Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Act 1961 and the activities violate Section 75M thereof.(v) The provisions of the Indian Electricity Act
  • Section 10 to 19 and Section 34 of the Indian Telegraph Act. Section 10
  • SECTION 51 ELECTRICITY ACT
  • Section 28 and 29 of the Indian Electricity (Supply) Act.
  • Indian Electricity Act and Electricity (Supply) Act
  • Section 51 of the Electric (Supply) Act 1948
  • Section 188 of the Indian Penal Code.(3)
  • Section 16 of the Indian Telegraph Act.
  • Section 76M of the Town Planning Act.
  • Section 10 unobstructed, Section 16
  • ELECTRICITY SUPPLY ACT 1948
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Act 1961 and the activities violate Section 75M thereof.(v) The provisions of the Indian Electricity Act
  • Section 10 to 19 and Section 34 of the Indian Telegraph Act. Section 10
  • SECTION 51 ELECTRICITY ACT
  • Section 28 and 29 of the Indian Electricity (Supply) Act.
  • Indian Electricity Act and Electricity (Supply) Act
  • Section 51 of the Electric (Supply) Act 1948
  • Section 188 of the Indian Penal Code.(3)
  • Section 16 of the Indian Telegraph Act.
  • Section 76M of the Town Planning Act.
  • Section 10 unobstructed, Section 16
  • ELECTRICITY SUPPLY ACT 1948
Smart Summary

Structured Summary of the Opinion (V.P. Mohan Kumar, J.)

Factual and Procedural Background

These writ petitions challenge the right of respondents-2 and -3 to draw a service line to supply electrical energy to the 4th respondent. The petitioners own various parcels of land in Siddedahalli Village, Yeshwanthpura Hobli, Bangalore North. The 4th respondent is a public limited company engaged in manufacturing goods mainly consumed by Central and State Government bodies.

By Government Order dated 12 May 1993 (Order No. DE 87 EEB 92 Bangalore), the 4th respondent was sanctioned additional power (500 KVA) from respondent-2, based on a recommendation of the 38th High Power Co-ordination Committee (meeting held 29.3.1993). The 2nd respondent issued Work Order (Annexure-G) dated 27.5.1994 directing the 4th respondent to draw 66 KV H.T. U.G. cables for a distance of 3 kms, in compliance with statutory provisions including the Karnataka Electricity Board Electricity Supply Regulation, 1988.

The petitioners challenged both the grant of power and the steps taken to implement the scheme and to draw service lines. Their complaints included alleged non-compliance with the work order, alleged statutory violations, lack of publication under Sections 28 and 29 of the Indian Electricity (Supply) Act, and an asserted change in alignment that included the petitioners' land. Respondents 2–4 filed detailed objections denying the allegations and asserting compliance with statutory and safety requirements.

This Court, by an interim order dated 22.7.1996, reserved liberty to the Board to approach the District Magistrate under Section 16 of the Indian Telegraph Act. Following an inquiry, the District Magistrate passed an order permitting the respondents to draw the line; that order was impugned in these writ petitions.

Legal Issues Presented

  1. Whether respondents-2 and -3 have the right to draw the service line to supply electrical energy to the 4th respondent, given the challenged sanction and work order.
  2. Whether the scheme and its implementation complied with statutory requirements, including the publication requirements under Section 28 and 29 of the Indian Electricity (Supply) Act.
  3. Whether the work being carried out violated the work order or statutory provisions (including alleged improper deviation from underground to overhead lines).
  4. Whether powers under Section 51 of the Electricity Act can result in conferral of Telegraph Act powers on the 4th respondent or its agents (and whether the consumer may lawfully carry out works under the Board's work order).
  5. Whether the activities amounted to development in breach of the Karnataka Town Planning Act (Section 75M / Section 76M) and whether that could be adjudicated in this proceeding.
  6. Whether the District Magistrate's order under Section 16 of the Telegraph Act is susceptible to judicial review on the merits of the underlying scheme.

Arguments of the Parties

Petitioners' Arguments

  • The work was being carried out by respondents-4 and -5 in violation of the work order issued by respondent-2.
  • The work was being executed by the 4th respondent itself without adherence to statutory requirements.
  • Section 51 of the Electric (Supply) Act 1948 does not permit conferring powers under the Indian Telegraph Act on the 4th or 5th respondent.
  • The activities amounted to development under the Karnataka Town Planning Act, 1961 and violated Section 75M (referred to in the opinion).
  • Provisions of the Indian Electricity Act were violated.
  • There was inadequate publication under Sections 28 and 29 of the Indian Electricity (Supply) Act; the alignment was changed to include petitioners' land due to undue influence of other landowners.

Respondents' Contentions

  • The scheme preparation and implementation complied with statutory provisions; there was no violation of regulations.
  • The work order was complied with while carrying out the work; due notice was given to affected parties.
  • The 4th respondent's need was for a public purpose; the route chosen minimized harm to landowners and was selected considering safety, soil conditions and technical feasibility.
  • The work involved technical decisions (e.g., overhead vs underground cables) for which the Board has expertise, and such matters are supervised by the Board's engineering officers.
  • The service line work is to be executed by the consumer/contractor under Board supervision per the relevant Regulation (Regulation 4 and subclauses), and such execution does not legally amount to impermissible delegation of Board powers.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mamoo v. State of Kerala, AIR 1980 KERALA 18 Explains the limited, ministerial nature of the District Magistrate's enquiry under Section 16 of the Telegraph Act — that the DM's role is to permit exercise of powers when resisted and not to adjudicate the validity of the underlying scheme. The Court relied on this authority to hold that the District Magistrate's order under Section 16 is not a forum to re‑open or re‑adjudicate the merits or validity of the sanctioned scheme; the DM's jurisdiction is limited to removal of obstruction and does not extend to evaluating the scheme's parameters.

Court's Reasoning and Analysis

The Court proceeded through a statutory and functional analysis emphasizing the limited scope of certain statutory powers and the technical competence of the electricity board:

  1. Statutory power: The Court analysed Section 51 of the Electricity Act (and provisions of the Indian Telegraph Act, notably Sections 10 and 16). Section 51 permits the State Government to confer on the electricity authority powers conferred on the Telegraph authority; Section 10 empowers placing and maintaining telegraph posts and lines; Section 16 permits the District Magistrate to order that the Telegraph authority be permitted to exercise those powers if resisted.
  2. Scope of District Magistrate's role: Drawing on Mamoo v. State of Kerala and the statutory text, the Court concluded that the DM's inquiry under Section 16 is ministerial/executive in nature — focused on whether a sanctioned scheme exists and whether implementation is being obstructed — and does not empower the DM to judge the validity, feasibility or technical parameters of the underlying scheme. The DM functions analogously to an executing court implementing a decree rather than as a court of first instance to try the scheme's merits.
  3. Effect of a valid sanctioned scheme: Once a sanctioned scheme exists and its implementation is obstructed, the authorities may seek an order under Section 16 for removal of obstruction; the scope of inquiry is limited to existence of the scheme and obstruction, not the scheme's substantive correctness.
  4. Deference to technical authority: The Court stressed that the 2nd respondent (the Electricity Board) is a technical/statutory body with expertise in preparing and implementing supply schemes. Courts lack the technical expertise to second-guess detailed engineering, safety or feasibility decisions and therefore should not lightly overturn such expert administrative choices unless clear legal infirmity is shown.
  5. Specific complaints addressed:
    • Publication under Sections 28 and 29: The Court held that the scheme did not amount to acquisition and that publication identifying the village through which the line would be drawn constituted substantial compliance; omission of plot (Sy. No.) specifics was not fatal given on‑the‑spot technical determinations necessary to fix the exact positions later.
    • Change from underground to overhead lines: The Court treated this as a technical decision falling within the Board's competence. The work order was not a rigid statutory charter mandating an immutable method; changes to the method for safety/practical reasons during execution were permissible when based on proper technical assessment by the Board's officers.
    • Conferment of powers under Section 51 to consumers/contractors: The Court referred to Regulation 4 (1988 Regulations) which contemplates the consumer having the responsibility to lay the service line under Board supervision; the arrangement was characterized as an agency/master‑servant relationship rather than an impermissible delegation of statutory power. The Court found the complaint that the 4th/5th respondents were illegally authorised under Section 51 untenable.
    • Town Planning Act (Section 76M / 75M): The Court declined to entertain this contention because the local authority — a necessary party for adjudication of that question — was absent; additionally, adjudication of the scheme's validity was outside the limited scrutiny appropriate in these proceedings.
    • Consent of owners: Where the line is being drawn under powers conferred (Section 51 read with Telegraph Act Sections 10 & 16), the Court observed that consent of owners is not required if a proper order exists permitting entry/works.
  6. Judicial review standard and limits: The Court discussed that the rights affected were not fundamental in a manner triggering strict scrutiny; the encumbrance on property was minimal. It reiterated that absent a demonstration that the competent authorities acted on irrelevant considerations or excluded relevant materials, the Court would not interfere with the Board's actions.
  7. Procedural posture: Because the District Magistrate had, after inquiry, permitted the respondents to draw the line, the Court observed that its scope to examine the correctness of that order under Section 16 was extremely limited and could not be used to re‑open the scheme's validity.

Holding and Implications

HOLDING: The writ petitions are WRIT PETITIONS DISMISSED — the Court found no grounds to interfere with the actions of the respondents and dismissed the petitions (paragraph 24 of the opinion).

Direct Consequences

  • The District Magistrate's order permitting respondents to draw the line stands and the Board (and its authorised agents/executors of the work) may proceed subject to any statutory requirements and the limits discussed.
  • The petitioners' stated grievances — as framed in these petitions — were not found to go to the root of the matter or to present grounds warranting judicial interference in the scheme's implementation.

Broader Implications and Court's Administrative Recommendation

The Court emphasized the difficulty faced by citizens in ventilating grievances arising from actions of a statutory monopoly technical body and recommended consideration of statutory or administrative reform. Specifically, the Court suggested creation of an independent adjudicatory forum (an institution akin to an Ombudsman) to receive and inquire into complaints against the 2nd respondent with minimum formality and cost. The opinion sets out the rationale for such an institution but does not itself create one; this remains an administrative recommendation rather than a judicially enforceable change.

Precedential Effect

The decision applies the statutory scheme and existing case law (notably Mamoo v. State of Kerala) to the facts and emphasizes deference to the technical expertise of the electricity authority and the limited scope of Section 16 inquiries. The Court did not announce a novel legal doctrine; it dismissed the petitions on the basis of the reasoning summarized above.

This summary is strictly based on the text of the provided opinion and does not add information beyond that opinion.

    S.M Rao & Others v. State Of Karnataka & Others

    V.P Mohan Kumar, J.:—

    The controversy raised in these Writ Petitions centers on the right of respondents-2 and 3 to draw service line for supply of electrical energy to the 4th respondent.

    2. The petitioners herein own various extents of land described in the Writ Petition in Siddedahalli Village, Yeshwanthpura Hobli, Bangalore North. The 4th respondent is a Public Limited Company engaged in the manufacture of certain goods whose main consumers are Central and State Government. As per Order No. DE 87 EEB 92 Bangalore dated 12th May 1993 of the Government of Karnataka the 4th respondent was sanctioned supply of additional power to an extent 500 KVA from the 2nd respondent on the basis of the recommendation of the 38th High Power Co-ordination Committee at its meeting held on 29.3.1993 The second respondent issued work order Annexure-G dated 27.5.1994, directing the 4th respondent to draw 66 KV H.T.U.G cables for a distance of 3 kms, in terms of the condition made mention therein and also in compliance with the statutory provisions including the Karnataka Electricity Board Electricity Supply Regulation 1988. The petitioners while questioning this grant itself they also challenge the steps taken by the respondents to draw the service lines. They question the very formulation of the scheme for the supply of electricity to 4th respondent and as a successive steps taken for the implementation of the scheme. The grounds on which the challenge is sustained are many fold. They include mainly.

    (i) The work is being carried out by respondents-4 and 5 in violation of the work order issued by the 2nd respondent;

    (ii) That the work is being executed by the 4th respondent himself without reference to the statutory requirements;

    (iii) That Section 51 of the Electric (Supply) Act 1948 do not envisage the conferring of the powers under the Indian Telegraph Act in favour of either the 4th respondent or the 5th respondent.

    (iv) That the activities of the respondents amount to development as envisaged under the Karnataka Town Planning Act 1961 and the activities violate Section 75M thereof.

    (v) The provisions of the Indian Electricity Act is also violated.

    3. The petitioners also complain that there has not been due publication of the scheme as required under Section 28 and 29 of the Indian Electricity (Supply) Act. It is averred that yielding to the undue influence of various land owners the alignment of the electrical line was changed, to exclude their land and to include that of the petitioners.

    4. These points are highlighted by several subsidiary points which can be dealt with simultaneously while we consider the main points.

    5. The respondents 2 to 4 have filed lengthy statement of objections traversing and denying every one of the allegations made by the petitioners. It is unnecessary to paraphrase the lengthy statements at this stage. The thrust of the contention is that there has not been violation of any statutory provisions while the preparation of the scheme, that the work order has been complied with while carrying out the work, that due notice has been given to all affected parties, that the need of the 4th respondent is a public purpose, that the service line is drawn in such a manner that minimum harm would be caused to the land owners through which the line passes that there may not be as much adverse affectation as has been complained of by the petitioners, that as the land is being used for placing the electrical post there would be no loss to the petitioners, that any variation to the work order effected is after keeping in view the safety aspect, that High Tension Underground cable is not feasible from the safety angle and that overhead cables are safer, that as per the present alignment there will be least injurious affectation to the petitioner, that all angles were kept in mind while preparing the scheme to draw the electrical line in question.

    6. Several documents were produced by both the sides and the matter was elaborately argued. Before we proceed in the matter it will be apposite to bear in mind the scope of judicial scrutiny in these areas. By virtue of Section 51 of the Electricity Act 1916, it is provided that the State Government may confer any of the powers conferred on the Telegraph authority under the Indian Telegraph Act 1885 on the 2nd respondent for the purpose of placing of electric supply lines and apparatus etc. It means by conferment of such power in writing as provided in Section 51 of the electricity authorities are entitled to exercise the power conferred under Section 10 to 19 and Section 34 of the Indian Telegraph Act. Section 10 in turn empowers to place and maintain telegraph posts. The main Section reads thus:

    “The Telegraph authority may, from time to time, place and maintain a Telegraph line under, over, along or across, and posts in or upon, any immovable property:

    Provided that:—

    (a) the Telegraph authority shall not exercise the powers conferred by this section except for the purposes of a Telegraph established or maintained by the Central Government, or to be so established or maintained;

    (b) the Central Government shall not acquire any right other than that of user only in the property under, over, along, across, in or upon which the Telegraph authority places any Telegraph line or post; and

    (c) except as herein provided, the Telegraph authority shall not exercise those powers in respect of any property vested in or under the control of management of any local authority without the permission of that authority; or

    (d) in the exercise of the powers conferred by his section the Telegraph authority shall do as little damage as possible, and when it is exercised those powers in respect of any property other than that pay full compensation to all persons interested for any damage sustained by them by reason of the exercise of those powers.”

    7. Now, while exercising this power, it is clear that there would be no transfer of ownership with respect to the property where the post is placed. It is only a limited right of entry to plant the post etc., and maintain them. Now, if the Telegraph authorities are resisted while exercising this right, the authorities are entitled to move the District Magistrate to remove the obstruction who can order that the concerned authorities may exercise the rights under Section 10 unobstructed, Section 16 in this behalf reads as under:

    (1) If the exercise of the powers mentioned in Section 10 in respect of property referred to in Clause (d) of that section is resisted or obstructed, the District Magistrate may, in his discretion, order that a Telegraph authority shall be permitted to exercise them.

    (2) If, after the making of an order under sub-section (1), any person resists the exercise of those powers, or, having control over the property, does not give all facilities for their being exercised, he shall be deemed to have committed an offence under Section 188 of the Indian Penal Code.

    (3) If any dispute arises concerning the sufficiency of the compensation to be paid under Section 10. Clause (d), it shall, on application for that purpose by either of the disputing parties to the District Judge within whose jurisdiction the property is situate, be determined by him.

    (4) If any dispute arises as to the persons entitled to receive compensation or as to the proportions in which the persons interested are entitled to share in it, the Telegraph authority may pay into the Court of the District Judge such amount as he deems sufficient, or, where all the disputing parties have in writing admitted the amount tendered to be sufficient or the amount has been determined under sub-section (3), that amount; and the District Judge, after giving notice to the parties and hearing such of them as desire to be heard, shall determine the persons entitled to receive the compensation or, as the case may be, the proportions in which the persons interested are entitled to share in it.

    (5) Every determination of a dispute by a District Judge under sub-section (3) or sub-section (4) shall be final:

    Provided that nothing in this sub-section shall affect the right of any person to recover by suit the whole or any part of any compensation paid by the Telegraph authority from the person who has received the same.”

    8. The wordings herein makes it abundantly clear that it is not an enquiry regarding the validity of the sanctioned scheme and there is no adjudication of any of the contention of the parties in such a proceedings regarding the para meters of the scheme except the right of the 2nd respondent for the removal of the obstructions. This aspect is clearly put across thus by the Full Bench of the Kerala High Court in Mamoo v. State of Kerala . AIR 1980 KERALA 18.,

    “If he is resisted or restricted he seeks permission from the District Magistrate whose adjudication does not cover the question whether a line is to be drawn over any specific item of property or whether posts are to be erected or not in any specific item of property. Section 16 does not indicate that as within the power of the District Magistrate. The enquiry by the District Magistrate would be in the nature of a ministerial enquiry. There is no question of calling for evidence, sifting such evidence and coming to a judicial decision thereon. In the event such judicial decision on issues was contemplated by Section 16(1) there would necessarily have been indication in the section as to the issues that could be so considered and judicially disposed of by the District Magistrate. No doubt Section 16(1) provides that in granting permission to the Telegraph Authority the District Magistrate is to exercise his discretion. Of course even in passing an executive order there is need for exercise of discretion and that need not render his proceedings judicial in character. The discretion has to be judicially deciding an issue.”

    9. Therefore there is a right in the Department for the purpose of implementation of a sanctioned scheme to enter into a property if authorised under Section 51 of the Act to lay its poles for drawing the electricity line. If they are resisted, the District Magistrate can be moved who can order removal of the obstruction if any. The scope of enquiry before the District Magistrate is thus far and no further. It is like an execution proceedings. All that the District Magistrate would be concerned with would be to ascertain, whether there exists a sanctioned scheme. He merely assist the Board to implement the scheme. It is like an executing Court which cannot jurisdictionally go behind the decree. Clearly in such an inquiry there is no scope for inquiry by the officer as to the feasibility or otherwise of the scheme itself. When, once thus a valid scheme shown to exist, then the authority exercising power under Section 16 is duty bound to order removal of any obstruction so as to implement the scheme. And any obstructions thereafter amounts to an offence punishable under Section 188 of I.P.C

    10. In this case this Court ordered thus on 22.7.1996:

    “The Board has filed a sketch showing the line originally proposed, the line subsequently proposed and the line now proposed. As per the latest proposal (shown in Green), no tower will be erected on the land of the petitioners. The Board has also stated that line will pass at the eastern extremity of the land causing minimum inconvenience to the petitioners. Learned Counsel for the petitioners however, does not agree.

    In view of the resistance and obstruction by the petitioners, it is obvious that Board cannot continue the work unless they obtain an order removing the obstruction under Section 16 of the Indian Telegraph Act. It is evident that no such order has been obtained. Hence, as on today, the Board cannot proceed with the work. Therefore, interim order has to be continued reserving liberty to the Board to approach District Magistrate under Section 16. If the Board is able to get an order from the District Magistrate for removal of obstruction, at that stage the Board may approach this Court again for modification of the order and the matter will be considered thereafter.

    Interim order to continue.”

    11. After the inquiry as directed, the District Magistrate passed the order now impugned, permitting the respondents to draw the line. In the light of the observation of the decision referred to above the scope inquiry of this Court vis-a-vis as to the correctness of the order under Section 16 is clearly nil. The competent authority need not enquire as to whether, the scheme was prepared validly, whether, relevant considerations alone were taken into account and irrelevant considerations were eschewed while preparing the scheme whether the petitioner had an effective opportunity to highlight his objections, whether the authority applied its mind while considering the objection etc. To put it differently it is not a jurisdiction akin to certiorari that is being exercised by the authority under Section 16 of the Act. The inquiry begins with the existence of a sanctioned scheme and whether its implementation is being obstructed, if that be so the question then would be, can the petitioner by means of a collateral attack of the scheme itself, contend that the power exercised by the District Magistrate under Section 16 is unsustainable? Or alternatively, can the petitioner disguise his attack on the scheme prepared by Board by attacking the implementation order made under Section 16 Telegraph Act?

    12. The right to judicial scrutiny of an action which has civil consequence on the rights of a citizen to enjoy his property has been always recognised by the Courts. The petitioners complain that their right to enjoy the property is curtailed by means of an illegal preparation of a scheme by a statutory body like the 2nd respondent. An inquiry into this contention would take us to examine the validity or otherwise of the scheme prepared by the 2nd respondent. Perhaps with the object to avoid such complaints the Electricity (Supply) Act 1948 have provided certain in built safeguard. The important provisions relied on by the Counsel for the petitioner in this behalf are Section 28 and 29.

    13. When we examine the question of judicial scrutiny, there are certain limitations on the powers of the Court in a situation like this. We have seen that drawing of electricity lines and supply of power to the consumers is the work entrusted to the second respondent by statute. Elaborate provisions are made in the Indian Electricity Act and Electricity (Supply) Act in this behalf. Statute itself provides framing of elaborate Regulation and Rules for the exercise of its powers under these enactments. The object of these subsidiary Rules and Regulation is to safeguard public safety visualised in the statute and to promote effective distribution of electricity. The 2nd respondent is a monopoly distributor of the power generated in the State. Therefore any scheme prepared should be in consideration and in accordance with these provisions utilise or conserve as the case may be the maximum of power resources. Therefore when a scheme prepared in accordance with these provisions is complained to be in violation of statutory provisions such complaints should not be entertained merely because for a layman the scheme appears to be defective. Because in the first place it has to be noticed that, the Board alone has the competency to decide as to whether the scheme thus prepared does violate the statutory requirements. Whether, all safety angles are kept in view while preparing the scheme and whether the power being supplied and put to optimum use. Admittedly, this Court do not have any technical competency to examine these aspects while dealing with such a complaint, and the absence of such inherent expertise should permit the Court to rely more on the decision taken by the expert like the 2nd respondent in this behalf.

    14. The Electricity Board, is a technical Body created by the statute for the purpose of supply of electrical energy generated in the State. In discharging the said function, it has to keep in mind and observe such technical and other matter insisted upon by the Statute and Regulations. It is an admitted fact that it is the routine business of the Board, to prepare and implement scheme for supply of electricity. It would have gained vast experiences in this behalf, gained by practice. In such cases, it would not be incorrect to assume that the Board's decision must normally rest on its own expertise acquired by implementing such schemes earlier and its judgment in this behalf should be accepted as correct rather than undertaking an autopsy of the same on the basis of any particular factual details discovered by a layman. In such cases, mathematical details need not be shown to exist to support the decision of the Board and its schemes. An expert Body like the 2nd respondent can be presumed to have conducted itself properly and prepared the scheme as an expert would rather than inferring the Board to have violated statutory and regulatory provisions.

    15. In this case the first violation complained of is the non-publication of the notification, Annexure-H with more details. According to learned Counsel Mr. Prabhu, such notification should have appeared simultaneously in the gazette and dailies and should have contained more details indicating the precise route that the line would travel unlike the cryptic notification, Annexure-H published in this case. To understand this contention, one has to keep in mind the scope and ambit of right being exercised by the Electricity Board. As is demonstrated earlier, the Electricity Board do not intend to acquire any right over the land over which the electric line is being placed. It is only seeking a right of the user of the land which according to them would be appropriate designated land to draw the line. It is for the Board to decide the appropriate land to locate the Towers/Poles etc., for the purpose of drawing line. The particular land that would be suitable can be identified by them after due investigation in the village. It is not for the owner or others to point out as to which land should be utilized for drawing the line and as to which land should not be used. If such objections are to be entertained, that would result in the serious interference with the technical functioning of the 2nd respondent executing its various projects. It would have choosen the point to tap the line taking into account the supply capacity technically and could have drawn the line keeping in mind the land condition. If people are permitted to dictate the land through which the line has to be drawn it may result in no technically feasible land being made available for the purpose of drawing the electric line. To highlight their complaint, the petitioners allege that there has been undue influence exerted in excluding more viable route and choosing the land of the petitioners. After the decision to supply power, the 2nd respondent inspects the village and decide the route through which the line has to travel. Various consideration would prevail with the competent authority in choosing the route. It may be the soil condition to erect the supply towers, lack of population to achieve safety, to diminish the distance of the line, transmission loss etc., etc. Merely because some land is left out, it need not be due to undue influence. Besides it is settled law that mere allegations of undue influence malafide etc., in the matter would not replace the proof. Without anything more it is difficult to hold that the present line for drawing the line was fixed yielding to the influence of any third party. The second respondent is a body corporate. It has to exercise its function rationally and in accordance with rules and Regulations. As long as it is shown that the alleged violation of Regulation 4 of the 1988 Regulation, even if it do exist (assuming for argument sake) do not affect the safety aspects, this Court cannot treat it as a ground to invalidate the very scheme. The Regulation of 1988 have been framed with safety as its prime object and not with intend to provide grounds of objections to the schemes framed and to challenge the scheme, at the behest of interested third parties.

    16. The other grievance of the petitioner is that sanction order produced shows that electrical lines should have been drawn underground and now, ignoring the said condition petitioners allege that overhead line are sought to be drawn. This according to the petitioners is a serious unauthorised alteration. This may be a point to be considered without anything more. But in reply to this allegation, the Electricity Board has indicated the care and caution taken by them while implementing the Scheme. In the statement it is stated thus:

    “The authorities to carry out the work one Chief Engineer (O & M) Bangalore is responsible for operation and maintenance of power systems. The Chief Engineer, Electricity, major works, Bangalore is the Officer-in-charge of construction of new lines including surveying etc. The Chief Engineer Major Works who has to finally decide whether the lines have to be drawn overhead or underground after inspection of the work spot. It is also responsible for obtaining clearance from statutory authorities like power telecommunication coordination committee which is a must.”

    This means they have made detailed study of the viability of the scheme as contained in the work order from various angles and hence would have adopted the overhead cable to replace the under ground cable. One cannot say that this is arbitrary or illegal. This Court do not possess sufficient technical know how to decide as to whether the change effected was right and whether there is any illegality in making the alteration of the work order. The work order merely states that a service line may be drawn for the supply of the power to the consumer and the work shall be carried out so as to facilitate in an efficient manner the supply of electricity to the consumer. It does not mean that it shall be done in the particular manner alone as indicated and in no other manner ignoring safety aspect. The work order is not a statutory order or a charter of condition. It is an order for the use of the 2nd respondent to make it possible to draw the line. Alterations of the work order in the course of tarrying out the work depending on the practicability of the drawing of line can always be given effect to and such power cannot be ruled out.

    17. The next contention is that Section 28 notification has not been duly published. As said earlier it is not an acquisition proceedings. The electrical line is being drawn for the supply of power to the consumers. It is sufficient to inform the public indicating the village through which the line is being drawn. As a matter of fact, the definite area on which the Tower etc., are to be placed can be known only after a spot inspection is made and viability is worked out. But I should certainly hasten to add, that if the Sy. nos. in the village are also indicated, that will make the notification more precise. Such details will also inform the affected person to arrange his affairs. But, absence of these details are not fatal. When the line has to travel a long distance as in this case, non mention of the Sy. Nos. is not certainly fatal. Many a time drawing of the line depends on the soil condition and other local situation as well. If that be so they cannot in advance contemplate as to through which property the line will have to be drawn. They need one say as to the village through which the line is being drawn. That has been complied in this case, and as such there is substantial compliance of the statute.

    18. Two other aspects that are also raised by the petitioners may now be adverted to. It was stated that conferment of power under Section 51 of the Act can be done only on the 2nd respondent and not on either the 4th respondent or the 5th respondent. Mr. Prabhu, learned Counsel, submitted that neither the 4th respondent nor his agent 5th respondent can exercise any of the powers under the Telegraph Act, as the said powers cannot be legally conferred on them under Section 51 of the Act. This submission in fact over looks the provision of Regulation 4 of 1998 Regulations referred to supra. It is clear from Regulation 4 that it is the duty of the consumer to carry out the work under the work order of laying the line from the point of supply to his premises on behalf of the 2nd respondent. The work will be supervised by the 2nd respondent. Regulation 4.14 states that the service line work from the terminal pole up to the point of commencement of supply, whether overhead underground, shall be got done by the consumer through a contractor. Regulation 4.16 makes it clear that permission to lay service line under, across or over the consumer's premises or for fixing apparatus upon the said premises by the Board, shall be deemed to be implied and vested with the Board. It is clear from these provisions that the service line once completed would belong to the Board. In fact what the Board has to carry out by its own management is being carried out at the instance of the Board by the consumer as its agent. The consumer only acts as the agent of the Board. The principle of “delegates non posest delagare” do not arise in such cases as there is no delegation at all of its power by the 2nd respondent to the 4th respondent or its employee the 5th respondent. It is the relm akin to master and servant relationship. Therefore the conferment of the power given on the Board under Section 51 of the Act will necessarily enure to the benefit of the consumer who act only as his agent or servant. It is also to be noted that the Board is collecting charges for supervision for the construction of the service line which circumstance is obvious to indicate that the entire responsibility of the construction is taken over by the Board. The Complaint that there has been illegal authorisation to the 4th and 5th respondent under Section 51 of the Act is therefore untenable.

    19. The other contentions urged by the learned Counsel is the violation of Section 76M of the Town Planning Act. But in view absence of necessary parties to the proceedings namely the local authority this question cannot be gone into. Besides, the examination of the said contention again beg the question where the validity of the scheme can be gone into by this Court. As this aspect is outside the judicial scrutiny of the Court, I reject this contention.

    20. The other contention urged, namely that consent of the owners of the land through which the line travel was not secured by respondents 4 and 5 before laying the poles and towers to draw the electric line recedes to back ground, when we remember that the line is being drawn, in exercise of the powers conferred, under the Section 51 of the Electricity Act read with Section 10 & 16 of The Telegraph Act. If there is an order in this behalf, then no consent is called for.

    21. Thus the grievance of the petitioners highlighted herein do not go to the root of the matter and cannot be examined.

    22. As regards to the right of judicial review in such circumstances, the following passage from “Philosophy of Law” Jeffrie G. Murphy & Jules L. Coleman may be adverted to:

    “In judicial review application of strict scrutiny to the encumbrance of a right involves the application by the Court of a two pronged test that places a very heavy burden of justification on the State. In order to justify encumbering a fundamental right, the State must show (1) that the right must be encumbered in order to accomplish a compelling (and not merely rationally desirable) state goal or interest, and (2) that in accomplishing its compelling interest, the State is employing the least restrictive means possible - i.e, it is encumbering the right only to the degree actually necessary to attain its compelling goal.”

    23. The claim of the petitioners in these cases cannot be described as fundamental in nature and if so there is no encroaching on the said right of the petitioner by the State. Likewise, the State is encumbering the right of the petitioner in has land to minimal extent. In such circumstances the impugned action does not call for any scrutiny by means of a judicial review.

    24. In these Writ Petitions, it is not demonstrated that the competent authorities were influenced by irrelevant considerations and have kept out relevant materials in decision making process. I do not find any grounds to interfere with the action of the respondents. Accordingly the Writ Petitions are dismissed.

    25. Before parting with this case I wish to highlight the difficulties experienced by a citizen in view of the exercise of a State Action, for want of an appropriate forum to ventilate his grievances. The 2nd respondent is the State and it exercises its statutory powers conferred on it in the matter of supply of electrical energy to its consumer. The 2nd respondent is a monopoly organisation as well. It exercises its right is professedly for the larger interest of the Society. This may include exercise of a right in relation to the drawing of electricity line, need for setting up transformers, locating of such transformers etc., etc. Besides, these be the difficulties commonly experienced in the matter of power consumption bills by the consumers. By virtue of the statutory exercise of the rights of the 2nd respondent, a citizen has to depend on them alone for adjudication of their various grievances. Due to a variety of technical limitations this Court may not be in a position to deal with such problems effectively. And even it does, it is not desirable to encourage a citizen to make frequent excursions to this Court in this behalf as it might delay, at times, important project works undertaken by the 2nd respondent. Besides avoidance of such recourse could reduce otherwise avoidable delay as well.

    26. This case illustrates an instance which is an appropriate case to draw the attention of the authorities as to the need to make such appropriate statutory amendments to the concerned legislation to create a forum before whom an aggrieved person like the petitioners herein can ventilate their grievances. Invariably, the contending parties may not and need be as powerful as in this case to approach this Court. Creation of an institution akin to Ombudsman in the 2nd respondent who has power to examine the grievance of a person, against the action of 2nd respondent including such as the one involved in the case is justified by the circumstances, Gellhorn in his book “Ombudsmen and Others” (1966), highlighting the need of such an institution states thus:

    “Whatever the merits and inadequacies of both the Continental and the common-law type of administrative justice may be, a number of countries of both systems - socialist as well as capitalist - have found it necessary to empower readily accessible, professionally qualified, wholly detached critics to inquire objectively into asserted administrative shortcomings. Institutionalising the giving of expert criticism accomplished by each of the countries in its own way, has distinctly contributed to strengthened public administration (Gellhorn, 1966, P. 422)

    27. It is desirable to create an institution who is independent from the control of the 1st and 2nd respondents and whose business is to receive and inquire into complaints brought by aggrieved person with minimum formality and cost. With the advancement of years the activities of the 2nd respondent is growing. When the Electricity Act of 1918 and The Electricity (Supply) Act of 1948 where legislated, the scientific achievement were not as advanced as it is today and the population was also far less. Large areas of land were available to lay electric lines etc; it was perhaps for this reason that need of such a body was not visualized in the Act. But with the passage of time the scenario has totally changed. With more and more utility for electricity and its generation having also been increased, it resulted in the increase in the number of consumers. Thereby it resulted in the 2nd respondent in expanding its activities. It is obvious that more and more citizens would feel aggrieved by such action of the 2nd respondent giving rise to more crop of litigations. In such circumstances there should be an in built mechanism to examine the grievance of ordinary persons rather than they being drawn in to Court and the Court stepping into and examining all matters for which it is not qualified technically. Even if thereafter, it becomes necessary for this Court to examine the dispute, then this Court will have the benefit of the decision of an independent body on this issue.

    28. In order to reduce complaints against the actions of the 2nd respondents of alleged arbitrariness and to mitigate Court litigation, I hope that 1st and 2nd respondent would pay immediate attention to what is stated above and take such statutory/administrative steps as are felt necessary for the constitution of an adjudicatory body as in the nature of Ombudsman referred to above.

    Use AI to get other relevant cases.

    Comments

    S.M Rao & Others v. State Of Karnataka & Others
    (Apr 5, 1999)