  • Clause 11 of the Special Conditions of Contract (SCC) and Clause 24 of the General Conditions of Contract
  • Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962.
  • SECTION 9 ARBITRATION AND CONCILIATION ACT 1996
  • Section 6(1)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Clause 11 of the Special Conditions of Contract (SCC) and Clause 24 of the General Conditions of Contract
  • Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962.
  • SECTION 9 ARBITRATION AND CONCILIATION ACT 1996
  • Section 6(1)
Smart Summary

Structured Summary of the Court Order

Factual and Procedural Background

The petitions arise under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim reliefs against encashment of bank guarantees. Petitioner M/s AMKV-TECPRO (a consortium including TECPRO Systems Limited) submitted two separate bids for Section-I and Section-II of the Kochi-Koottanad-Mangalore-Bangalore Pipeline Project (KKMBPP) after an e-tender floated by Mecon Limited on behalf of GAIL (India) Limited on 28 June 2011. Letters of acceptance were issued (intimations dated 12 January 2012 and letters of acceptance dated 2 February 2012) and separate contracts dated 20 January 2012 were executed for each section with specified contract prices.

Contract terms required the Petitioner to furnish Performance Bank Guarantees (PBGs) of 10% and Advance Bank Guarantees (ABGs) of 11% of the contract price. The Petitioner furnished specified ABGs (IDBI Bank) and PBGs (Axis Bank) for both sections. Mobilisation advances (5% and a further 5%) were released by Respondent No.1 in July and October 2012.

Once work commenced, the Petitioner discovered that the Right of User (ROU) over significant stretches of land had not been fully acquired by Respondent No.1. Acquisition under the Petroleum and Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962 required notices under Section 3, a declaration under Section 6(1) by gazette notification, and payment of compensation, but these processes were not completed for many stretches and continued in instalments well after commencement. The Petitioner alleges that this non-availability of ROU, late gazette notifications, encumbrances, ongoing occupation by landowners, and protests (including an interim order from the Kerala High Court restraining possession until compensation was paid) impeded construction and altered the scope of work.

The Petitioner claims it extended time and the guarantees, contends that Respondent No.1 misrepresented the availability of ROU at the time of bidding and contract, and alleges this amounted to a fraud vitiating the contracts. The Petitioner sought interim orders restraining Respondents from invoking the PBGs and ABGs; an interim order was granted by this Court on 4 February 2014 restraining invocation subject to the Petitioner keeping the guarantees alive. An arbitral tribunal has been constituted and the Court considered continuation of interim measures during arbitration.

Legal Issues Presented

  1. Whether the Court should restrain Respondents from invoking and encashing the Performance Bank Guarantees (PBGs) furnished by the Petitioner.
  2. Whether the Court should restrain Respondents from invoking and encashing the Advance Bank Guarantees (ABGs) furnished by the Petitioner.
  3. Whether the interim order previously granted (on 4 February 2014) should continue during the pendency of the arbitral proceedings and on what conditions (for example, keeping the guarantees alive).

Arguments of the Parties

Petitioner's Arguments (Mr. Sudhir Nandrajog, Sr. Counsel)

  • Respondent No.1 falsely and misleadingly represented at bid stage and contract execution that requisite ROUs had been acquired, whereas acquisition had not even been initiated; this alleged misrepresentation amounts to an egregious fraud vitiating the contracts.
  • Because ROU acquisition was not completed and land remained occupied/encumbered, the Petitioner could not carry out construction on many stretches and had to refrain from work (including awaiting harvests and compensation), altering scope and schedule of work.
  • The Petitioner extended the PBGs and ABGs and sought provisional extension of time; invocation of the bank guarantees at this stage would cause irretrievable injury and injustice to the Petitioner.
  • The Petitioner contends it has carried out work and incurred costs exceeding the mobilisation advance; some bills (approx. Rs. 4 crore for each section) have been withheld by Respondents.
  • Requested continuation of interim orders restraining invocation/encashment of guarantees during pendency of arbitral proceedings.

Respondent No.1 / GAIL's Arguments (Mr. Ramji Srinivasan, Sr. Counsel)

  • The contention that ROUs were not acquired is incorrect; Respondent produced a chart (Annexure R-1/24) showing ROU availability versus work completion demonstrating substantial ROU availability at relevant dates.
  • As to Section-I, the chart indicated 49.4 kms available out of 91 kms as on 12 January 2013 while work completion was only 0.51 kms; as to Section-II, 78.096 kms were shown as available while no work had been completed.
  • Invocation of PBGs and related matters should depend on the outcome of the arbitral proceedings; however, there is no justification to restrain encashment of ABGs since mobilisation advances had been disbursed and little work was completed, entitling Respondent to encash ABGs.
  • Denied that any fraud was played on the Petitioner by GAIL (a public sector undertaking) and relied on the Supreme Court precedent that interference with invocation of bank guarantees is exceptional.

Petitioner's Rejoinder

  • Challenged the correctness of the Respondent's chart (Annexure R-1/24) and pointed to documentary evidence showing that Section 6 notifications were issued as late as August 2013.
  • Emphasised that continuous stretches of ROU were necessary to lay pipeline and that handing over of land in several instances had not occurred and would require evidence to be examined in arbitration.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
U.P. State Sugar Corporation v. Sumac International Ltd., (1997) 1 SCC 568 That only in exceptional circumstances will a court interdict the invocation and encashment of bank guarantees. The Court noted that Respondent relied upon this authority. The Court nevertheless conducted a prima facie analysis of the facts and contract provisions and concluded that, on the material before it, the Petitioner had made out a prima facie case (and balance of convenience) for restraining encashment of both PBGs and ABGs during the arbitration, subject to conditions. Thus, while the precedent was acknowledged, the Court applied its own prima facie assessment to allow continuation of interim relief.

Court's Reasoning and Analysis

The Court proceeded by assessing whether the Petitioner had a prima facie case and whether the balance of convenience favored continuation of interim relief. The Court examined relevant contract provisions and the factual record produced to it:

  • The Court referred to Clauses 5 and 35 of the Instructions to Bidders (ITB) requiring bidders to examine the site and route, and Clause 5.1 which states that claims due to ignorance of existing conditions will not be considered after bid submission. It reference Clause 26 (Force Majeure) and Clause 29.1 (employer's right to determine the contract if contractor refuses or fails to execute work).
  • The Court analysed Clause 28.1 of the Special Conditions of Contract (SCC), which expressly stated that the Company (GAIL) has acquired the ROU under the P&MP Act and that acquiring ROU means publishing Sections 3(1) and 6(1) Gazette notifications; it also assigned responsibilities to contractor to open ROU with revenue team and to remove obstructions, while compensation under the Act was to be paid by the Company.
  • The Court also considered Clause 28.6 of the SCC on detours when legal ROU is not available, which contemplated contractor arranging ROU for detours with costs except compensation to be paid by GAIL and Company proceeding with notifications in due course; however such detours should not affect overall construction schedule.
  • Respondent No.1 had placed on record a document (R-1/17) showing details of acquisition as on 8 August 2013, indicating that full acquisition had not been completed on the contract date and was made in instalments thereafter. The Court observed that even if the Petitioner had inspected the site, that might not have revealed facts exclusively in Respondent's knowledge about ROU acquisition timing.
  • The Court emphasised that factual disputes on whether Respondent failed to make lands available or whether Petitioner failed to perform on stretches made available would require evidence to be led before the arbitral tribunal; these could not be conclusively determined at the interim stage.
  • On the PBGs, the Court found that the Petitioner had made out a prima facie case in its favour for restraining Respondent from invoking and encashing the PBGs because the question whether Respondent failed to provide essential ROU could not be finally resolved without evidence.
  • On the ABGs, the Court noted that mobilisation advances had been released and some work had been commenced and completed. It found that encashment of ABGs at this stage would cause irretrievable injustice to the Petitioner because the Petitioner had claims for work already performed and had incurred costs in excess of mobilisation advances. Therefore, the balance of convenience favored restraint on encashment of ABGs as well.
  • Weighing these factors, the Court concluded that continuation of the interim order (granted on 4 February 2014) restraining invocation and encashment of the stated bank guarantees during the pendency of the arbitral proceedings was appropriate, subject to the Petitioner keeping the PBGs and ABGs alive.

Holding and Implications

HOLDING: The Court directed that the interim order passed on 4 February 2014 in both petitions shall continue during the pendency of the arbitral proceedings, subject to the Petitioner keeping the Performance Bank Guarantees (PBGs) and Advance Bank Guarantees (ABGs) alive. The petitions were disposed of in these terms.

Implications:

  • Direct effect: Respondents are restrained from invoking and encashing the PBGs and ABGs during the arbitral proceedings, provided the Petitioner ensures the guarantees remain alive. The petitions are disposed of on that basis.
  • Arbitral determination: The underlying disputes about whether Respondent failed to make ROU available, whether the Petitioner failed to perform on stretches that were made available, the correctness of the Respondent's chart, and other factual contentions remain for detailed adjudication in the arbitral proceedings where evidence will be led and examined.
  • Precedential effect: The Court did not purport to create or alter legal precedent; it applied established principles on interim relief, prima facie assessment, and balance of convenience to the facts before it. The opinion does not state any new legal rule beyond its interlocutory determination.
To access the original judgment, please Sign In or Subscribe.

    M/S. Amkv-Tecpro Petitioner v. Gail (India) Limited & Anr. S

    ORDER

    1. These are two petitions under Section 9 of the Arbitration and Conciliation Act, 1996 (‘Act’) seeking interim reliefs.

    2. The Petitioner M/s AMKV-TECPRO is a consortium of TECPRO Systems Limited which undertakes turnkey projects. Mecon Limited (Respondent No. 2), on behalf of Gail (India) Limited (Respondent No. 1) floated an e-tender on 28th June, 2011 inviting bids on open international competition basis for laying of the Phase-II of the Kochi-Koottanad-Mangalore-Bangalore Pipeline Project (KKMBPP) which involved testing and commissioning of 884 Kms long steel pipeline for transportation and distribution of re-gasified Liquid Natural Gag (LNG) and associated facilities in the states of Kerala, Tamil Nadu and Karnataka from intermediate piping system (IPS) of Phase-I at FACT Udyogmandal to IPS of Phase-II at Kootanad and from there to Bangalore and Mangalore.

    3. The Petitioner submitted two bids, one for Section-I and the other for Section-II. By separate letters dated 12 January 2012 Respondent No. 1 intimated to the Petitioner the acceptance of both its above bids [at the contract price of Rs. 89,82,69650/- and Rs. 68,97,37,075/- respectively. The details of Section-I and Section-II awarded to the Petitioner were as under:

    Section- I Pipeline from dispatch terminal at existing 30″ × 91km IP. Station-I at FACT Udyoghmandal of Phase-I at Ch.0.000Km to IP Station-1 of Phase-Ii atApprox. Ch. 90.615 Km at Koottand including piping works at despatch terminal at existing IP Station-I, SV-1, SV-2, SV-3, SV-4 & SV-5 Stations and IP Station-I at Kootanad.”

    “Section- II Pipeline from IP Station-1 atApprox. Ch. 24″ × 114km 90.615 Km at Koottand to IP Station-2 at Ch. 188.80 Km plus IP Station-1 (Ch 90.615) to SV-1M (Ch 15.99 Km on Mangalore spur line) including piping works at SV-1M, SV-6, SV-7, SV-8, SV-9&SV-10 and IP Station-2.”

    4. The work was to be completed and kept ready for commissioning within 12 months from the Fax of Acceptance (FOA) i.e from 12 January 2012. The commissioning of gas including all stations/terminals was to be effected within three months after mechanical completion. Respondent No. 1 issued letters of acceptance in respect of both bids on 2nd February 2012. In respect of each of the sections a separate contract agreement dated 20 January 2012 was executed by the Petitioner and Respondent No. 1.

    5. In terms of Clause 37 of the instructions to bidders (ITB) read with Clause 11 of the Special Conditions of Contract (SCC) and Clause 24 of the General Conditions of Contract (GCC) the Petitioner had to furnish, in respect of each contract, Performance Bank Guarantee (PBG) for 10% of the contract price within 15 days of the receipt of the FOA which was to be valid till expiry of 90 days after the end of the defect liability period. Further in terms of Clause 26 of the SCC, the Petitioner was to furnish Advance Bank Guarantees (ABGs) for 11% of the contract price. In respect of both sections the Petitioner furnished to Respondent No. 1 the following bank guarantees:

    ADVANCE BANK GUARANTEE with IDBI BANK LTD CHENNAI

    Sl. No.BG No.Expiry DateAmt (Rs)Section11203801BGA0013613.05.201549404721.00I21203801BGA0013713.05.201549404721.00I31203801BGA0013813.05.201537935539.00II41203801BGA0013913.05.201537935539.00II

    PERFORMANCE BANK GUARANTEE with AXIS BANK CHENNAI

    Sl. No.BG No.Expiry DateAmt(Rs)Section11165010000174731.07.201589826765.00I21165010000174831.07.201568973708.00II

    6. Since the project involved laying, testing and commissioning of the pipeline for transportation of long steel pipeline, Respondent No. 1 had to acquire the Right of User (ROU) over the land through which the proposed pipeline was to be laid. According to the Petitioner, it was represented to it by Respondent No. 1 that the said ROU had already been acquired.

    7. In respect of both contracts, Respondent No. 1 released the mobilisation advance on 20 July (5%) and 17 October 2012 (the balance 5%). The Petitioner claims that once the work commenced, it was realised that the process of acquiring ROU over the lands through which the pipeline had to pass had not been completed by Respondent No. 1. For that purpose notices had to be issued under Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962. After hearing objections to the notice under Section 3(1) of the Act, a declaration under Section 6(1) by means of a notification in the official gazette had to be issued and this had to be followed by payment of compensation to the concerned land owners.

    8. It is claimed by the Petitioner that the details of the gazette notifications were forwarded to Respondent No. 1 for the first time almost eight and a half months after the commencement of the project. Further, the declaration under Section 6(1) of the Act was not for the entire stretches of land through which the proposed pipeline had to pass but for different parcels. The Petitioner further claims that even in respect of these parcels there were encumbrances and land owners continue to occupy the lands with their cultivations and/or permanent structures. This compelled the Petitioner to refrain from carrying out any construction activities on these stretches till the paddy harvesting was completed by the end of December 2012. It is then stated that due to non-settlement of compensation some of the farmers/land owners protested and declared that they would not hand over possession of the land or allow any pipeline to pass through it.

    9. According to the Petitioner, as on the date of the FOA, 12 January 2012, in respect of Section-I out of the entire stretch of 91 kms, only 11.339 kms of ROU had been provided. In respect of Section-II, out of the entire stretch of 114 kms, only 0.375 kms of ROU was provided. As on that date of the filing of the petitions, in respect of Section-I, only 65 kms was available. As far as Section-II is concerned, only about 15 kms is made available on that date and that too in instalments. It is stated that the acquisitions of the ROUs continued well after the stipulated date of completion of the contract. It is claimed that correspondence was exchanged between the parties in relation to such delay and stoppage of work. Reference is made to a writ petition filed in High Court of Kerala by some of the land owners and an interim order passed therein by the High Court on 13 February 2013 directing status quo to be maintained till such time adequate compensation was not paid for the standing crops and the land at market value to the Petitioners. It is further claimed that the Petitioner's workforce was beaten up by mobs and activists claiming to safeguard the interests of the landowners. In the meanwhile, Respondent No. 1 was asked by the Government of Kerala to enhance the compensation and sometimes reroute the pipeline. According to the Petitioner, this completely altered the scope of the work.

    10. The Petitioner states that in the above circumstances, it was constrained to seek provisional extension of time up to 11 October 2013 for completion of the balance activities. It kept extending the PBGs and ABGs. The Petitioner contends that Respondent No. 1 made a false and misleading representation to the Petitioner at the time of the issuance of bid documents, and even at the time of execution of the contracts, that it had already acquired the requisite ROUs whereas it had not even initiated the process of acquisition. This is claimed to be an egregious fraud that vitiates both contracts. It is further pleaded that in the circumstances any attempt by the Respondent No. 1 to invoke the afore-mentioned PBGs and ABGs at this stage would be impermissible in law. It is pleaded that unless the Respondent No. 1 is restrained from doing so, irretrievable injury or irretrievable injustice would be caused to the Petitioner. It is claimed that Rs. 4 crores approximately in respect of the bills of the Petitioner for each of the sections has been withheld by Respondents 1 and 2.

    11. This Court on 4 February 2014 passed an interim order restraining the Respondents to invoke the aforementioned PBGs and AVGs subject to the Petitioner keeping them alive.

    12. It is pointed out by Mr. Sudhir Nandrajog, learned Senior counsel for the Petitioner, that an arbitral tribunal (AT) has since been constituted and the interim orders passed by the Court should continue during the pendency of the arbitral proceedings.

    13. Mr. Ramji Srinivasan, learned Senior counsel appearing for GAIL (India) Limited, vehemently opposed the above plea. He submitted that the plea that ROUs were not acquired for the work to commence was wholly incorrect. He referred to a chart (Annexure R-1/24) enclosed with the reply filed in OMP No. 151/2014 showing ‘ROU availability vs. Work completion’. He submitted that as far as Section-I was concerned of the 91 kms stretch, 49.4 kms was available as on 12 January 2013 whereas work was completed only to the extent of 0.51 kms. Likewise as regards Section-II of the 114 kms, ROU in respect of 78.096 kms was available and no work had been completed till then. It is submitted that while the question of invocation of PBGs would depend upon the outcome of the arbitral proceedings and that may be kept alive by the petition during the pendency of the arbitral proceedings, there was no justification whatsoever for restraining the encashment of the ABGs. According to the Petitioner, despite disbursement of over Rs. 9.88 crores for Section-I and over Rs. 7.58 crores for Section-II as mobilisation advance, there was very little work completed and, therefore, Respondent No. 1 is entitled to seek encashment of the ABGs. He submitted that this was not a case where any fraud was played on the Petitioner by Respondent No. 1 which is a public sector undertaking. He relied upon the judgment of the Supreme Court in U.P State Sugar Corporation v. Sumac International Ltd.. (1997) 1 SCC 568 to state that only in exceptional circumstances would the Court interdict the invocation and encashment of bank guarantees. He submitted that the Petitioner has failed to make out a such case for such interdiction.

    14. Mr. Sudhir Nandrajog, in rejoinder, seriously disputed the correctness of the chart at Annexure R-1/24 enclosed with the reply of the Respondent. He has referred to documents placed on record which showed that notifications were being issued under Section 6 of the Act for certain stretches of lands even as late as in August 2013. He has pointed out that where a continuous stretch was not available, it would be impossible to lay any pipeline. Also in several instances the actual handing over of the land was yet to take place and this could be established only in arbitral proceedings.

    15. The above submissions have been considered. The first factor to consider is whether the Petitioner has a prima facie case in its favour. Clauses 5 and 35 of the ITB require the bidders to visit and examine the site of work and the pipeline route. Clause 5.1 states “Claims and objections due to ignorance of existing conditions will not be considered after submissions of the bid and during implementation.” Clause 26 specifies the conditions for Force Majeure. Clause 29.1 states that if the contractor refuses or fails to execute the work the employer i.e, Respondent No. 1 can determine the contract or take over any part of the work.

    16. Clause 28.1 of the SCC which is relevant to the disputes between the parties reads as under:

    “28.1 Company has acquired the ROU free of any encroachments/temporary/permanent structures under P&MP act in general. Acquiring of ROU means publishing of 3(1) and 6(1) Gazette notification under P&MP Act 1962.

    Contractor shall open the ROU with revenue team of competent authority appointed by GAIL and start the construction activities. Opening of ROU to start for construction and related activities & maintaining of ROU during entire period of construction shall be the responsibility of contractor. In case any obstruction by landowner(s)/farmers or encroachments or structures are encountered during execution, the same shall be got removed by the contractor. All costs towards such activities shall be to Contractor's account. Necessary compensations applicable under P&MP act shall be paid by Company.”

    17. Clause 28.6 states that in case of any detour from the acquired ROU due to constructability problems or otherwise, the contractor would be permitted to do so after approval of Respondent No. 1. It further states as under:

    “28.6 ……However, such activity shall not affect the construction schedule and overall completion period. In case of local detour due to non availability of Legal ROU, contractor has to negotiate and arrange the ROU for laying of pipe line without affecting the schedule. Compensation payable under P&MP act shall be paid by GAIL. All other costs if any shall be to the contractors account. Company shall proceed with regular notifications etc. In due course for the detoured portion.”

    18. Respondent No. 1 has with its reply annexed document R-1/17 giving details of acquisition as on 8 August 2013. This makes it clear that entire stretch in respect of both projects had not been acquired as on the date of the contract and this was completed in instalments after that date. Even if the site had been inspected by the Petitioner, that may not have revealed the fact which was exclusively in the knowledge of Respondent No. 1. However, these are aspects for which evidence have to be led by both parties. The above observations of the Court at this stage are only of a prima facie nature. The stand of the Respondent “It is not mandatory that the entire ROU is made available to the Petitioner at the very beginning” will have to be established in the arbitral proceedings. To what extent the Petitioner failed in commencing and completing work on stretches made available to it from time to time will also be a matter of evidence and examined in the arbitral proceedings. However it does appear to the Court that question whether the Petitioner failed to perform its obligations under contract or whether the Respondent No. 1 failed to make available the land necessary for performance of such work cannot be conclusively determined at this stage. However it does appear that the Petitioner has made out a prima facie case in its favour as far as restraining Respondent No. 1 from invoking and encashing the PBGs is concerned.

    19. As regards the ABGs, it is not the case of Respondent No. 1 no manpower and machinery had been deployed of the Petitioner. Even as per the chart produced to Respondent No. 1 some amount of work has already commenced and has been completed by the Petitioner. In other words, it is not as if the mobilisation advance released to the Petitioner has not been utilised by it. In the circumstances, at this stage to permit encashment of the ABGs would definitely cause irretrievable injustice to the Petitioner since the Petitioner also has its claims against the Respondent No. 1 in respect of the work already done by it.

    20. According to the Petitioner, for the work completed by it, it has incurred amounts far in excess of the mobilisation advance released in respect of both Sections I and II. In the considered view of the Court, therefore, apart from a prima facie case in favour of the Petitioner, the balance of convenience is also in its favour at this stage in restraining the Respondent invoking and encashing the ABGs.

    21. In the circumstances, the Court directs that the interim order passed on 4 February 2014 in both petitions will continue during the pendency of the arbitral proceedings subject to the Petitioner keeping alive the PBGs and ABGs during the pendency of the arbitral proceedings.

    22. The petitions are disposed of in the above terms.