Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of the Kerala Revenue Recovery Act, 1968 or the Indian Revenue Recovery Act, 1890.
  • S. 68(1) of the Kerala Revenue Recovery Act 1968,
  • REVENUE RECOVERY ACT
  • S. 6(e) of the Transfer of Property Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of the Kerala Revenue Recovery Act, 1968 or the Indian Revenue Recovery Act, 1890.
  • S. 68(1) of the Kerala Revenue Recovery Act 1968,
  • REVENUE RECOVERY ACT
  • S. 6(e) of the Transfer of Property Act
Smart Summary

Structured Summary of the Provided Opinion

Factual and Procedural Background

This appeal was filed by the State of Kerala and the Director of Fisheries, Trivandrum, against a judgment of a learned Judge of the Kerala High Court which had allowed the respondent's writ petition and restrained the appellants and several officials from taking steps to recover Rs. 24,974.94 mentioned in Ext. P5 notice under the Kerala Revenue Recovery Act, 1968 or the Indian Revenue Recovery Act, 1890. The learned Judge's judgment is reported at 1977 KLT. 949.

The operative facts, according to the appellants as set out in the opinion, are:

  • An ice-plant storage and freezing plant at Azheekode was leased to the writ petitioner under Ext. P1 agreement dated 5-5-1970 for one year at a rent of Rs. 30,001.
  • Rs. 15,000 was paid on 7-5-1970; the balance was payable on or before 23-11-1970 but was actually paid on 30-1-1971.
  • The lessee was to pay electric charges; supply was disconnected on 30-3-1971 for non-payment.
  • By Ext. P2 (20-3-1971) the 3rd petitioner informed the Director of Fisheries that the petitioner could not continue the lease and proposed to hand over the plant before the end of the month; a complaint of harassment by local officials was made.
  • The Sub Inspector of Fisheries locked the factory and listed the articles (Ext. P3). On 14-5-1971 parties met at the plant and agreed the petitioner would pay estimated arrears of Rs. 13,194.64; this amount was paid on 28-5-1971 and supply was reconnected.
  • The plant was test-run on 4-6-1971; defects required rectification and were subsequently rectified; the factory was reauctioned for Rs. 60,000.
  • On 9-2-1974 the expenses and alleged loss due to the plant not being returned on 7-5-1971 were calculated at Rs. 29,974.94. After adjusting a security amount of Rs. 5,000 a notice for Rs. 24,974.94 was issued and revenue recovery proceedings were proposed.
  • By Ext. P4 reply dated 14-8-1973 the writ petitioner stated the full lease amount (Rs. 30,001) had been paid, that the plant was surrendered on 31-5-1971, that the Government had re-leased the plant, and that the security deposit had not been returned.
  • Ext. P5 notice of demand dated 9-2-1974 under the Revenue Recovery Act was issued by the Tahsildar, Mangalore, threatening recovery of Rs. 24,974.94; the writ petitioner then approached the High Court.

Legal Issues Presented

  1. Whether sums claimed by the lessor under Ext. P1 (including amounts described as expenses, loss of profit and other claims) are recoverable as arrears under the Revenue Recovery Act without prior adjudication of liability.
  2. Whether clauses in Ext. P1 (in particular clauses 16 and 17) confer on the lessor/Government a valid contractual machinery or power to determine the amount due and thereby permit recovery under the Revenue Recovery Act as if the amounts were arrears of land revenue.
  3. Whether some heads of claim (for example, claim for loss of profits or interest on belated remittance) amount to unliquidated damages requiring adjudication by a court or other adjudicatory authority before they can be converted into a debt recoverable by revenue recovery procedures.

Arguments of the Parties

Appellants' (Government) Arguments

  • Clause 16 of Ext. P1 makes all sums found due under the agreement recoverable from the security amount and the balance recoverable from the lessee and their properties under the Revenue Recovery Act, treating such sums as arrears of land revenue.
  • Section 68(1) of the Kerala Revenue Recovery Act, 1968 applies: monies due to Government under a written agreement are recoverable as arrears of public revenue or land revenue and may be recovered under the Act.
  • Clause 17 of Ext. P1 gives the lessor/government the right to decide amounts due in case of dispute, and that decision is final and conclusive and binding on the lessee—thus providing an internal adjudicatory mechanism.
  • Relying on a series of authorities (identified in the opinion), the Government contended the contract clauses supported their position that they could quantify and recover amounts due without seeking a prior court decree in every case.

Respondent's (Writ Petitioner) Arguments

  • The learned Judge (for the respondent) relied on the principle from Union of India v. Raman Iron Foundry that a claim for unliquidated damages does not give rise to a debt until liability is adjudicated and damages assessed by a court or adjudicatory authority; therefore coercive recovery under revenue law was inappropriate before adjudication.
  • Certain heads of claim raised by the Government (for example interest on belated remittance and loss of profits calculated on differing surrender dates) were not specifically provided for by Ext. P1 and thus gave rise to claims for damages to be assessed by ordinary modes, not by unilateral assessment by the Government.
  • The respondent disputed the date of surrender of the plant (respondent: 31-5-1971; appellants placed other dates) which impacted calculation of claimed loss; respondent also asserted that the full lease amount had been paid and that the security deposit had not been returned.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Raman Iron Foundry ((1974) 2 SCC 231 : AIR 1974 SC 1265) Principle that a claim for unliquidated damages does not give rise to a debt until liability is adjudicated and damages assessed by a court or other adjudicatory authority. The High Court had relied on this principle to hold that coercive revenue recovery could not be initiated without adjudication. The Division Bench on appeal considered this principle but concluded that the contract clauses (in particular clause 17) conferred an internal adjudicatory power on the Government which changed the applicability of that principle in this case.
Iron and Hardware (India) Co. v. Firm Shamlal and Bros. (AIR 1954 Bombay 423) Explains that damages are not a pecuniary liability until determined by a court — the injured party's right is to sue for damages which are the fiat of the court. Quoted by the Supreme Court in Raman Iron Foundry and used by the High Court to support the view that damages must be adjudicated. The appellate court referred to the same line of reasoning but distinguished the present contract clauses as conferring adjudicatory authority.
State of Kerala v. Joseph & Another (1975 KLT 551) Construction of a similar contractual clause which was held to confer a power analogous to the adjudicatory/quantifying power claimed by the Government. The Division Bench relied upon Joseph to hold that clause 17 in Ext. P1 is wide enough to authorize the lessor/Government to decide amounts due in dispute and that such a clause provides machinery for adjudication; the court treated Joseph as directly supportive of validating clause 17.
State of Rajasthan v. Raghubir Singh ((1979) 3 SCC 102 : AIR 1979 SC 852) Decision under the Interest Act concerning when a debt can be said to 'arise' or when a sum certain is said to have materialized. The Advocate General drew the Court's attention to this decision; the opinion records the reference but does not elaborate further factual application beyond noting it was cited on the point when a debt can be said to arise.
Achuthan v. State Bank of Travancore (1974 KLT 806 para 17) Authority cited by counsel for the respondent (no rule excerpted in the opinion). The opinion records that counsel for the respondent drew attention to this decision. The court's text does not elaborate its application beyond noting the reference.
General Manager, N.E.F. Ry. v. Chakraborty (1978 (1) SCWR 392) Authority considered by the learned Judge below (the opinion records its citation and the appellate court's view of its relevance). The appellate court observed that Chakraborty did not confer the right on the controller to quantify the liability of the subscriber and therefore did not support the learned Judge's conclusion in this case.
M.R. Breweries v. Union of India (AIR 1975 Delhi 248) Decision in which the relevant clause was construed by the Delhi High Court not to confer a power of adjudication. The appellate court noted that Breweries was referred to by the learned Judge but reiterated that in Breweries the clause did not confer adjudicatory power; by contrast, the appellate court held clause 17 in the present contract did confer such a power.

Court's Reasoning and Analysis

The Division Bench's analysis proceeded in the following steps, as reflected in the opinion:

  1. Identification of the contract clauses: The court examined Ext. P1, focusing on clause 16 (which authorizes recovery from the security amount and thereafter from the lessee's movable and immovable property "under the provisions of the Revenue Recovery Act ... as though they were arrears of land revenue") and clause 17 (which provides that in case of any dispute the lessor's decision will be "final and conclusive and shall be binding on the lessee").
  2. Acknowledgment of the learned Judge's reliance on authorities (notably Union of India v. Raman Iron Foundry and the reasoning that unliquidated damages do not constitute a debt until adjudicated): the learned Judge concluded that several heads of the Government's claim were unliquidated and therefore could not be recovered by coercive revenue proceedings without adjudication.
  3. Comparison with precedents and clause construction: The Division Bench reviewed the precedents cited by both sides. It accepted the general principle from Raman Iron Foundry and related authorities regarding unliquidated damages, but turned to the contractual wording, especially clause 17 and the prior Division Bench decision in State of Kerala v. Joseph, to determine whether the contract itself provided a valid and operative mechanism to quantify amounts due.
  4. Interpretation of clauses 16 and 17: The court concluded that clauses 16 and 17, read together, are "wide and comprehensive" and permit the lessor to recover "all sums found due to the lessor under or by virtue of this agreement" from the security and, thereafter, by invoking revenue recovery machinery. Clause 17, in particular, was held to confer on the Government the right to decide the amount due in disputes and to make that decision final and binding on the lessee.
  5. Distinguishing contrary cases: The court explained that some authorities referred to by the learned Judge (e.g., General Manager N.E.F. Ry. v. Chakraborty and M.R. Breweries v. Union of India) did not involve clauses that conferred a power of adjudication analogous to clause 17 and thus were distinguishable.
  6. Application to facts: The court noted that pursuant to the contract clauses the Government had issued a notice (26-6-1973 referred to in Ext. P4) setting out the amounts due. It recorded that no exception was taken to the Government's adjudication of liability except a counter-claim about the surrender date and the non-return of security deposit. On that basis, the court concluded the learned Judge erred in holding that the demand was unjustified, improper or without jurisdiction.

Holding and Implications

Holding: The Division Bench allowed the appeal, set aside the judgment of the learned Judge, and directed that O.P. No. 1859 of 1974-B be dismissed. The court made no order as to costs.

Implications:

  • The direct effect is that the Government's assessment and notice for Rs. 24,974.94 (after adjustment of security) is not struck down by the High Court order that had previously restrained recovery; the appellate court validated the contractual mechanism (clauses 16 and 17) by which the Government adjudicated amounts due and thereby permitted the recovery process contemplated by those clauses.
  • The court distinguished authorities that limit recovery of unliquidated damages pending adjudication, concluding that a contract clause conferring a final adjudicatory power on the lessor can change the legal effect and permit recovery as if amounts were arrears under the Revenue Recovery Act. The opinion treated the Division Bench's reliance on State of Kerala v. Joseph as confirming that such contractual clauses can be validly construed to confer adjudicatory power.
  • The opinion does not state that it establishes a new broader precedent beyond its application to the clauses before the court; it confines its ruling to the construction of the contract clauses and the facts as presented and reverses the High Court's order in favour of the Government.

This summary is strictly limited to the information contained in the provided opinion and does not add facts or inferences not present in the text.

    State Of Kerala v. Universal Marine Agencies

    Gopalan Nambiyar, C.J:— This appeal is by the State of Kerala and the Director of Fisheries, Trivandrum, against the judgment of a learned Judge of this Court, allowing the respondent's writ petition and restraining the appellants and the Deputy Director, the Assistant Director, the Sub Inspector of Fisheries and the District Collector, Trichur, from taking steps for the recovery of a sum of Rs. 24,974.94 mentioned in Ext. P5 notice, under the provisions of the Kerala Revenue Recovery Act, 1968 or the Indian Revenue Recovery Act, 1890. The learned Judge's judgment is reported (vide 1977 KLT. 949). An Ice-plant Storage and Freezing plant at Azheekode was leased to the writ petitioner under Ext P1 agreement dated 5-5-1970 for a period of one year. The rent was Rs. 30,001/-. Rs. 15,000/- had been paid on 7-5-1970 and the balance was payable on or before 23-11-1970. It was actually paid on 30-1-1971. Electric charges had to be paid by the lessee. As the charges were not so paid, the electric supply was disconnected on 30-3-1971. On 20-3-1971 by Ext. P2 letter from the 3rd petitioner, (the Managing Director of the 1st petitioner), the Director of Fisheries was informed that the petitioner was unable to continue the lease till the end of the period of agreement, and proposing to hand over the plant at any time before the end of the month. The 3rd petitioner complained of harassment from the local officials. As articles were inside the factory, the 5th respondent (to the OP.), the Sub Inspector of Fisheries put a lock on the factory and listed the articles (vide Ext. P3). On 14-5-1971, the writ petitioner and the respondents came to the ice-plant. Rs. 13,194.64 was estimated to be the arrears towards the electric charges and it was agreed that the petitioner would pay the amount. On 28-5-1971 the petitioner actually paid the amount and the electric supply was reconnected. On 4-6-1971 the plant was test-run. The plant had to be rectified. But this was not done. The writ petitioner was issued a notice for the security amount of Rs. 5,010/- and an additional claim of Rs. 5,000/-. The mistakes in the plant were rectified. The factory was reauctioned for Rs. 60,000/-. On 9-2-1974, the expreses and the loss caused to the Government by not returning the factory on 7-5-1971, were calculated at Rs. 29,974.94. After adjusting the security amount of Rs. 5,000/- a notice was issued for Rs. 24,974.94. Revenue Recovery Proceedings for the said amount were proposed to be taken. By Ext. P4 reply dated 14th August, 1973, the writ petitioner had stated that the entire lease amount of Rs. 30,001/- was paid in full and the plant was surrendered on 31st May, 1971, that subsequently the plant was leased out by the Government to another party, and that the security amount of Rs. 5,000/- had not been returned to the writ-petitioner. Ext. P5 notice of demand dated 9-2-1974 under the Revenue Recovery Act was issued by the Tahsildar, Mangalore, threatening revenue recovery proceedings for the amount of Rs. 24,974.94 that was due. It was at that stage that the writ petitioner approached this Court for redress. These were the facts according to the appellants.

    2. The learned Judge referred to Ext. P1 contract, and in particular to clause 16 of the said agreement which reads as follows:

    “16. The lessee do further agree that all sums found due to the lessor under or by virtue of this agreement shall be recoverable from the security amount and the balance, if any shall be recoverable from the lessee and their properties movable and immovable under the provisions of the Revenue Recovery Act for the time being in force as though they were arrears of land revenue or in such other manner as the lessor may deem fit.”

    3. Before the learned Judge, it was the Government's contention that the above clause would attract S. 68(1) of the Kerala Revenue Recovery Act 1968, according to which all monies due from any person to the Government under written agreement, are recoverable as arrears of public revenue due on land, or land revenue, and may be recovered under the provisions of the Act. The learned Judge referred to the decision of the Supreme Court in Union Of India v. Raman Iron Foundry . ((1974) 2 SCC 231 : AIR. 1974 SC. 1265), where in respect of a more or less similar clause, it was observed by the Supreme Court:

    “Now the law is well settled that a claim for unliquidated damages does not give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a Court or other adjudicatory authority. When there is a breach of contract, the party who commits the breach does not eo instanti incur any pecuniary obligation, nor does the party complaining of the breach becomes entitled to a debt due from the other party. The only right which the party aggrieved by the breach of the contract has is the right to sue for damages. That is not an actionable claim and this position is made amply clear by the amendment in S. 6(e) of the Transfer of Property Act which provides that a mere right to sue for damages cannot be transferred.”

    4. The Supreme Court cited with appraval a passage from the decision of Chagla C.J in Iron and Hardware (India) Co. v. Firm Shamlal and Bros. (AIR. 1954 Bombay 423), where the learned Chief Justice stated thus:

    “As already stated, the only right which he has is the right to go to a court of law and recover damages. Now, damages are the compensation which a Court of law gives to a party for the injury which he has sustained. But, and this is most important to note, he does not get damages or compensation by reason of any existing obligation on the part of the person who has committed the breach. He gets compensation as a result of the fiat of the Court. Therefore, no pecuniary liability arises till the Court has determined that the party complaining of the breach is entitled to damages. Therefore, when damages are assessed, it would not be true to say that what the Court is doing is ascertaining a pecuniary liability which already existed. The Court in the first place must decide that the defendant is liable and then it proceeds to assess what that liability is. But till that determination there is no liability at all upon the defendant.”

    5. After noticing the above Bombay judgment, the Supreme Court summed up the position thus:

    “This statement in our view represents the correct legal position and has our full concurrence. A claim for damages for breach of contract is, therefore, not a claim for a sum presently due and payable and the purchaser is not entitled, in exercise of the right conferred upon it Under clause 18, to recover the amount of such claim by appropriating other sums due to the contractor”.

    6. In the light of the above principles, the learned Judge took the view that unless there was an appropriate adjudication of liability of the writ-petitioner, he cannot be made liable, nor should coercive steps for revenue recovery be set in motion against him. The learned Judge noticed that some of the items of claim were not specifically covered by any clause in Ext. P1 agreement. For instance, there was no stipulation in Ext. P1 for interest on belated remittance of any instalments. The learned Judge also noticed that Department and the writ-petitioner were at variance as to the date on which the ice-plant was surrendered back. The appellants herein placed it as on 17-8-1971, and calculated loss of profits on the basis of what the appellants had been deprived of, or the profits that they would have made, had the plant been surrendered on 8-5-1971. The writ-petitioner would claim that it was surrendered on 31-5-1971 (vide Ext. P4). The learned Judge was of the view that the two heads of claim above referred to, can only give rise to a claim for damages for the appellant, which had to be assessed in ordinary modes, and not assessed by the appellants themselves to confront the writ-petitioner with. The learned Judge found that there was no provision under the contract to cover the assessment for the items of claim for which demand was raised against the writ-petitioner. Reliance was placed by the learned Government Pleader before the learned Judge, (and by the learned Advocate General before us) on the following passage in the Union Of India v. Raman Iron Foundry . ((1974) 2 SCC 231 : AIR. 1974 SC. 1265):

    “Now the law is well settled that a claim for unliquidated damages does not give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a court or other adjudicatory authority.”

    7. Reliance was also placed on a Division Bench ruling of this Court in State Of Kerala…* v. Joseph & Another… (1975 KLT. 551). In addition to these, the learned Advocate General drew our attention to the decision in State of Rajasthan v. Raghubir Singh ((1979) 3 SCC 102 : AIR. 1979 SC. 852). This latter decision was under the provisions of the Interests Act and concerned itself with the question as to when a debt can be said to ‘arise’, or a sum certain can be said to have been stipulated for, or to have materialised. Counsel for the Respondent before us (the writ petitioner) drew our attention to the decision in Achuthan v. State Bank of Travancore (1974 KLT. 806 para 17). We may extract the clause in Ext. P1 agreement relied upon by the learned Advocate General.

    “3. The department will employ one Assistant Operator for the Plant whose pay and allowances sanctioned from time to time by Government including leave salary and pension contribution shall be borne by the lessee.

    4. The lessee shall keep the Plant, in working order and in good condition meeting the expenses for the proper maintenance and repairs at the lessee's cost and on expiry of the lease period shall return the same in working order and good condition.

    16. (quoted in page 189)

    17. If any dispute or question shall arise between the lessee and the lessor touching on or relating to any of the matters or things hereinbefore contained the same will be decided by the lessor and the decisions of the lessor shall be final and conclusive and shall be binding on the lessee.

    18. The lessee shall be prepared to terminate the lease any time before May One thousand Nine hundred and Seventyone if so required by the lessor.”

    8. It seems to us that clauses 16 and 17 are wide enough to give the lessor the right to recover “all sums found due to the lessor under or by virtue of this agreement”, from the security amount, and the balance if any from the movable and the immovable properties of the lessee under the provisions of the Revenue Recovery Act. This provision clearly embraces whatever is due to the Government under or by virtue of Ext. P1.

    9. We now turn to clause 17 extracted supra. That gives the Government the right of deciding the amount due to the Government by reason of the operation of the agreement in cases of dispute between the lessor and the lessee as to the said amount. The Government's decision is to be final and conclusive and binding on the lessee. This clause again is wide and comprehensive, and approximates to the clause that was construed by this Court in the Division Bench ruling in State Of Kerala…* v. Joseph & Another… (1975 KLT. 551). In the presence of this clause, we are not prepared to agree with the learned Judge that there was no provision or machinery provided in Ext. P1 to adjudicate on the amount due by reason of the working of the provisions of the agreement. The learned Judge was inclined to view the clause as acting in terrorem and as penal in nature, in so far as it concedes to one party to the contract a right of deciding against the other. The learned Judge apparently failed to note or to appreciate the ratio of the Division Bench ruling in Joseph's case (1975 KLT. 551). That decision construed a similar clause and found it conferred a power similar to what is sought for in this case. The basis of treating as valid the conferral of such a power was explained in detail in the said decision. The learned Judge referred to General Manager. N.E.F Ry. v. Chakraborty (1978 (1) SCWR. 392), but an examination of the decision will show that there was no right on the controller to quantify the liability of the subscriber and seek to deduct the same. In M.R Breweries v. Union of India (AIR. 1975 Delhi 248) again, referred to by the learned Judge, the relevant clause did not confer a power of adjudication, and was so construed by the Delhi High Court. But in this case we are of the opinion that clause 17 confers such a power. We are unable to follow the learned Judge's comment that there was no argument before the Division Bench in 1975 KLT. 551 that the power of adjudication was not conferred by the contract. We are afraid the learned Judge has missed the ratio of the decision. In pursuance of the clauses in the agreement, the notice dated 26-6-1973 referred to in Ext. P4 had clearly set out the amount due from the lessee. No exception was taken to the adjudication of liability thus made by the Government. There was only a counter-claim that the plant was surrendered on 31st May 1971 and was leased by the Government to a third party and that the security deposit of Rs. 5,000/- had not been returned. In the circumstances, we cannot agree with the learned Judge that the demand raised by the Government was unjustified and improper and without jurisdiction. We allow this appeal and set aside the judgment of the learned Judge and would direct that O.P No. 1859 of 1974-B will stand dismissed. We make no order as to costs.

    10. Allowed.