this appeal is dealt with separately.

    The plaintiff, Seth Thawardas Pherumal, entered into an agreement with the Additional Chief Engineer, New Delhi, under which the plaintiff agreed to supply 2½ crores of bricks to the Central Public Works Department for the Sindri Fertiliser project. The terms of this agreement are substantially the same as in the other suit. Owing to differences between the parties, the dispute was referred to Mr. Dixon. Superintending Engineer, for his decision under the terms of the arbitration clause of the agreement which are identically the same as those of the other already quoted. The contractor claimed Rs. 4,76,138-12-0 plus interest at 6 per cent for 16 months, that is, a total sum of Rs. 5,38,003 under different heads. But the arbitrator allowed Rs. 2,35,346-6-0 only under his award dated the 8th May, 1949. The contractor thereupon filed the present suit for the enforcement of the award. The appellant objected to the award on various grounds. The learned Subordinate Judge overruled the objections of the appellant and accepted, the award in its entirety and passed a decree in terms thereof. The award has been contested before us with respect to claims nos. 2, 5, 8, and 17 only, which are as follows:—

    Claim no. 2.—Payment for loss sustained, due to closing of kiln no. 3—Rs. 8,443-12-0.

    Claim no. 5.—Payment for 88 lacs of kuchcha bricks destroyed by rain—Rs. 75,900.

    Claim no. 8.—Payment on account of additional wages paid to labourers because of non-availability of rations and cloth—Rs. 51,495.

    Claim no. 17.—Payment of Interest on money blocked—Rs. 27,665.

    In the result, the appeals are allowed in part. In appeal no. 252 the decree of the lower court will be modified by excluding claims nos. 4 and 17, and in appeal no. 253 the decree of the lower court will be modified by excluding claims nos. 5, 8 and 17. In the circumstances, the parties will bear their own costs in each case.

    Chatterji, J.:— I agree.

    Appeals partly allowed.
    S.H